R-2017-4513 - 7/13/2017 RESOLUTION NO. R-2017-4513
WHEREAS, Section 395.058 of the Texas Local Government Code ("the Act") requires the
Capital Improvement Advisory Committee ("CIAC") to report to the City Council the progress of the
capital improvements plan and any perceived inequities in implementing the plan or imposing the
impact fee; and
WHEREAS, the CIAC is also required to advise the Council of the need to update the land use
assumptions, capital improvements plan and impact fees; and
WHEREAS, the CIAC has submitted a Capital Improvement Plan Progress Semi-Annual
Report; and
WHEREAS, the City Council has reviewed the attached Capital Improvement Plan Progress
Semi-Annual Report and has determined same to be in compliance with the Act,Now Therefore
BE IT RESOLVED BY THE COUNCIL OF THE CITY OF ROUND ROCK, TEXAS,
That the Capital Improvement Plan Progress Semi-Annual Report, attached hereto as Exhibit
"A" and incorporated herein, is hereby approved.
The City Council hereby finds and declares that written notice of the date, hour, place and
subject of the meeting at which this Resolution was adopted was posted and that such meeting was
open to the public as required by law at all times during which this Resolution and the subject matter
hereof were discussed, considered and formally acted upon, all as required by the Open Meetings Act,
Chapter 551, Texas Government Code, as amended.
RESOLVED this 13th day of July, 2017.
/,/ # z
CRAIGGANPexas or
City of R�Aund Roc
ATTEST:
qlw�, V&
SARA L. WHITE, City Clerk
0112.1704,00381235
EXHIBIT
A.,
i
r'
ROUND ROCK TEXAS
UTILITIES AND ENVIRONMENTAL SERVICES
CitywAftf Round Rock
Utilities & Environ mental
Services Department
SUMMARY
The Local Government Code Section 395.058 requires the Capital
Improvement Advisory Committee (CIAC) to report to the political
subdivision the progress of the capital improvements plan and any
perceived inequities in implementing the plan or imposing the impact
fee. Included herein is the semi-annual report for the reporting period
of October 1, 2016 to April 1, 2017. This report includes an updated
assessment of the actual growth rate in comparison to the projections
and assumptions made in the report; projects completed or initiated
during the period; and impact fees collected during the period. These
comparisons are used as indicators of the need to update the land use
assumptions, capital improvements plan or impact fees.
The local government code also requires the Capital Improvement
Advisory Committee to advise the City Council of the need to update the
land use assumptions, capital improvements plan and impact fees.
These items were last updated by the City in November 2015.
1 7/5/2017
Figure 1 represents Ground and Surface water use, along with the
number of active water services over the past two years. Although the
City continues to grow, the total water production has remained fairly
level over the past two years. Part of this reason could be because
water usage is dependent on weather patterns; however, the City's
conservation and reuse water programs are also affecting the amount
of potable water usage by the City. New water services continue to
increase, but at a slower pace compared to the early 2000's.
Figure 1
Water Treatment Plant
3.000 ,........._.................___............_................._......_._.__....__........_...................................................................................................
.......................___............_.............._._._..._...._.._...._.._.__...._..__._..__...._ 34
2,50Q ...........................................................................................................................................................................................
....................................................
^ 365
2,000 _..._...._.. _.......... S ._._......._.................__...._...._..._................{ .�
-i 33
�3
U
...................... ....15CD _............ _..__...._......_.... .................................. —
d
Ms
1,000 +-
77 �-
t� C3
32
SCID ......................... ..................................................................._...........................................................__.................._........
......................._._....j
0 __...,.._ .. _ _;_._......W_.___ _ ....__........
2rdQOrFY 3rd CirFY s 4th Ctr FY 1st Qtr FY f 2nd Qtr FY 3rd Ctr FY 4th CtrFY 1st Mr FY 2nd Cir FY
X15 15 '15 `16 ' '16 `15 '16 °17 117 `
...... ................. .....a..... '
... ............_�............................................. .... ........................................ ..................ti...............................,.;...
x Grcund Water 1188,620,000 12140,
300 :226,270,000 1-0,340,000 196,240,Ca) 217,31(1,(300 222,59D,OM:20R,18D,0001 21,84QCDO.
...................................
&Kface Waterl 1,030,268.0 1,2&2,620,0:2 426 800 O 1492 430,0,1,211,910,0 1412 06RO 2 044 50D 0 1,379,79Q0 1„255 550,0
_ ....... .
...... ................. .......
Acme Se 32375 32418 1 32588 1 32574 1 32703 32732 32930 33465 33695
2 7/5/2017
Figure 2 reflects the monthly potable water production over the past
seven years. As can be expected, the average daily demand increases
during the summer months; however, total water production is
dependent on weather conditions, which effects discretionary water
usage.
Figure 2
Average Potable Daily Demand Each Month
40 .. ....... .
35
30
25
C 9
`.�2
c0
G
15
10 `
5 `S
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2010 ij 2011 2012U 2013 ':..1 2014 U 2015 W 2016 2017
3 7i5i201 7
Figure 3 reflects the monthly potable treated water production and the
Type I Reuse treated water production. The City's reuse water system
began production in October 2012 with three customers: Old Settlers
Park, Dell Diamond, and Forest Creek Golf Course. Since that time, the
City has expanded the system to include Forest Creek HOA, Legends
Village Subdivision, Austin Community College, Texas A&M Health
Science Center, the Forest Grove and Vizcaya Subdivisions. The City
continues to promote the reuse water system in the Northeast part of
Round Rock and as depicted in Figure 3, the demand continues to grow.
Figure 3
Potable vs. Reuse Water
Average Daily Demand Each Month
36
32
28
24
U1 20 3
O 3 y a
16 } r
1
I
12 .: " is
4
p v
so
� O 5EQ
FY-13 Average Potable Treated W FY-14 Average Potable Treated w FY-15 Average Potable Treated
w FY-16 Average Potable Treated a FY-17 Average Potable Treated uAverage Reuse Treated
4 7/5/2017
Figure 4 shows the number of single-family building permits issued
annually. The number of new housing starts per year in the City of
Round Rock has ranged from 222 to 480 over the past eight years.
Single-family permits have remained steady over the past year due to
new subdivisions available within the City. Of the 419 permits issued in
FY-161 310 were for single-family residences and 109 were for
townhomes. With the release of four new subdivisions, single-family
permitting has remained steady for the first half of FY-17. Several
Municipal Utility Districts (MUDs) that are located in Round Rock's extra-
territorial jurisdiction (ETJ) continue to experience a steady number of
single-family housing starts over this same time period as well.
Ficiure 4
3
Annual Single-Family Building Permits Issued
Residential & MUDs
800
750
71s
3
700 677
650
600 581 591
556
550 526 535
500
450
400
350 r__ 338 342
300
250
200
150
'100
50
0
FY-2009 FY-2010 FY-2011 FY-2012 FY-2013 FY-2014 FY-2015 FY-2016 FY-2017
3 Oct-Mar
E Round Rock N Paloma MUD#1 a Paloma MUD#2 E Tera Vista#10 0 Tera Vista#11 1 Walsh Ranch
f
5 7i5i201 7
Table 1 represents the number of multi-family building permits issued
annually. During FY-07, a large number of new apartment complexes
were constructed within the City. This is reflected in the amount of
impact fees collected during that year. The following years did not see
this amount of multi-family construction; however, the population
continued to grow despite the fewer permits issued. In FY-14, there
was an increase in the number of multi-family projects under
construction; however, these projects were permitted in FY-13, as
shown in the table below. For FY-15 and FY-16, there were several
multi-family complexes that were either under construction or in permit
review. Currently, there are four projects under construction with
another two in for a permit. There are also three senior living/assisted
living projects and two Alzheimer units under construction.
Table 1
Fiscal Year Units Permitted
FY 2005 538
FY 2006 56
FY 2007 2147
FY 2008 224
FY 2009 274
FY 2010 130
FY 2011 0
FY 2012 280
FY 2013 884 (124 L UEs)
FY 2014 334 (63.5 L UEs)
FY 2015 792 (302 LUES)
FY 2016 608 (157 L UEs)
FY 2017 (Oct— Mar) 330 (170 LUEs)
Note: The number of LUEs that were determined for these developments are
shown in parenthesis.
6 7i5i2017
Table 2 reflects the number of new commercial building permits issued
annually. Over the past several years the number of permits has been
steady, ranging from 20 to 30 permits annually. However, from FY-13
thru FY-16, there was a significant increase in new commercial building
permits, specifically for restaurants, hospitals, medical clinics, banks,
convenient stores, and office buildings.
Table 2
Commercial
Fiscal Year
Permits
Build
FY 2009 30
FY 2010 29
FY 2011 27
FY 2012 20 (100 LUEs)
FY 2013 37 (185 LUEs)
FY 2014 33 (165 LUEs)
FY 2015 47 (202 LUEs)
FY 2016 63 (442.5 LUEs)
FY 2017 (Oct — Mar) 10 (31 LUEs)
Note: The number of LUEs for these developments is shown in parenthesis.
Commercial growth continues to be heavy in the City in FY-17 as well.
Several new office buildings are under construction and in for permits.
These facilities include medical offices, convenient stores, storage
facilities, retail strip centers, hotels, Austin Community College
expansion, and Round Rock Independent School District additions.
7 7/5/2017
Table 3 and Figure 5 summarize the impact fees collected from FY-13 thru
the first six months of FY-17 for residential and commercial building
permits. There was a significant increase in the amount of impact fees
collected in FY-15 and FY-16, due to the construction that occurred in
single-family residential, multi-family residential and commercial
developments.
Table 3
Impact
Fees
Mar)
i
Residential Water $ 2,407,646 $ 961,767 $ 1,616,580 $ 1,5161823 $ 1,218,585
Commercial Water $ 1,296,258 $ 941,463 $ 2,2731857 $ 21342,270 $ 514,994
Wholesale Water N/A $ 1,163,887 $ 11035,951 $ 11117,590 $ 331,287
Residential Sewer $ 1,106,716 $ 322,936 $ 618,240 $ 701,551 $ 516,973
Commercial Sewer $ 4771758
$ 398,361 $ 1,084,193 $ 1,020,587 $ 751,039
_.. r. _.....
Wholesale Sewer N/A $ 920,972 $ 11304,686 $ 11529,096 $ 551,538
Total Collected $ 5,288,378 $ 4,709,386 $ 71933,507 $ 8,227,917 $ 3,8841416
.............. w......
8 7/5/2017
Figure 5
Impact Fees Collected FY 2013 - 2017
f '
$9,000,000 $8,227,917 '
o $7,933,507 ...................... __ . ......._.. ........................................................................
..: ...................... ....... ....... .:.....::..,
$8,000,000
$7,000,000
$5,288,378
$6,000,000 .
-- �$4,709,386 y�
$5,000,000
$3,884,416
l
v...v...mwww.n.....n....w..... wnn..„.
4,000,000 .._. ....,_.. .wnw....� _,..........
.
$3,0 00,00 0
$2,000,000 �f
ii
r`� 1
$1,000,000
4 .. ..
FY-13 FY-14 FY-15 FY-16 FY-17(Oct-Mar)
Residential Water K Commercial Water Wholesale Water N Residential Seger ra Commercial Sewer Wholesale Seeder
In 2015, the latest version of the water model assumed that 1,524 LUEs
per year would be added to the water system. For an impact fee of
$4,025 per LUE, this would indicate that the City should have collected
approximately $6.13 million per year in water impact fees if the City
would be growing as projected.
The wastewater model assumed that 1,089 LUEs would be added to the
wastewater system per year. For an impact fee of $2,099 per LUE, this
would indicate that the City should have collected approximately $2.29
million per year in wastewater impact fees if the City would be growing
as projected.
Comparing these assumptions to the actual impact fees collected
indicates that new connections to our water and wastewater systems
are occurring as projected.
9 7i5i201 7
Table 4 provides population projections for Round Rock and Round
Rock's ETJ over the coming years. These projections, anticipating a
steady growth rate, indicate that in order to keep up with growth, capital
improvements to the City's water and wastewater utility systems would
be necessary. However, 2012-2016 estimates, shown in parenthesis,
indicate the City's population growth rate is slightly slower than
projected.
Table 4
Inside City City's ETJ
Year Projections Growth Rate Projections Growth Rate'
2010 Year
99f887 - 141,807 -
2011 1001659 0.8% 143,960 1.5%
2012 102,349 / (101,702) 1.7% (1.0%) 147,027 2.1%
2013 104,805 / (102,349)" 2.4% (0.6%) 151,133 2.8%
2014 107,635 / (103,494) 2.7% (1.1%) 155,613 3.0%
2015 110,757 / (105,405) 2.9% (1.9%) 160,385 3.1%
2016 1131968 / (107,158)1 2.9% (1.7%) 165,024 2.9%
2017 117,160 / (108,353) 2.8% (1.1%) 169,213 2.5%
2018 120,440 2.8% 173,490 2.5%
2019 123,812 2.8% 177,859 2.5%
2020 1271279 2.8% 182,323 2.5%
2021 1301461 2.5% 1861062 2.1%
2022 133,723 2.5% 189,881 2.1%
2023 137,066 2.5% 193,508 1.9%
2024 140,492 2.5% 197,218 1.9%
2025 143,302 2.0% 200,312 1.6%
2026 146,168 2.0% 2031462 1.6%
2027 1491092 2.0% 2061670 1.6%
2028 152,073 2.0% 2091651 1.4%
2029 155,115 2.0% 2121693 1.5%
2030 158,217 i 2.0% 215,795 1.5%
Notes: 2010 is the base year for these projections
( ) Annual Estimates by Planning & Development Services Department
10 7/5/2017
Table 5 provides a summary of the Water System Capital Improvement
Projects that have been completed or are in progress since the last
impact fee analysis was completed in November 2015. In addition,
projects that are anticipated over the next 10 years are also shown
below. Table 5
Completed Water Projects Completion Cost
Water Distribution System Model 2012 $ 200 000
2012 Water Distribution System Master Plan & 2012132 000
Impact Fee $
BCRUA Phase 1A - Construction Management & 2012 1 507 000
Inspection Services
BCRUA Raw Water Line & Intake Barge, Contract 1 2012 $ 81590,000
.......................____...___...._..................._.... ..__..............__........................__........_.......
BCRUA Raw .
Water Li. ............... ...... _..
................................................_.._...._._..... ._...._......................................._............................._.....__..................................
........................
....................
BCRUA Raw Water Line & Intake Barge, Contract 3 2012 $ 1,134,000
{
BCRUA Treated Water Line - Phase 1, Segment 1 2012 $ 3,6081000
BCRUA Treated Water Line - Phase 1, Segment 2A 2012 $ 364,000
............_._......................... _._.... _ __._........__ .......___.�...___._............................_............
BCRUA Treated Water Line - Phase 1, Segment 2B 3 2012 $ 51168,000
i
BCRUA Treated Water Line - Phase 1, Segment 2C 2012 $ 3,350,000
....._............................_.........................................................................._......................................................................._.......
.................._................................._......___...._....._..............................._-...................................
BCRUA Water Treatment Plant - Phase 1A 2012 $ 19,048,000
Clearwell at RR-WTP 2012 $ 21851,000
.........................................................................................._.........................................................................................................
..............................................................................................................._..._......._...........................................................................
....................
BCRUA Treated Water Line - Phase 1, Segment 3 2015 $ 81749,000
University Blvd Water Line Phase 1 2015 $ 1,877,000
Parcel 150 2015 $ 31144,000
...................................................................................................................................................................................................
.....................................................__.._........_...................L..._........__....._..................................._._...._.................................................
......................
CR 112 Phase 2 - 24" Water Line (890 PP) 2015 $ 888,000
Water Distribution System Master Plan & Impact Fee 2015 $ 141,000
Creek Bend 12" Water Line 2016 $ 415,000
$ 62,857,000
Water Projects In Progress Completion Cost
Arterial H Waterline 2018 $ 1,5031000
$ 1,503,000
11 7/5/2017
Upcoming Water Projects Estimated Estimated
9 Completion Cost
BCRUA Water Treatment Plant - Phase 1B 2017 $ 31,000
South Creek Water Line 2018 $ 6171000
Water Distribution System Master Plan & Impact Fee 2018 $ 150,000
Palm Valley Water Line 2019 $ 11484,000
Double Creek Water Line 2019 $ 11841,000
BCRUA Water Treatment Plant - Phase 1C 2019 j $ 4,152,000
Avery Center East 2019 $ 2,9151000
Meadow Lake Lines 2019 $ 969,000
Southeast Red Bud Lane Water Lines 2020 $ 559,000
............................................................................................................................................_........_..............._..........................
..........................._.........................._......................_....
......._._........._..._._._....._............... _._........._.......
Saddle Brook Water Lines 2020 $ 598,000
Ground Water Treatment Plant at Lake Creek 2020 '
$ 6,707,000
..__...._... ........................................................................................._....____.._._.__._._.__.............___.._...._......... ......_
...........
Round Rock Glen Water Lines 2020 $ 1,169,000
_._........_...__._....._...._.._ _ __..._.__._._..._......._..............._..__ _...._._..._..._......_. __-.___........................_...................._._._........_x........__.
...._..._.__..__ ....._..................................
Brenda Lane Water Lines 2020 i $ 1,141,000
Arterial A Water Line 2020 $ 5,012,000
......... ...................................__.................................._._..._..........................._..._..._............_..__..........._.........._........................
................._........................ ... .._..._......_...........................
.......................
Arterial H Phase II 2020 $ 1,470,500
Water Distribution System Master Plan & Impact Fee 2021 $ 154,000
Parcel 185 2022 $ 817,000
_....................................................
__......__.._r.._........_..........................................................................................
.
Gattis School Road 2022 $ 1,827,000
2.0 MGD Elevated Storage Tank (PP 890) 2022 $ 5,029,000
East Loop II 2022 $ 6,619,000
Sam Bass Phase II 2022 $ 1,624,000
South Creek Phase II 2022 $ 2,312,000
East Loop III 2022 $ 7,2031000
West Loop 2022 $ 17,818,000
....................._.....I........................._ _. ..........._......._..................................._............... .......__......_........_................................
.................................................................................................._.............__...._.:_.._................._........................................................
_......._.......
.
BCRUA Raw Water Line - Phase 2A, Segment 5 2023 $ 16,866,000
BCRUA Deep Water Intake 2023 $ 23,821,000
BCRUA Water Treatment Plant - Phase 1D 2023 $ 11047,000
Sam Bass Phase I 2023 $ 14,469,000
$ 128,421,500
12 7/5/2017
Table 6 provides a summary of the Wastewater System Capital
Improvement Projects that have been completed or are in progress
since the last impact fee analysis was completed in November 2015. In
addition, projects that are anticipated over the next 10 years are also
shown below.
Table 6
Completed Wastewater Projects Completion Cost
Chandler Creek 1 (Lower) 2013 $ 424 000
McNutt Creek C3 2014 $ 9401000
McNutt Creek C9 2015 $ 11471,000
McNutt Creek C13 2015 $ 561,000
Chandler Creek 1 (Upper) 2015 $ 5731000
Wastewater Master Plan and Impact Fee
2015 $ 165,000
Update
Lake Creek 2 2017 $ 1,9161000
Lake Creek 3 2017 $ 563,000
McNutt Creek C2 (referred to as C5) 2017 $ 11762,000
$ 81375,000
Wastewater Projects in Progress Completion Cost
Forest Creek LS 2017 $ 2231000
Brushy Creek 5 2017 $ 288,000
$ 511,000
Upcoming n Wastewater Projects Estimated Estimated Cost
p g jCompletion
Chandler Creek 2 2018 $ 428,000
Brushy Creek 2 2018 $ 349,000
Chandler Creek 3 2018 $ 655,000
................................................................................................................_..............._.................................................................
..........................................._..........................................................................................................................................
.................
McNutt Creek 15 (referred to as 12) 2018 $ 488 000
................................................................................................................_.........................._................................................._.
........................_. _._._......_._.............................._..........................................__...
3
Dry Creek 2019 $ 856,000
McNutt Creek C10 2019 $ 937,000
.....................................................I ..........................................................._.................__._............._.............................................
....................................................................................................................................................
.....................................................................................
13 7/5/2017
Upcoming Wastewater Projects Estimated Estimated Cost
Continued... _ Completion
Brushy Creek 4 2020 $ 173 000
............................._..._........._....................._.._.......................... _ _ ._._._.._....._._..___ __._............
i 1
McNutt Creek D2 2020 $ 31339,000
McNutt Creek C4 2020 $ 154,000
Hilton Head LS 2020 $ 17,000
Lake Creek 1 2021 $ 11287,000
Lake Creek 4 2021 $ 1,712,000
........................................................................................._...._.................................................................................................
...... ......_............................:......................._......................
McNutt Creek C12 2022 $ 714,000
SE Annex LS 2022 $ 616,000
_............................_........._.........................................................._............._.................._.................._....................__-._._................
........................_......._..._ ... __ _._...................._........_....._................._............................_......
........
Forest Creek 2 2022 $ 1,948,000
..................................................................................._...........___...__............._.............._._.__....__......___...._...__...........................
__ _ _ ..................................................... __:..__..._......._.._._..........................................................................
McNutt Creek D4 2022 $ 11108,000
Onion Creek 1 2022 $ 134,000
McNutt Creek C6 2022 $ 2021000
Onion Creek 2 2022 $ 99,000
Spanish Oak 1 2022 $ 1,179,000
McNutt Creek D5 2022 $ 748,000
Mayfield Park 2 2022 $ 1 549 000
........................................................................... ..................-...................................._.....................w.._................_.........._.....
..__..................._..._....._......_.
McNutt Creek C8b 2022 ' $ 649,000
Mayfield Park 1 2022 $ 3111000
WWTP Expansion 1 2023 $ 39 179-f-0,0 0
WWTP Rerate 2023 $ 5,000,000
Stone Oak LS 2023 $ 295,000
$ 64,349,000
Completed Reuse Projects Completion Cost
Reuse Phase II 2015 $ 2,108,500
Reuse Phase VI 2016 $ 900,000
$ 3,008,500
Upcoming Reuse Projects Estimated Cost
Completion
Reuse Phase V - Stony Point High School 2022 $ 600 000
$ 600,000
14 7/5/2017
Figure 6 provides a comparison of the Single-Family Residential Utility
Rates for Round Rock customers versus surrounding Central Texas City
and Municipal Utility Districts. As depicted, Round Rock utility rates
remain some of the lowest in the region.
Figure 6
Single-Family Residential
Water and Wastewater Rates Comparison
(monthly cost)*
$180
$160 $153.48 -
$150.90
$140 w _,.$134.60._
$124.00$123.75
$120
$106.80 $99,60
$100 ___.___. ... µ__.,...,.. �,..._._:.... $96.69
_... ..__,.. 92.45
$85.30 $81.20 $79.98
$80
$69.10 $63.65 $62.60
$60
$40
$20 _..._ _._._... _..., w_.. ..
$0 _ . a.... '.....'I'rrrrr.......
�atoo5 �oAP �a�\
Sam Qa\off �1a\So •j�S� ��Stia� atm\S CA161
Qat
(era date Lee Glee
■Water 0 Wastewater
* assumes 10,000 gallons water & 8,000 gallons wastewater used
15 7/5/2017
Table 7 compares Round Rock's Water and Wastewater Impact Fees to
other Central Texas cities. Historically, Round Rock had one of the
highest total impact fees charged for new connections to the water and
wastewater systems. However, several of the surrounding cities have
increased their fees over the past few years and have surpassed Round
Rock. Round Rock's philosophy is for new customers and developments
to pay for the capital improvements that are required due to the growth.
Table 7
• "' . Impact Fee Comparison
WaterLast
« Total
........................_. L -Up ated_
Brush Creek MUD
Brushy 2016 $21095 $1,804 $3,899
Cedar Park 2014 $2,250 $2,000 $4,250
Leander 2012 $3,880 $1,615 $5,495
Jonah Water SUD 2013 $4,636 $1,068 $5,704
Hutto 2013 $3,625 $2,128 $5,753
San Marcos 2013 $2,285 $3,506 $5,791
Round Rock 2016 $4,025 $2,099 $6,124
Pflugerville 2014 $4,241 $2,725 $6,966
Austin 2014 $5,400 $2,200 $7,600
Georgetown 2016 $6,139 $2,997 $9,136
Georgetown
(South San Gabriel Basin) 2016 $6,139 $4,452 $10,591
16 7i5i2017
CONCLUSION AND RECOMMENDATIONS
The CIAC and City Council approved the new Impact Fees which went
into effect March 1, 2016. Although the projected population growth in
Round Rock is proceeding at a slightly slower rate than what was
anticipated in the impact fee report, this has not caused a significant
concern since the number of connections to the water and wastewater
systems are occurring at the projected rate anticipated by the City.
As a result of the potential volatility in growth rates and infrastructure
requirements, the City recommends the impact fees be reviewed every
three years so that the fees are set according to the growth patterns
and needs of the water and wastewater utility system improvements.
The next Capital Improvements Plan Progress Report will be presented
to the CIAC and to the City Council in approximately six months.
17 7/5/2017