Contract - Lewis Contractors - 4/9/2015 Page 1 of 3
Contract Quantity Adjustment/Change Order
rev,08/12
Department: Utilities and Enviromental Services
Project McNutt Creek Wastewater Segment C9
Name: Project Date: 3/17/15
City Project Change Order/Quantity
ID Number MCNC9 Adjustment No. 1
Justification
Change Order/Quantity Adjustment#1 is needed for additional work days due boring Atmos and Seminole Gas Lines and heavy machinery
crossing details,and additional 135 LF of encasement pipe which will increase the contract cost by 4.74%.
SUMMARY Amount %Change
Original Contract Price: $2,092,349.50
Previous Quantity Adjustment(s): $0.00
This Quantity Adjustment: $99,225.00
Total Quantity Adjustment(s): $99,225.00
Total Contract Price with Quantity Adjustment(s): $2,191,574.50
Previous Change Order(s): 0.00
This Change Order: $0.00 0.00
Total Change Order(s)To Date: $0.00 0.00
Adjusted Contract Price [Original Contract Price Plus
Quantity Adjustment(s) Plus Change Order(s)]: $2,191,574.50
Difference between Original and Adjusted Contract Prices: $99,225.00
Original Contract Time: 240
Time Adjustment by previous Quan.Adj./Change Order: 0
Time Adjustment by this Quan.Adj./Change Order: 42
New Contract Time: 282
Submitted for Approval
Prepared By-29- 4&4, Eddie Zapata, Project Manager, City of Round Rock 3/17/15
Signature 0 Printed Name,Title, Company Date
Approvals I , �' �/'
Contractor: 1� W 1�,S V;CR.��`f� (�w�5 (qAJ a0OYS�.vr. 3/l
i ure/9 Printed Name,Title,Company D to
City Project
Manager: v Eddie Zapata, Project Manager, City of Round Rock l /�
Signatu Printed Name,Title Date
Mayor/City L OAYL��Manager NALA W • J
Signature Printed Name,Title Date
--20i1:�-02
Page 2 of 3
s Contract Quantity Adjustment/Change Order
rev,08/12
Project Name: McNutt Creek Wastewater Segment C9 Project
Quan. Adj./Change Order No.: 1
Change Order Data
Contract
Time
Adjustment
Item # Item Description Unit Qty. Unit Price Amount (Days)
Delay at Manhole #1 due to Hobas
CO 1 - 1 Fittings Manufacturing $0.00 12
CO 1 - 2 Bore under Atmos Gas Lines $0.00 10
CO 1 - 3 Bore under Seminole Gas Lines $0.00 5
Atmos and Seminole Gas Line Crossing
CO 1 -4 Details $0.00 15
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
TOTALS: 0.00 42
Page 3 of 3
Contract Quantity Adjustment/Change Order
I
0.no uND HO(:K.,TFaAS
rev,08/12
Project Name: McNutt Creek Wastewater Segment C9 Project
Quan. Adj./Change Order No.: 1
Quantity Adjustment Data
Contract
Time
Bid Item # Item Description Unit Adjustment
p Qty. Unit Price Amount
3 Jacking or Boring 42 In. Pipe, Class 150 LF 135 $735.00 $99,225.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
TOTALS: $99,225.00 0