R-11-03-24-11B3 - 3/24/2011RESOLUTION NO. R -11-03-24-11B3
WHEREAS, the City of Round Rock ("City") has previously entered into a Cooperative
Agreement with the Bureau of Reclamation for the Williamson County Water Reclamation and Reuse
Project, and
WHEREAS, on February 11, 2010, the City approved Modification 001 to the Agreement
which extended the project schedule, and
WHEREAS, the Bureau of Reclamation has corrected Modification 001 to reflect the correct
amount of Federal funds obligated, and
WHEREAS, the City now desires to enter into an Assistance Agreement with the Bureau of
Reclamation regarding Modification 001 to the Cooperative Agreement, Now Therefore
BE IT RESOLVED BY THE COUNCIL OF THE CITY OF ROUND ROCK, TEXAS,
That the Mayor is hereby authorized and directed to execute on behalf of the City an Assistance
Agreement with the Bureau of Reclamation, a copy of same being attached hereto as Exhibit "A" and
incorporated herein.
The City Council hereby finds and declares that written notice of the date, hour, place and
subject of the meeting at which this Resolution was adopted was posted and that such meeting was
open to the public as required by law at all times during which this Resolution and the subject matter
hereof were discussed, considered and formally acted upon, all as required by the Open Meetings Act,
Chapter 551, Texas Government Code, as amended.
RESOLVED this 24th day of March, 2011.
ALAN MCGRAW, Mayor
City of Round Rock, Texas
ATTEST:
SARA L. WHITE, City Secretary
O:\wdox\SCC1nts\0112\ 1104\MUNICIPAL\00216871.DOC/rmc
7-2279 (05-22-09)
Bureau of Reclamation
[ EXHIBIT
„ A„
„/A„
UNITED STATES DEPARTMENT OF THE INTERIOR
BUREAU OF RECLAMATION
ASSISTANCE AGREEMENT
1A. AGREEMENT NUMBER
R1OAC60R43
1B. MOD NUMBER
001
2. TYPE OF AGREEMENT
[ ] GRANT
[ x ] COOPERATIVE AGREEMENT
3. CLASS OF RECIPIENT
Local Government
4. ISSUING OFFICE (NAME, ADDRESS)
5. RECIPIENT (NAME, ADDRESS)
Bureau of Reclamation
City of Round Rock
P.O. Box 36900
221 East Main Street
Billings, MT 59107-6900
Round Rock, TX 87664
Ph. (512 218-5403
EIN #:
74-6017485
County:
Williamson
DUNS #:
10-274-0792
Congress. Dist:
31
6. ADMINISTRATIVE POINT OF CONTACT (NAME, ADDRESS)
7. RECIPIENT PROJECT MANAGER (NAME, ADDRESS)
Lindsey Nafts
Michael Thane
Grants Officer
2008 Enterprise Drive
Bureau of Reclamation
Round Rock, TX 78664.
Great Plains Regional Office
Ph. (512) 218-3236
P.O. Box 36900
Email. mthaneround-rock.tx.us
Billings, MT 59107-6900
Ph. (406) 247-7684
Email: Inafts(a�usbr.gov
8. GRANTS OFFICER TECHNICAL REPRESENTATIVE (NAME, ADDRESS)
9A. INITIAL AGREEMENT
9B. MODIFICATION
Collins Balcombe
Bureau of Reclamation
EFFECTIVE DATE:
EFFECTIVE DATE:
Oklahoma Texas Area Office
5316 Hwy 290 West Ste. 510
08-31-2010
See Block 17a
Austin, TX 78745
10. COMPLETION DATE
Ph. (512) 899-4162
Email: cbalcombe(a usbr.gov
04-30- 2012
11. PROGRAM STATUTORY AUTHORITY
CFDA
Reclamation Wastewater and Groundwater Study and Facilities Act, Title XVI, PL 102-575, as amended by
15.504
PL 108-316 Sec. 1636
12. FUNDING
RECIPIENT/OTHER
RECLAMATION
13. REQUISITION NUMBER
INFORMATION
Total Estimated
Amount of Agreement
$5,750,338
$1,228,575
14. ACCOUNTING AND APPROPRIATION DATA
This Obligation
$-0-
$-0-
Previous Obligation
$5,750,338
$1,188,575
Total Obligation
$5,750,338
$1,188,575
Cost -Share %
82%
18%
15. PROJECT TITLE AND BRIEF SUMMARY OF PURPOSE AND OBJECTIVES OF PROJECT
Project Title: Williamson
County Water Reclamation and Reuse Project — Phases IA and IB
See attached updated project schedule. The modification extends the agreement period to April 30, 2012.
16a. Acceptance of this Assistance Agreement in accordance with
17a. Award of this Assistance Agreement In accordance with the
the terms and conditions contained herein is hereby made on
terms and conditions contained herein is hereby made on
behalf of the above-named recipient
behalf of the United States of America, Bureau of Reclamation
BY:
BY:
DATE:
DATE:
16b. NAME, TITLE, AND TELEPHONE NUMBER OF SIGNER
17b. NAME OF GRANTS OFFICER
John F. Soucy
Assistant Regional Director
Additional signatures are attached
Modification 1
This Modification changes Section 5 of the agreement to the following:
5. SCOPE OF WORK
The Recipient proposes construction of treatment, storage, and pumping facilities at the Brushy
Creek Wastewater Treatment Plant (BCWWTP), along with installation of approximately 2.0
miles of pipelines to provide up to 2,500 acre-feet of Type I treated wastewater effluent per year
to customers, including Old Settlers' Park and Dell Diamond Baseball Fields. Implementation
of the project is a significant part of the City's plans to address a projected future water deficit.
The scope of work included under this agreement is herein divided into two phases: Phases IA
and IB. Remaining project phases (II — V) that would install infrastructure delivering an
additional 7 mgd are included as part of a separate Cooperative Agreement (No. ROAC60018).
Phase 1 A of this agreement's scope of work includes the installation of 2.0 miles of pipeline
from the BCWWTP to Old Settler's Park (also known as the OSP Pipeline). Phase 1B includes
the installation of the following at the BCWWTP: (1) a 1.0 MG storage clear well; (2) filter
basins and treatment filters; and (3) a pump station housing vertical turbine and horizontal split -
case pumps.
Listed below are the major tasks and project milestones by year and quarter. The starting date
for pre -award activities was January 1, 2010. The completion of all tasks, construction by phase
is anticipated to be prior to April 30th, 2012. Reports will be submitted in accordance with
Section 9. The agreement will end on September 30, 2012 to allow for final clean up, manual
preparations, and inspection work.
2010 January -March, 1St Quarter
1. Pre -Award and Administrative work to select engineer, complete design, and
prepare bid documents.
2010 April -June, 2"d Quarter
1. Enter into Contract with Design Engineer to complete City of Round Rock
(CORR) Reuse Water Projects Phase IA and IB design.
2. Complete Design, Construction Plans, and Bid Documents for CORR Reuse
Water Project, Phase IA — Old Settlers Park (OSP).
4. Review and Approve; Construction and Bid Documents (Phase IA).
5. Advertise for Bids (Phase IA).
6. Receive, and Review Bid Documents; and Award Construction Contract (Phase
IA).
7. Complete pressure testing of existing 24 -inch Reuse Water Line (Phase IA and
IB).
2010 July -September, 3rd Quarter
IA).
4. In -Situ verification of existing utilities (Phase IA).
5. Furnish and Install 24 -inch OSP-Reuse Water Line (Phase IA).
6. Furnish and Install 12 -inch OSP-Reuse Water Line (Phase IA).
1. Pre -Construction Conference and Notice to Proceed (Phase IA).
2. Construction Contractor to Mobilize and Begin Construction (Phase IA).
3. Install Temporary Fencing, Erosion Controls, and Sedimentation Controls (Phase
2010 October -December, 4th Quarter
1. Complete Design of CORR Reuse Water Treatment Facilities (RRRWTF) at
Brushy Creek Wastewater Treatment Plant (BCWWTP) Site (Phase IB).
2. Review and Approve; Construction and Bid Documents (Phase IB).
3. Advertise for Bids (Phase IB).
4. Receive, and Review Bid Documents; and Recommend Award of Construction
Contract (Phase IB).
5. Complete Installation of 24 -inch OSP-Reuse Water Line (Phase IA).
6. Complete Installation of 12 -inch OSP-Reuse Water Line (Phase IA).
7. Begin clean-up, re -vegetation, concrete and pavement repair (Phase IA).
2011 January -March, 1St Quarter
IB).
1. Award Construction Contract (Phase IB).
2. Pre -Construction Conference and Notice to Proceed (Phase IB).
3. Complete clean-up, re -vegetation, concrete and pavement repair (Phase IA).
4. Install Temporary Fencing, Erosion Controls, and Sedimentation Controls (Phase
5. In -Situ verification of existing utilities (Phase IB).
2011 April -June, 2"d Quarter
IB).
1. Construction Contractor (General) to Mobilize and Begin Construction (Phase
2. General Contractor in-situ verification of Site conditions (Phase IB).
3. 1.0 Million Gallon (MG) Clearwell (Reuse Water Storage Tank) Contractor in-
situ verification of Site and sub -surface conditions (Phase IB).
4. Begin Shop -Drawing Submittals for Design Engineer's and Owner's Review and
Approvals (Phase IB).
5. General Contractor orders High Service Pumps, Controls and Filter Equipment, as
approved by Engineer and Owner (Phase IB).
2011 July -September, 3rd Quarter
1. Begin Site -Piping Installation (Phase IB).
2. Begin 1.0 MG Reuse Water Storage Tank Construction (Phase IB).
3. Continue Shop -Drawing Submittals for Design Engineer's and Owner's Review
and Approvals (Phase IB).
4. Manufacture's delivery of mechanical, electrical, and pumping equipment (Phase
IB).
5. Begin Construction of Concrete Filter Basins, various concrete vaults (Phase IB).
2011 October -December, 4m Quarter
1. Continue Site -Piping Installation (Phase IB).
2. Continue 1.0 MG Reuse Water Storage Tank Construction (Phase IB).
3. Manufacture's delivery of mechanical, electrical, and pumping equipment (Phase
IB).
4. Construction of Concrete Filter Basins, various concrete vaults (Phase IB).
2012 January -March, 1st Quarter
IB).
1. Continue Site -Piping Installation (Phase IB).
2. Continue 1.0 MG Reuse Water Tank Construction (Phase IB).
3. Manufacture's delivery of mechanical, electrical, and pumping equipment (Phase
4. Continue construction of Concrete Filter Basins, various concrete vaults, etc. and
installation of HVAC equipment at Mechanical Control Room (Phase IB).
5. Installation of the Reuse Water Filter Equipment and Controls (Phase IB).
6. Begin verification of valves, lines, connections and meters on CORR's existing
OSP (potable water) irrigation system (Phase IB).
7. Complete asphalt roadway paving and concrete sidewalk construction (Phase IB).
2012 April
1. Completion of all Site -Piping Installation (Phase IB).
2. Completion and Painting of 1.0 MG Reuse Water Storage Tank (Phase IB).
3. Functional testing of all pumps, filters, mechanical and electrical control
equipment (Phase IB).
4. Final verification of valves, lines, connections and meters on CORR's existing
OSP (potable water) irrigation system and cross -connection (Phase IB).
5. Disconnect potable water system from CORR's OSP irrigation system and test for
cross -connections (Phase IB). .
6. Make Final connections of new Reuse Water Lines installed in Phase IA to the
CORR's OSP irrigation system (Phase IB).
7. Test new CORR's OSP Reuse Water irrigation system for any cross -connections
and correct, as necessary (Phase IB).
8. Re -testing, as necessary (Phase IB).
9. Final clean-up and re -vegetation (Phase IB).
10. Contractor's submittal of Operation and maintenance (O&M) Manuals (Phase
IB).
11. Design Engineer delivers Phase IA and Phase IB "Record Drawing" to City of
Round Rock (Phase IB).
ROUND ROCK, TEXAS
PURPOSE. PASSION. PROSPERITY
Agenda Item No. 1163.
City Council Agenda Summary Sheet
Consider a resolution authorizing the Mayor to execute Modification 1 to the Cooperative
Agenda Caption: Agreement for the Williamson County Water Reclamation and Reuse Project.
Meeting Date: March 24, 2011
Department: Finance
Staff Person making presentation: Cheryl Delaney
Finance Director
Item Summary:
This is a correction of Modification 001 to the Williamson County Water Reclamation and Reuse Project originally
approved by the City Manager on February 11, 2010, which extended the project schedule. Modification 001 (Form
7-2279) incorrectly stated the amount of Federal funds obligated. The attached "Exhibit A" has been corrected by
the Bureau of Reclamation and now reflects the correct amount.
The Bureau of Reclamation was appropriated $1 billion under the American Recovery and Reinvestment Act (ARRA)
of 2009 to repair America's water infrastructure and help address the country's Tong -term water supply challenges.
The City was approved to receive $1,228,575 in federal funds to complete phases IA & IB of the Williamson County
Water Reclamation and Reuse Project. These funds represent a 25% cost reimbursement to the city for the design
and construction of the Old Settlers Park Reuse Water Line (Phase IA) and the Treatment and Pumping
Improvements at the Brushy Creek Regional Wastewater Treatment Plant (Phase IB). A consolidated water
reclamation and reuse system within the City will help accelerate the conversion to effluent reuse at locations now
using raw water, or potable drinking water, for irrigation purposes and will free up current and future sources of raw
and potable drinking water.
Strategic Plan Relevance:
Goal 27.0 "Ensure there is an adequate, affordable, and safe water supply."
Cost: -$0-
Source of Funds: U.S. Department of Interior — Bureau of Reclamation
Date of Public Hearing (if required): N/A
Recommended Action: Approval
7-2279 (05-22-09)
Bureau of Reclamation
UNITED STATES DEPARTMENT OF THE INTERIOR
BUREAU OF RECLAMATION
ASSISTANCE AGREEMENT
1A. AGREEMENT NUMBER
R1 OAC60R43
1B. MOD NUMBER
001
2. TYPE OF AGREEMENT
[ 1 GRANT
[ x ] COOPERATIVE AGREEMENT
3. CLASS OF RECIPIENT
Local Government
4. ISSUING OFFICE (NAME, ADDRESS)
5. RECIPIENT (NAME, ADDRESS)
Bureau of Reclamation
City of Round Rock
P.O. Box 36900
221 East Main Street
Billings, MT 59107-6900
Round Rock, TX 87664
Ph. (512) 218-5403
EIN #:
74-6017485
County:
Williamson
DUNS #:
10 274-0792
Congress. Dist:
31
6. ADMINISTRATIVE POINT OF CONTACT (NAME, ADDRESS)
7. RECIPIENT PROJECT MANAGER (NAME, ADDRESS)
Lindsey Nafts
Michael Thane
Grants Officer
2008 Enterprise Drive
Bureau of Reclamation
Round Rock, TX 78664.
Great Plains Regional Office
Ph. (512) 218-3236
P.O. Box 36900
Email. mthaneround-rock.tx.us
Billings, MT 59107-6900
Ph. (406) 247-7684
Email: Inafts usbr.gov
8. GRANTS OFFICER TECHNICAL REPRESENTATIVE (NAME, ADDRESS)
9A. INITIAL AGREEMENT
9B. MODIFICATION
Collins Balcombe
Bureau of Reclamation
EFFECTIVE DATE:
EFFECTIVE DATE:
Oklahoma Texas Area Office
08-31-2010
See Block 17a
5316 Hwy 290 West Ste. 510
Austin, TX 78745
10. COMPLETION DATE
Ph. (512) 899-4162
Email: cbalcombe a.usbr.gov
04-30- 2012
11. PROGRAM STATUTORY AUTHORITY
CFDA
Reclamation Wastewater and Groundwater Study and Facilities Act, Title XVI, PL 102-575, as amended by
PL 108-316 Sec. 1636
15.504
12. FUNDING
RECIPIENT/OTHER
RECLAMATION
13. REQUISITION NUMBER
INFORMATION
Total Estimated
$5,750,338
$1,228,575
14. ACCOUNTING AND APPROPRIATION DATA
Amount of Agreement
This Obligation
$-0-
$-0-
Previous Obligation
$5,750,338
$1,188,575
Total Obligation
$5,750,338
$1,188,575
Cost -Share %
82%
18%
15. PROJECT TITLE AND BRIEF SUMMARY OF PURPOSE AND OBJECTIVES OF PROJECT
Project Title: Williamson
County Water Reclamation and Reuse Project — Phases IA and IB
See attached updated
project schedule. The modification extends the agreement perio• • April 3'
2012.
16a. Acceptance of this Assistance Agreement in accordance with
17a. Awar of this Assi ante A re ment in accordance with the
the ter and conditions contained herein ' hereby made on
term- . • co io s cont• n d herein is hereby made on
beha of ove-name cipient
beha America, Bureau of Reclamation
BY:
BY:
DATE: • ZIt . i (
DATE:
(y l)
J
16b. NAME, TITLE, AND TELEPHONEA.NUMBER OF SIGNER
17b. NA .
OF G - S
OFFICER
AcIG 0 PI L 6-114W
W
John F.
Soucy
Mc.,°,•
Assistant Regional Director
Additional signatures are attached Z .247/• 9403
Modification 1
This Modification changes Section 5 of the agreement to the following:
5. SCOPE OF WORK
The Recipient proposes construction of treatment, storage, and pumping facilities at the Brushy
Creek Wastewater Treatment Plant (BC W WTP), along with installation of approximately 2.0
miles of pipelines to provide up to 2,500 acre-feet of Type I treated wastewater effluent per year
to customers, including Old Settlers' Park and Dell Diamond Baseball Fields. Implementation
of the project is a significant part of the City's plans to address a projected future water deficit.
The scope of work included under this agreement is herein divided into two phases: Phases IA
and IB. Remaining project phases (II — V) that would install infrastructure delivering an
additional 7 mgd are included as part of a separate Cooperative Agreement (No. ROAC60018).
Phase 1 A of this agreement's scope of work includes the installation of 2.0 miles of pipeline
from the BCWWTP to Old Settler's Park (also known as the OSP Pipeline). Phase 1B includes
the installation of the following at the BCWWTP: (1) a 1.0 MG storage clear well; (2) filter
basins and treatment filters; and (3) a pump station housing vertical turbine and horizontal split -
case pumps.
Listed below are the major tasks and project milestones by year and quarter. The starting date
for pre -award activities was January 1, 2010. The completion of all tasks, construction by phase
is anticipated to be prior to April 30th, 2012. Reports will be submitted in accordance with
Section 9. The agreement will end on September 30, 2012 to allow for final clean up, manual
preparations, and inspection work.
2010 January -March, 1st Quarter
1. Pre -Award and Administrative work to select engineer, complete design, and
prepare bid documents.
2010 April -June, 2nd Quarter
1. Enter into Contract with Design Engineer to complete City of Round Rock
(CORR) Reuse Water Projects Phase IA and IB design.
2. Complete Design, Construction Plans, and Bid Documents for CORR Reuse
Water Project, Phase IA — Old Settlers Park (OSP).
4. Review and Approve; Construction and Bid Documents (Phase IA).
5. Advertise for Bids (Phase IA).
6. Receive. and Review Bid Documents; and Award Construction Contract (Phase
IA).
7. Complete pressure testing of existing 24 -inch Reuse Water Line (Phase IA and
IB).
2010 July -September, 3'd Quarter
IA).
4. In -Situ verification of existing utilities (Phase IA).
5. Furnish and Install 24 -inch OSP-Reuse Water Line (Phase IA).
6. Furnish and Install 12 -inch OSP-Reuse Water Line (Phase 1A).
2010 October -December, 4th Quarter
1. Pre -Construction Conference and Notice to Proceed (Phase IA).
2. Construction Contractor to Mobilize and Begin Construction (Phase IA).
3. Install Temporary Fencing, Erosion Controls, and Sedimentation Controls (Phase
1. Complete Design of CORR Reuse Water Treatment Facilities (RRRWTF) at
Brushy Creek Wastewater Treatment Plant (BCWWTP) Site (Phase IB).
2. Review and Approve; Construction and Bid Documents (Phase IB).
3. Advertise for Bids (Phase IB).
4. Receive, and Review Bid Documents; and Recommend Award of Construction
Contract (Phase IB).
5. Complete Installation of 24 -inch OSP-Reuse Water Line (Phase IA).
6. Complete Installation of 12 -inch OSP-Reuse Water Line (Phase IA).
7. Begin clean-up, re -vegetation, concrete and pavement repair (Phase IA).
2011 January -March, 1St Quarter
IB).
1. Award Construction Contract (Phase IB).
2. Pre -Construction Conference and Notice to Proceed (Phase IB).
3. Complete clean-up, re -vegetation, concrete and pavement repair (Phase IA).
4. Install Temporary Fencing, Erosion Controls, and Sedimentation Controls (Phase
5. In -Situ verification of existing utilities (Phase IB).
2011 April -June, 2u Quarter
IB).
1. Construction Contractor (General) to Mobilize and Begin Construction (Phase
2. General Contractor in-situ verification of Site conditions (Phase IB).
3. 1.0 Million Gallon (MG) Clearwell (Reuse Water Storage Tank) Contractor in-
situ verification of Site and sub -surface conditions (Phase IB).
4. Begin Shop -Drawing Submittals for Design Engineer's and Owner's Review and
Approvals (Phase IB).
5. General Contractor orders High Service Pumps, Controls and Filter Equipment, as
approved by Engineer and Owner (Phase IB).
2011 July -September, 3rd Quarter
1. Begin Site -Piping Installation (Phase IB).
2. Begin 1.0 MG Reuse Water Storage Tank Construction (Phase IB).
3. Continue Shop -Drawing Submittals for Design Engineer's and Owner's Review
and Approvals (Phase IB).
4. Manufacture's delivery of mechanical, electrical, and pumping equipment (Phase
IB).
5. Begin Construction of Concrete Filter Basins, various concrete vaults (Phase IB).
2011 October -December, 4th Quarter
IB).
1. Continue Site -Piping Installation (Phase IB).
2. Continue 1.0 MG Reuse Water Storage Tank Construction (Phase IB).
3. Manufacture's delivery of mechanical, electrical, and pumping equipment (Phase
4. Construction of Concrete Filter Basins, various concrete vaults (Phase IB).
2012 January -March, 1st Quarter
IB).
4. Continue construction of Concrete Filter Basins, various concrete vaults, etc. and
installation of HVAC equipment at Mechanical Control Room (Phase IB).
5. installation of the Reuse Water Filter Equipment and Controls (Phase IB).
6. Begin verification of valves, lines, connections and meters on CORR's existing
OSP (potable water) irrigation system (Phase IB).
7. Complete asphalt roadway paving and concrete sidewalk construction (Phase IB).
2012 April
1. Continue Site -Piping Installation (Phase IB).
2. Continue 1.0 MG Reuse Water Tank Construction (Phase IB).
3. Manufacture's delivery of mechanical, electrical, and pumping equipment (Phase
1. Completion of all Site -Piping Installation (Phase IB).
2. Completion and Painting of 1.0 MG Reuse Water Storage Tank (Phase IB).
3. Functional testing of all pumps, filters, mechanical and electrical control
equipment (Phase IB).
4. Final verification of valves, lines, connections and meters on CORR's existing
OSP (potable water) irrigation system and cross -connection (Phase IB).
5. Disconnect potable water system from CORR's OSP irrigation system and test for
cross -connections (Phase IB).
6. Make Final connections of new Reuse Water Lines installed in Phase IA to the
CORR's OSP irrigation system (Phase IB).
7. Test new CORR's OSP Reuse Water irrigation system for any cross -connections
and correct, as necessary (Phase 1B).
8. Re -testing, as necessary (Phase IB).
9. Final clean-up and re -vegetation (Phase IB).
10. Contractor's submittal of Operation and maintenance (O&M) Manuals (Phase
1B).
11. Design Engineer delivers Phase IA and Phase IB "Record Drawing" to City of
Round Rock (Phase IB).