Loading...
R-13-11-14-H13 - 11/14/2013RESOLUTION NO. R -13-11-14-H13 WHEREAS, the City of Round Rock has previously entered into a contract ("Contract") with Chasco Constructors for the Kenney Fort Boulevard (Arterial A) Project, and WHEREAS, the Council has determined that it is necessary to make adjustments/changes to the quantity of work to be performed or materials, equipment, or supplies to be provided, and WHEREAS, it has been determined that it is necessary to adjust/change the quantities in said Contract in accordance with the attached Quantity Adjustment/Change Order No. 5, Now Therefore BE IT RESOLVED BY THE COUNCIL OF THE CITY OF ROUND ROCK, TEXAS, That the Mayor is hereby authorized and directed to execute on behalf of the City, Quantity Adjustment/Change Order No. 5 to the Contract with Chasco Constructors for the Kenney Fort Boulevard (Arterial A) Project, a copy of said quantity adjustment/change order being attached hereto as Exhibit "A" and incorporated herein for all purposes. The City Council hereby finds and declares that written notice of the date, hour, place and subject of the meeting at which this Resolution was adopted was posted and that such meeting was open to the public as required by law at all times during which this Resolution and the subject matter hereof were discussed, considered and formally acted upon, all as required by the Open Meetings Act, Chapter 551, Texas Government Code, as amended. RESOLVED this 14th day of November, 2013. ALAN MCGRAW, Mayor City of Round Rock, Texas ATTEST: SARA L. WHITE, City Clerk 0112.1304; 00285904 Department Protect Name City Project TO Number Justification EXHIBIT Transportation Kenney Fort Blvd. (Arterial A) TX02ARTA Pane I of 3 Date: 10/7/2013 Change Order/quantity Adjustmentnt Contract Quantity Adjustment/Change Order No. Add decomposed granite at road medians, and flumes at MSE wail, add RFD's at outfall channel, revise traffic signalizat:on at Forest creek Intersection, hold PEC power pole, deduct for pavement mark ng revisions SUMMARY Or'gnal Contract Price: Previous Quantity Adjustment(s). This Quantity Adjustment: Teta: Quant ty Adjustment(s). Total Contract Pr ce with Quantity AdJustment;s): Previous Change Order(s): This Change Order: Total Change Order(s) To Date: Adjusted Contract Price [Orin nal Contract Price Adjustment(s) Plus Change Order's)]: Difference between Original and Adjusted Contract Prices Original Contract lime: Time Adjustment by previous Quan Adj./Change Order: Time Adjustment by this Quan Adj./Change Order. New Contract Time: Prepared By Chasco Constructors Engineer City of Round Rock Signature Signature Signature Pius Quantity Submitted for Approval Amount $17,095,753.80 >129,175,92 $0 00 $16,966,378.88 $829,520.47 $77,305.00 5906,825.47 $17,873,204.35 $777,450.55 Calendar Days Calendar Days 0 Calendar Days 730 28 758 Calendar Days % Change 4.89°/o 0.4 6% 5.34% )0-16._13 Bill Stablein, Project 'Manager, CORR Date Appyoval?y , it Charles Glace 3r. iPr siden,thasco Constructors Date 1 tt —�r. /U//0/f3 Date David Holtman, Engineer, HDR Signature Alan McGraw, Mayor, C ty of Round Rock Date rev. 05/12 Department Project Name City Project ID Number Transportation Kenney Fort Blvd. (Arterial A) TX02ARTA Page 2 of 3 Date: 10/7/2013 Change Order/Quantity Adjustment Contract Quantity Adjustment/Change Order No. 5 h G�`M{.A' Item # Item Description Unit Qty. Unit Price Amount Contract Time Adjustment 1 Concrete flumes at MSE walls * Add 4 ea concrete flumes with rock rip -rap athe ends of MSE walls EA 4.00 $750.00 $3,000.00 0 2 PEC electric pole * Hire subcontractor to clamp on to existing PEC power pole with pole truck during storm sewer installation. LS 1.00 $1,500.00 $1,500.00 3 Rock Filter dams an outfall channel * Install Ty 3 rock filter dams at outfall channel near Brushy creek to dissipate flow LF 36 $50.00 $1,800.00 4 Traffic signalization and illumination * Revise signalization at Kenney Fort and Forest Creek intersection LS 1 $1,855.00 $1,855.00 * Revise light pole foundation due to stormLS sewer conflict 1 $2,650.00 $2,650.00 Subtotal $4,505.00 5 Decomposed Granite medians Install decompesed granite at center medians in$67,107.00 roadway Ls 1 $67,107.00 6 Pavement striping Deduct for eliminated turn lanes & hashouts LS 1 -$607.00 ($607.00) TOTALS: $77,305.00 0 .. ....._.. CK. rrxwv rev.05/12 Department Transportation Project Name City Project ID Number Kenney Fort Blvd. (Arterial A) TX02ARTA Page 3 of 3 Date: 10/7/2013 Change Order/Quantity Adjustment Contract Quantity Adjustment/Change Order No. 5 Da Bid Item # Item Description Unit QtY. Unit Price Amount Contract Time Adjustment rimzel TOTALS: $0.00 0 Chasco Constructors JOB NAME: KENNEY FORT BOULEVARD JOB #11104 10/3/2013 CHANC9t rhCurU.bAL NV I 1 DESCRIPTION QTY UNIT UNIT PRICE TOTAL PRICE Revise light pole foundation to stradle 66" SS line Concrete flumes at moc vuaaus 1 Install concrete flumes with rock rip -rap at outfall of MSE walls 4 EA $750.001 $3,000.00 $3.000.00 2 Concrete flumes at MSE outfalls PEG electric pole 1 Rework signalization at Forest Creek intersection Hire subcontractor with pole truck to clamp on to LS $1,855.00 $1,855.00 2 Revise light pole foundation to stradle 66" SS line 1 and hold existing PEC power pole during installation 1 $150000 $1,500.00 $1,5D0.00 of storm sewer within 5' of pole $1.500.00 PEC electric pole Rock filter dams (TY 3) 1 install rock filter dams in outfall channel Rock filter dams (TY 3) 36 EA 1 $50.00 $1,800.00 $1,800.00 Traffic s gnai ana wummaavn Guanyva 1 Rework signalization at Forest Creek intersection 1 LS $1,855.00 $1,855.00 2 Revise light pole foundation to stradle 66" SS line 1 LS $2,650.00 $2,650.00 $4,605.00 raffic s gnat an Decomposed granite medians Remove trurf at island medians and replace with DC granite 1 Decomposed granite medians 1 LS Page 1 of 1 $67,107.00 $67,107.00 $67,107.00 CP #12 Total changes I $77,912.00 CHANGE ORDER PROPOSAL 72. m u cm m O at A e 00000000pgo� C4 0 N- � N N r' d is is 40 v-- O 00000000000 O OOOOa!Q�mi°° N u ) '-'re-e-N�r 000000 0000000CD00O oocioo•tLricecqui't • tC) 00 O O o OD v- Cp Item Number 0 E m m fA6666666JJ W W iJDCC J ZL]❑ D rt cv Z J ZZ -J ro — —HQ w w w W W 0 c Z U (7 (7 ?:: t.J.5.(n � 4 WWWWWZv4a❑ }LJJJJJ—vim=W --'ZZZZZZZ UZZ ZN� -'- .--r�F..N0 UUUUUUJJHC WWWWWWWmmUiii fn u) v) U) O, C0 U U W ZP_C9(9(9(9C9(9O0tiiQ �YcoCDU)OD0)ODcncn❑U :DU=2222❑ti-u-❑❑ J Q W W W W W W DC DC W W <LM>>>>>Qt—(—MJ ODC4OD'CfLID IS. ChC,uNOOO O O N N N N N NS N N N N N N N N N N N N CONNNNNNNNS' d'O00 M OD 00 0D 0D 00 0D OD OD OD 00 O CSD CO CO CO CO CO C4 CO CO CO aD t` O O p 0 0 0 0 0 0 0 0 O OrNMd'ulCOCANOCD CD r r r V- c' .r. r V- c- r "V"' 0 0 LCi 00 r tf3 Total Bid Amount { { 0 W. In ▪ 0 COI- X• 0' W- U -W ZI J <, m. U2 00100CC' 1- CO01CC a�U{ J LL • J M. U Q M 0 ~ (i a { O J J <. - U 4 N 0 .cc v0_ 0 2 CC O w a rD U Q 1,0 O C J U1LL m MO W 0 u 0 ZU 0J OG w r r rCD LLCD 1l1LL MO ..2J- \ 2 0 ow H o r -11 LLa ?a tw 2 Old LLm 1 0w0 Jt - 1 of 0- ''w'' O 1z w 0 z 3 CI o x w 0 1 Z i (O W N EL g/ 4 ;;► so is. to UNci < °Y N N r Zwin P. 0 ct 0 z 0 0 J ze VS 0 Er. LL nX Et V p r re O p OD _ w- OcD =0 CI0 XS o Z Q ~ �W I M 0 O .� X o� N c 0 E s m 3 CV 74 is fa CHANGE ORDER Total Bid Amount C) 11) 110 N 1.0 (1) 0 .2 0) O N it 40) V L o L 1 d .10T r V L ti O • W )— 0 act rC7 !t03, 00 C3 W 0- = Co) . CO .>> Q 111 Z a r N z �-ta :bre €« (Drilled Orfila Shaft OHVA?7flW .1X0122NN3A NI =WA WI CM/1/490o 4,0WPMPX.W.ONLWROAAff..06M 1,71.41 F Lr�•'f�—` `Fstfttt •� �t nM_ L+4 91K4Y • �r—�—�1 r-ROUNDCK TD(AS PURPOSE N rwswrx City of Round Rock Agenda Item Summary Agenda Number: H.13 Title: Consider a resolution authorizing the Mayor to execute Quantity Adjustment/Change Order No. 5 with Chasco Constructors for the Kenney Fort Boulevard (Arterial A) Project. Type: Resolution Governing Body: City Council Agenda Date: 11/14/2013 Dept Director: Gary Hudder, Transportation Director Cost: $77,305.00 Indexes: RR Transportation and Economic Development Corporation (Type B) Attachments: Resolution, Exhibit A, Map Department: Transportation Department Text of Legislative File 13-858 The original contract for construction services was approved by the City Council on June 23, 2011 for the amount of $17,095,753.80 to extend Kenney Fort Boulevard from Joe DiMaggio south to Forest Creek Boulevard. Quantity Adjustment No. 1 added John Harris and Susan Hickox as additional insured and reinforced concrete pipe was replaced with 36" corrugated concrete pipe for culvert the crossing at the request of Union Pacific Railroad at the cost of $10,519. Quantity Adjustment No. 2 was for quantity adjustments in railroad related work and field related quantity changes at a cost of $34,007.70. Quantity Adjustment No. 3 was for expected, but unknown railroad costs and street light installation expenses at a cost of $540,949.30. Fourteen days were added to the construction contract. The total cost of the construction contract would be $17,681,229.80. Change Order No. 4 /Quantity Adjustment was for revisions to the storm sewer system 1A and revisions to the intersection layout at Forest Creek Blvd. It also added joint restraints for the 16 -inch waterline bore and the addition of a 24 -inch steel casing for a total cost of $114,669.55. Once the project was substantially complete and open to traffic, the City Manager asked about the lack of planned landscaping to portions of the median. Weeds had grown up City of Round Rock Page 1 Printed on 11/12/2013 Agenda Item Summary Continued (13-858) rapidly due to seasonal rain, and were an eyesore on a brand new, expensive arterial road. He asked the department to look into optional treatments to the median that would be cost effective and not create new, additional, ongoing maintenance. Change order #5, addresses this issue as well as some final adjustments to the project that were exposed during the development of the punch list items. The total cost of Change Order No. 5 is $ 77,305.00 with the addition of 28 calendar days to the contract to complete the required work. This change order adds the decomposed granite to the roadway medians, flumes at the MSE walls, and rock filter dams at the outfall channel, revised traffic signalization at Forest Creek Intersection, holding of a utility pole while trenching and the deduct of pavement marking revisions. The total contract price after revisions is $ 17,873,204.35. Cost: $77,305.00 Source of Funds: Round Rock Transportation and Economic Development Corporation Staff recommends approval. City of Round Rock Page 2 Printed on 11/12/2013 EXECUTED ORIGINAL DOCUMEN1S FOLLOW Department Transportation Project Kenney Fort Blvd. (Arterial A) Name City Project TX02ARTA ID Number Justification P'rp_ 1st :, Date: 10:7/2013 Change Order/Quantity Ad,ustment -1"›"' Contract Quantity Adjustment/Change Order No. Add decomposed granite at road medians, and flumes at MSE wall, add RFD's at outfall channel, revise traffic signalizat`.on at Forest creek intersection, hold PEC power pole, deduct fcr pavement mark rg revislcns SUMMARY Original Contract Price: Previous Quantity Adjustment(s). This Quantity Adjustment: Total Quart ty Adjustment(s). Total Contract Pr ce with Quantity Adjustment(s). Prevlcus Change Order(s): This Change Order - Total Change Orders) To Date. Adjusted Contract Price [Orig nal Contract Price Plus Quantity Adjustment(s) Plus Change Order(s)] Difference between Original and Adjusted Contract Prices Original Contract Time: Time Adjustment by previous Quan .Adj./Change Order. Time Adjustment by this Quan Adj./Change Order New Contract Time: Prepared By Chasm Constructors Engineer City of Round Rock Signature Signature Submitted for Approval Amount $17,095,753.80 4129,374.92 $000' (S129.37 97) $16,966,378.88 $829,520.47 $77,305.00 $906,825.47 $17,873,204.35 $777,450.55 730 Calendar Days 28 0 Calendar Days Calendar Days 758 Calendar Days BIlI Stablein, Project Manager, CORR Ap. •vat Change 4.89% 0.46°/a 5.34% )O -I6 -13 Date Charles Glace r.,iip . iden., hasco Constructors Date / TSL f-�� /0//o//3 David Hohman, Engineer, NOR Date .A1 tlA=, .14"13 Alan McGraw, Mayor, C ty of Rounock Date rev. 05/12 Department Transportation Project Name City Project ID Number Kenney Fort Blvd. (Arterial A) TX02ARTA Page 2 of 3 Date: 10/7/2013 Change Order/Quantity Adjustment Contract Quantity Adjustment/Change Order No. 5 Item # Item Description Unit Qty. Unit Price Amount Contract Time Adjustment 1 Concrete flumes at MSE walls * Add 4 ea concrete flumes with rock rip -rap athe ends of MSE walls EA 4.00 $750.00 $3,000.00 0 2 PEC electric pole * Hire subcontractor to clamp on to existing PEC power pole with pole truck during storm sewer installation. LS 1.00 $1,500.00 $1,500.00 3 Rock Filter dams an outfall channel * Install Ty 3 rock filter dams at outfall channel near Brushy creek to dissipate flow LF 36 $50.00 $1,800.00 4 Traffic signalization and illumination * Revise signalization at Kenney Fort and Forest Creek intersection LS 1 $1,855.00 $1,855.00 * Revise light pole foundation due to storm sewer conflict LS 1 $2,650.00 $2,650.00 Subtotal $4,505.00 5 Decomposed Granite medians Install decompesed granite at center medians in roadway LS 1 $67,107.00 $67,107.00 6 Pavement striping Deduct for eliminated turn lanes & hashouts LS 1 -$607.00 ($607.00) TOTALS: $77,305.00 0 1400,5, rev. 05/12 Department Transportation Project Name City Project ID Number Bid Item # Contract Quantity Adjustment/Change Order Kenney Fort Blvd. (Arterial A) TX02ARTA Item Description Unit Qty. Page 3 of 3 Date: 10/7/2013 Change Order/Quantity Adjustment No. Unit Price Amount 5 Contract Time Adjustment TOTALS: $0.00 0 Chasco Constructors JOB NAME: KENNEY FORT BOULEVARD JOB #11104 10/3/2013 GI1ANGt rNvrvDML- ify ii DESCRIPTION QTY UNIT UNIT PRICE TOTAL PRICE $3,000.00 concrete rwmes at MSE outfalls 1 Install concrete flumes with rock rip -rap at outfall of MSE walls 4 EA $750.00 $3,000.00 _ _ _ .. 53.000.00 Concrete flumes at MSE ou PEG electric pole 1 Hire subcontractor with pole truck to clamp on to and hold existing PEC power pole during installation of storm sewer within 5' of pole 1 $150000 $1,500.00 $1,500.00 51.500.00 PEC electric pole Rock filter dams (TY 3) 1 (install rock filter dams in outfall channel Rock filter dams (TY 3) 36 EA 1 $50.00 Traffic signal and illumination changes 1 Rework signalization at Forest Creek intersection 2 Revise light pole foundation to stradle 66" SS line Traffic s gnal and Illumination changes 1 LS 1 LS Decomposed granite medians Remove trurf at island medians and replace with DC granite 1 Decomposed granite medians $1,800.00 $1,800.00 $1,855.00 $1,855.00 $2,650.00 $2,650.00 54,505.00 1 LS $67,107.00 Page 1 of 1 CP #12 Total changes $67,107.00 $67,107.00 $77,912.00 0 O Z �rn ay 0) 0 m 73 O. c N 0 v a (ii 0 !D � rn tD v N :6111 C4 NO CotN O 0 for til N tl1 01 op to ..L ;unowd pig Ieloi ft 133 cn Cil O O OD OD ND CO CD cn 01.p.-0.wwwwwww�0 y �� N o �n 0 �c Z -1 Z 00 0 0 0 0 0 0 0 0 0 0 0 0 J CD O C4 CD O) CD (D CD CD CA 0oowQoCOC0000000CO 0) m W X useal p0p0-D. NNNNNNNO CO -1 Z CO ° 0 N N N N N N N N N N N N r 70 0 0 0 0 0 0 0 0 0 0 0 0 < 0 /11 CCD CD D CD y(Njt.Wt.)0)- vX `♦ r -0 -I --I 13 « « < 03 D mmxmmmmrnmmvr0 vv-n-n02222I0C 0 C) c, 0GOu,cnNcncnGo2r OmG)G)G)0610001 .1/Z (' n Zmc0cIcncncncncocn�� r _,(-) --jj ��jj ; 0 n NG^CNNNNNNN� rD Q Z�C�D 'zzzzz?.� a 71 _�> GI rrrrrill 0c>>9vmvvrnvmvmco D C)-- --000 *.4270 GG7Gin $ �G)Ommm7)� = C D orti �^ 0v D Z Z /1� g 7J Ti 0v z z 0 Co 0 li.1Li Z N ,.< wii Oft 40) 413 Eft 40 Oft 4A c b t0 4ft�3�4ftN sN N CTtN -0 0 ..a�0 ti 000000000000 0 °. J ■ N t77 N O O p C D C7 0 0 0 C D C D 000a00000000 tt, 4g4fl4e r Oft Nft O 40403 �•C7jjN0 •c)00 0 as aaooCD o0 0 00 i N 40' ----•- 4 FT RAD 1 - - -- - R 30 FT 17+43.83 18+08.88 - --LIP OF GUTTER __ 2.35' LT 19' LT �QNC RIPRA�'—\ — LIP OF-GDTT R PROPCLF MATCHPROPCLF 13+83.52 1 150 FT APPROX -i-- MATCH EXISTING 5.80 LT LEF TURN SAY - - - - - -- CURB AND GUTTER.-J- PROPCLF I 4 FT RAD --- - - - - �- ------ 1 —--d- -- -- p �CIfrbF151 00 - —. - 16+89.00 �- 17*54.05 R a 300 FT 15+39.00 LIP OF GUTTER --' -~ of 6.58 RT--- —2.60' 4.23' LT -� , NEW TURNOUT PROPCLF PROPCLF PROPCLF 21 NEW LOCATION FOR ;; ;;1 NEW LOCATION FOR CURB RAMP ;i CURB RAMP R = 35 FT PED POLE FOUNDATION LIP OF GUTTER,, LIP OF GUTTER TO BE REMOVED y,l ;.1 o OTh Z v � E nwei 0 o r m70 „ v a. N.... X 0 Cn II m C1 w 71 w 0. Ft, ▪ O -! 0 0 1.4 CD O V ■ CO z 0 lunowd p!8 Ieoi a`4 NI C O i mO a Eu 3 :1 r N e K mi n Oj el 3 z� W 0 i Fa 3� S oc cy -4zz o � to c -o gr - 0 .1 m v oo '7'I 0 z n 0 1- Z ca --ii W IN 2 O Z 1:6 m G) r 0z c 0 rn 0 o O XI y m 0 Zi n C > M XII C) y ;r1 :4.1 I; 'b mz0 .� �� 3 i De N a 8 �13 II; �o 0 &oet i N 1 )111 ....< 0 0 re - 144.,tmsr 3= g �• rr & soman KENNET FORT BOULEVARD ;o s lt. _ =§N ° :3 101171171-. 14, QQi GO 44 al tai