CM-2018-1777 - 7/13/2018Page I of 3 . . Contract Quantity Adjustment/Change Order rr+,0i 1; Department: Utilities and Environmental Services Project Name: Dry Branch Tributaries Channel Im royements Date: City Project Change Order/Quantity ID Number DRYER Adjustment No. i Vendor Chasco Constructors P.O. Box 1057 Round Rock, TX 78680 512-244-0600 Company Name Address Phone No, Justification 1. Addition of drainage channel at 600 Ray Berglund Boulevard SUMMARY Amount a/o Change Original Contract Price: $1,3za,o52.oa Previous Quantity Adjustment(s): $0.00 Thts Quant;ty Adjustment: $4,446.00 Total Quantity Adjustment(s): $4 946.00 Total Contract Price with Quantity Adjustment(s): $1,332,548.00 Previous Change Order(s): $0.04 0% This Change Order: $44,526.00 4% Total Change Order(s) To Date: $44,526.00 4% Adjusted Contract Price [Original Contract Price Plus Quantity Adjustment(s) Plus Change Order(s)]: $1,382,074.00 Difference between Original and Adjusted Contract Prices: $54,022,00 Original Contract lime: 240 Time Adjustment by previous Quan. Adj./Change Order: 0 Time Adjustment by this Quart. Adj./Change Order: 21 New Contract Time: 261 t �; _ rreparea by: Signature Contractor: Signature City Project Manager: 244 5- re Mayor/city /- ,.,,,,, - d/L/"-%-vy [-/ 77 Federico Sanche?,_trqject Manager, CORR _ 612W18 Printed Name, Title, Company �._ Date .- dwro Printed Name, Tide, Company Date Printed Name, We Dam 7 -7-/3-4 Printed Name, Title Date Contract Quantity Adjustment/Change Order +4w ol! w Project Name: Dry Branch Tributaries Channel improvements Quan. Adj./Change Order No.: Chnnen flrriar nm,= Page 2 ort Item Item Descri- tion Unit Qtv. 1 Drainage Channel @ 600 Ray Berglund LS 1 Revisions to 5WPPP for the new added channel and for additional staging / access paths outside the orginal LDC 2 requested by Chasco. L5 1 _ Unit price Amount $51,276.00 $51,276.00 -$1,750.00 -$1750.00 0.00 $0.00 $0.00 $0.00 0.00 Contract Time Adjustment .., �i'aa s 21 $0.00 0,00 $0.00 0.00 $0.013 $0.00 $0.013 $0.013 $0.00 $0.00 0.00 - $0.00 $0.00 $0.00 $0.00 0.00 z$49,52G.U91 Page 3 of 3 ++� Contract Quantity Adjustment/Change Order -�f Rawo �apc Project Name: Dry Branch Tributaries Channel Improvements Quan, Adj./Change Order No.: Quantity Ad ustment Data Contract Time Adjustment Bid Item # Item Description Unit Unit Price Amount tnnvei 2 Cannel Excavation CY 164 $20 --ug $ , 80.00 24 Native Seeding SY 1240 $0.90 $1,116.00 $0.00 $0.00 $0.00 $0.00 OO $0.00 $0.00 $0.00 $0.00 — — $0.00 $a. a $0.00 $0.00 $0.00 $0,05 $0.00 0.00 $0.00 $0.0a $0.00 $0.00 0.00 -� $0.00 TOTAR. $4.496.001 City of Round Rock ROUND Rack TEXAS Agenda Item Summary Agenda Number: Title: Consider executing Quantity Adjustment/Change Order No. 1 with Chasco Constructors for the Dry Branch Tributaries Channel Improvements Project. Type: City Manager Item Governing Body: City Manager Approval Agenda Date: 7/13/2018 Dept Director: Michael Thane, Director of Utilities and Environmental Services Cost: $54,022.00 Indexes: 2014 Drainage Revenue Bonds Attachments: LAF.pdf, MAP.pdf, QAICO #1.pdf Department: Utilities and Environmental Services Text of Legislative File CM -2018-1777 The Dry Branch Tributaries Channel Improvements project is located north of Gattis School Road near the Joyce Lane and Ray Berglund Boulevard residential neighborhoods. The Dry Branch Tributaries Channel Improvements project will provide improvements for a portion of Dry Branch and an unnamed tributary to Dry Branch. The project will provide conveyance improvements for flood control and will correct erosion and protect City wastewater infrastructure. This Quantity Adjustment/Change Order No. 1 (QAICO No. 1) is for some additional work that is being added to the project. The City is adding a small drainage channel located at 600 Ray Berglund Boulevard. The City will construct the drainage channel in an effort to alleviate stormwater drainage problems that have been experienced by citizens in the South Creek residential neighborhood north of 600 Ray Berglund Boulevard, QAICO No. 1 includes the cost of labor, additional materials, equipment for the work and revisions to the stormwater pollution prevention plan, as well as adds 21 days to the construction contract. This QAICO No. 1 is for $54,022 which brings the total contract amount to $1,382,074. Cost: $54,022 Source of Funds: 2014 Drainage Revenue Bonds City of Round Rock Page 1 Prinfed on 7/12/2016 Vr'- E_L4ER At ` Jc X71 _YRIpGE ST u , 00- 0 4 a R _ I. zl w. xw c4#Pp4 4 G $I ��k30tlb•J al,", '"'�� .0 {53a�H9cl2! al 0, b4 �Nms ID _ rs _ F S MAYS 5_T 1 M i ykIS amvw f z r'� G C cv �- =�m a Mc55 o _ At ` Jc X71 _YRIpGE ST u , 00- 0 4 a R _ I. zl w. xw c4#Pp4 4 G $I ��k30tlb•J al,", '"'�� .0 {53a�H9cl2! al 0, b4 �Nms ID _ rs _ F S MAYS 5_T 1 M i ykIS amvw f z r'�