R-2018-5636 - 7/26/2018 RESOLUTION NO. R-2018-5636
WHEREAS, the City of Round Rock has previously entered into a Contract for Engineering
Services ("Contract") with Alan Plummer Associates, Inc. for the BCRWWTS East WWTP Expansion
Project, and
WHEREAS, Alan Plummer Associates, Inc. has submitted Supplemental Contract No. 1 to the
Contract to modify the provisions for the scope of services and to increase the compensation, and
WHEREAS, the City Council desires to enter into said Supplemental Contract No. 1 with Alan
Plummer Associates, Inc., Now Therefore
BE IT RESOLVED BY THE COUNCIL OF THE CITY OF ROUND ROCK, TEXAS,
That the Mayor is hereby authorized and directed to execute on behalf of the City Supplemental
Contract No. 1 to the Contract with Alan Plummer Associates, Inc., a copy of same being attached
hereto as Exhibit "A" and incorporated herein for all purposes.
The City Council hereby finds and declares that written notice of the date, hour, place and
subject of the meeting at which this Resolution was adopted was posted and that such meeting was
open to the public as required by law at all times during which this Resolution and the subject matter
hereof were discussed, considered and formally acted upon, all as required by the Open Meetings Act,
Chapter 551, Texas Government Code, as amended.
RESOLVED this 26th day of July, 2018.
/,.
CRAI MON, Mayor
City of Rou Rock, Texas
ATTEST:
SARA L. WHITE, City Clerk
0112.1804;00405356
EXHIBIT
STATE OF TEXAS §
COUNTY OF WILLIAMSON §
SUPPLEMENTAL CONTRACT NO. 1
TO CONTRACT FOR ENGINEERING SERVICES
FIRM: ALAN PLUMMER ASSOCIATES, INC. ("Engineer")
ADDRESS: 6300 La Calma, Suite 400,Austin, TX 78752
PROJECT: BCRWWTS East WWTP Expansion
This Supplemental Contract No. 1 to Contract for Engineering Services is made by and between
the City of Round Rock, Texas, hereinafter called the "City" and Alan Plummer Associates, Inc.,
hereinafter called the "Engineer".
WHEREAS, the City and Engineer executed a Contract for Engineering Services, hereinafter
called the "Contract", on the 10th day of August, 2017 for the BCRWWTS East WWTP
Expansion Project in the amount of$1,662,593.00; and
WHEREAS, it has become necessary to amend the Contract to modify the provisions for the
scope of services and to increase the compensation by$500,000.00 to a total of$2,162,593.00;
NOW THEREFORE, premises considered, the City and the Engineer agree that said Contract
is amended as follows:
I.
Article 2, Engineering Services and Exhibit B, Engineering Services shall be amended as set
forth in the attached Addendum to Exhibit B. Exhibit C, Work Schedule shall be amended as set
forth in the attached Addendum to Exhibit C.
II.
Article 4, Compensation and Exhibit D, Fee Schedule shall be amended by increasing by
$500,000.00 the lump sum amount payable under the Contract for a total of$2,162,593.00, as
shown by the attached Addendum to Exhibit D.
IN WITNESS WHEREOF, the City and the Engineer have executed this Supplemental
Contract in duplicate.
[signature pages follow]
Supplemental Contract Rev.06/16
0199.1730-2;00404214 84275
1
ALAN PLUMMER ASSOCIATES,INC.
By:
Date
Supplemental Contract Rev.06/16
0199.1730-2;00404214 84275
2
CITY OF ROUND ROCK APPROVED AS TO FORM:
By:
Craig Morgan,Mayor Stephan L. Sheets, City Attorney
Date
Supplemental Contract Rev.06/16
0199.1730-2;00404214 84275
3
ADDENDUM TO EXHIBIT B
Engineering Services
Project Understanding
The Brushy Creek Regional East Wastewater Treatment Plant (East Plant) is owned by the
Brushy Creek Regional Wastewater System (BCRWWS)who are the Cities of Round Rock,
Cedar Park, and Austin. The City of Leander currently contracts treatment service from the
plant and plans on becoming an owner with this expansion. The City of Round Rock is the
managing partner for the East Plant Expansion project. The plant is currently operating under a
phase in their permit that allows the treatment and discharge of an annual average flow of 21.5
million gallons per day (MGD) and an average two-hour peak of 52,083 gallons per minute (75
MGD). The effluent quality required for the discharge in the existing TPDES permit is 10
milligrams per liter(mg/L) carbonaceous biochemical oxygen demand (CBOD), 15 mg/L total
suspended solids (TSS), and 2 mg/L ammonia-nitrogen (NH3).
The partner cities are currently experiencing rapid growth within their drainage basins.
Additional treatment capacity will be required to accommodate this growth. The partner cities
retained the Alan Plummer Associates, Inc. (APAI) team to provide Professional Engineering
Services in connection with the expansion of the East Plant. A Preliminary Engineering Phase
was completed in June 2018. Based on the results of that Study, the partners are interested in
proceeding to the Design Phase of an expansion to a capacity of 30 MGD.
The partners have further indicated a desire to use Pre-Selection of equipment during the
Design/Bidding Phase. The use of Pre-Selection provides the designers with a better
understanding of the design requirements for the equipment being installed. Pre-Selection of
equipment can result in a lengthening of the Design Phase as limited design can take place until
the equipment is selected. As the schedule for the completion of the expansion is important to
the partners, the partners have expressed a desire to control the schedule as much as possible.
It is anticipated that the full Design/Bidding Phase Engineering Contract will not be ready until
the October 2018 time-frame.
In order to make the best use of the time before October 2018, the partners requested that a
Supplemental Amendment to the existing contract be prepared so that Pre-Selection and other
activities can be pursued while the full Design/Bidding Engineering contract is being prepared.
Upon authorization of this Supplemental Amendment, the following services will be provided
and then folded into the full Design/Bidding Engineering contract.
SCOPE OF SERVICES
The following scope of services is not intended to be "all inclusive". It is intended to provide a
description of the types of tasks to be undertaken under the Supplemental Amendment. A
comprehensive scope of services for the project will be presented with the Design/Bidding
Phase proposal and the money authorized under this Supplemental Amendment will be
deducted from the approved fee for the Design/Bidding Phase Agreement.
1
TASK 1. EQUIPMENT PRE-SELECTION
Equipment pre-selection task will include development of one equipment pre-selection package,
including front-end documents, technical specifications, and supporting drawings, as well as
bidding assistance. The Equipment Pre-Selection task will include the following
1.1. Identify Equipment for Pre-Selection
Prepare a preliminary list of equipment needed for the project as identified in the Design Basis
Memoranda. Review the equipment needs for the project with the Partners to develop a list of
equipment recommended for pre-selection. Meet with project partners to finalize the list of
equipment.
1.2. Pre-selection Front Ends
Develop front-end documents for one equipment pre-selection package in conjunction with the
Partners for obtaining equipment bids. The front-end documents will identify the method to be
used for equipment selection; low equipment cost versus best value. The benefits of each will be
discussed with the partners in a meeting.
1.3. Pre-selection Specifications
Develop equipment specifications for equipment to be preselected. Develop performance
requirements and information necessary for evaluating bids with Partner's input. Specifications
will identify acceptable manufacturers based on project experience and needs. Up to three
suppliers will be evaluated for each piece of equipment.
1.4. Pre-selection Drawings
Develop supporting drawings for the equipment pre-selection package. Drawings will include
process and instrumentation diagrams as well as site layouts. The drawings are intended to
provide suppliers with information concerning the environment in which their equipment will be
placed and the role that the equipment will play in the overall treatment process.
1.5. Pre-selection Bidding Assistance
1.5.1. Assist the Partners during advertisement for equipment proposals. Respond to
requests for information and prepare addendum items.
1.5.2. Attend pre-bid meeting and proposal evaluation meeting with the Partners.
1.5.3. Perform proposal reviews for conformance to the specifications and contract
documents.
1.5.4. Prepare proposal review summary memorandum and selection recommendation
letters for each equipment item.
Meetings: Pre-selection Workshop 1— Task Kickoff and Package definition; Pre-selection
Workshop 2 — Front Ends; Pre-selection Workshop 3 — Draft Pre-selection Document
Review, Pre-selection Pre-bid meeting, Pre-selection Package Bid Opening.
2
TASK 2. TOPOGRAPHIC SURVEYS
Prepare a topographic survey, which will be used to complete the design of the site plan. The
topographic survey will be based on an on-the-ground survey and will be produced at a one (1)-
foot interval. A point cloud survey will be conducted of existing facilities that require modification.
The results will be incorporated in the engineering construction plans.
Using the survey information, prepare an existing conditions site map to identify above ground
features and utilities that will play a part in the design of the project.
TASK 3. FIELD GEOTECHNICAL SURVEYS
Perform field investigations/testing to determine the existing site conditions and proper methods
of demolition and construction. Provide geotechnical investigation services to characterize the
subsurface soils for the areas affected by the Project. The results shall be formalized in a report
and sealed by a registered professional engineer.
Submit an electronic copy of the report to PARTNERS PROJECT MANAGER. The Geotechnical
Data Report supplied by the Geotechnical sub-consultant will be reviewed and evaluated.
3
ADDENDUM TO EXHIBIT C
Work Schedule
Attached Behind This Page
ATTACHMENT C
SUPPLEMENTAL AMENDMENT SCHEDULE
BRUSHY CREEK EAST WWTP EXPANSION
Aug-18 Sep-18 Oct-18 Nov-18 Dec-18
Task 1 2 3 4 5 1 2 3 4 1 2 31 4 1 2 3 4 5 1 2 3 4
1.1 Identify Equipment for pre-selection
1.2 Pre-Selection front end documents
1.3 Pre-Selection specifications
1.4 Pre-Selection drawings
1.5 Pre-Selection bidding assistance
2.1 Topographic survey
3.1 Geotechnical survey
ADDENDUM TO EXHIBIT D
Fee Schedule
Total Total Other
Task Labor Hours Loaded Labor Cost Direct Costs Subconsultants' TOTALS
Task 1: Equipment Pre-Selection 1,950 $ 307,000 $ 3,000 $ 50,000 $ 360,000
Task 2: Topographic Survey 90 $ 15,000 $ 2,500 $ 60,000 $ 77,500
Task 3: Geotechnical Survey 50 $ 10,000 $ 2,500 $ 50,000 $ 62,500
LUMP SUM TOTAL: 2,090 $ 332,000 1 $ 8,000 $ 160,0001 $ 500,000
L Subconsultant fees will be reconciled in the Design/Bidding Phase.