R-2019-0095 - 2/14/2019 RESOLUTION NO. R-2019-0095
WHEREAS, the City Round Rock ("City") assumed the responsibilities of operating the
Brushy Creek Regional East Wastewater Treatment Plant ("Wastewater Treatment Plant") from
Brazos River Authority on October 1, 2018; and
WHEREAS, the City's operational responsibilities include paying for all goods and services
completed at the Wastewater Treatment Plant; and
WHEREAS, on February 27, 2018, the Brazos River Authority issued a purchase order to
Austin Armature Works,LP to repair a pump used at the Wastewater Treatment Plant; and
WHEREAS, the pump repair was not completed until November 16, 2018, after the City had
taken over operation of the Wastewater Treatment Plant;and
WHEREAS, although the City did not procure the repair, it is responsible for payment of the
obligation, and requests authorization for payment to Austin Armature Works, LP for the repair of the
pump,Now Therefore
BE IT RESOLVED BY THE COUNCIL OF THE CITY OF ROUND ROCK,TEXAS,
That the City Council hereby authorizes payment in the amount of $57,746.70 to Austin
Armature Works, LP for the repair of a pump at the Wastewater Treatment Plant.
The City Council hereby finds and declares that written notice of the date, hour, place and
subject of the meeting at which this Resolution was adopted was posted and that such meeting was
open to the public as required by law at all times during which this Resolution and the subject matter
hereof were discussed, considered and formally acted upon, all as required by the Open Meetings Act,
Chapter 551, Texas Government Code,as amended.
RESOLVED this 14th day of February,2019.
oiiziwz;wainai
_ A
CRAIG ORGA ayor
City of omd R Texas
ATTEST: �`.�-may"_
�vV'VIMY�,LO
SARA L. WHITE, City Clerk
2