CM-2019-0069 - 3/15/2019Contract Quantity Adjustment/Change Order rev, aev�x Department: Transportation Department Project Name: Texas Avenue City Project ID Number lustification Change in Plans - Additional Quantities Used SUMMARY Original Contract Price: Previous Quantity Adjustment(s): This Quantity Adjustment: Total Quantity Adjustment(s): Total Contract Price with Quantity Adjustment(s): Previous Change Order(s): This Change Order: Total Change Order(s) To Date: Adjusted Contract Price (Original Contract Price Plus Quantity Adjustment(s) Pius Change Order(s)]: Difference between Original and Adjusted Contract Prices: Orlg',nal Contract Time: Time Adjustment by previous Quan. Adj./Change Order: Time Adjustment by this Quan. Adj./Change Order; New Contract Time. gy. City Project Manager: Mayor/City Signature ew-,� C9,�� Signature + x w Submitted fbr Approval bm Carrillo. Project Coordinator, Printed Name, Title, Company Approvals Printed Name, Tithe,, Company Printed Name, Title algnalure PrlydW Name, Title 60-2014.0014 Date: 2/28/19 Change Order/Quantity Adjustment No. 1 0 Evans Amount $579,009.20 $14,116.00 $593,125.20 $0.00 $13,200.00 $13,200.00 $606,325.20 $27,316.00 Page i ora % Change 2/28119 Date Date ^1 ! 0.00 0.02 0.02 Page 3 ora Contract Quantity Adjustment/Change Order ' III��Y}DIY. 1e :M6 ProJect Name: Texas Avenue Quan. Ad1./0ange Order No.: Ouantity ed4ucrmnnr nahM Bid Item # Item Description Unit Qty. Unit Price Amount Contract Time Adjustment $0.001 $0.00 1 436 PC CONC Valley - Addt'I Quantities 400439 1 Req. and Install. 5F 789 $8.00 $6,312.002 430-1 Curb and Gutter LF 30 $21.00 $630.001 Subgrade Preparation 5Y 4075 $1.70 $6,927.50 Nigh- Early Concrete YD 17 $14.50 $246.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 14116.00 5 City of Round Rock - ' ROUND ROCK P XA Agenda Item Summary Agenda Number: Title: Consider executing Quantity AdjustmentlChange Order No. 1 with Jimmy Evans Company for the Texas Avenue Project. Type: City Manager Item Governing Body: City Manager Approval Agenda Date: 3/15/2019 Dept Director: Gary Hudder Cost: $27,316.00 Indexes: RR Transportation and Economic Development Corporation (Type B) Attachments: Correct QA-CO#1 w- Jimmy Evans Department: Transportation Department Text of Legislative File CM -2019-0069 This project to improve the neighborhood connectivity of the roadway systems in Round Rock includes Texas Avenue extension from Green Hill to Gregory lane. This is a local street to help improve local commuters and aid in reducing traffic on Old Settlers Boulevard. This Change Order #1 and Quantity Adjustment is for the addition of a footer on the rock Gabion which aided in the stability of the Gabion during the heavy rains that we received during the construction phase. The City also added two type 7 Curb Ramps, two type 10 Curb Ramps, and one valley gutter at Green Hill to provide better drainage and storm water conveyance. The Change Order amount is $13,200.00 and the Quantity Adjustment amount is $14,116.00 for a total of $27,316.00 . Staff recommends approval. Cost: $27,316.00 Source of Funds: Round Rock Transportation and Economic Development Corporation (Type B) City of Round Rack Page 1 Printed on 31412019