CM-2019-0185 - 6/21/2019STATE OF TEXAS §
COUNTY OF WILLIAMSON §
SUPPLEMENTAL CONTRACT NO. 1
TO CONTRACT FOR ENGINEERING SERVICES
FIRM: 2P CONSULTANTS ("Engineer")
ADDRESS: 507 W. Liberty Avenue Round Rock TX 78664
PROJECT: Fire Station 3 - Sundance
This Supplemental Contract No. 1 to Contract for Engineering Services is made by and between
the City of Round Rock, Texas, hereinafter called the "City" and 2P Consultants, hereinafter
called the "Engineer".
WHEREAS, the City and Engineer previously executed a Contract for Engineering Services,
hereinafter called the "Contract" for the Fire Station 3 Sundance Project in the amount of
$49,500.00; and
WHEREAS, it has become necessary to amend the Contract to modify the provisions for the
scope of services and to increase the compensation by $5,000.00 t o a total of $54,500.00;
NOW THEREFORE, premises considered, the City and the Engineer agree that said Contract
is amended as follows:
Article 2, Engineering Services and Exhibit B. Engineering Services shall be amended as set
forth in the attached Addendum to Exhibit B. Exhibit C Work Schedule shall be amended as set
forth in the attached Addendum to Exhibit C.
Article 4,_ Compensation and Exhibit D, Fee Schedule shall be amended by increasing by
$5,000.00 the lump sum amount payable under the Contract for a total of $49,500.00, as shown
by the attached Addendum to Exhibit D.
IN WITNESS WHEREOF, the City and the Engineer have executed this Supplemental
Contract in duplicate.
Supplemental Contract
01421801, 00125325
�i1> 7-
[signature pages follow]
Rev 06 16
81275
2P CONSULTANTS
Date
Supplemental Coniract Rev.06 16
0199 1901, 00425325 84275
CITY OF ROUND ROCK
By: 110! 2 J�
s f &--6 A--"04-
& -2
Date
Supplemental Contract
0199,1801; 00425325
APPROVED AS TO FORM:
Ste han L. Sheets, City Atto ey
Rcv.06.1 G
84"
City of Round Rock
Eire Station No. 3 - Addendum
ADDENDUM TO EXHIBIT "B"
CIVIL ENGINEERING SERVICES
Enclosure CM -2018-1755
Task Item I — Construction Administration
A. Submittal Review
a. Submittal Review
I. 2PC will review the contractor's product submittals for compliance in accordance with the City
of Round Rock's Development Code.
2 2PC will maintain copies of all submittals for delivery to the City upon project closeout.
3. These tasks will in addition to the previously executed tasks for this project.
City of Round Rock
Fire Station No. 3 - Addendum
ADDENDUM TO EXHIBIT "C"
PROJECT SCHEDULE
Enclosure CM -2018-1755
Project schedule will follow approved construction schedule. Submittal review will allow for 3 -
Business days per submittal upon receipt of submittal.
City of Round Rock
Fire Station No. 3 - Addendum
ADDENDUM TO EXHIBIT "D"
FEE SUMMARY
CIVIL ENGINEERING DESIGN SERVICES:
Enclosure CM -2018-1755
I. SUBMITTAL REVIEW.
A. Submittal Review $ 5.000.00
City of Round Rock
I
.OUNEXASDRO Agenda Item Summary
Agenda Number:
Title: Consider a resolution authorizing the Mayor to execute Supplemental
Contract No. 1 with 2P Consultants for the Fire Station No. 3 Project.
Type: City Manager Item
Governing Body: City Manager Approval
Agenda Date: 6/21/2019
Dept Director: Chad McDowell, General Services Director
Cost: $5.000.00
Indexes: 2017 General Obligation Bonds
Attachments: Agreement
Department: General Services Department
Text of Legislative File CM -2019-0185
Supplemental to 2P's Consultants contract to include submittal review for construction of the
new Fire Station #3 project.
Cost. $5,000.00
Source of Funds: 2017 General Obligation Bonds
09y ofRound Rock Page 1 Pdnfed on 6/2!/2019