CM-2019-0244 - 8/16/2019Page 100
Contract Quantity Adjustment/Change Order
Mv, 01 15
Department: Utilities and Environmental Services
Project
Name: _ Kensington Detention Improvements _ Date: V119
City Project Change Order/Quantity
ID Number KENSG Adjustment No. 3
Vendor D&5 Concrete Contractors 515 Sheffield Rd, Seguin TX 78155 830-556-8794
Company Name Address Phone No.
>ltistff kaUon
This Is a quantity adjustment to Bid Item No.SP132 "EMBANKMENT." Additional soil material was used on the north berm due to over excavation or
the subgrade material and placement or flu material In low elevation areas that when: not accounted for in the original bid.
5UMMAKT
Original Contract Prim,
Previous Quantity Adjustment(s):
This Quantity Adjustment:
Total QuantityAdjustment(s):
Total Contract Price with Quantity Adjustment(s):
Previous Change Order(s):
This Change Order:
Total Change Order(s) To Date:
Adjusted Contract Price [Original Contract Price Plus
Quantity Adjustment(s) Plus Change Order(s)):
Difference between Original and Adjusted Contract Prices:
Original Contract Time:
Time Adjustment by Previous Quan. Adj4Change Osier:
Time Adjustment by this Quan. Adj./Change Order.
New Contract Time:
Subra t> d for Approvii
Name, Title, C
Approribs
Amount % Change
¢938,545.25 Cr
$12,600.00
$25,020.00;
$37,620.00
976165.25
$29,100.00 3%
$0.00 0%
$29100.00 3%
F—$1,005,265.251,
$66,720.00
210 Days
34 Days
54 Rain Days + Qty Adj.
298 Days
Date
Contractor.
lobe jy (, I_�I
Te -t Ar D an �,%ItM2 pyfta) O tiS C
v�irfxC Cwryth►�'trS �j 7 i 1 °t
Signature
Printed Name, Title, Company
Date
City Project
Manager
—11
Sanche2 Project Manager
8/7/19
-gribmture 0
Printed Name, The
Date
Mayor/City
tAuerk d�&
/
Manager
Slgnahrre
Printed Name, Tide 21Date
e1q-WIq-a�
Contract Quantity Adjustment/ Change Order
7-M
gnu
rer, 01 16
Project Name: Kensington Detention Improvements
Quan. Adj./Change Order No.:
Change Order Data
Page ? of 3
Contract
Time Adjustment
Item # Item Description Unit Qty. Unit Price Amount Da
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
Page 3 of 3
Contract Quantity Adjustment/ Change Order
reV, Ot 16
Project Name: Kensington Detention Improvements
Quan. Adj./Change Order No.: 3
Ouantitv Adiustment Data
Contract
Time Adjustment
Bid Item # Item Description Unit Qty. Unit Price Amount (Days)
SP132 EMBANKMENT CY 834 $30.00 $25,020.00 21
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
50.00
$0.00
$0.00
$0.00
$0.00
$0.00
TOTALSt ---$25,020.0 21
Kensington Detention Improvements ;,'
00 y{,
y• _ .�«F, •^ -���` Tom' \=
1 ,
°
tet,
}q . !�. ■ � -M. .. QTY r 'y�� '
4 r��
�'35. � `�_ ! ash
LIM
35. 1
35 + f
35
City of Round Rock
IROUND ROCK
:.,% Agenda Item Summary
Agenda Number:
Title: Consider executing Quantity Adjusement/Change Order No. 3 with D&S
Concrete Contractors for the Kensington Detention Improvements Project.
Type: City Manager Item
Governing Body: City Manager Approval
Agenda Date: 8/16/2019
Dept Director: Michael Thane, Utilities and Environmental Services Director
Cost: $25,020.00
Indexes: 2014 Drainage Revenue Bonds
Attachments: CO No. 3.pdf, MAP.pdf
Department: Utilities and Environmental Services
Text of Legislative File CM -2019-0244
The Kensington Detention Improvements project is located just south of Dell Way, adjacent to
Dell's Building No. 1 at 401 Dell Way. The project consists of two in-line detention ponds where
concrete walls are being constructed to form the two ponds. An existing berm is being
renovated to accommodate one of the walls and increase pond capacity.
Quantity Adjustment/Change Order No. 3 includes the additional cost of the earthen
embankment on the North Pond. The quantity adjustment is for additional material that was
used on the construction of the berm due to some additional over excavation of the subgrade
material and placement of additional material on low elevation areas that where not accounted
for in the original bid quantities. Quantity Adjustment/Change Order No. 3 is for $25,020. This
includes the cost of labor and additional materials and equipment for the work. The total
contract amount will be adjusted to $1,005,265.25.
Cost: $25,020
Source of Funds: 2014 Drainage Revenue Bonds
Clry of Round Rock Page f Printed on W1012019