CM-2019-0250 - 8/23/2019I ROUND RUCNi rev, 06/15 Department: Project Name: City Project ID Number Justification Contract Quantity Adjustment/Change Order General Services Luther Peterson Service Center Page I of 3 Date: 8/8/19 Change Order/Quantity Adjustment No. 2 3y line item: OBA #24 Awning Steel Column -added additional concrete and steel column to front awning to resolve cantilver beam deflection; DBA #26 Room 105 Window- owner add to admin office area for visiblility and lighting; OBA #27 Main Building AV/IT- update AV/IT equipment :o match current specifications; OBA #31 Trans Screening Room -owner add two monitors and upgrade to fiber connectivity Original Contract Price: Previous Quantity Adjustment(s): This Quantity Adjustment: Total Quantity Adjustment(s): Total Contract Price with Quantity Adjustment(s): Previous Change Order(s): This Change Order: Total Change Order(s) To Date: Adjusted Contract Price (Original Contract Price Plus Quantity Adjustment(s) Plus Change Order(s)]: Difference between Original and Adjusted Contract Prices: Original Contract Time: Time Adjustment by previous Quan. Adj./Change Order: Time Adjustment by this Quan. Adj./Change Order: New Contract Time: Prepared By: ���z G✓ Signature Contractor: Signature City Project Manager: ffnature f Mayor/City 1 1 _ Al A1,2101 q, 62 ST) Submitted for Approval Richard Will, Construction CORR Amount $15,483,000.00 $0.00 $0.00 $15,483,000.00 $33,471.00 $49,913.00 $83,384.00 $15,566,384.00 405/435 30/30 0/0 435/465 Printed Name, Title, Company Approvals '•+Grv3hq.'o?44i.0 Clic lelM,iJ Robert Manley, Project Manager, Jacobs Printed Name, Title, Company Chad McDowell General Services Director CORR Printed Name, Title Printed Name, Title $83,384.00 Change Date rA*1lit 8/12/2019 Date Date Date 0.00 0.00 0.01 Contract Quantity Adjustment/Change Order e. ROUND HM f( rev, 06/15 Project Name: Luther Peterson Service Center Quan. Adj./Change Order No.: 2 Change Order Data Item Item Description 1 Awning Column SupE UOBA 2Room 105 Window 3Main 4rans Building AV/IT Screening Room wiw$14.924 it Price $13,000 $9,190 $12,799 Amount $13, $9, Page 2 of 3 Contract Time Adjustment (Daus) 0 0 0 0 Luther Peterson Service Center Change Order #2 Summary Date: 8/13/2019 CORR Change Order #2, includes project changes #24, #26, #27, #31 Cost: $49,913.00 Overview: As the project is nearing completion, minor changes are incurring costs. This Change Order represent the larger cost changes not covered by contingency within the construction contract. 1. OBA #24 -Awning Steel Column -added additional concrete and steel column to front awning to resolve cantilever beam deflection. The boxed beam specification for the cantilever beam resulted in deflection unacceptable to Building Construction Division. The cost to add the column support was divided between the Engineer, Contractor, and City of Round Rock. 2. OBA #26 Room 105 Window- owner add to admin office area for visibility and lighting. Original project design included windows from hallway to admin work area. The window was removed early on in the project. During construction owner decided to add window back into project for visibility and lighting into admin work area. 3. OBA #27 Main Building AV/IT- update AV/IT equipment to match current specifications. Since the start of the project, AV/IT industry has released new products. This change updates to current industry standards and CORR specifications. 4. OBA #31 Trans Screening Room -owner add two monitors and upgrade to fiber connectivity. Since the beginning of the projects, updates the current Transportation Traffic Control Room have occurred. This change updates the equipment and network to most current standards. Contingency Reserve (not encumbered in contract) Original $346,161.74 Betterment (encumbered in contract) Original $355,329.00 Remaining to Date (not including Change Order) $132,690.74 Remaining to Date J+tS July 22, 2019 212 Commence Blvd Round Rock, Texas 78664 RE: Project CoRR Luther Peterson Service Center — Change Order No. 24 Background The new Luther Peterson Service Center Complex will consolidate Round Rock's Utilities and Environmental Services, Transportation, and General Services Departments within one facility. Phase 1 of the project includes design of 30,000 square feet of building structures and 20,000 square feet of premanufactured buildings on 8.96 acres of sheds, open storage, and heavy truck parking situated on approximately 12 acres of land in north east Round Rock. During the project various changes to the project will be required. They will include City, and Contractor generated items. These items will generally modify functional considerations, add or delete materials and systems, and clarify design intent. Purpose The purpose of this change order is to add or modify items to the project scope requirements. Detailed information on each item is included in the item descriptions. Justification This change order is necessary to formally incorporate the recommended scope of work modifications into the construction contract. More detailed information on each item is included in the item descriptions. Cost The total cost for adding or deleting labor and/or materials are summarized below. The complete cost breakdown is included on the attached pricing proposals. Summary of Change Order Costs Item No. 1: RFP No. 44 Purpose: Addition of Column and Pier for the Overhanging Area C Canopy. Justification: Per the Owner's request please provide additional column for the overhang Area C Canopy Description: Please refer to RFI 127 Total Cost: $ 13,000.00 Time There is no change in contract time. The above and foregoing is hereby reviewed this 22nd day of July, 2019 and the undersigned agree to perform the work at the price indicated. ATTEST: Secretary Lee Lewis Construction, Inc. President The prices shown for Change Order No. 24 were established by negotiation and appear fair and reasonable. Roberf C. Manley Project Architect Lee Lewis Construction, Inc. DALLAS I LUBBOCK I AUSTIN July 16,2019 Mr. Ali Mojdehi Jacobs Engineering RE: CORR Luther Peterson Service Center- F8Z94300 Owner Change Order Request #024- Column at Area C Canopy Ali - Please find the attached pricing and support documentation comprising the above-mentioned change order request. This request reflects the added Column and Pier for the Overhanging Area C Canopy.The quantities and areas of the noted material are outlined in the attached documents as per the agreed upon amount to be paid by the Owner. Included herewith is a detailed breakdown of costs associated with this work, quantity take -off, quotation, and back up documentation. The total cost of this change is to be Thirteen Thousand Dollars and 00/100($13,000.00) to be added as change order to the project total. Please issue a formal change at your earliest convenience if approved. Best Regards, Z)W0 0094" Drew Gregston Project Manager — Lee Lewis Construction, Inc. Att: Change Order Request #024 — Cost Summary Change Order Request #024 — Cost Detail Absolute Roofing Price Quote Cc: Matt Vitek — Lee Lewis Construction, Inc. Lee Lewis Construction, Inc. DALLAS I LUBBOCK I AUSTIN Owner Change Order Request # 24 CORR Luhter Peterson Service Center Round Rock, Texas Quote By: Drew Gre ston - Lee Lewis Construction, Inc, LLCI Job # DATE: REV.: 6/6/2019 SUMMARY: Owner Betterment Adjustment #024 -Added Column at Area C Canopy ITEM DaONQTyUNIT 1 GENERAL COND00 2 SITEWORK00 3 CONCRETE00 4 MASONRY00 5 METALS0 6 WOOD & PLASTI0 7 THERMAL & MOI0 DOORS & WINDO0 9 FINISHES 10 SPECIALTIES 11 EQUIPMENT 12 FURNISHINGS 13 SPECIAL CONSTRUCTION 14 CONVEYING SYSTEMS 15 MECHANICAL 16 ELECTRICAL SUBTOTAL SUB WORK 1.00 1.00 1.00 1.00 1.00 1.00 1.0011 1.001 LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS 1 LABOR U.P. 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 TOTAL 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 EQUIPMENT/MATERIAL SUBCONTR. U.P. TOTAL TOTAL 0.00 0.00 0 0.00 0.00 0 3891.00 3,891.00 0 0.00 0.00 0 9109.00 9,109.00 0 0.00 0.00 0 0.00 0.00 08 0.00 0.00 0 0.00 0.00 0 0.00 0.00 0 0.00 0.00 0 0.00 0.00 0 0.00 0.00 0 0.00 0.00 0 0.00 0.00 0 0.00 0.00 0 13,000.00 0 TOTAL 0 0 3,891 0 9,109 0 0 0 0 0 0 0 0 0 0 13,000 NOTES: 1. The Contract Time will extend 0 days to incorporate above changes. 3UB-TOTALS ALL WORK OVERHEAD@ l0%SUB 0 13,000 0%-13,000SUB PROFIT @ 5% LEE LEWIS CONSTRUCTION. INC OVERHEAD & PROFIT @ 15% LEE LEWIS CONSTRUCTION, INC BOND PREMIUM @ 1% 0 0 0 0 0 TOTAL COST $13.000 ®Lee Lewis Construction, Inc DALLAS I LUBBOCK I AUSTIN Owner Betterment Adjustment #024 -Added Column at Area C Canopy Cost Detail Description General Conditions( Supervision, Clean Up, Dumpster) Added Steel Column Added Pier for Colmn Change Subtotal Subcontractor Overhead (10%) & Profit (5%) Contractor Overhead & Profit (15%) Bond Premium (included in OH&P) Subcontractor Amount LLCI $ _ Southern Steel $ 9,109 CJs Concrete $ 3,891 $ 13,000 included above Lee Lewis Construction, Inc. $ _ Lee Lewis Construction, Inc. $ - TOTAL $ 13,000 Requested Time Extension: 0 days Page 2 W�B April 25, 2019 212 Commence Blvd Round Rock, Texas 78664 RE: Project CoRR Luther Peterson Service Center — Change Order No. 26 Background The new Luther Peterson Service Center Complex will consolidate Round Rock's Utilities and Environmental Services, Transportation, and General Services Departments within one facility. Phase 1 of the project includes design of 30,000 square feet of building structures and 20,000 square feet of premanufactured buildings on 8.96 acres of sheds, open storage, and heavy truck parking situated on approximately 12 acres of land in north east Round Rock. During the project various changes to the project will be required. They will include City, and Contractor generated items. These items will generally modify functional considerations, add or delete materials and systems, and clarify design intent. Purpose The purpose of this change order is to add or modify items to the project scope requirements. Detailed information on each item is included in the item descriptions. Justification This change order is necessary to formally incorporate the recommended scope of work modifications into the construction contract. More detailed information on each item is included in the item descriptions. Cost The total cost for adding or deleting labor and/or materials are summarized below. The complete cost breakdown is included on the attached pricing proposals. Summary of Change Order Costs Item No. 1: RFP No. 43 Purpose: Add an Interior Window to the North Wall in Room 105 Justification: Owner's Request Description: Install the Window as shown on RFI 130 Total Cost: $ 9,190.00 Time There is no change in contract time. The above and foregoing is hereby reviewed this 25th day of April, 2019 and the undersigned agree to perform the work at the price indicated. ATTEST: Secretary Lee Lewis Construction, Inc. President The prices shown for Change Order No. 6 were established by negotiation and appear fair and reasonable. 1i �-� Robert C. Manley Project Architect Lee Lewis Construction, Inc. DALLAS I LUBBOCK I AUSTIN June 6,2019 Mr. Ali Mojdehi Jacobs Engineering RE: CORR Luther Peterson Service Center- F8Z94300 Owner Change Order Request #026- Room 105 Window Ali - Please find the attached pricing and support documentation comprising the above-mentioned change order request. This request reflects the added Interior Window to Room 105 North Wall.The quantities and areas of the noted material are outlined in the attached documents as per the agreed upon amount to be paid by the Owner. Included herewith is a detailed breakdown of costs associated with this work, quantity take -off, quotation, and back up documentation. The total cost of this change is to be Nine Thousand One Hundred and Ninety Dollars and 00/100 ($9,190.09) to be added as change order to the project total. Please issue a formal change at your earliest convenience if approved. Best Regards, Vwo 41110.1A Drew Gregston Project Manager — Lee Lewis Construction, Inc. Aft: Change Order Request #026 — Cost Summary Change Order Request #026 — Cost Detail Bell Glass Price Quote Hidell Price Quote TCM Price Quote Cc: Matt Vitek — Lee Lewis Construction, Inc. M Lee Lewis Construction Inc DALLAS LUBBOCK AUSTIN Owner Change Order Request # Y6 CORR Luhter Peterson Service Center Round Rock, Texas LLCI Job # 1835 DATE: 6/19/2019 Quote By. Drew Gregston - Lee Lewis Construction, Inc. REV.: SUMMARY: Owner Betterment Adjustment #026 -Room 105 Window Add LABOR EQUIPMENT/MATERIAL SUBCONTR, ITEM DESCRIPTION QTY UNIT U.P. TOTAL U.P. TOTAL TOTAL TOTAL 1 GENERAL CONDITIONS 1.00 LS 0.00 1 0.00 0.00 0.00 0 p 2 SITEWORK 1.00 LS 0.00 0.00 0.00 0.00 0 p 3 CONCRETE 1.00 LS 0.00 0.00 0.00 0.00 0 0 4 MASONRY 1.00 LS 0.00 0.00 0.00 0.00 0 p 5 METALS 1.00 LS 0.00 0.00 0.00 0.00 0 0 6 WOOD & PLASTICS 1.00 LS 0.00 0.00 0.00 0.00 0 0 7 THERMAL & MOISTURE PROT. 1.00 El LS 0.00 0.00 0.00 0.00 0 0 8 DOORS & WINDOWS 1.00 LS 0.00 0.00 1450.00 1,450.00 0 1,450 9 FINISHES 1.00 LS 0.00 0.00 6380.00 6,380.00 0 6,380 10 SPECIALTIES 1.00 LS 0.00 0.00 922.00 922.00 0 922 11 EQUIPMENT 1.00 LS 0.00 0.00 0.00 0.00 0 0 12 FURNISHINGS 1.00 LS 0.00 0.00 0.00 0.00 0 0 13 SPECIAL CONSTRUCTION 1.00 LS 0.00 0.00 0.00 0.00 0 14 CONVEYING SYSTEMS 1.00 LS 0.00 0.00 0.00 0.00 0 0 15 MECHANICAL 1.00 LS 0.00 0.00 0.00 0.00 0 p 0 16 ELECTRICAL 1.00 LS 0.00 0.00 0.00 0.00 0 p SUBTOTAL SUB WORK 0.00 8,752.00 0 8,752 NOTES: 1. The Contract Time will extend 0 days to incorporate above changes. SUB -TOTALS ALL WORK SUB OVERHEAD @ 10% 0 8,752 01 8,752 SUB PROFIT @ 5% ncluded above LEE LEWIS CONSTRUCTION, INC. OVERHEAD & PROFIT @ 5% 0 0 0 ncluded above LEE LEWIS CONSTRUCTION, INC. BOND PREMIUM @ 1% 0 438 0 included in OH&P TOTAL COST $9,190 ®Lee Lewis Construction, Inc. DALLAS I LUBBOCK I AUSTIN Owner Betterment Adjustment #026 -Room 105 Window Add Cost Detail Description New Window Frame Re work of Sheet Rock and Framing Glass for Window Change Subtotal Subcontractor Overhead (10%) & Profit (5%) Contractor Overhead & Profit (15%) Bond Premium (included in OH&P) Subcontractor Hidell TCM Bell Glass Lee Lewis Construction, Inc. Lee Lewis Construction, Inc. TOTAL Requested Time Extension: 0 days Page 2 Amount $ 1,450 $ 6,380 $ 922 $ 8,752 included above $ 438 $ 9,190 4801 Roy J Smith Dr * Killeen TX, 76543 Ph (254) 699-1900 Date 6/13/2019 CHANGE ORDER Contractor Lee Lewis Construction Austin Address 8303 N Mopac Expressway, Ste. A215 City Austin State TX Zip 78759 PO Box PO Zip Phone (512) 369-3921 Fax (512) 369-3928 Project No. 6482 Name Luther Peterson Service Center Address 3400 Sunrise Road city Round Rock State Tx Zip 78664 Add 1/4" clear tempered to room 105 per RFI 130 Materials Shop Labor Field Labor Miscellaneous Sub Total Overhead Profit Bond Tax Pay App: Total Contractor's Number Change Order Number 6482-003 Line Items $576.00 mh X 4 mh X $65.00 $260.00 $836.00 5% $41.80 5% $43.89 $921.69 Amount Of This Change Order $921.69 qAc cepted Please sign and return as soon as possible. Approved By: Date: Hidell firic dec-c,r-rili ' !`I :.rtiv5.car- 327 Cole St. Dallas, Texas 75207 Phone: 214-528-0331 / Fax 214-559-0425 CHANGE ORDER #06 June 18, 2019 RP Hidell Job #: HH17777 Attn: Drew Gregston Project: CoRR Luther Peterson Lee Lewis Construction, Inc Location: 3400 Sunrise Road 512-369-3921 Round Rock, TX The following is our scope and price for providing the following material on the above referenced project. Hollow metal borrowed lite at room 105. Total including freight: $1,450.00 See attached for break down. NOTES / QUALIFICATIONS / EXCLUSIONS GENFRAI OIIAIIFI ATIONS 1. Formal change order to be received from contractor. Unless otherw,se noted, we exclude, cartoning, insect screens, wire mesh, glass, glazing, installation, steel lintels, steel channels, sub bucks, ceiling struts, wood frames, mortar, grout, louvers in frames, bituminous coatings, lead for lead lined frames, signage, cabinet locks, aluminum door hardware, material/hardware storage, on site lockers, or containers. This quotation is valid for a period of 30 days, and 's subject to our standard terms and conditions of sale, attachment "A' hereto, which includes payment terms of Net 30 without retention, subject to the approval of our Cred t department. vvnere rife puce or rnarenam, equipment or energy rncredses siynn cantly uunny rife term of rife con;rdcr rruouyn nu tau« or nweu rraruware, we reserve rile nynr ru equitably adjust the contract tota by change order. A significant price increase means a change in price from the date of the contract execution to the date of performance by an amount exceed ng I've percent (5%). Such price increase sha" be documented by vendor quotes, invoices, catalogs, receipts or other documents of commercial use. We thank you for the opportunity to offer our quote on this project, and if further assistance is required, please do not hesitate to contact this office. Upon acceptance, olease Sion one coov of this or000sal and return to us. Respectfully submitted, Hidell Hardware Co. Pa,ft& i7 ACCEPTANCE: Signed: Patty Robinson Title: General Manager Date: PO Box 270249 Austin, TX 78727 512.712.4091 (office) 512.362.8776 (fax) Change Order 14 ATTN: Drew Gregston BUILDER: Lee Lewis PROJECT: Luther Peterson Service Center SUBJECT: RFI 130 This change order includes all labor, materials, and equipment to complete the project under the following conditions: Change Order Total: $ 6,380 SCOPE & We will provide material and labor to do the following work at the above -referenced job: Qualifications: Inclusions: Demo AM wall at Corridor C5 & Room 105. Re -frame wall with 18 gauge studs, bracing, and opening for 4'x24' HM window. " Add 18 gauge box beam header at HM window opening. Install 4'x 24' HM window frame. Excludes installation of glass. TCM Enterprises - Texas By signing below, builder accepts this Change Order. Jowan mag 6/12/19 By: Brian Kiddy Date brian tcmenterorises net By: Date JACOBSS July 31, 2019 212 Commence Blvd Round Rock, Texas 78664 RE: Project CoRR Luther Peterson Service Center — Change Order No. 27 Background The new Luther Peterson Service Center Complex will consolidate Round Rock's Utilities and Environmental Services, Transportation, and General Services Departments within one facility. Phase 1 of the project includes design of 30,000 square feet of building structures and 20,000 square feet of premanufactured buildings on 8.96 acres of sheds, open storage, and heavy truck parking situated on approximately 12 acres of land in north east Round Rock. During the project various changes to the project will be required. They will include City, and Contractor generated items. These items will generally modify functional considerations, add or delete materials and systems, and clarify design intent. Purpose The purpose of this change order is to add or modify items to the project scope requirements. Detailed information on each item is included in the item descriptions. Justification This change order is necessary to formally incorporate the recommended scope of work modifications into the construction contract. More detailed information on each item is included in the item descriptions. Cost The total cost for adding or deleting labor and/or materials are summarized below. The complete cost breakdown is included on the attached pricing proposals. Summary of Change Order Costs Item No. 1: RFP No. 44 Purpose: Add AV equipment and cabling for respective AV changes. Justification: Owner's Request Description: Add AV equipment over IP transmitters and receivers; replace the NEC Monitors; replace the LogicTech video conference package; and add respective cabling: Provide and install twenty additional CAT 6 network cables between 2nd floor TR Room C1 OA and the A/V cabinet within room A110. Provide and install two 24 port patch panels for cable terminations within network racks / cabinet in each room. Test and label each cable. Total Cost: $ 12,799.00 Time There is no change in contract time. The above and foregoing is hereby reviewed this 31st day of July, 2019 and the undersigned agree to perform the work at the price indicated. ATTEST: Secretary Lee Lewis Construction, Inc. President The prices shown for Change Order No. 6 were established by negotiation and appear fair and reasonable. Ro rt . Manle Project Architect Lee Lewis Construction, Inc. DALLAS I LUBBOCK I AUSTIN July 31,2019 Mr. Ali Mojdehi Jacobs Engineering RE: CORR Luther Peterson Service Center- F8Z94300 Owner Change Order Request #027- AV Changes Ali - Please find the attached pricing and support documentation comprising the above-mentioned change order request. This request reflects the added Audio Visual Equipment Changes by the City IT Department, quantities and areas of the noted material are outlined in the attached documents as per the agreed upon amount to be paid by the Owner. Included herewith is a detailed breakdown of costs associated with this work, quantity take -off, quotation, and back up documentation. The total cost of this change is to be Twelve Thousand Seven Hundred and Ninety Nine Dollars and 00/10,0 ($12,799.00) to be added as change order to the project total, Please issue a formal change at your earliest convenience if approved. Best Regards, DWO Drew Gregston Project Manager — Lee Lewis Construction, Inc. Aft: Change Order Request #027 — Cost Summary Change Order Request #027 — Cost Detail Black Box Price Quote Austin Structured Cabling Price Quote Cc: Matt Vitek — Lee Lewis Construction, Inc. ®Lee Lewis Construction Inc DALLAS LUBBOCK AUSTIN Owner Change Order Request # 27 CORR Luhter Peterson Service Center Round Rock, Texas LLC/ Job # 1835 DATE 7/3112019 Quote By: Drew Gregston - Lee Lewis Construction, Inc. REV.: n SUMMARY: Owner Betterment Adjustment #027 -AV Changes ITEM LABOR EQUIPMENT/MATERIAL SUBCONTR. DESCRIPTION QTY UNIT U.P. TOTAL U.P. TOTAL TOTAL TOTAL 1 GENERAL CONDITIONS 1.00 LS 0.00 0.00 0.00 0.00 0 p 2 SITEWORK 1.00 LS 0.00 0.00 0.00 0.00 0 0 3 CONCRETE 1.00 LS 0.00 0.00 0.00 0.00 0 p 4 MASONRY 1.00 LS 0.00 0.00 0.00 0.00 0 p 5 METALS 1.00 LS 0.00 0.00 0.00 0.00 0 0 6 WOOD & PLASTICS 1.00 LS 0.00 0.00 0.00 0.00 0 0 7 THERMAL & MOISTURE PROT, 1.00 LS 0.00 0.00 0.00 0.00 0 p 8 DOORS & WINDOWS 1.00 LS 0.00 0.00 0.00 0.00 0 0 9 FINISHES 1.00 LS 0.00 0.00 0.00 0.00 0 p 10 SPECIALTIES 1.00 LS 0.00 0.00 0.00 0.00 0 0 11 EQUIPMENT 1.00 LS 0.00 0.00 9960.00 9,960.00 0 9,960 12 FURNISHINGS 1.00 LS0.00 0.00 0.00 0.00 0 0 13 SPECIAL CONSTRUCTION 1.00 LS 0.00 0.00 0.00 0.00 0 p 14 CONVEYING SYSTEMS 1.00 LS 0.00 0.00 1 0.00 000 0 p 15 MECHANICAL 1.00 LS 0.00 0.00 0.00 0.00 0 p 16 ELECTRICAL SUBTOTAL SUB WORK 1.001 LS 0.00 0.00 2839.00 2,839.00 0 2,839 0.00 12,799.00 0 12,799 NOTES: 1. The Contract Time will extend 0 days to incorporate above changes. SUB -TOTALS ALL WORK 0 SUB OVERHEAD @ 10% 12,799 0 12,799 included above SUB PROFIT @ 5°!° LEE LEWIS CONSTRUCTION, INC. OVERHEAD & PROFIT @ 5"10 0 0 0 included above LEE LEWIS CONSTRUCTION, INC. BOND PREMIUM @ I% 0 0 0 included in OH&P TOTAL COST $12,799 rpLee Lewis Construction, Inc DALLAS I LUBBOCK I AUSTIN Owner Betterment Adjustment #027 -AV Changes Cost Detail Description Subcontractor Amount AV Equipment Black Box $ 9,960 Cabling Additons for AV Changes Austin Structured Cabling $ 2,839 Change Subtotal $ 12,799 Subcontractor Overhead (10%) & Profit (5%) included above Contractor Overhead & Profit (15%) Lee Lewis Construction, Inc. $ Bond Premium (included in OH&P) Lee Lewis Construction, Inc. $ TOTAL $ 12,799 Requested Time Extension: 0 days Page 2 AUSTIN STRUCTURED CABLING Austin Structured Cabling LLC 4703 Pinehurst Drive S Austin, Texas 78747-1421 Name / Address Lee Lewis Construction Drew Gregston 8303 N. MoPac Suite A215 Austin Texas 78759 Description Quote Date �Quote 7/23/2019 1971 DIR-TSO-4358 Project Change Order #I - Provide and install twenty (20) additional CAT 6 network cables between 2nd floor TR Room C 1 OA and the AN cabinet within room Al 10 at the new Luther Peterson Service Center in Round Rock, Texas. Provide and install two 24 port patch panels for cable tenninations within network racks / cabinet in each room. Test and label each cable. ** Labor** ** Materials ** j Subtotal Sales Tax (0.0%) Qty Rate Total 0.00 O.00T Total E-mail 512-448-9555 jleblanc@austinstructuredcabling.com $0.00 $2,838.75 BLACK BOX Date: Jun 18, 2019 Opportunity #: 100690 To: Lee Lewis Construction 7810 Orlando Ave Lubbock, Texas 79423 2535 Brockton Drive Suite 400 Austin, Texas 78758 (512) 837-4400 Account Manager Sales Engineer e -Mail: Bob Cotton Chris Timothy Phone: 806-797-8400 512-719-6619 832-435-2024 Fax: b�Cptt hfackttox.rom nhric timoth yC blackbox com Project: Luther Peterson Service Center AV Systems - Change Order 2 Scope of Work - Add some Additional AV over IP transmitters and Receivers in the following areas. Receivers Lobby Monitor #1 Lobby Monitor #2 Large Conference Room Warehouse Lobby Monitor Outside Utilities Control Room Transmitters (2) located in the IDF that connect to (2) Digital Sign Players - Replace the NEC 90" HD Monitors with NEC 86" UHD 4K monitors Upgrade the infrastructure in Conference Room 100A and one of the Standard conference rooms to have a 4K input at the table. - Replace the (2) Logictech Group 960-001054 systems with (2) Logictech Rally Plus 960-001225 Systems. Material Lica Qty Manufacturer Model # Description Price Extended ADD AV OVER IP TRANSMITTERS AND RECEIVERS 5 Crestron DM-NVX-351 - Rece DigitalMedia 41<60 4:4:4 HDR Network AV iver Encoder/Decoder $1,330.00 $6,650.00 2 Crestron DM-NVX-351 - Tran DigitalMedia 41<60 4:4:4 HDR Network AV $1,330.00 $2,660.00 smitter Encoder/Decoder REPLACE THE NEC E905 MONITORS -5 NEC E905 90" High -Performance LED Backlit Commercial -Grade Display w/ Integrated Speakers $7,300.00 -$36,500.00 Limited Warranty: 3 Years parts and Labor including backlight Luther Peterson Service Center AV Systems - Change Order 2 Proprietary and Confidential Black Box Date: Jun 18, 2019 To: Lee Lewis Construction Project: Luther Peterson Service Center AV Systems - Change Order 2 Qty I Manufacturer Model # I Description Price Extended 5 NEC V864Q 86" UHD 4K High -Performance Monitor with Internal $6,800.00 $34,000.00 Speakers Limited Warranty: 3 Years parts and Labor including backlight -2 Crestron HD -MD -400 -C -E HD Scaling Auto-Switcher & Extender 400 $600.00 -$1,200.00 2 Crestron HD-EXT3-C-B_SYS 4K HDMI over HDBaseT Extender w/IR & RS -232, $730.00 $1,460.00 TEM Black; includes HD-RX3-C-B and HD-TX3-C-B REPLACE THE LOGICTECH VIDEO CONFERENCE PACKAGE -2 Logitech 960-001054 Group Videoconferenceing System $1,240.00 -$2,480.00 - Full HD Video Camera - High Quality Duplex Speaker Phone - Wireless Remote Control 2 Logitech 960-001225 Rally Plus Group Videoconferenceing System $2,685.00 $5,370.00 Full HD Video Camera - High Quality Duplex Speaker Phone - Wireless Remote Control Job Site tsde-Rtes City of Round Rock 3400 Sunrise Road Round Rock, Texas 78664 Materials: $9,960.00 Labor: $0.00 Expenses: $0.00 Shipping: $0.00 Quote Total: $9,960.00 + Sales Tax if applicable Luther Peterson Service Center AV Systems - Change Order 2 Proprietary and Confidential Black Box Material due upon Delivery - Net 30. Labor - Monthly Progress Billing based on percentage of work completed - Net 30. You hereby consent to the incorporation of the applicable terms and conditions, applicable software licenses and service plan(s) posted at: http-cJ/www.blackbox.com/us/about-usLterms-conditions-of-sale To initiate this request Black Box Network Services requires a signed Statement of Work to be followed up with an authorized Purchase Order. Please include the following business entity and address information on the Purchase Order: Norstan Communications, Inc, d/b/a Black Box Network Services Address: 2535 Brockton Drive, Suite 400, Austin, Acceptance The above prices, specifications and conditions are satisfactory and are hereby accepted. Black Box Network Services CUSTOMER ACCEPTANCE: Authorized Signature Name NORSTAN COMMUNICATIONS, INC. d/b/a BLACK BOX NETWORK SERVICES ACCEPTANCE: Authorized Signature Luther Peterson Service Center AV Systems - Change Order 2 Name Title Title Proprietary and Confidential Black Box JACOBS' July 31, 2019 212 Commence Blvd Round Rock, Texas 78664 RE: Project CoRR Luther Peterson Service Center — Change Order No. 31 Background The new Luther Peterson Service Center Complex will consolidate Round Rock's Utilities and Environmental Services, Transportation, and General Services Departments within one facility. Phase 1 of the project includes design of 30,000 square feet of building structures and 20,000 square feet of premanufactured buildings on 8.96 acres of sheds, open storage, and heavy truck parking situated on approximately 12 acres of land in north east Round Rock. During the project various changes to the project will be required. They will include City, and Contractor generated items. These items will generally modify functional considerations, add or delete materials and systems, and clarify design intent. Purpose The purpose of this change order is to add or modify items to the project scope requirements. Detailed information on each item is included in the item descriptions. Justification This change order is necessary to formally incorporate the recommended scope of work modifications into the construction contract. More detailed information on each item is included in the item descriptions. Cost The total cost for adding or deleting labor and/or materials are summarized below. The complete cost breakdown is included on the attached pricing proposals. Summary of Change Order Costs Item No. 1: RFP No. 46 Purpose: Modify Screen Wall AV systems in Transportation Screening Room 100B Justification: Owner's Request Description: Install video wall monitors, HDMI transmitters and receivers, HDMI cables, pair cable and mounting hardware. Wire monitors back to Room C10A with a fiber optic cable between the second floor and Screening room. Provide and install a fiber optic adapter panel for existing fiber optic enclosure in TR Room C1 OA. Connect fiber optic cable to panel and label. Total Cost: $ 14,924.00 Time There is no change in contract time. The above and foregoing is hereby reviewed this 31st day of July, 2019 and the undersigned agree to perform the work at the price indicated. ATTEST: Secretary Lee Lewis Construction, Inc. President The prices shown for Change Order No. 6 were established by negotiation and appear fair and reasonable. Lee Lewis Construction, Inc. DALLAS I LUBBOCK I AUSTIN July 31,2019 Mr. Ali Mojdehi Jacobs Engineering RE: CORR Luther Peterson Service Center- F8Z94300 Owner Change Order Request #031- Screening Room Ali - Please find the attached pricing and support documentation comprising the above-mentioned change order request. This request reflects the changes to the Screening Room AV Systems. The quantities and areas of the noted material are outlined in the attached documents as per the agreed upon amount to be paid by the Owner. Included herewith is a detailed breakdown of costs associated with this work, quantity take -off, quotation, and back up documentation. The total cost of this change is to be Fourteen Thousand Nine Hundred and Twenty Four Dollars and 001100 ($14,924.00) to be added as change order to the project total. Please issue a formal change at your earliest convenience if approved. Best Regards, Do Drew Gregston Project Manager — Lee Lewis Construction, Inc. Aft: Change Order Request #031 — Cost Summary Change Order Request #031 — Cost Detail Black Box Price Quote Austin Structured Cabling Price Quote Cc: Matt Vitek — Lee Lewis Construction, Inc. ®Lee Lewis Construction, Inc. DALLAS I LUBBOCK I AUSTIN Owner Change Order Request # 31 CORR Luhter Peterson Service Center Round Rock, Texas LLCI Job # DATE: 1835 7/31/2019 Quote By: Drew Gregston - Lee Lewis Construction, Inc. REV.: 0 SUMMARY: Owner Betterment Adjustment #031 -Screening Room ITEM DESCRIPTION 1 GENERAL CONDITIONS 2 SITEWORK 3 CONCRETE 4 MASONRY 5 METALS 6 WOOD & PLASTICS 7 THERMAL & MOISTURE PROT 8 DOORS & WINDOWS 9 IFINISHES 10 ISPECIALTIES 11 EQUIPMENT 12 FURNISHINGS 13 SPECIAL CONSTRUCTION 14 CONVEYING SYSTEMS 15 MECHANICAL 16 ELECTRICAL SUBTOTAL SUB WORK QTY 1.00 1.00 1.00 1.001 1.0101 1.001 1.001 1001 1.001 1.00 1.00 1.00 1.00 1.00 1.00 1.00 UNIT LS LS LS LS LS 1 LS LS LS LS LS LS LS LS LS LS LS LABOR U.P. 1000.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 TOTAL 1,000.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Ho 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,000.00 EQUIPMENT/MATERIAL SUBCONTR. U.P. TOTAL TOTAL 0.00 0.00 0 0.00 0.00 0 0.00 0.00 0 0.00 0.00 0 0.00 0.00 0 0.00 0.00 0 0.00 0.00 0 0.00 0.00 0 0.00 0.00 0 0.00 0.00 0 0.00 0.00 0 0.00 0.00 0 11644.00 11,644.00 0 0.00 0.00 0 0.00 0.00 0 1680.00 1,680.00 0 13,324.00 0 TOTAL 1,000 0 0 0 0 0 0 0 0 0 0 0 11,644 0 0 1,680 14,324 NOTES: 1. The Contract Time will extend 0 days to incorporate above changes. SUB -TOTALS ALL WORK SUB OVERHEAD @ 10% SUB PROFIT @ 5% LEE LEWIS CONSTRUCTION, INC. OVERHEAD & PROFIT @ 5% LEE LEWIS CONSTRUCTION, INC. BOND PREMIUM @ 1% 1,000 0 0 13,324 0 0 14,324 Included above lincluded above 600 in OH&P 0 lincluded TOTAL COST $14,924 ®Lee Lewis Construction, Inc DALLAS I LUBBOCK I AUSTIN Owner Betterment Adjustment #031 -Screening Room Cost Detail Description Wiring for Screen Wall Modifications Screen Wall Modifications General Conditions Change Subtotal Subcontractor Overhead (10%) & Profit (5%) Contractor Overhead & Profit (15%) Bond Premium (included in OH&P) Requested Time Extension: 0 days Page 2 Subcontractor Austin Structured Cabling Black Box LLCI Amount $ 1,680 $ 11,644 $ 1,000 $ 14,324 included above Lee Lewis Construction, Inc. $ - Lee Lewis Construction, Inc. $ 600 TOTAL $ 14,924 � AUSTIN Ell STRUCTURED CABLING Austin Structured Cabling LLC 4703 Pinehurst Drive S Austin, Texas 78747-1421 Name / Address Lee Lewis Construction Drew Gregston 8303 N. MoPac Suite A215 Austin Texas 78759 Date 7/23/2019 Quote Quote # 1972 DIR-TSO-4358 Project LPSC Change Order #2 Description Qty Rate Total - Provide and install one 6 strand, single -mode, plenum rated inner -locking armored, fiber optic cable 0.00 O.00T between the second floor TR Room C I OA and the Trans. Screening Room. Provide and install one wall or rack mounted fiber optic enclosure with LC style adapter panel. Provide and install one fiber optic adapter panel for existing fiber optic enclosure in TR Room C I OA. Terminate fiber optic cable with LC style connecters. Test, label and provide test results. *** Labor*** ***Materials*** btotal 0 Lsales Tax (0.0%) Total E-mail 512-448-9555 jleblanc@austinstructuredcabling.com I 720.00 720.00T 960.21 960.21T $1,680.21 $0.00 $1,680.21 'BLACK BOX Date: Jul 24, 2019 3090422 - Change Order To: 2535 Brockton Drive Lee Lewis Construction Samsung Suite 400 55" D -LED Video Wall Monitor seamless bezel $4,165.50 Austin, Texas 78758 7810 Orlando Ave (512) 837-4400 Lubbock, Texas 79423 2 Chief Account Manager Sales Engineer e -Mail: Bob Cotton Chris Timothy Phone: 806-797-8400 512-719-6619 832-435-2024 Fax: bob cotton ` hlackbox,cam Chris-timothy@blactit Dxxom Project: Luther Peterson Service Center AV Systems - Change Order 3 HD -RX -101 -C -E Scone of Work Provide and Install (2) Additional 55" Video Wall Monitors. The video wall will become a 4X2. Provide and Install (2) HDMI over Cat extenders. Provide and Install all additional mounts, cables, hardware for a complete installation of the additional (2) monitors. The Owner will provide the source for the video wall including the (2) additional Monitors. The PC source will be located in the network rack inside the room. Owner will furnish additional electrical power outlets located behind each monitor. Material List Qty I Manufacturer Model # Description Price Extended TRANSPORTATION SCREENING LABOR / INSTALLATION 1 Black Box LABOR AV installation labor $900.00 $900.00 Luther Peterson Service Center AV Systems - Change Order 3 Proprietary and Confidential Black Box ROOM 100B 2 Samsung UM55H-E 55" D -LED Video Wall Monitor seamless bezel $4,165.50 $8,331.00 500 NIT, 1.7mm Bezel to Bezel 2 Chief LVSIU ConnexSys Video Wall Monitor Mount $637.50 $1,275.00 2 Crestron HD -TX- 10 1 -C-E HDMI® over CATx Transmitter - Surface Mount $220.00 $440.00 2 Crestron HD -RX -101 -C -E HDMI® over CATx Receiver - Surface Mount $220.00 $440.00 2 Cables to Go 56783 6ft High Speed HDMI Cable, - 4K@50/60, 2160p $18.00 $36.00 b1tPXWWw rab1eSWg❑ cnmldnr_clapffmheepSJt 0MI5.0000AM D9 -8_4290Q -02 -snare pdi 2 Cables to Go 56784 1 Oft High Speed HDMI Cable, - 4K@50/60, 2160p $9.50 $19.00 hllp-lLmarx �e1�1es1agacomlrf�cslspecstreetsl4QIAa1.5ffopllLgp3 03-A 47 00_02-spers pdf 150 Crestron DM -CBL -8G -PL Ultra High Performance Category Type Shielded $0.80 $120.00 Twisted Pair Cable 1 Black Box Misc. Mounting Hard Mounting Hardware, Uni-Strut, Threaded Rod, $80.00 $80.00 ware Toggle Bolts LABOR / INSTALLATION 1 Black Box LABOR AV installation labor $900.00 $900.00 Luther Peterson Service Center AV Systems - Change Order 3 Proprietary and Confidential Black Box Date: Jul 24, 2019 To: Lee Lewis Construction Project: Luther Peterson Service Center AV Systems - Change Order 3 Qty I Manufacturer I Model # I Description Price Extended Job Site -1 Site Dotes Materials: $10,741.00 City of Round Rock Labor: $900.00 Expenses: $0.00 3400 Sunrise Road Shipping: $0.00 Round Rock, Texas 78664 Tax: $2.97 CUSTOMER ACCEPTANCE: NAME Luther Peterson Service Center AV Systems - Change Order 3 TITLE Acceptance Change Order Total: $11,643.97 DATE Proprietary and Confidential Black Box City of Round Rock ROUND ROCK TEXAS Agenda Item Summary Agenda Number: Title: Consider executing Quantity Adjustment/Change Order No. 2 with Lee Lewis Construction, Inc. for the Luther Peterson Service Center Project. Type: City Manager Item Governing Body: City Manager Approval Agenda Date: 8/23/2019 Dept Director: Chad McDowell, General Services Director Cost: $49,913.00 Indexes: General Self -Financed Construction; Utility Fund Attachments: Change Order No. 2 Department: General Services Department Text of Legislative File CM -2019-0250 Change Order includes item, Added additional concrete and steel column to front awning to resolve cantilever beam deflection. Added window to admin office area for visibility and lighting, update AV/IT equipment to match current specifications. Added two monitors and upgraded the fiber connectivity in Transportation Screening Room. Cost: $49,913.00 Source of Funds: Self -Financed Water Construction City of Round Rock Page 1 Printed on 812312019