TB-2019-014 - 9/12/2019 RESOLUTION NO. TB-2019-014
WHEREAS, the Round Rock Transportation and Economic Development Corporation
("RRTEDC") has previously adopted a Transportation Capital Improvement Program ("TCIP"), and
WHEREAS, the Board wishes to amend said TCIP,Now Therefore
BE IT RESOLVED BY THE BOARD OF DIRECTORS OF THE ROUND ROCK
TRANSPORTATION AND ECONOMIC DEVELOPMENT CORPORATION,
That the amended Transportation Capital Improvement Program for the Round Rock
Transportation and Economic Development Corporation, attached hereto as Exhibit "A", is hereby
approved.
The Board of Directors hereby finds and declares that written notice of the date, hour, place and
subject of the meeting at which this Resolution was adopted was posted and that such meeting was
open to the public as required by law at all times during which this Resolution and the subject matter
hereof were discussed, considered and formally acted upon, all as required by the Open Meetings Act,
Chapter 551, Texas Government Code, as amended.
RESOLVED this 12th day of September, 2019.
By:
CRAIG ORG,4X, President
Round ock T nsportation and Economic
Development Corporation
ATTEST:
JONLOAN, Secretary
IK
0112.1902;00430773
of • • Rock t- S Funds
September1
FY2O19 FY202O FY2O21 FY2O22 FY2O23
TCIP#42-Pending Projected Estimated Estimated Estimated Estimated
Arterial Improvement Program(bottleneck projects) $ 1,276,000 $ 1,350,000 $ 1,450,000 $ 1,750,000
Arterial Sidewalks 250,000 300,000 300,000 350,000
County Road 112 West(AW Grimes to CR117) 125,000 300,000 3,250,000 7,450,000 11,200,000
County Road 112 East(CR110 to 3,800'East) 1,500,000 1,500,000
Deepwood Drive(RM 620 to Sam Bass Rd) 650,000 1,000,000 400,000 2,200,000
Gattis School Road-Lawnmont to Windy Park Dr 400,000 2,150,000 5,200,000
Gattis School Road-Segment 3 117,448 4,892,552 8,690,000 9,175,200
Gattis School Road-Segment 6 642,417 5,332,583 8,700,000 1,720,000
Kenney Ft.Blvd.Seg 2&3 Design 874,882 6,100,118 9,750,000 5,280,180
Kenney Ft.Segment 4 12,350,000 8,995,000
Logan Bridge 1,900,000 1,765,000
Major Arterial Maintenance 4,700,000 5,000,000 5,000,000 5,000,000
Master Transportation Plan 600,000
N.Mays St.(Jeffrey Way to Old Settlers) 75,000 350,000 350,000 1,325,000
Neighborhood Connectivity 350,000 350,000 350,000 350,000
Northeast Downtown Improvements 300,000
Nutty Brown 2,876,000
Oakmont Dr.(Nutty Brown to Sunrise Rd) 1,600,000 300,000
Old Settlers Blvd(N Red Bud Ln to CR 110) 450,000 475,000
Quiet Zone 1,500,000
Red Bud North 1,775,000 6,020,800 6,400,000 1,600,000
Red Bud South 320,000 600,000 760,000 5,500,000
RM 620 RR Grade Separation/TXDOT Project 21,045 2,000,000
Roundville Lane-UPS 39,000
SH45 Frontage Roads 745,000 2,320,000 2,210,000
Texas Avenue 27,316
Traffic Signals&Signal Coordination 1,109,000 1,400,000 1,400,000 1,400,000
Transportation Design and Construction Standards 500,000
University East _ 392,638 5,727,362 2,830,000
--- - -3-20,0-0-0----
- --- -
Wyoming Springs -3-2-0-,0-0-0 -
320--,000- - 480,000---- -880,000 5,1--
80,000
TCIP#42 Projects-Pending $4,059,746 $56,448,615 $65,350,800 $45,725,380 $42,630,000
2023 is as far out as the TCIP is programmed
EXHIBIT
"A„