CM-2019-0285 - 9/20/2019Page I of 3 Contract Quantity Adjustment/Change Order rraurm rmac .:.. . rv, 01/16 Department: Utilities & Environmeental Services Project Name: Downtown Historic Water Tank Date: 9/4/19 City Project Change Order/Quantity ID Number DTTNK Adjustment No. 1 Vendor NG Painting_ 1225 Bandera Hy,, St. A2, Kerrville, TX 76026 830-257-5990 Company Name Address Phone No. 3ustification "rocurement & placement of security ladder and gate and security panels on lower lattice legs. SUMMARY Original Contract Price: Previous Quantity Adjustment(s): This Quantity Adjustment: Total Quantity Adjustment(s): Total Contract Price with Quantity Adjustment(s): Previous Change Order(s): This Change Order: Total Change Order(s) To Date: Adjusted Contract Price [Original Contract Price Plus Quantity Adjustment(s) Plus Change Order(s)): Difference between Original and Adjusted Contract Prices: Original Contract Time: Time Adjustment by previous Quan. Adj./Change Order: Time Adjustment by this. Quan. Adj./Change Order: New Contract Time: Prepared By: Subrnkted for Approval kriLES - Printed Name, Title, Company Approvals 0 Amount $371,120.00 $0.00 $0.00 $371,120.00 $0.00 $11,500.00 $382,520.00 $11,500.00 Contractor: SignaturePrinted Name, Title, Company Date Change 0% 0% 3% City Project Manager: igna Printed Name, Title Date Mayor/City } 47Db Manager Signature 0 Printed Name, Title J Date �,.+' -2eriq-oZ k5 Contract Quantity Adjustment/Change Order ��nxwti m�. o�rsa Project Name: Downtown Historic Water Tank Quan. Adj./Change Order No.: Chanve Order Data Page 2 of 3 Item # Item Description Unit Qtv- Unit Price Amount Contract Time Adjustment Da Vandal Guard LS 1 $3,000.00 $3,000.00 Leg Security LS 1 $8,500.00 $8,500.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 _ $0.00 $0.00 PO $0.00 $0.00 $0.00 City of Round Rock IROU TM5 ROq` Agenda Item Summary Agenda Number: Title: Consider executing Quantity Adjustment/Change Order No. 1 with N.G. Painting for the Downtown Historic Water Tank Project. Type: City Manager Item Governing Body: City Manager Approval Agenda Date: 9/20/2019 Dept Director: Michael Thane, Utilities and Environmental Services Director Cost: $11,500.00 Indexes: Self -Financed Water Construction Attachments: CO No.1 Department: Utilities and Environmental Services Text of Legislative File CM -2019-0285 The original downtown water tank now referred to as the Downtown Historical Water Tank was erected by Pittsburgh -Des Moines Steel Company (PDM) in 1936 and immediately placed in service. It remained in service until 1986 when the Lake Creek well system and ground storage tank were constructed. The tank is an icon of the City of Round Rock and is visible to the entire downtown area. Due to the age of the tank, the Utility Department staff recommended a high-level structural evaluation of the tank and associated repairs and new coating system to insure the tank's long term integrity. During the project, it became evident the City would need additional safety features installed on the tank. Additional safety features included leg protection ($8,500) to eliminate climbing of the lattice legs and a locking ladder access vandal guard ($3,000). The Utility Staff requests the City Manager to authorize Change Order No. 1 for $11,500 for this additional work. This amends the original contract amount of $371,120 to $382,620. Cost: $97,500 Source of Funds: Self -Financed Water Construction City olRound Rock Page 1 Prinred on .M2019