CM-2019-0302 - 10/11/2019t WARO Contract Quantity Adjustment/Change Order -U-0— PJac1 u'3 , J Department: PARD Project Name: Adult Recreation Project Date: 10/2/19 City Project Change Order/Quantity ID Number Adjustment No. 5 Vendor Prime Construction Company, Inc. 20907 Martin L. Pflu erville, TX 78660 512.244.7799 Company Name Address Phone No. Justification See attached Change Order Summary Report and backup documentation SUMMARY Original Contract Price: Previous Quantity Adjustment(s): This Quantity Adjustment: Total Quantity Adjustment(s): Total Contract Price with Quantity Adjustment(s): Previous Change Order(s): This Change Order: Total Change Order(s) To Date: Adjusted Contract Price [Original Contract Price Plus Quantity Adjustment(s) Plus Change Order(s)): Difference between Original and Adjusted Contract Prices: Original Contract Time: Time Adjustment by previous Quan. Adj./Change Order: Time Adjustment by this Quan. Adj./Change Order: New Contract Time: Submittedifor Approval $470,404.95 16% $26,088.00 1% $496,492.95 17% $3,367,312.95 ,@ _,1 $496,492.95 240 days 10 days sod install date Feb 11, 2019) 0 250 days Signature Printed Name, Title, Company Date J4pprorals. Contractor: Brian Ritter - President Prime Constrcution Company Inc. 10-4-19 P Y City Project 5i� qh11-- jnoenr Printed Name, Title, Company Date Manager: Pure . PA((Llr DtiV . VtA CX 1—po a /,,, �vjr�p lG.o3o2 - •acx Item # Contract Quantity Adjustrnent/Change Order Project Name: Adult Recreation Project Quan. Adj./Change Order No.: 5 ___Change Order Data Item Description I Unit Unit Price I Amount 3 landscape area L5 -1 $530.001 -$530.00 Page 2 of 3 Contract Time Adjustment Contract Quantity Adjustment/Change Order Project Name: Adult Recreation Project Quan. Adj./Change Order No.: 5 uantity Adjustment Data Bid Item # Item Description Unit Qty. Unit Price Amount Pagc 3 of 3 Contract Time Adjustment Old Settlers Park Adult Recreation Complex Change Order #5 Summary Date: 10/02/2014 Change Order #t5 to the contract with PCCI includes changes to the current phase of construction. These changes include: Additional Backstop Support: After installation of the backstop netting at the fields, it was determined it would be best to include additional backstop support to decrease the amount of net drift. While the nets are tight at time of installation, the concern is that they might begin to stretch as the wind and sun wear on them. This support is just an added measure to make sure they stay tight. Cost: $6,457.00 Addition of Maintenance Gate: PARD team members requested an additional maintenance gate to access the field to decrease wear and tear on the fields by constantly utilizing the same two gates during high maintenance activities, such as top dressing. Cost: $3,162.00 Deduction of irrigation and sod in small landscape area: Sod was intended to be installed in a very small landscape area behind one of the dugouts. PARD team members decided this would be difficult to maintain so the decision was made to remove this from the scope. PARD team members will install artificial landscape turf in this area. Cost: ($530.00) Concrete Wall and Handrail: It was determined in the field that a portion of the concrete bleacher area would need a turn down wall. For safety reasons, a railing was installed as well. Additional railing was installed at a walkway where a turndown curb was installed to prevent a tripping risk. Cost: $4,477.00 Addition of 2" water line: The 1" water line service that was originally installed was sufficient for this phase of construction. In order to save money on any future phases of construction and to provide flexibility, the line was upgraded to a 2" service. Cost: $11,312.00 Field Walkway Extension: To avoid installing a ramp at the entry to the field, the walkway was extended to create a consistent ADA accessible grade. Cost: $1,210.00 TOTAL: $26,088.00 City of Round Rock f ' ROUND ROCK xa Agenda item Summary Agenda Number: Title: Consider executing Quantity Adjustment/Change Order No. 5 with Prime Construction Company, Inc. for the Adult Recreation Complex Project. Type: City Manager Item Governing Body: City Manager Approval Agenda Date: 10/11/2019 Dept Director: Rick Atkins, Director Cost: $26,088.00 Indexes: 2017 General Obligation Bonds Attachments: Contract Adjustment Change Order, IAF - QA-CO#5 w- Prime Construction Co - Adult Recreation (00433005xA08F8) Department: Parks and Recreation Department Text of Legislative File CM-20IM302 This Change Order to the contract with Prime Construction Company, Inc. (PCCI) includes adding additional support wires to the backstop netting, adding a maintenance gate for an additional entrance to the fields, and deduction of irrigation and sod in a small landscape bed that will be converted to artificial turf. Additionally, this includes adding a concrete wall and handrail at an area of walkway for safety purposes and extending a walkway to make it ADA accessible. Finally this includes upsizing the water service from a 1" line to a 2" line to support future expansion of the complex. The Adult Recreation Complex at Old Settlers Park includes construction of two (2) lighted recreational softball fields, a small restroom facility, spectator seating and shade, flexible field space, and parking. This project will serve as the first phase of the Recreation Complex and will replace the two softball fields currently located in McNeil Park which will be removed as part of the Nutty Brown Development. Cost. $26,088.00 Source of Funds: 2017 General Obligation Bonds City of Round Rock Page 1 Printed on 10/10/2019