Loading...
CM-2019-0348 - 11/1/2019Page I of 3 Contract Quantity Adjustment/ Change Order AouNorenrx:: MV. 04116 Department: General Services Project Name: Fire Station 6 Bathroom Date: 10/25/19 City Project Change Order/Quantity ID Number Adjustment No. 1 Vendor Partners Remodel Restoration and Waterip 3913 Harpers Ferry Lane, Austin, TX 78745 512-825-3950 Company Name Address Phone No. Justification Water damage remediation due to flooding during project resulted in new cove base needing installation. Flooding was caused by existing urinal valve sticking and not under the contractors scope control. SUMMARY Original Contract Price: Previous Quantity Adjustment(s): This Quantity Adjustment: Total Quantity Adjustment(s): Total Contract Price with Quantity Adjustment(s): Previous Change Order(s): This Change Order: Total Change Order(s) To Date: Adjusted Contract Price [Original Contract Price Plus Quantity Adjustment(s) Plus Change Order(s)j: Difference between Original and Adjusted Contract Prices: Original Contract Time: Time Adjustment by previous Quan. Adj./Change Order: Time Adjustment by this Quan. Adj./Change Order: New Contract time: Prepared By: $17,400.001 Signature Contractor: $2,500.00 14% Signature City Project $19,900.00 Manager: $2,500.00 14 days Si tura Mayor/City Manager 59 da s Signature M,2011 -0::N& Submitted for Approval Richard Printed Name, Title, Company Approvals Daniel Besa, Owner, PRRW Printed Name, Title, Company Chad McDowell, Director, CORR Printed Name, Title r w f! .if nted Name, Title Amount % Change $17,400.00 $0.00 $0.00 L $17,400.001 0% $2,500.00 14% $2,500.00 14% $19,900.00 $2,500.00 14 days 0 45 days 59 da s CORR /II Date %O Date /.s RUUNO ROCk fE�.�k� Item # Contract Quantity Adjustment/ Change Order Project Name: Fire Station 6 Bathroom Quan. Adj./Change Order No.: Item sum Unit Order Data Unit Price I Amount Page ? of 3 Contract Time Adjustment �Partncrs Rcmvddint:, Rcstorauvn and Waterproofing Partners Remodeling, Restoration and Waterproofing October 23, 2019 Change Order Fire Station 6 Partners Remodeling Restoration and Waterproofing is proposing to install sheetrock and cove base in Fire Station 6 where it was cut out. (CORR will provide sheetrock and cove base) 9 Total $950 Partners Remodeling Restoration and Waterproofing is proposing to remove and install approximately 675 LF of cover base in Fire Station 6. PRRW will move and necessary furniture out of the way (CORR will provide cove base) Total $155_ P �4 3219 Harpers Ferry Lane Austin, Texas 78745 Phone: 512-297-7032 Fax: 512-291-5451 Fire Station 6 Bathrooms Change Order 001 Summary Date: 10/25/2019 Change Order # to the contract: 001 Cost: $ 2,500.00 Total this Change Order: $19,900.00 Contingency Original $0,00 Betterment There was a bad/stuck diaphragm in the urinal which caused the water not to cut off and flood the facility. Please see attached pictures to see the damage. So, we had to go in and cut the sheet rock 2" off the ground so that it would dry out properly. City of Round Rock ROUND ROCK Agenda Item Summary xrs, Agenda Number: Title: Consider executing Quantity Adjustment /Change Order No. 1 with Partners Remodeling and Waterproofing, LLC for construction services related to a restroom remodel project at Fire Station No. 6. Type: City Manager Item Governing Body: City Manager Approval Agenda Date: 11/1/2019 Dept Director: Chad McDowell, General Services Director Cost: $2,500.00 Indexes: General Self -Financed Construction Attachments: Change Order Department: General Services Department Text of Legislative File CM -2019-0348 This change order will cover additional work to be done due to flooding of bathroom during construction. Cost: $2,500.00 Source of Funds: General Self -Financed Construction City of Round Rock Page i Printed on imi/2ai8