CM-2019-0360 - 11/22/2019Construction Change Order
Department: Community Development Block Grant
Program: Home Repair Program
Location: 2001 Buckeye Lane
Homeowner. Wanda & Walter Moore
Original Contract Price: $24,879.00
This Change Order $750.00
Change Orders to Date: V
Maximum Change Order Allowed $ amount $6,219.75
Balance available
Change Data
Page: 1 of 1
Date: 11/04/19
Change Order No. 1
Original Contract: 24,879
Justification:
Master Bath. Existing wood concealed
by the tub surrouond was not
structuraly sound. Replace rotted wood
at bath tub surround. Repair sheetrock
and base trim at toilet side of wall.
Item #
(-)or
(+)
Description of Chan es
Unit
QTY
Unit Price
Amount
Days +/-
1
(+
Replace rotted wood at master bath tub
surround, sheetrock at toilet side of wall
E4
1
$750.00
$750.00
2
(+
EA
1
$750.001
2
By: B&O Construction 11/4/2019
Tifle Owner Date
W,
oi9� - 6�(00
11/4/2019
Date
11/4/2019
Percent of Original Contract Price
Maximum % allowed 25.00%
This Change Order 3.01%
Total % Change 3.6 e 4
Contract + Change Orders: $25,629.00
AV�A7)-/4-X;,-/
Approve
Title L 7aii2 dle , c Manager
Date
CDBG Form 2019
1 sof 1 11/12/2019
City of Round Rock
.f
RouNn RoCCK Agenda Item Summary
Agenda Number:
Title: Requesting approval of Change Order #1 for Farnum Enterprises dba B&O
Construction in the amount of $750.00 for rehab at 2001 Buckeye Lane.
Type: City Manager Item
Governing Body: City Manager Approval
Agenda Date: 11/22/2019
Dept Director: Brad Wiseman
Cost: $750.00
Indexes: CDBG HUD Entitlement Grants
Attachments: LAF change order #1 2001 Buckeye Lane B&O Construction, Change order
#12001 Buckeye Lane B&O CONSTRUCTION
Department: Planning and Development Services Department
Text of Legislative File CM -2019-0360
The Home Repair Program assists low income homeowners with a CDBG grant up to $25,000
for substantial repairs such as roofing, plumbing and electrical work. The program does not
address cosmetic improvements.
Home Repair Contracts may be amended if a change order is needed to complete any of the
items in the work write up as long as total change orders does not exceed 25% of the original
contract amount.
Requesting approval of change order #1 in the amount of $750.00 for the home repair at 2001
Buckeye Lane. The Home Repair Agreement with B&O Construction was approved on
October 18, 2019 in the amount of $24,879. Change order #1 is needed in order for the
contractor to complete work write up item Exterior #4. City inspector Darrell Hall verified that
this additional work and change order amount is justifiable. This change order is 3.01 % of the
original contract amount.
Cost: $750.00
Source of Funds: CDBG HUD Entitlement Grants
City of Round Rock page 1 Printed on 11/2112019