CM-2019-0376 - 12/6/2019"M MOCK
Department:
Project
Name:
City Project
FD Number
Vendor
Page 1 00
Contract Quantity Adjustment/ Change Order
23000
Rabb Pavilion Improvements Project Date: 11/19/19
Change Order/Quantity
Adjustment No.
I
Fazzone Construction Co. 1302 West Blanco Road San Antonio, TX 78232 210-408-9095
Company Name Address Phone No.
Justification
It was determined that the contractor should carry out some of the more difficult conduit work for this project. Existing drinking fountain was
found to be at the end of its useful life. After requesting inspection of the existing double-check backflow preventer, PARD learned it was out of
compliance and needed to be replaced with an above ground RPZ unit. Sidewalk panels were creating a trip hazard and needed to be replaced.
SUMMARY
Original Contract Price:
Previous Quantity Adjustment(s):
This Quantity Adjustment:
Total Quantity Adjustment(s)-.
Total Contract Price with Quantity Adjustment(s):
Previous Change Order(s)-
This Change Order:
Total Change Order(s) To Date:
Adjusted Contract Price (Original Contract Price Plus
Quantity Adjustments) Pius Change Order(s)]:
Difference between Original and Adjusted Contract Prices:
Original Contract Time
Time Adjustment by previous Quan. Adi,/Change Order:
Time Adjustment by this Quan. Adj /Change Order:
New Contract Time
submitted for°ApPiatrIl
Rachel Morris, Park Developm
Printed Name, Title, Company
Amount a/a Chanae
$0.00 0%
$16,902.55 4%
$16,902.55 4%
E: $405,290.22
$16,902.55
120 days
none
15 days
_ 135 days
CORR
Date
Contractor: Paul Whetstone, Senior Project Manager 11-21-2019
City Project Signature Printed Name, Title, Company Date
Manager: Rim" orris GA -k- . S °a�;s� 1� Z2 tq
Sign re Printed Name, Title Date
Mayor/City ,.
ManagerL*akyjhL6kj%-12- �.
Signature Printed Name, Title U narp
%0— Contract Quantity Adjustment/ Change Order
MROCK
Project Name: Rabb Pavilion Improvements Project
Quan. Adj.Xhange Order No.:
Item
unit
Data
Unit Price I Amount
Contract
Time
Adjustment
Owner/Customer
Item Description
Contact
Katie Baker
Company
City of Round Rock, Texas
Address
221 East Main Street
City, State, Zip
Round Rock, TX 78664
Phone
512.218.7044
Fax
512.218.5563
Prime Contract Change Order (CO)
Contractor
Contact Paul Whetstone
Company Fazzone Construction Co., Inc.
Address 1302 West Blanco Road
City, State, Zip San Antonio, TX 78232
Phone 210.408.9095
Fax 512.335.3711
Project Information Prime Contract Change Order
Project # 00001 CO # 001
Project Name Rabb Pavilion Improvements Issue Date 30 -Sep -2019
Address 3300 E Palm Valley Blvd
City, State, Zip Round Rock, TX 78665
All labor, materials and conditions of performance involved in this change order shall be In accordance with the provisions of
the original contract for work described below:
Item No.
Item Description
quantity
Unit
Unit Price
Total Price
1
275 LF of conduit buried and stubbed for future use. Excavate
1
$2,750.00
$2,750.00
30" install pipe with risers T above FF
2
The price to saw cut trench bed pipe and pour concrete cap is
1
$2,63S.00
$2,635.00
3
4" pipe under the parking lot. Bottom of pipe is 36" has bedding
1
$1,192.55
$1,192.55
and foil tae with 90 risers on both ends.
4
Provide the fountain unit with install. That includes removing the
1
$2,800.00
$2,800.00
old unit and slab. Install new slab utilizing the existing water and
drain lines.
5
Replace RPZ at Rabb Pavilion
$3,575.00
$3,57S.00
6
Concrete Panel replacement at Silver Slugger 4 panels @ 100 sq
1
$3,950.00
$3,950.00
ft per panel
Total = $16,902.55
All other terms and conditions of the Contract Documents shall remain in effect.
Original Contract Price $388.387.67
Net change by previous Change Orders $0.00
Contract Amount Prior to this Change $388,387.67
Amount of this Change Order $16,902.55
Revised Contract Amount, including this Change Order $405,290.22
The Contract time due to this Change Order has increased by 15 Working Days
City of Round Rock Texas Fazzone Construction Co.. Inc.
Architect Owner / Representative Contractor
By (Signature)
Printed Name, Title
By (Signature)
Printed Name, Title
By (Signature)
Printed Name, Title
Date Date Date
Please sign and return original to:
Fauone Consimction Co , Inc. , Attn. Acmunq^g
1302 West 91anco Road, San Antonio, TX 78232
acmundngigaaoneconstrucbon.com
Page 1 of 1
City of Round Rock
,-
f` ROUND ROCK
Agenda Item Summary
Agenda Number:
Title: Consider executing Quantity Adjustment/Change Order No. 1 with Fazzone
Construction Company, Inc. for the Rabb Pavilion Improvements Project.
Type: City Manager Item
Governing Body: City Manager Approval
Agenda Date: 12/6/2019
Dept Director: Rick Atkins, Director
Cost: $16,902.55
Indexes: 2014 General Obligation Bonds
Attachments: From Fazzone - Rabb CO#1, Change Order #1—Fazzone (signed)
Department: Parks and Recreation Department
Text of Legislative File CM -2019-0376
This item will authorize the City Manager to execute a change order with Fazzone Construction
Company for the Rabb Pavilion Improvements Project. After construction began, PARD
decided it would be the best value to have the Contractor install electrical conduit beneath all
driveways to be utilized for future electrical connections of the restroom and pavilions. The
existing drinking fountain was found to be at the end of its useful life. The Contractor had a
similar drinking fountain in stock and offered it to the City at a heavily discounted price. Finally,
after requesting inspection of the existing double-check backflow preventer, PARD learned it
was out of compliance and needed to be replaced with an above ground RPZ unit. At an
adjacent facility in Old Settlers Park, several sidewalks had shifted due to the expansive soils,
creating a trip hazard. Since the Contractor was already pouring concrete for the Rabb Pavilion
Improvements Project, it was the best value to the City to have the Contractor replace these
panels at the same time as the concrete work associated with this project.
The Rabb Pavilion Improvements Project includes the installation of a new pavilion, improved
parking lot, accessible cricket batting cage, concrete slab under existing shade structure, new
sidewalk, prefab restroom, water & wastewater service, grading for better drainage, irrigation,
and various other improvements.
Cost. $16,902.55
Source of Funds: 2014 General Obligation Bonds