Loading...
CM-2020-054 - 2/21/2020Page I of 3 WOM rev, 01116 Department: Project Name: City Project ID Number Vendor Justification Contract Quantity Adjustment/Change Order Utilities & Environmeental Services Arterial H 16 inch Waterline Extension 2018 Date: 1/28/20 Change Order/Quantity ARTH2 Adjustment No. 1 QA Construction Services, Inc. Company Name Address Phone No. )ry utilities were placed in our assignment and mislocated during design. The existing w/w forcemain was not located as shown in the Record )rawings. SUMMARY Original Contract Price: Previous Quantity Adjustment(s): This Quantity Adjustment: Total Quantity Adjustment(s): Total Contract Price with Quantity Adjustment(s): Previous Change Order(s): This Change Order: Total Change Order(s) To Date: Adjusted Contract Price (Original Contract Price Plus Quantity Adjustment(s) Plus Change Order(s)]: Difference between Original and Adjusted Contract Prices: Original Contract Time: Time Adjustment by previous Quan. Adj./Change Order: Time Adjustment by this Quan. Adj./Change Order: New Contract Time: Submitted for A.tsrovail Amount $1,285,000.00 $43,820.00 $43,820.00 $1,328,820.00 $0.00 $0.00 $1,328,820.00 $43,820.00 240 Days 20 Days 260 Days Change 0% 0% 0% Prepared By: h Jeff Bell / Project Manager 2/11120 k Signature Printed Name, Title, Company Date JEW Apptovais Contractor: Dave Fernandez Project Manager QA Construction Services inc. 2/11/20 5ignatur Printed Name, Title, Company Date City Project Manager: Jeff Bell / Project Manager 2/11/20 Sign re Printed Name, Tide Date Mayor/Ci Manage y, ,.0 0 2.p Signature Ll Printed Name, Title Date Page 2 of 3 Contract Quantity Adjustment/Change Order IIOUHL, MefOc oi; Lf. Project Name: Arterial H 16 inch Waterline Extension 2018 Quan. Adj./Change Order No.: Chance Order Data Item # Item Description Unit Qty. Unit Price Amount Contract Time Adjustment (Days) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Page 3 of 3 Contract Quantity Adjustment/Change Order i I 14 Project Name: Arterial H 16 inch Waterline Extension 2018 Quan. Adj..,-Change Order No.: Quantity Adjustment Data I Bid item # Item Description Unit Qty. Unit Price Amount Contract Time Adjustment 10 Jacking Or Boring 30" pipe, 7/16 steel Pipe LF 40 $550.00 $22,000.00 15 16" C906 DR 11 HDPE, Open LF 30 $80.OD $2,400.00 27 DI Fittings TN 1.1 $5,200.00 $5,720.00 Potholes (4' to 7' deep) Relocate Fire Hydrant Remove & Dispose additional trees not reflected on original plans EA EA LS 8 1 1 $1,000.00 $2,500.00 $3,200.00 $8,000.00 $2,500.00 $3,200.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 TOTALS., $43,820.00 20 74, Y f 7i yF2 ••fir ° t v' '"�~ ,1�� � ' A 7� #�+� � d, � i " �- ��•-'. r•r`Lr �.14g'rl lam+.°. "yle , ic. �,.•• `�t �` +`4� + - ail i .lb • i5. �r�i� s'�.1t i•Ly7.'*** �a i�ly'��,,>i�,c �Sx ,i'� `��`• ,-ti4 .�,/�}� s 3 r ��,� �4-'4 iJo� 'a. ��f� � ��, rur• +� a � k. 4� � r .�•i,t-;�+�• � �_ �,^ r•tiY-`*.t .`��r�r`�~ � � � • , 1 ;fir' 1* .��i '�°r ' - py. �'-' a � ? f'' 7r Jam: p165*' Nh v7ajYa?mat; �yg '.:';'' `� } �•u i{� y� l# � r � f _ •�y •'F � }''r.� �'�r'f mil' � ' y�V•> �?1r ii�h, . '�,:.s,�. �i 1h " _'.R:��l p{ . I,• .if??� _�,*-t .• •4r�+.'- 9� f�}Li'�{� �r � 7i�+�ti'►;?s� i r �f` �,H4 =y .c::•`;'�'-�"•',.�. s�: ,' i ]y '•'+�-•�l�j 13�t7 qr =•i .Jr[:�iu-L1]rLiir].� �_• _ 5rr-f� •��1` - � � �•i }} I�� JR.OU City of Round Rock ND ROCK S Agenda Item Summary Agenda Number: Title: Consider executing Quantity Adjustment/Change Oder No. 1 with QA Construction Services, Inc. for the Arterial H Waterline Extension Project Type: City Manager Item Governing Body: City Manager Approval Agenda Date: 2/21/2020 Dept Director: Michael Thane, Utilities and Evironmental Services Director Cost: $43,820.00 indexes: Self -Financed Water Construction Attachments: QA No. 1, MAP Department: Utilities and Environmental Services Text of Legislative File CM-2020-054 A 16-inch waterline was constructed in 2017 with the Arterial H roadway to provide water for the newly constructed Gardens at Mayfield Ranch Subdivision. This project was the first phase of a transmission main needed to serve the City of Round Rock's 1071 pressure plane with high pressure water from the Brushy Creek Regional Utility Authority's 48-inch transmission main. This project, the second phase of the Arterial H waterline project, consists of constructing 4,547 linear feet of 16-inch high density polyethylene waterline and 536 linear feet of 12-inch ductile iron waterline that will connect to the 1071 pressure plane. The project includes a connection with the City of Georgetown at the east end of the waterline to serve as an emergency interconnect for the 1071 pressure plane, as well as provide a delivery point for treated water from Round Rock to the City of Georgetown. During the trenching phase of this project, it became evident that the existing City of Georgetown's wastewater forcemain and its electrical duct bank were not in their designated alignment. It has become necessary to realign the Arterial H 16-inch water line further to the south to maintain Texas Commission on Environmental Quality (TCEQ) required clearances from the forcemain. This Quantity Adjustment (QA No. 1) also includes an additional 40 linear feet of jacking and boring at Crest Lane because existing dry utilities prevent open trenching. The cost of this realignment and bore extension is $43,820. This QA No. 1 will also add a time extension of 20 days to the contract. City o/Round Rock Pape 4 Pdnfed on 2/2MO20 Agenda item SUMM82 Continued CM-2020.054 Cost: $43,820 Source of Funds: Self -Financed Water Construction City of Round Rock Page 2 Printed on z2vao2o