CM-2020-136 - 5/15/2020Page I of 3 Wa,WutROCK Department: Project Name: City Project ID Number Vendor Justification Contract Quantity Adjustment/Change Order PARD Old Settlers Park Tennis Court Improvement Project 2019 Date: 5/1/20 Change Order/Quantity Adjustment No. 1 Precision Construction and Contracting, LL PO Box 320, Lone Jack, MO 64070 855-697-4194 Company Name Address Phone No. 3enches needed to be raised to maintain ADA clearances after the court surface was raised. Upsized drainage was recliured to capture and nove all water away from the courts, due to the slopes and heavy rains-revegetation was not able to establish so all parties decided sod and emporary irrigation was the best course of action. Finally, PARD received a credit for the hydromulch that was replaced by sod. .said MMI Original Contract Price: Previous Quantity Adjustment(s): This Quantity Adjustment: Total Quantity Adjustment(s): Total Contract Price with Quantity Adjustment(s): Previous Change Order(s): This Change Order: Total Change Order(s) To Date: Adjusted Contract Price [Original Contract Price Plus Quantity Adjustment(s) Plus Change Order(s)]: Difference between Original and Adjusted Contract Prices: Original Contract Time: Time Adjustment by previous Quan. Adj./Change Order: Time Adjustment by this Quan. Adj./Change Order: New Contract Time: Prepared By: Signature Contractor: Signature City Project Manager: Signature Mayor/City Manager _ w - / Signature Submitted for.Approval Printed Name, Title, Company Ethan Stanfill- PCC SPORTS Printed Name, Title, Company 0 Amount 54. $0.00 $0.00 , $749,154.58 % Change 0% $35,582.84 5% $35,582.84 5% $784,737.42 $35,582.84 5-5-2020 Date /5-- 2—b Zcs Date Page 2 of 3 Contract Quantity Adjustment/Change Order ' R'OtINO ROCK - Project Name: Old Settlers Park Tennis Court Improvement Project 2019 Quan. Adj./Change Order No Chance Order Data Item # Item Description Unit Qty. Unit Price Amount Contract Time Adjustment (Days) Raise Benches LS 1 $3,695.34 $3,695.34 Install 10" culvert at sidewalk crossings EA 8 $1,225.00 $9,800.00 Sod Installation LS 1 $23,375.00 $23,375.00 Temporary Irrigation LS 1 $750.00 $750.00 Credit for hydromulch LS 1 -$2,037.50 -$2,037.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Jr TOTALS: 1 5, Page 3 of 3 Contract Quantity Adjustment/Change Order RMNO ROCK Project Name: Old Settlers Park Tennis Court Improvement Project 2019 Quan. Adj./Change Order No Quantity Adjustment Data Bid Item # Item Description P Unit Qty. Unit Price Amount Contract Time Adjustment $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 TOTALS.-I0.00 0 City of Round Rock ii ROUND ROCK TEXAS Agenda Item Summary Agenda Number: Title: Consider executing Quantity Adjustment/Change Order No. 1 with Precision Construction and Contracting, LLC for the Old Settlers Park Tennis Court Improvement Project 2019. Type: City Manager Item Governing Body: City Manager Approval Agenda Date: 5/15/2020 Dept Director: Rick Atkins, Director Cost: $35,582.84 Indexes: General Self -Financed Construction Attachments: Backup OSP Tennis Courts, LAF - QA-CO#1 w- Precision Construction and Contracting - Old Settle Department: Parks and Recreation Department Text of Legislative File CM-2020-136 Change order 1 includes raising court benches by eight inches so they remain ADA compliant. The process of rehabilitating the tennis courts caused the surface of the court to raise by eight inches, so the benches had to be extended as a result. Additionally, in order to capture all drainage due to the change in slopes at the courts, the contractor had to install larger culverts under the sidewalks. Finally, because of extremely heavy rains during construction, PARD felt that it was best to change the revegetation method from hydromulch seeding to sod installation. PARD received a credit for the hydromulch that was not installed, and paid the additional amount for the sod. The Old Settlers Park Tennis Court Improvement Project included installing a post -tension concrete court overlay over the existing asphalt tennis courts at Old Settlers Park. This was necessary due to excessive cracking which had made the courts difficult and unsafe to play on. This project also included replacing all netting, windscreen, and resurfacing the courts. Cost: $35,582.84 Source of Funds: General Self -Financed Construction City of Round Rock Page 1 Printed on 511412020