CM-2020-226 - 8/28/2020Page I of 3 - aouNoaouc rev, 01/16 Department: Project Name: City Project ID Number Vendor Contract Quantity Adjustment/Change Order TRANSPORTATION SMITH CONTRACTING CO. INC. Company Name justification Field Changes & Owner Requests McNeil Phase 2 Date: 8/24/20 Change Order/Quantity Adjustment No. 2 15308 GINGER ST AUSTIN TX 78728 512-990-7640 Address Phone No. SUMMARY Amount % Change Original Contract Price: $3,019,974.93 Previous Quantity Adjustment(s): $0.00 This Quantity Adjustment: $28,009.01 Total Quantity Adjustment(s): $28,009.01 Total Contract Price with Quantity Adjustment(s): $3,047,983.94 Previous Change Order(s): $34,265.15 1% This Change Order: $21,180.30 1% Total Change Order(s) To Date: $55,445.45 2% Adjusted Contract Price [Original Contract Price Plus Quantity Adjustment(s) Plus Change Order(s)]: $3,103,429.39 Difference between Original and Adjusted Contract Prices: $83,454.46 Original Contract Time: 255 Time Adjustment by previous Quan. Adj./Change Order: 0 Time Adjustment by this Quan. Adj./Change Order: 40 New Contract Time: 295 Submitted for Approval Prepared By: C f gip Christopher R. Lopez, Project Manager, Smith Contracting 8/24/20 Signature Printed Name, Title, Company Date Approvals / Contractor: C Christopher R. Lopez, Project Manager, Smith Contracting 8/24/20 Signature U Printed Name, Title, Company Date City Project Manager: Bill Stablein, Project Manager �6 --Z-4 "20 nature Printed Name, Title Date Mayor/City ��2g Manager Signature / / Printed Name, 67 )- - 2�& Page 2 of 3 Contract Quantity Adjustment/Change Order ROUND Rout ; rev, Ol/16 Project Name: McNeil Phase 2 Quan. Adj./Change Order No. Chance Order Data Item # Item Description Unit Qty. Unit Price Amount Contract Time Adjustment (Days CO# 2-1 T&M for Amtos Cleanup LS 1 $915.41 $915.41 1 CO# 2-2 Grate Inlets Risers LS 1 $1,218.88 $1,218.88 1 CO# 2-3 Pipe & Headwall Removal LS 1 $8,261.80 $8,261.80 1 CO# 2-4 WW Manhole Coring LS 1 $1,362.62 $1,362.62 0 CO# 2-5 WL Service EA 1 $1,900.00 $1,900.00 1 CO# 2-6 Detectable Warning Panel EA 1 1 $500.66 $500.66 0 CO# 2-7 Rock Riprap SY 49 $37.59 $1,841.91 1 CO# 2-8 Wastewater Manhole (Materials Only) EA 1 $1,592.39 $1,592.39 0 CO# 2-9 Driveway Culverts w/SETs LS 1 $3,586.63 $3,586.63 3 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Page 3 of 3 :- Contract Quantity Adjustment/Change Order s" ROUND ROCK rev, 01/16 Project Name: McNeil Phase 2 Quan. Adj./Change Order No Quantity Adjustment Data Bid Item # Item Description Unit Qty. Unit Price Amount Contract Time Adjustment (Days) i -_ ----3 6 Excavation CY 3005 $15.00 $45,075.00 10 7 Select Fill Ty A CY 3005 $27.00 $81,135.00 0 8 Embankment Ty C CY -6 8.4 $18.0 - 12,571.20 0 16 Lime Slurry TON -284 $170.00 -$48,280.00 0 17 Lime Treatment SY -9015 $7.25 -$65,358.75 0 28 CL A CONC (MISC)-CVGs SF 176.12 $8.00 $1,408.96 6 65 CURB RAMPS (TY 2) EA 1 $1,300.00 $1,300.00 2 66 CURB RAMPS (TY 7) EA 2 $1,600.00 $3,200.00 6 67 IN SM RD SN SUP&AM TYIOBWG(1)SA(P) EA 1 $500.00 $500.00 0 94 REMOVE EXISTING MANHOLE, 48-INCH DIA. EA 1 $2,500.00 $2,500.00 0 95 NEW MANHOLE CONSTRUCTION, 48- INCH DIA. EA 2 $4,200.00 $8,400.00 5 111 REMOVAL OF EXISTING FIRE HYDRANT ASSEMBLY EA 1 $1,500.00 $1,500.00 1 112 FIRE HYDRANT ASSEMBLY EA 1 $4,200.00 $4,200.00 1 114 Critical Locates EA 2 $2,500.00 $5,000.00 1 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 28 009.01 32 City of Round Rock ROUND ROCK TEXAS Agenda Item Summary Agenda Number: Title: Consider executing Quantity Adjustment/Change Order No. 2 with Smith Contracting, Co., Inc for the McNeil Road Extension Phase 2 Project. Type: City Manager Item Governing Body: City Manager Approval Agenda Date: 8/28/2020 Dept Director: Gary Hudder, Transportation Director Cost: $49,189.31 Indexes: RR Transportation and Economic Development Corporation (Type B); Self -Financed Wastewater Construction; Self -Financed Water Construction Attachments: QA-CO#2_revised_1_part exec Department: Transportation Department Text of Legislative File CM-2020-226 This Change Order #1 is for field changes like installing waterline services, removal of existing fences, and driveway culverts not shown on the plans. Change order is in the amount of $34,265.15. Change Order #2 and Quantity Adjustment #2 is for items like rock rip rap for the drainage channels to prevent erosion, extra water line service, waste water manhole coring, pipe and headwall removal. The quantity adjustment portion of this includes removal of a lot of the lime slurry and treatment that was called out. Removal of Type C embankment and the addition of select fill type A. Additional curb ramps that were installed, an additional fire hydrant and additional new manholes. This Change order/Quantity Adjustment #2 is in the amount of $49,189.31. Cost: $49,189.31 Source of Funds: RR Transportation and Economic Development Corporation (Type B), Self -Financed Water Construction, and Self -Financed Wastewater Construction City of Round Rock Page 1 Printed on 812712020