CM-2020-251 - 9/25/2020Page I of 3
Contract Quantity Adjustment/Change Order
Department: 23000
Project
Name: Rabb Pavilion Improvements Project Date: 8/21/2020
City Project Change Order/Quantity
ID Number Adjustment No. 3
Vendor Fazzone Construction Co. 1302 West Blanco Road San Antonio, TX 78232 210-408-9095
Company Name Address Phone No
Justification
Zhanges in the field made it necessary to add irrigation around the new cricket cage and a concrete mow strip around the restroom. Concrete
vas added to the cricket cage area in order to make it more accessible.
SUMMARY
Or g na Contract Price:
Previous Quantity Adjustment(s):
This Quantity Adjustment:
Total Quantity Adjustment(s):
Total Contract Pr ce with Quantity Adjustment(s);
Previous Change Order(s)
This Change Order:
Total Change Order(s) To Date;
Adjusted Contract Price (Original Contract Price Plus
Quantity Adjustment(s) Plus Change Order(s)):
Difference between Original and Adjusted Contract Prices:
Original Contract Time:
7 ime Adjustment by previous Quan. Adj,/Change order
Time Adjustment by this Quan. Adj./Change Order
New Contract Time:
Submitted for Approval
Amount
$386,387.67
$0.00
$0.00
$0.00
$388,387 67
$65,773.32
$3,200.67
$68,973.99
$457,361.66
$68,973.99
120 days
45 days
30 days
195 days
9/6 Change
17%
Prepared 1 y,_r _ Rachel Morris, Park Develqpment Specialist, CORR 9IzI 12P20
Signature Printed Name, Title, Company Date
Approvals
Contractor: �, , �} �i L : ae , i c J n ,r .n �� > Cc�c C azza,e C +_ a� Q s
Signature Printed Name, Title; ompany� Date
City Project
Manager: ��,1 Mor�:s1-_pork Dr, Sacs_ G2.� q(n � --
ignature _ Printed Name, Title �— Date
Mayor/City � _�
Manager u G t
ignature Printed Name, Tl le Date
N- 2 0-20 --25)
I?Contract Quantity Adjustment/Change Order
NDIX
Project Name: Rabb Pavilion Improvements Project
Quan. Adj./Change Order No.:
Change Order Data
DescriptionUnit.Price
Contract
Time
Adjustment
(Days)
I
c
_i
Page 3 of 3
Contract Quantity Adjustment/Change Order
ROUND FOLK
rF1 ((01 15
Project Name: Rabb Pavilion Improvements Project
Quan. Adj./Change Order No.:
uantity Adjustment Data
Contract
Time
Adjustment
Item Description Unit Qty. Unit Price Amount (Days)
Owner/Customer
Contact Katie Baker
Company City of Round Rock, Texas
Address 221 East Main Street
City, State, Zip Round Rock , TX 78664
Phone 512.218.7044
Fax 512.218.5563
Prime Contract Change Order (CO)
Contractor
Contact Paul Whetstone
Company Fazzone Construction Co., Inc.
Address 1302 West Blanco Road
City, State, Zip San Antonio, TX 78232
Phone 210.408.9095
Fax 512.335.3711
Project Information Prime Contract Change Order
Project # 00001 CO # 003
Project Name Rabb Pavilion Improvements Issue Date 19-Aug-2020
Address 3300 E Palm Valley Blvd
City, State, Zip Round Rock, TX 78665
All labor, materials and conditions of performance involved in this change order shall be in accordance with the provisions of
the original contract for work described below:
Item No.
Item Description
Quantity
Unit
Unit Price
Total Price
1
Restroom Mow Strip
1
$2,151.27
$2,151.27
2
ADA Extension Cricket Cage
1
$349.80
$349.80
3
Adding New Irrigation at Cricket Cage
1
$699.60
$699.60
Total = $3,200.67
All other terms and conditions of the Contract Documents shall remain in effect.
Original Contract Price $388,387.67
Net change by previous Change Orders $65,773.32
Contract Amount Prior to this Change $454,160.99
Amount of this Change Order $3,200.67
Revised Contract Amount, including this Change Order $457,361.66
The Contract time due to this Change Order is to be determined at a later date.
City of Round Rock, Texas Fazzone Construction Co., Inc.
Architect Owner/ Representative Contractor
By (Signature)
Printed Name, Title
Date
By (Signature)
Printed Name, Title
Date
Please sign and return original to:
Fazzone Construction Co., Inc. - Attn. Accounting
1302 West Blanco Road, San Antonio, TX 78232
accoundng@fazzoneconstruction.com
By (Signature)
Printed Name, Title
Date
Page 1 of 1
city of Round Rock
ROUND ROCK Agenda Item Summary
TEXAS
Agenda Number:
Title: Consider executing Quantity Adjustment/Change Order No. 3 with Fazzone
Construction Company, Inc. for the Rabb Pavilion Improvements Project.
Type: City Manager Item
Governing Body: City Manager Approval
Agenda Date: 9/25/2020
Dept Director: Rick Atkins, Director
Cost: $3,200.67
Indexes: 2017 General Obligation Bonds
Attachments: From Fazzone - Rabb CO_3, Change Order _3_Fazzone (signed), LAF -
QA-CO#3 w- Fazzone Construction Co. - Rabb Pavilion Improvements
(00454678xA08F8)
Department: Parks and Recreation Department
Text of Legislative File CM-2020-251
This item will authorize the City Manager to execute a change order with Fazzone Construction
Company for the Rabb Pavilion Improvements Project. Changes in the field made it necessary to add
irrigation around the new cricket cage and a concrete mow strip around the restroom. Concrete was
added to the cricket cage area in order to make it more accessible.
The Rabb Pavilion Improvements Project includes the installation of a new pavilion, improved
parking lot, accessible cricket batting cage, concrete slab under existing shade structure, new
sidewalk, prefab restroom, water & wastewater service, grading for better drainage, irrigation, and
various other improvements.
Cost: $3,200.67
Source of Funds: 2017 General Obligation Bonds
Page 1 of 1