CM-2020-313 - 11/13/2020Pagel of 3
Contract Quantity Adjustment/Change Order
l
rev. 01/16
Department: Transportation
Project
Name: 2017 CDBG Sidewalk Project - Chisholm Valley Subdivision Date: 10/29/20
City Project Change Order/Quantity
ID Number Adjustment No. 1
Vendor Partner's Remodeling, Restoration, and W 512-825-3950
Company Name Address Phone No.
justification
The intent of the project was to cut a 6-foot wide path across existing driveway approaches to provide ADA access. Several driveway
approaches were too steep to be cut in this way, so they required full replacement in order to meet ADA slope requirements. Adjacent
sidewalk panels needed to be reconstructed in association with the driveway approach replacements.
SUMMARY
Original Contract Price:
Previous Quantity Adjustment(s):
This Quantity Adjustment:
Total Quantity Adjustment(s):
Total Contract Price with Quantity Adjustment(s):
Previous Change Order(s):
This Change Order:
Total Change Order(s) To Date:
Adjusted Contract Price [Original Contract Price Plus
Quantity Adjustment(s) Pius Change Order(s)]:
Difference between Original and Adjusted Contract Prices:
Original Contract Time:
Time Adjustment by previous Quan. Adj./Change Order:
Time Adjustment by this Quan. Adj./Change Order:
Amount % Change
$231,115.50
$0.00
$47,825.00
$47,825.00
$278,940.50
$0.00 0%
$0.00 0%
$0.00 0%
$278,940.50
$47,825.00
New Contract Time: 0
Prepared By: Matthew Bushak, Transportation Engineer, CORR 10/29/2020
Signature_ Printed Name, Title, Company Date
Appm
Contractor:
Signature Printed Name, Title, Company Date
City Project
Manager: Matthew Bushak, P.E., Transportation Engineer 10/29/2020
Page 2 of 3
Contract Quantity Adjustment/Change Order
ROUND 110- '.
rev, 01/16
Project Name: 2017 CDBG Sidewalk Project - Chisholm Valley Subdivision
Quan. Adj./Change Order No
Chance Order Data
Ttom It
TI-am rinar•rinti—
IInit
Atv
Ilnit Driro
Amnnt
Contract
Time
Adjustment
rr. _.._�
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
TOTALS:
Page 3 of 3
Contract Quantity Adjustment/Change Order
aouNo aoac rF x is
rev, 01116
Project Name: 2017 CDBG Sidewalk Project - Chisholm Valley Subdivision
Quan. Adj./Change Order No.:
Quantity Adjustment Data
Bid Item #
Item Description
Unit
Qty,
Unit Price
Amount
Contract
Time
Adjustment
1
Concrete Sidewalk (4")
SF
1180
$6.00
$7,080.00
2
Remove and Replace Concrete Driveway
SF
5620
$7.25
$40,745.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
47 825.00
0
I '27�
f ROUND ROCK
TEXAS
City of Round Rock
Agenda Item Summary
Agenda Number:
Title: Consider executing Quantity Adjustment/Change Order No. 1 with Partners
Remodeling, Restoration and Waterproofing for the 2017 CDBG Sidewalk Project -
Chisholm Valley Subdivision.
Type: City Manager Item
Governing Body: City Manager Approval
Agenda Date: 11/13/2020
Dept Director: Gary Hudder, Transportation Director
Cost: $47,825.00
Indexes: CDBG HUD Entitlement Grants
Attachments: CAA#1_Signed
Department: Transportation Department
Text of Legislative File CM-2020-313
This Quantity Adjustment/Change Order (QA/CO) consists of additional sidewalk repair and driveway
replacement. Several driveway approaches were too steep and required full replacement in order to meet
ADA slope requirements. Adjacent sidewalk panels needed to be reconstructed in association with the
driveway replacements.
The original contract amount was $231,115.50 with this QA/CO being $47,825.00 adjusting the new
contract price to $278,940.50.
Cost: $47,825.00
Source of Funds: CDBG HUD Entitlement Grants
City of Round Rock Page 1 of 1