CM-2020-346 - 12/11/2020Page I of 3 Contract Quantity Adjustment/Change Order rev, 01/16 Department: TRANSPORTATION ADMINISTRATION Project Name: McNeil at St Willaims - Quiet zone Date: 11/20/20 City Project Change Order/Quantity ID Number Adjustment No. Four (4) Vendor AUSTIN TRAFFIC SIGNAL CONST. CO., IN( PO BOX 120 ROUND ROCK, TX 78680 512-255-9951 Company Name Address Phone No. Justification :abinet Damaged by Vehicle 10-27-20 repairs - Railpro Invoice as a pass through SUMMARY Original Contract Price: Previous Quantity Adjustment(s): This Quantity Adjustment: Total Quantity Adjustment(s): Total Contract Price with Quantity Adjustment(s): Previous Change Order(s): This Change Order: Total Change Order(s) To Date: Adjusted Contract Price [Original Contract Price Plus Quantity Adjustment(s) Plus Change Order(s)]: Difference between Original and Adjusted Contrail Prices: Original Contract Time: Time Adjustment by previous Quan. Adj./Change Order: Time Adjustment by this Quan. Adj./Change Order: New Contract Time: Submitted for Approval 0 Amount % Change $419,195.08 $0.00 $0.00 $419,195.08 $85,523.26 $11,414.00 $96,937.26 $516,132.34 $96,937.26 20% 3% 23% t Collette Phillips, Asst Controller Austin Traffic Signal Cosnt. Co, Prepared By: Inc. 11/20/20 ire Printed Name, Title, Company Date ApprowaIs Con Ed Schroeder, VP Austin Traffic Si nal Const. Co. Inc. 11/20/20 City Prow Signature Printed Name, Title, Company Date Manager: � .����������... 12 3 -10 nature Printed Name, Title Date Mayor) Am L Manager k111/�vtS. A5 �fliJfl�l`1llr l - /(—� �2 Page 2 of 3 Contract Quantity Adjustment/Change Order rev, 01/16 Project Name: McNeil at St Willaims - Quiet Zone Quan. Adj./Change Order No.: Four (4) Change Order Data Item # Item Description Unit Qty. Unit Price Amount Contract Time Adjustment D s 9007-RPRI Cabinet Damages 10-27-20 Repaired 1 Is $6,432.00 $6,432.00 9008-RPRO RailPro Invoice #A12724620201031 1 Is $4,982.00 $4,982.00 $0.00 $0.00 $0.00 0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 0.00 0.00 $0.00 $0.00 $o.00 $0.00 Page 3 of 3 rev, O1j16 _. Contract Quantity Adjustment/Change Order Project Name: McNeil at St Willaims - Quiet Zone Quan. Adj./Change Order No.: Four (4) Quantity Adjustment Data •.1 11 •. 1 1 1 •.1 11 • t' 1 Ill 1 INVOICE Invoice To AUSTIN TRAFFIC SIGNAL CONSTRUCTION COMPANY PO Box 130 Round Rock, TX 78680 Location: Round Rock, TX Period: Services from 10/22/2020 through 10/30/2020 Description: Building traffic signal/paving - Round Rock, TX - 161.26,162.59,163.10-161.80 -Sub Austin M11RjULPROS Remit To: 1320 Greenway Dr #490 Irving, TX 75038 Phone: (682) 223-6897 accountin g.fs@railprosxom Total Due : $4,982.00 Invoice Number Invoice Date PO Number Task Order Number :AT2724620201031 :04 Nov 2020 :2010343 :27246 DESCRIPTION QUANTITY RATE AMOUNT Jerry Shimek Standard shift (Days) 4.00 $998.00 $3,992.00 Overtime hours (Hours) I 7.50 $132.00 $990.00 Mom Thank you for your business! Terms: Due on receipt treated on 11/4/2020 page 1 of ROUND ROCK TEXAS City of Round Rock Agenda Item Summary Agenda Number: Title: Consider executing Quantity Adjustment/Change Order No. 4 with Austin Traffic Signal Const. Co., Inc. for the Traffic Signal at McNeil and St. Williams - Quiet Zone Project. Type: City Manager Item Governing Body: City Manager Approval Agenda Date: 12/11/2020 Dept Director: Gary Hudder, Transportation Director Cost: $11,414.00 Indexes: RR Transportation and Economic Development Corporation (Type B) Attachments: QA-CO #4_partexec Department: Transportation Department Text of Legislative File CM-2020-346 Change order # 1 was for the third party inspection required by Union Pacific Rail Road when doing wor their ROW. The Quiet Zone work of installing a traffic signal at St. Williams Street is within UPRR's ROV does require RailPros Field Services, Inc. The amount of that change order was $36,442.00 for inspectic services from April of 2020 through May of 2020. Change Order #2 was for RailPro's Field Services while the City's contractor completed work within UPF ROW on St. Williams Street and McNeil Road. This change order is in the amount of $31,363.26. Change Order #3 was for another RailPro's invoice that should cover the last of the work activities on UPRR's rail line for the purposes of installing a traffic signal at the St. Williams crossing. This change or( in the amount of $17,718.00. Change Order #4 is for replacement of the control cabinet for the traffic signal at St. Williams and McNei Street and the RailPro's Services to perform that work. A vehicle ran the other one over and totaled it therefore the replacement. The cost of this unit installed is $6,432.00. The cost of RailPro's Services is 4,982.00 totaling $11,414.00 for CO#4. The adjusted contract price will be $516,132.34. Cost: $11,414.00 Source of Funds: RR Transportation and Economic Development Corporation (Type B) City of Round Rock Page 1 of 1