CM-2021-041 - 2/5/2021Page 1 of 3 Contract Quantity Adjustment/Change Order rev, 01/16 Department: UES Project Name: Wastewater Collection System Pipe Bursting Rehabilitation 2020 Date: 1/25/21 City Project Change Order/Quantity ID Number RHB20 Adjustment No. 2 Vendor PM Construction & Rehab, LLC 131 North Richey Road - Pasadena TX 77506 (832) 252-4811 Company Name Address Phone No. Justification Change Order No. 2 is needed for final quantity adjustment. SUMMARY Original Contract Price: Previous Quantity Adjustment(s): This Quantity Adjustment: Total Quantity Adjustment(s): Total Contract Price with Quantity Adjustment(s): Previous Change Order(s): This Change Order: Total Change Order(s) To Date: Adjusted Contract Price [Original Contract Price Plus Quantity Adjustment(s) Plus Change Order(s)]: Difference between Original and Adjusted Contract Prices: Original Contract Time: Time Adjustment by previous Quan. Adj./Change Order: Time Adjustment by this Quan. Adj./Change Order: New Contract Time: d Submitted for Approval Amount % Change $1,443,120Z5 $0.00 $62,884.16 $62,884.16 $1,506,004.41 $186,098.00 12% -$13,801.10 -1% $172,296.90 11% —,,678,301.31 F—s $235,181.06 0 Prepared By: Eddie Zapata, Senior Project Manager, City of Round Rock 6/24/ Signature ✓ Printed Name, Title, Company Date Approvals Contractor: Emily High, Project Manager, PM Construction & Rehab, LLC n , natur City Project Printed Name, Title, Company Date Manager: �i �" Eddie Zapata, Senior Project Manager l �r/l�nature MayoManarerl Printed Name, Title ate 1 11F�S &-/ c �-J -90 9 K c /` /�( �Signa re/� �I Printed Name, Title Date ( CA4— 2,0 2 '0 Page 2 of 3 NogocF Contract Quantity Adjustment/Change Order rev, 01116 Project Name: Wastewater Collection System Pipe Bursting Rehabilitation 2020 Quan. Adj./Change Order No. rhanna nrdar nnfta Item # Item Description Unit Qty. Unit Price Amount Contract Time Adjustment (Days) CO 2-1 DISCOUNT Item #1207 - Remove and replace or install cleanout EA 89 -$686.75 -$61,120.75 CO2-2 Repair / Rehab 2" Asphalt Pavement SY 802.85 $46.00 $36,931.10 CO2-3 Repair / Rehab 6" Concrete Driveway SY 9 $80.00 $720.00 CO2-4 Repair / Rehab 4" Concrete Sidewalk SY 35.55 $65.00 $2,310.75 CO2-5 Repair / Rehab Concrete Curb & Gutter LF 449 $32.20 $14,457.80 CO2-6 Egger Avenue Paving Credit LS 1 -$6,000.00 -$6,000.00 CO2-7 Black Street Asphalt Repair LS i -$1,100.00 -$1,100.00 TAL : Page 3 of 3 P NogoIX Contract Quantity Adjustment/Change Order rev, 01116 Project Name: Wastewater Collection System Pipe Bursting Rehabilitation 2020 Quan. Adj./Change Order No.: 2 Ouantitv Adiustment Data Bid Item # Item Description p Unit Qty. Unit Price Amountrnavi Contract Time Adjustment CO 1 -2 Burst existing 8" wastewater line to 12" HDPE wastewater line LF -121 $80.00 -$9,680.00 CO 1 -3 Post TV Inspection after rehabilitation LF 324 $5.00 $1,620.00 CO 1 - 4 12" Wastewater line point repair (8' - 12' deep) EA -2 $4,830.00 -$9,660.00 CO 1 -5 Wastewater service lateral reconnect EA 1 $920.00 $920.00 CO 1-6 Install 8" wastewater line by open cut (0 - 8' deep) LF -5 $75.00 -$375.00 CO 1 -7 Wastewater service lateral reconnect up to 5' EA 0 $920.00 $0.00 CO 1 -8 Extra length service connection over 5' LF 175 $40.00 $7,000.00 CO 1 -9 Remove & replace end of line cleanout EA 11 $1,840.00 $20,240.00 CO 1 -11 Repair/Rehab 2" Asphalt pavement SY -250 $46.00 -$11,500,00 CO 1 -12 Flowable Fill CY -170 $140.00 -$23,800.00 CO 1 -13 Cement stabilized sand TN -36 $38.00 -$1,368.00 Travel and Mobilization EA -4 $6,000.00 -$24,000.00 4911 Barricades, Signs, and Traffic Handling EA 0.5 $7,000.00 $3,500.00 4915 SWPPP EA -1 $2,500.00 -$2,500.00 204 Burst existing 6" or 8" to 8" IPS SDR 19 0'-B' deep) LF 6134 $55.00 $337,370.00 205 Burst existing 6" or 8" to 8" IPS SDR 19 8'-12' deep) LF -7009 $60.00 -$420,540.00 401 Sewer Main Television Inspection 8" through 15" Diameter LF -1365.48 $4.00 -$5,461.92 409 Sewer Main Cleaning - Normal 8" through 15" Diamter LF -1366.48 $4.00 -$5,465.92 451 6" - 12" Post TV Inspection After Rehabilitation LF -877 $5.00 -$4,385.00 1201 External reconnect 0'-8' deep) up to 5 linear feet EA 75 $920.00 $69,000.00 1206 Extra length service connection over 5 linear feet LF 126 $40.00 $5,040.00 1207 Remove and replace or install cleanout EA 77 $1,850.00 $142,450.00 1711 Repair/Rehab wooden fence with new LF -150 $36.80 -$5,520.00 TOTALS: 62 884.16 0 W N U- Z N 0 O� W< J Q J = O W C) 0� wO W z 11 w W F- m U) W Qa �a paw8ugvngad!d-qeyai � OZOABupvngad!d-deyai � OZOZllpuna❑�pZOZISdVWla�etlsyiom saV!IVM\SIJ sa�edsyioM�p iped�uawnaop 1 Y R' =wi.-. ai .e - •i9 � � WAYNE 6.i oD rt 61, io `V 6" ROINNI DR 6"' i• a„ °��,• � d� :KAROLYN DR ; �'� -1r5 ` i�r"}� t 8„ 6" iVOAKOR E OAK OR 1 r r 2q„ LILAC DR 1 y. � Egger Acres Pipebursting - Project Map ® Active Manhole N —♦ Active Wastewater Gravity Main AMains to be Pipebursted Date: 1/2020 City of Round Rock ,-?ROUND ROCK t TEXAS Agenda Item Summary Agenda Number: Title: Consider executing Quantity Adjustment/Change Order No. 2 with PM Construction & Rehab, LLC for the Wastewater Collection System Pipe Bursting Rehabilitation 2020 Project. Type: City Manager Item Governing Body: City Manager Approval Agenda Date: 2/5/2021 Dept Director: Michael Thane, Utilities and Environmental Services Director Cost: $49,083.06 Indexes: Self -Financed Wastewater Construction Attachments: QA.00 No. 2-Partially executed, Overall Project Map, MAP_Egger Acres Department: Utilities and Environmental Services Text of Legislative File CM-2021-041 The City is required to continue our Wastewater Collection System Rehabilitation Program to comply with the Texas Commission on Environmental Quality's Edwards Aquifer Recharge Zone Protection Program. This program requires that the City inspect the wastewater collection systems located over the Edwards Aquifer and complete any necessary rehabilitation every five years. The elimination of defects not only helps to protect the Edwards Aquifer but also reduces inflow and infiltration entering the City's wastewater collection system; thereby, reducing the City's wastewater treatment costs. The City has completed the inspection of four sub -basins to determine areas that require rehabilitation for this project. The City will perform the work in sub -basins BC-08, BC-21, BC-22Z, and OC-24Z (Egger Acres Subdivision). The original contract for construction phase services was based on the developed construction plans and specifications to rehabilitate the wastewater collection system in a portion of these sub -basins. The project includes pipe bursting 11,390 linear feet of existing 6-inch wastewater line with 8-inch High -Density Polyethylene Pipe(HDPE) wastewater line, and 3,750 linear feet of existing 8-inch wastewater line with 8-inch HDPE wastewater line. Change Order / Quantity Adjustment (CO/QA) No. 2 includes additional wastewater service lines, cleanouts, asphalt pavement, concrete sidewalk, and curb and gutter repairs. This CO/QA also includes a credit for a portion of 8-inch wastewater line that was not installed and pavement repairs that were not required. The total cost for CO/QA No. 2 comes out to $49,083.06. CO/QA No. 1 increased the contract City of Round Rock Page 1 of 2 Agenda Item Summary Continued (CM-2021-041) value to $1,629,218.25. This CO/QA No. 2 will increase the contract total amount to $1,678,301.31. Cost: $49,083.06 Source of Funds: Self -Financed Wastewater Construction City of Round Rock Page 2 of 2