CM-2021-060 - 2/22/2021Construction Change Order
Department: Community Development Block Grant
Program: Home Repair Program
Location: 802 Fairway Green Cove
Homeowner: James and Patty Shrader
Original Contract Price: $23,868.00
This Change Order $920.40
Change Orders to Date: $875.00
Maximum Change Order Allowed $ amount $5, 967.00
Balance available r nag nn
Change Data
Page: 1 of 1
Date: 02/08/21
Change Order No. 2
Original Contract: 23,868
Justification:
Floora t Laundry room to match
adjoining kitchen.Move appliances
required for work,Repair water leak due
to worn out water valves
Item #
(-)or
(+)
Description of Changes
Unit
OTY
Unit Price
Amount
Days +/-
1
(+)
1. Laundry Room - Remove and reset
washer and dryer.
EA
2
$42.00
$84.00
2
(+)
Remove and replace Vinyl Flooring at
laundry room
EA
1
$336.00
$336.00
3
(+)
Remove and replace emergency water
shut off valves and hoses at washing
machine
EA
1
$500.40
$500.40
$920.40
0
By: B&O Construction 2/8/2021
Title Owner Date
/ Percent of Original Contract Price
Maximum % allowed 25.00%
This Change Order 3.87%
Total % Change 7.54%
Contract + Change Orders: $25,663.40
Approve L
Title Laur Hadl 7y—City Ma ger
Date
Homeowner Date CDBG Form 2019
1 of 1 2/8/2021
City of Round Rock
ITEMS
OD ROCK
Agenda Item Summary
Agenda Number:
Title: Consider executing Quantity Adjustment/Change Order No. 2 with Farnum
Enterprises, Inc. for the home repair project at 802 Fairway Green Cove.
Type: City Manager Item
Governing Body: City Manager Approval
Agenda Date: 2/12/2021
Dept Director: Brad Wiseman
Cost: $920.40
Indexes:
Attachments: change order #2 802 fairway green cove, LAF - Quantity Adjustment -Change
Order #2 w- Farnum Enterprises Inc. for CDBG Home Repair at 802 Fairway Green
Cove (02 09 21)
Department: Planning and Development Services Department
Text of Legislative File CM-2021-060
Consider executing Quantity Adjustment/Change Order No. 2 with Farnum Enterprises, Inc. for the home
repair at 802 Fairway Green Cove in the amount of $920.40. this change order allows B&O Construction to
complete Kitchen Interiors #1 Flooring. The Home Repair Program assists low-income homeowners with a
CDBG grant up to $25,000 for substantial repairs such as roofing, plumbing, and electrical work. The
program does not address cosmetic improvements.
Home Repair Contracts may be amended if a change order is needed to complete any of the items in the
work write up if the total change orders does not exceed 25% of the original contract.
Original Contract Amount $23,868
Maximum Change Order Amount Allowed (25%) $5,967
Amount being requested at this time $920.40 (3.87%)
The original home repair agreement with B&O Construction was approved on October 30, 2020 in the
amount of $23,868 by CM-2020-302. This is the second change order for this home repair at 802 Fairway
Green Cove. Change order No. 1 in the amount of $875 was approved by city manager item
CM-2021-016. This second change order is needed for B&O Construction to complete work write up items
Interior Kitchen #1. City inspector Marc Schmidt verified that this additional work is needed, and the
change order amount is justifiable.
Cost: $920.40
City of Round Rock page 1 of 2
Agenda Item Summary Continued (CM-2021-060)
Source of Funds: CDBG 2019
City of Round Rock page 2 of 2