R-2021-063 - 3/11/2021RESOLUTION NO. R-2021-063
WHEREAS, the City of Round Rock has previously entered into a contract ("Contract") with
PM Construction & Rehab, LLC for the Lake Creek 10 & 11 Wastewater Improvements Project, and
WHEREAS, the Council has determined that it is necessary to make adjustments/changes to
the quantity of work to be performed or materials, equipment, or supplies to be provided, and
WHEREAS, it has been determined that it is necessary to adjust/change the quantities in said
Contract in accordance with the attached Quantity Adjustment/Change Order No. 1, Now Therefore
BE IT RESOLVED BY THE COUNCIL OF THE CITY OF ROUND ROCK, TEXAS,
That the Mayor is hereby authorized and directed to execute on behalf of the City, Quantity
Adjustment/Change Order No. 1 to the Contract with PM Construction & Rehab, LLC for the Lake
Creek 10 & 11 Wastewater Improvements Project, a copy of said quantity adj ustment/change order
being attached hereto as Exhibit "A" and incorporated herein for all purposes.
The City Council hereby finds and declares that written notice of the date, hour, place and
subject of the meeting at which this Resolution was adopted was posted and that such meeting was
open to the public as required by law at all times during which this Resolution and the subject matter
hereof were discussed, considered and formally acted upon, all as required by the Open Meetings Act,
Chapter 5 51, Texas Government Code, as amended.
RESOLVED this 11 th day of March 2021.
CRAIG PO'RAN, Mayor
City of Roun Rock, Texas
ATTEST:
W*t I# Rtvk
SARA L. WHITE, City Clerk
01 12.20212; 00466254
EXHIBIT
Contract Quantity Adjustment/ Change Order
NOUN" "03(A f
iv-y� OUT4
y.
r'�n n+m
tje6 HCC
Flage t of 3
Project
Name: Lake Creek 10 & 11 Wastewater Imorovernents Date: 2/10/21
City Prqject Change Order/Quantity
TD NW.,;mber LCPID Adjustment No. 1
Vendor PM Construction & Rehab, LLC North Richey Road - Pasadena, TX 77506
Company Name Address Phone No.
Justification
Tuantity Adjustment No. 1 is needed for final quantity adjustment.
----------------------
SUMMARY
Original Contract Price:
Previous Quantity Adjustment(s):
This QUdntity.Adjustfnent:
Total Quantity Adjustment(s):
Total Contract Price with Quantity Adjustment(s):
Previous Change Order(s),
This Change Order:
Total Change Ordeqs) To Date:
Adjusted Contract Price (Original Contract Price Plus Quantity Adjustment(s) Plus Change
order(s)]..
Difference between Original and Adjusted Contract Prices:
Original Contract Tirne,
Time Ad'justment by previous Quan. Adj./Change Order:
Tifne Adjustment by this Quan. Adj./Change Order.
Amount
Change
�591,93 J
5�4 0
.............
... .....
.............
......... .
$0.00
.... ... . .......
. . .... .. . ...
-$55�69115
........... X.-
. .. ... .... .......
$536,2
. .... .... . .. ..
0%
$0.00
0%
%
-$55,692.15
55
New Contract "Time:
.... ......... ...... . .... ..... .......... - .. .... . ... . ...
. .... ..
..... .................. . .... ..
............
.............
.......................
..................... .. . ..... . ............. . .... ...... ..... ..... ......
W ...........
g:
............. .. . ........ .
.............
.......... .. .........
................. . .......... S
.... .....
..........
bmitted for Ap prova .. .. .. ........ ........... . .. .... ...........
Prepared By: Eddie Zapata, Senior Project ManaqerCity of Round Rock 2/22121
Printed Name, Title, Cumpany Date
..... .... .... . . ....... I ................ ...
....... ... ..... . .. .................... ... ... .... ... ............. ... . . .... .... .. ...... ........
...... .. ..... . . .... ..., ................
X. . . .......... ................ ........ ....... .......... . .......... ............... .................. ........ . ... ..... v ....................... ....... ..... .. ....
.......... . .. . ...... .
.. . .......... .......
............. ................... . .... . .. . ....... .
... . ................ .. ...........
.......... . ....... ... .... -
.............. ................ -:: *::::; ........... . ........ ...... ........ ... ..... .. . .......
............ -.1 ................... . .. ........ % .... ...... ...... ......... ...... .....
. . . . .......
-X:
............. ............ v- % %-..I-.-`--..-.-:::-. :"' - -1:,,:- .
.......... . ....-s" :::,
......... .. ..........
*.'*.*,.*,,* ............. - .... ... . ..... . . . . ...... . .... ... ....... ..... ..... .... ............. . . ... ... . . .. ................. ............. . ... .
X . ...... . . .... .....
si'unature
City Project
Signature
oe7 -07 --1
F-qifly P!Pjed Mananer. PM Construction & Rehab, LLC raVITIU-6mul 6,C)L,
Printed Name, Tide, Company Date
Eddie ...Zapeta, Senior. Proiect rylanagiql ................ 2/22/2021
Printed'Name, Title Date
Mayor/City
Manager cm- -Morga", Mayor
------------ � S -- . .
Signature Printed Name, Title Date
Page 2 of 3
Contract Quantity Adjustment/Change Order
M.
Project Name,*, Lake Creek 10 & ii Wastewater Improvements
Quan. Adj.JChange Order No.,: 1
Contract Quantity Adjustment/ Change Order
Project Name: Lake Creek 10 & 11 Wastewater Improvements
Quan. Adj./Change Order No.: I
UantftY Atiiustn►ent Data
I Bid Item#
..........
..................................... .. . Item Descriptlan
................. .............. . ....... ......
------------ ----- ----------- M ---------------- ----........
Unit
: . .......
tUnit
- - ------------Price .
Amount
. ......
...... .... .........
...... ........... ...
.... .... .. ....... ........ . .
. ...
...........
i i
haltie Concrete Pavement Re-r
. . .......
. ...... ....
SY
.
10A&-$940o50
...........
....... ......
. ...... .... ...
. . . .......... ...
. .... . . .
552
Concrete-------
Drainage ... pai ---------------- ------ --
------- SY
-$l,84le95.1
3
P. C. Concrete Curb and Gutter
LF M"0*00000-21v6*7
-95
$40400
-------- -$3800-00
4
New 4"* Concrete sidewalk
.265--$14,26150---------
5
Concrete Drivqyy;�y Kepair
SY
-9123
$90400...
9
Removal of Exl'sbng Manhole 4 dia.
EA
1
$208-50.,
— -----------00$i,85t�.t�0�8,390:70
10
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
-New Manhole Construction
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
EEi
-:40 3
$5*25*0,,00
-$15o750v00S. .
12
Trench Safety ystems
LF
-2050
$1000
..................
42r050,0013
12" Dl"a. SDR-26 PVC in teel Encawmenf ---------- ---------
--- - ------ --LF
46
$97a5O
$4,485qoo
4
112
. ...........
DO. SDR-26 PVCall..depthL),.,,,,, ------------------------------ ------------------
------ -
------- ----------- - LF
---- - -15
�9
$85�00
3765.00
15 Dia., SDR-26 PVCLolldepth
LF
W09
$105,00
-$945-0016
Pre- CCTV
LF
164�4.50
17
Post ." CCTV
LF
14
$1.25
Si7,5Q
-- ------
18 I
Room$
Installin ar Reconnecting. Service ------ -- ---------------
------- EA -
p ------------ -
-------------
---- ... ... $545.00,
$645A0
AMA -- ------- ---
LUt 12 Sewer Line
S?Le Reha /Instaii---------
LF
1119
.$1i5:0�X$1,925.,00n
I -------------- ------------------
21
5tabized Constructl'on Entrance..
EA
-665
-$10,075,sOO22
Silt Fence ---------- ------- I --- --- -
-- ---------- LF
-1554
$1,050
-,$Z331.00Mll
VMPvVVVW~ 24
Wood Fence ---------------------------- --
------------ lF ------- -------------------
-60
$&5.00 ------ -
-----------------------------------------------
V11,000900:
MIAWWWWOWS 26 --------
-Pipe burst B°' to 10" DR29
LF
�33
$4100
-es1,386itOO27
---------
Pipe burst 8" to 12" DR19
LF
"16
$50000-$800.00
28
ioeburst 10" to 12"DR 19
LF
23
,
11,265,*00
Page, 3 of 3
Contract
Time
Adjustment