R-2021-319 - 12/2/2021 RESOLUTION NO. R-2021-319
WHEREAS, Section 395.058 of the Texas Local Government Code ("the Act") requires the
Capital Improvement Advisory Committee ("CIAC") to report to the City Council the progress of the
capital improvements plan and any perceived inequities in implementing the plan or imposing the
impact fee; and
WHEREAS, the CIAC is also required to advise the Council of the need to update the land use
assumptions, capital improvements plan and impact fees; and
WHEREAS, the CIAC has submitted Capital Improvement Plan Progress Semi-Annual
Reports; and
WHEREAS, the City Council has reviewed the attached Capital Improvement Plan Progress
Semi-Annual Reports and has determined same to be in compliance with the Act,Now Therefore
BE IT RESOLVED BY THE COUNCIL OF THE CITY OF ROUND ROCK, TEXAS,
That the Capital Improvement Plan Progress Semi-Annual Reports, attached hereto as Exhibit
"A" and incorporated herein, are hereby approved.
The City Council hereby finds and declares that written notice of the date, hour, place and
subject of the meeting at which this Resolution was adopted was posted and that such meeting was
open to the public as required by law at all times during which this Resolution and the subject matter
hereof were discussed, considered and formally acted upon, all as required by the Open Meetings Act,
Chapter 551, Texas Government Code, as amended.
RESOLVED this 2nd day of December, 2021.
- & M /I
CRAIG RGA ayor
City of R and Rock, Texas
ATTEST:
�4" Z.0�& ,
Colql(l - I Ju 6�
MEAGAN $31NKS, City Clerk
0112.20212;4860-3787-2388
EXHIBIT
Capital
Improvements Plan
Progress
Semi-Annual Report
November 2021
ROUND ROCK TEXAS
UTILITIES AND ENVIRONMENTAL SERVICES
SUMMARY
The Local Government Code Section 395.058 requires the Capital Improvement Advisory
Committee (CIAC) to report to the political subdivision the progress of the capital
improvements plan and any perceived inequities in implementing the plan or imposing
the Impact Fee. Included herein is the semi-annual report for the reporting period of April
1 , 2021 , to September 30, 2021. This report consists of assessing the actual growth rate
in comparison to the projected growth rate, the status update of capital improvement
projects, and the Impact Fees collected during the reporting period.
The local government code also requires the CIAC to advise the City Council on updating
the land use assumptions, capital improvements plan, and Impact Fees. These items
were last updated by the City in November 2020.
1 10/27/2021
Figure 1 shows the groundwater and surface water produced and the number of active
water services over the past two years. Although the City continues to grow, the total
water production remains relatively steady. Water usage is highly dependent on weather
patterns-, however, the City's conservation and reuse water programs are also significant
factors impacting water usage.
Figure 1
Water Treatment Plant
2,500 37
36
2,000
35
c �
o
— 1,500 34
o
c H
— c
33 v
1,000
2 >
a` v
c 32
o —
500 Q
31
0 1st Qtr FY'20 2nd Qtr FY'20 3rd Qtr FY'20 4th Qtr FY'20 1st Qtr FY'21 2nd Qtr FY'21 3rd Qtr FY'21 4th Qtr FY'21 30
Active Services 35664 35821 35979 36045 36123 36237 36328 36439
♦Groundwater 184,333,000 197,829,000 324,375,000 356,849,000 262,705,000 323,949,000 304,168,000 329,234,000
-.-Surface Water 1,535,740,000 1,125,756,000 1,566,909,000 2,190,844,000 1,588,619,000 1,124,305,000 1,507,802,000 2,011,458,000
2 10/27/2021
Figure 2 reflects the daily average of potable water produced each month over the last
five years. Total water production is dependent on weather conditions; therefore,
discretionary water usage is higher during the summer months.
Figure 2
Average Potable Daily Demand Each Month
40
35
30
25
o i
20
0
15
10
5
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
■2017 u 2018 ■2019 of 2020 N 2021
3 10/27/2021
Figure 3 reflects the monthly potable treated water production and the Type I Reuse
treated water production. The City's reuse water system began production in October
2012 with three customers: Old Settlers Park, Dell Diamond, and Forest Creek Golf
Course. The City has since expanded the system to Forest Creek HOA, Legends Village
Subdivision, Austin Community College, Texas A&M Health Science Center, Forest
Grove and Vizcaya Subdivisions, and the newly opened Kalahari Resort. The City
continues to promote reuse water in the northeast part of Round Rock, and as depicted
in Figure 3, the demand continues to grow.
Figure 3
Potable vs. Reuse Water
Average Daily Demand Each Month
35
30
25
c
° 20
�o
c
0
15
� I
10
5
0
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sept
■FY-17 ■FY-18 ■FY-19 ■FY-20 ❑FY-21 ■Reuse
4 10/27/2021
Figure 4 shows the number of new single-family building permits issued in the City of
Round Rock and the City's extra-territorial jurisdiction (ETJ). Over the past five years,
new single-family housing starts in the City have ranged from 556 to 929 per year. Single-
family permits issued have continued to increase to an average of about 80 permits per
month over the past six months. Most of the current construction activity is in the northeast
part of Round Rock in the Saul's Ranch, Vizcaya, Salerno, Quick Ranch, and University
Heights Subdivisions. There is also new single-family construction occurring in other parts
of the City in the Chisholm Trail Park, Preserve at Wyoming Springs, and Clear Creek
Subdivisions. Townhomes under construction include Sonoma Townhomes, Schulz
Townhomes, Townhomes at Gattis School Road, and Tiger Trail Townhomes. Most of
the Municipal Utility Districts (MUDs) in Round Rock's ETJ are nearing buildout; however,
as noted in Figure 4, Siena MUD No. 2 continues to experience a steady number of new
housing starts.
Figure 4
Annual Single-Family Building Permits
Issued Residential & MUDS
1800
1600 1512 1511
1400 1328
1200 1121
1043
1000
800 -
600
400
200
0 - —
FY-17 FY-18 FY-19 FY-20 FY-21
■Round Rock ■Paloma #1 = Paloma #2 ■Teravista #10 ■Teravista #11 Siena #1 Siena #2
5 10 2712021
Table 1 reflects the number of multi-family units permitted annually. Currently, there are
four multi-family complexes in plan review and five complexes under construction. These
include two Legacy facilities on University Boulevard and Red Bud Lane, Warner Ranch,
Round Rock Phase 2 behind the outlet mall, and Arrington Ridge.
Table 1
Fiscal Year Multi-Family Units
FY 2017 330 (170 LUEs)
FY 2018 652 (327.5 LUEs)
FY 2019 432 (218 LUEs)
FY 2020 430 (196.5 LUEs)
FY 2021 584 (391 .5 LUEs)
6 10/27/2021
Table 2 reflects the number of new commercial building permits issued annually. This
number has been steady, ranging from 25 to 50 annually, and commercial development
in the City continues to trend upward. Current permits are mostly office property, hotels,
small retail, light industrial, and restaurants.
Table 2
_ Commercial
ar
Fiscal Y
Building Permits
FY 2017 25 (168 LUEs)
FY 2018 43 (220.5 LUEs)
FY 2019 50 (262 LUEs)
FY 2020 44 (150.5 LUEs)
FY 2021 39 (161 LUEs)
Table 3 and Figure 5 summarize the Water and Wastewater Impact Fees collected for In-
City retail residential (single-family and multi-family) and commercial customers and Out-
of-City wholesale customers. From FY-17 to FY-19, there was an increase in the total
Impact Fees collected due to new developments; however, FY-20 showed a significant
decrease attributed to the virus pandemic. FY-21 indicates that the Impact Fee collections
in the City trended upward to prior FY-20 amounts, and Out-of-City wholesale decreased
in FY-21 mainly due to the buildout of many of the MUDs.
Table 3
Impact - • 1
In-City Retail
Residential
Water $2,812,465 $3.830.017 $2,770,650 $2,008,822 $2,649,580
Residential
Wastewater $1,201,518 $1,905,615 $1,381,154 $930,467 $1,296,554
Commercial
Water $915,617 $2,399,541 $2,750,040 $1,752,110 $2,934,225
Commercial $567,288 $1,102,400 $1,701,974 $461,347 $1,457,580
Wastewater
Out-of-City Wholesale
Water $818,121 $692,763 $639,567 $406,253 $114,713
Wastewater $1,532,360 $639,776 $1,650,108 $895,448 $20,711
Total Collected $7,847,369 $10,570,111 $10,893,493 $6,454,447 $8,473,362
8 10/27/2021
Figure 5
Impact Fees Collected FY 2017 - FY 2021
S12 000.000 -
$10,570,111 $10,893,493
S10.000.000 -
$8,473,362
$7,
$8,000,000 847,369
$6,454,447
$6,000,000 - --
$4,000,000 - -
$2,000,000 - —
FY-17 FY-18 FY-19 FY-20 FY-21
■Residential Water ■Commercial Water Wholesale Water
■Residential Wastewater ■Commercial Wastewater Wholesale Wastewater
During the latest water model update in 2020, the City assumed that 1,433 LUEs per year
would be added to the water system. At an Impact Fee of $4,234 per LUE, this would
indicate that the City should be collecting approximately $6.07 million per year in Water
Impact Fees if the City's growth rate is as projected starting in FY-21.
In addition, the wastewater model update assumed that 1 ,027 LUEs would be added to
the wastewater system per year. At an Impact Fee of$1,799 per LUE, this would indicate
that the City should be collecting approximately $1.85 million per year in Wastewater
Impact Fees if the City's growth rate is as projected in FY-21 .
Comparing these assumptions to the actual Impact Fees collected indicates that the
number of new connections to our water and wastewater systems for FY-21 occurred as
expected.
9 10 27/2021
Table 4 provides population projections for Round Rock and Round Rock's ETJ. These
projections, anticipating a steady growth rate, indicate that capital improvements to the
City's water and wastewater utility systems would be necessary to keep up with growth.
However, the annual estimates, shown in parenthesis, convey a slower growth rate in the
City limits than projected. New projections for "Inside City" from 2021 through 2030 are
currently being developed by the City's Planning and Development Services Department.
Table 4
Year
•- City's ETJ
Projections Growth Rate
2010(Census) 99,887 - 141,807 -
2011 100,659 0.8% 143,960 1.5%
2012 102,349 (101,702) 1.7% (1.0%) 146,380 1.7%
2013 104,805 (102,349) 2.4% (0.6%) 151,133 3.2%
2014 107,635 (103,107) 2.7% (0.7%) 155,613 3.0%
2015 110,757 (105,405) 2.9% (2.2%) 160,385 3.1%
2016 113,968 (106,591) 2.9% (1.1%) 165,024 2.9%
2017 117,160 (108,353) 2.8% (1.7%) 169,213 2.5%
2018 120,440 (112,201) 2.8% (3.6%) 173,490 2.5%
2019 123,812 (116,120) 2.8% (3.5%) 177,859 2.5%
2020 (Census) 119,468 2.9% 182,323 2.5%
2021 122,827 2.8% 186,062 2.1%
2022 - - 189,881 2.1%
2023 - - 193,508 1.9%
2024 - - 197,218 1.9%
2025 - - 200,312 1.6%
2026 - - 203,462 1.6%
2027 - - 206,670 1.6%
2028 - - 209,651 1.4%
2029 - - 212,693 1.5%
2030 - - 215,795 1 1.5%
Notes: 2010 is the base year for all projections in this table
( )Annual Estimates by Planning & Development Services Department
10 10/27/2021
Table 5 summarizes the status of the Water System (Impact Fee eligible) Capital
Improvement Projects included in the November 2020 Impact Fee Analysis.
Table 5
Completed Water Projects Completion Impact Fee ReportActual Cost
wf Estimated Cost
Creek Bend 12" Waterline 2016 $415,000 $415,000
Arterial H Waterline 2017 $856,400 $162,460
BCRUA Water Treatment Plant- Ph 1B 2018 $34,000 $31,000
South 81 Elevated Storage Tank Pump Station 2019 $157,000 $1,070,900
Arterial H Phase II 2020 $1,470,500 $1,375,045
BCRUA Phase 1C -WTP Expansion to 32MGD 2020 $4,465,000 $3,635,540
Water Dist. Master Plan & Impact Fee 2020 $66,000 $220,570
$7,463,900 $6,910,515
Water Projects In Progress Completion Impact Fee Report Actual Cost
Estimated Cost
GR-01: E Liberty Ave, N Shephard St & Fannin 2022 $500,000 $938,983
Ave
GR-05: University Blvd extension from end of 36" 2022 $1,150,000 $801,000
main to CR-110
GR-02: Kenny Fort Blvd from Forest Creek Blvd 2022 $1,570,000 $1,787,073
to SH45
GR-03: Kenny Fort Blvd from Old Settlers to 2024 $2,450,000 $4,325,000
Chandler Creek
GR-04: Sam Bass Rd from FM-1431 to Wyoming 2025 $7,000,000 $9,073,000
Springs Dr
GR-06: Redbud Ln from south of Palm Valley 2026 $4,560,000 $4,560,000
Blvd to Gattis School Rd
BCRUA Phase 2 - Deep Water Intake 2027 $60,608,500 $73,080,384
$77,838,500 $94,565,440
1 1 10/27/2021
Upcoming Water Projects Estimated Impact Fee Report
Completion Estimated Cost
GR-07: Nester's Crossing & CR-172 from west 971 zone to S-81 2025 $3,270,000
EST
BCRUA Phase 1 D - WTP Expansion to 42MGD 2025 $4,000,500
GR-08: FM-1460 toward Westinghouse Rd, east to future road 2027 $2,350,000
GR-09: Palm Valley Blvd (north side) extension to CR-110 2029 $600,000
GR-10: Loop from GR-09 to Westinghouse to University 2030 $2,440,000
$12,660,500
12 10 2T2021
Table 6 summarizes the status of the Wastewater System (Impact Fee eligible) Capital
Improvement Projects included in the November 2020 Impact Fee Analysis.
Table 6
Completed Wastewater Projects Completion Impact Fee Report Actual Cost
Estimated Cost
Lake Creek 2 2017 $2,652,000 $1,916,000
Lake Creek 3 2017 $591,000 $563,000
McNutt Creek C2 (referred to as C5) 2018 $1,324,000 $1,762,000
Brushy Creek 5 2018 $288,000 $282,618
Brushy Creek 2 2019 $685,000 $349,000
Brushy Creek 4 2019 $173,000 $173,000
$5,713,000 $5,045,618
Wastewater Projects in Progress Completion Impact Fee Report Actual Cost
Estimated Cost
Lake Creek 1 2022 $1,856,000 $1,856,000
$1,856,000 $1,856,000
13 10 27,2021
Upcoming Wastewater Projects Estimated Impact Fee Report
Completion Estimated Cost
MC-1: New 6,760LF of 18-in 2022 $1,973,000
Forest Creek LS and FM - Increase Capacity 2022 $3,168,000
Hilton Head LS and FM - Increase Capacity 2022 $1,751,000
BC-1: Upsize 3,015LF to 12-in and 18-in 2023 $831,000
CC-1: Upsize 3,975LF to 12-in and 15-in 2024 $1,026,000
MC-2: New 9,120LF of 12-in 2025 $1,576,000
MC-3: New 5,155LF of 24-in 2026 $1,602,000
CC-2: Upsize 955LF to 12-in and 15-in 2027 $230,000
WWTP Expansion to 40MGD - PER 2030 $2,500,000
$14,657,000
14 10/27/2021
Table 7 summarizes the status of the Reuse Water System (Impact Fee eligible) Capital
Improvement Projects included in the November 2020 Impact Fee Analysis.
Table 7
Completed Reuse Projects Completion Impact Fee Report Actual Cost
Estimated Cost
Reuse Phase VI 2016 $900,000 $900,000
Reuse Phase IV-B 2016 $3,719,000 $3,013,152
$4,619,000 $3,913,152
Reuse Projects in Progress Completion Impact Fee Report Actual Cost
Estimated Cost
1.0 MG Reuse Ground Storage Tank 2023 $1,628,400 $1,628,400
$1,628,400 $1,628,400
Upcoming Reuse Projects Estimated Impact Fee Report
Completion Estimated Cost
Reuse Phase V— Stony Point High School 2023 $614,328
$614,328
15 10/27/2021
Figure 6 compares Single-Family Residential Utility Rates for Round Rock to
surrounding Central Texas Municipalities and Municipal Utility Districts. As
depicted, Round Rock utility rates remain among the lowest in the region.
Figure 6
Single-Family Residential
Water and Wastewater Rates Monthly Comparison
$200
$183.03
$180 --
$162.40
$160 - 5155.02---
$123.75
$120 $115.80 $113.82-
$100 $98•22—W�—$96.as
$91.38 $86.70
$82.51
$80 —
$67.43
$60
$40
$20 -
$0 — - - - —
Hutto San Austin Pflugerville Leander Paloma Walsh Vista Teravista 11 Cedar Teravista 10 Fern Round Georgetown Brushy
Marcos 1&2 Ranch Oaks Park Bluff Rock Creek
(Annual
Avg)
■Water Wastewater
* assumes 10,000 gallons water and 8,000 gallons wastewater used
16 10/27/2021
Table 8 compares Round Rock's Water and Wastewater Impact Fees to
surrounding cities and Municipal Utility Districts. Historically, Round Rock had one
of the highest total Impact Fees charged for new connections to the water and
wastewater systems. However, several surrounding cities have increased their
fees over the past few years and surpassed Round Rock. Round Rock's
philosophy is for new customers and developments to pay for the required capital
improvements due to the growth.
Table 8
Area Impact Fee Comparison
Last
City/Utility Updated Water Wastewater Total
Brushy Creek MUD 2012 $2,095 $1 ,804 $3,899
Round Rock 2020 $4,234 $1,799 $6,033
Cedar Park 2020 $3,160 $3,170 $6,330
San Marcos 2018 $3,801 $2,684 $6,485
Leander 2017 $4,309 $2,820 $7,129
Austin 2018 $4,700 $2,500 $7,200
Pflugerville 2020 $7,897 $1,898* $9,795
Georgetown 2018 $6,921 $3,115* $10,036
Hutto 2021 $8,832 $2,788 $11,620
*Indicates the City has two different Wastewater Impact Fees, based on service area. The
number in the table above reflects the lowest fee charged by that City.
17 10/27/2021
CONCLUSION AND RECOMMENDATIONS
Due to the volatility in growth rates and infrastructure requirements, the City
recommends a review of the Impact Fees every three to four years. The current
Impact Fees were adopted on January 14, 2021, and went into effect on February
1 , 2021.
Over the past several years, the population growth in Round Rock has proceeded
slower than projected in the Impact Fee Analysis. However, the number of
connections to the water and wastewater systems has occurred as anticipated.
The next Capital Improvements Plan Progress Report will be presented to the
CIAC and the City Council in approximately six months.