Contract - Royal Vista, Inc - 4/28/2022Page I of 3 Contract Quantity Adjustment/Change Order rev, 0l/16 Department: Project Name: Chisholm Valley Water, Wastewater, and Storm Drain Improvements Area 3 Date: 4/11/22 Change Order/Quantity CVDAS Adjustment No. 2 Royal Vista, Inc. 350 Co Rd. 260, Liberty Hill, Tx, 78642 (512) 515-6824 Company Name Address Phone No. City Project ID Number Vendor Utilities and Environmental Services lustification Zepair four wastewater pipe joints externally on a 36-inch wastewater main and three manhole pipe seal penetration failures to reduce ground eater infiltration into the wastewater system. SUMMARY Original Contract Price: Previous Quantity Adjustment(s): This Quantity Adjustment: Total Quantity Adjustment(s): Total Contract Price with Quantity Adjustment(s): Previous Change Order(s): This Change Order: Total Change Order(s) To Date: Adjusted Contract Price [Original Contract Price Plus Quantity Adjustment(s) Plus Change Order(s)]: Difference between Original and Adjusted Contract Prices: Original Contract Time: Time Adjustment by previous Quan. Adj./Change Order: Time Adjustment by this Quan. Adj./Change Order: New Contract Time: Submitted for Approval i:tt 3 $0.00 0% $250,000.00 12% $250,000.00 12% $2,284,702.90 $297,205.90 Prepared By: / � ��_ Christopher Perkins �� 12 5ignature Printed Name, Title, Company Date Signature / Printed Name, Title, Company Dafe City Project // , L cti �/ _ , ' M Manager. i ,l.L� l6 � i .i f l /�� hC�/- In I Z Mayor/City Date I_p2Z 0-E Page 2 of 3 Contract Quantity Adjustment/Change Order 0N6 Project Name: Chisholm Valley Water, Wastewater, and Storm Drain Improvements Area 3 Quan. Adj./Change Order No.: Change Order Data Item Description Unit Qty. Unit Price Amount Contract Time Adjustment (Days) Item # 30 1 Four point repairs and three manhole pipe seal repairs. TM 1 $250,000.00 $250,000.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 T TALS: Page 3 of 3 Contract Quantity Adjustment/Change Order rev, 01/16 Project Name: Chisholm Valley Water, Wastewater, and Storm Drain Improvements Area 3 Quan. Adj./Change Order No.: 2 Quantity Adjustment Data Item Description Contract Time Adjustment ¢bra 111a