R-2022-182 - 5/26/2022 RESOLUTION NO. R-2022-182
WHEREAS, Section 395.058 of the Texas Local Government Code ("the Act") requires the
Capital Improvement Advisory Committee ("CIAC") to report to the City Council the progress of the
capital improvements plan and any perceived inequities in implementing the plan or imposing the
impact fee; and
WHEREAS, the CIAC is also required to advise the Council of the need to update the land use
assumptions, capital improvements plan and impact fees; and
WHEREAS, the CIAC has submitted a Capital Improvement Plan Progress Semi-Annual
Report; and
WHEREAS, the City Council has reviewed the attached Capital Improvement Plan Progress
Semi-Annual Report and has determined same to be in compliance with the Act,Now Therefore
BE IT RESOLVED BY THE COUNCIL OF THE CITY OF ROUND ROCK,TEXAS,
That the Capital Improvement Plan Progress Semi-Annual Report, attached hereto as Exhibit
"A" and incorporated herein, is hereby approved.
The City Council hereby finds and declares that written notice of the date, hour, place and
subject of the meeting at which this Resolution was adopted was posted and that such meeting was
open to the public as required by law at all times during which this Resolution and the subject matter
hereof were discussed, considered and formally acted upon, all as required by the Open Meetings Act,
Chapter 551, Texas Government Code, as amended.
RESOLVED this 26th day of May, 2022.
11,41
CRAIG l R " , Mayor
City of Round ock, Texas
ATTEST:
4.�P
MEAGAN S I KS, (TiClerk
0112 20222,4883-1724-8031
EXHIBIT
"All
Capital
Improvements Plan
Progress
Semi-Annual Report
May 2022
ROUND ROCK TEM5
UTILITIES ANO ENVIRONMENTAL SERVICES
SUMMARY
The Local Government Code Section 395.058 requires the Capital Improvement
Advisory Committee (CIAC)to report to the political subdivision the progress of the
capital improvements plan and any perceived inequities in implementing the plan
or imposing the Impact Fee. Included herein is the semi-annual report for the
reporting period of October 1, 2021, to March 31, 2022. This report consists of
assessing the actual growth rate in comparison to the projected growth rate, the
status update of capital improvement projects, and the Impact Fees collected
during the reporting period.
The local government code also requires the CIAC to advise the City Council on
updating the land use assumptions, capital improvements plan, and Impact Fees.
These items were last updated by the City in November 2020.
1
Figure 1 shows the groundwater and surface water produced and the number of
active water services over the past two years. Although the City continues to grow,
the total water production remains relatively steady. Water usage is highly
dependent on weather patterns; however, the City's conservation and reuse water
programs are also significant factors impacting water usage.
Figure 1
Water Treatment Plant
2,500 —_ 38
37
2,000 -
36
N N
C
C
05
1,500 3
C 34
� C
u N
6 1,000 33 u
O
a y
O
_ 32 7},
M 500 4
31
0 3rd Qtr FY'20 4th Qtr FY'20 1st Qtr FY'21 2nd Qtr FY'21 3rd Qtr FY'21 4th Qtr FY'21 1st Qtr FY'22 2nd QtrFY'22 30
®Active Services 35979 36045 36123 36237 36328 36439 36679 36914
+Groundwater 324,375,00D 356,849,000 262,705,000 323,949,Q0D 304,168,000 7 329,234,000 122,548,000 86,114,000
=OwSurfaceWater 1,566,909,000 2,190,844,000 1,588,619,000 1 1,124,305,000 1,507,802,000 1 2,011,458,000 1,566,460,000 1,305,889,000
2
Figure 2 reflects the daily average of potable water produced each month over the
last five years. Total water production is dependent on weather conditions;
therefore, discretionary water usage is higher during the summer months.
Figure 2
Average Potable Daily Demand Each Month
40
35
30
25
0
7o
c 20
0
15
10
5
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
■2018 0 2019 hi 2020 ■2021 d 2022
3
Figure 3 reflects the monthly potable treated water production and the Type I
Reuse treated water production. The City's reuse water system began production
in October 2012 with three customers: Old Settlers Park, Dell Diamond, and Forest
Creek Golf Course. The City has since expanded the system to Forest Creek HOA,
Legends Village Subdivision, Austin Community College, Texas A&M Health
Science Center, Forest Grove and Vizcaya Subdivisions, and the newly opened
Kalahari Resort. The City continues to promote reuse water in the northeast part
of Round Rock, and as depicted in Figure 3, the demand continues to grow.
Figure 3
Potable vs. Reuse Water
Average Daily Demand Each Month
35
30
25
0 20
M
t7
c
a
= 15
10
5
0
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sept
■FY-18 ■FY-19 ■FY-20 ■FY-21 ❑FY-22 ■Re use
4
Figure 4 shows the number of new single-family building permits issued in the City
of Round Rock and the City's extra-territorial jurisdiction (ETJ). Over the past five
years, new single-family housing starts in the City have ranged from 556 to 929
per year. Single-family permits issued have continued to increase to an average
of about 90 permits per month over the past six months. Most of the current
construction activity is in the northeast part of Round Rock in the Vizcaya, Salerno,
Quick Ranch, Homestead, and University Heights Subdivisions. There is also new
single-family construction occurring in other parts of the City in the Chisholm Trail
Park, Preserve at Wyoming Springs, and Clear Creek Subdivisions. Townhomes
under construction include Sonoma Townhomes, Schulz Townhomes,
Townhomes at Gattis School Road, The Depot, and Tiger Trail Townhomes. Most
of the Municipal Utility Districts (MUDS) in Round Rock's ETJ are nearing buildout;
however, as noted in Figure 4, Siena MUD No. 2 continues to experience a steady
number of new housing starts.
Figure 4
Annual Single-Family Building Permits
Issued Residential &MUDS
1800
1600 1512 1511
1400
1200 1121
1043
1000
800
600 547
400
200
a
FY-18 FY-19 FY-20 FY-21 FY-22
■Round Rock ■Paloma #1 Paloma #2 ■Teravista#10 -°Teravista#11 Siena #1 Siena #2
5
Table 1 reflects the number of multi-family units permitted annually. Currently,
there are four multi-family complexes in plan review and six complexes under
construction. These include two Legacy facilities on University Boulevard and Red
Bud Lane, Warner Ranch, Crossing at Palm Valley, Round Rock Phase 2 behind
the outlet mall, and Arrington Ridge.
Table 1
In-City Retail
Fiscal Year Multi-Family Units
FY 2018 652 (327.5 LUEs)
FY 2019 432 (298 LUEs)
FY 2020 430 (196.5 LUEs)
FY 2021 584 (391.5 LUEs)
FY 2022 (Oct-Mar) 577 (364 LUEs)
Out-of-City Wholesale
Fiscal Year Multi-Family Units
FY 2022 (Oct-Mar) 522 (305.4 LUEs)
6
Table 2 reflects the number of new commercial building permits issued annually.
This number has been steady, ranging from 25 to 50 annually, and commercial
development in the City continues to trend upward. Current permits are mostly
office property and light industrial. There are also permits in for hotels, small retail,
and restaurants.
Table 2
Fiscal Year Commercial
Building Permits
FY 2018 43 (220.5 LUEs)
FY 2019 50 (262 LUEs)
FY 2020 44 (950.5 LUEs)
FY 2021 39 (161 LUEs)
FY 2022 (Oct-Mar) 15 (58 LUEs)
7
Table 3 and Figure 5 summarize the Water and Wastewater Impact Fees collected
for In-City retail residential (single-family and multi-family) and commercial
customers and Out-of-City wholesale customers. From FY-17 to FY-19, there was
an increase in the total Impact Fees collected due to new developments; however,
FY-20 showed a significant decrease attributed to the virus pandemic. FY-21
indicates that the Impact Fee collections in the City trended upward to prior FY-20
amounts, and Out-of-City wholesale decreased in FY-21 mainly due to the buildout
of many of the MUDs.
Table 3
Impact
Fees •
In-City Retail
Residential $3,830,017 $2,770,650 $2,008,822 $2,649,580 $1,273,518
Water
Residential $1,905,615 $1,381,154 $930,467 $1,296,554 $994,846
Wastewater
Commercial $2,399,541 $2,750,040
Water $1,752,110 $2,934,225 $2,188,594
Commercial $1102,400 $1,701,974 $461,347 $1,457,580 $1,052,124
Wastewater
Out-of-City Wholesale
Water $692,763 $639,567 $406.253 $114,713 $32,200
i
Wastewater $639,776 $1,650,108 $895,448 $20,711 $655,443
Total $10,570,111 $10,893,493 $6,454,447 $8,473,363 $6,196,725
i Collected '
8
Figure 5
Impact Fees Collected FY 2018 - FY 2022
$12,000,000
$10,570,111 $10,893,493
$10,000,000
$8,473,362
$8,000,000
$6,454,447
$6,000,000
$4,534,566
$4,000,000
$2,000,000
$0
FY-18 FY-19 FY-20 FY-21 FY-22
(Oct-Mar)
■Residential Water ■Commercial Water ■Wholesale Water
■Residential Wastewater Commercial Wastewater ■Wholesale Wastewater
During the latest water model update in 2020, the City assumed that 1,433 LUEs
per year would be added to the water system.At an Impact Fee of$4,234 per LUE,
this would indicate that the City should be collecting approximately $6.07 million
per year in Water Impact Fees if the City's growth rate is as projected starting in
FY-21.
In addition, the wastewater model update assumed that 1,027 LUEs would be
added to the wastewater system per year. At an Impact Fee of $1,799 per LUE,
this would indicate that the City should be collecting approximately $1.85 million
per year in Wastewater Impact Fees if the City's growth rate is as projected in FY-
21.
Comparing these assumptions to the actual Impact Fees collected indicates that
the number of new connections to our water and wastewater systems for FY-21
occurred as expected.
9
Table 4 provides population projections for Round Rock and Round Rock's ETJ.
These projections, anticipating a steady growth rate, indicate that capital
improvements to the City's water and wastewater utility systems would be
necessary to keep up with growth. The annual estimates, shown in parenthesis,
convey a slower growth rate in the City limits than projected by the City in 2010.
However, recent new permits for single family and multi-family projects indicate
that we should "catch back up" to the trend initially projected.
Table 4
Year
•- City's ETJ
• - • . MOF - Projections Growth Rate
2020 (Census) 127,279(119,468) - 182,323 -
2021 130,461 (122,827) 2.4 % (2.7%) 186,062 2.0%
2022 133,723 (124,614) 2.4% (1.4%) 189,881 2.0%
2023 137,066 9.1% 193,508 1.9%
2024 140,492 2.4% 197,218 1.9%
2025 143,302 2.0% 200,312 i 1.5%
2026 146,168 2.0% 203,462 1.5%
2027 149,092 2.0% 206,670 1.6%
2028 152,073 2.0% 209,651 1.4%
2029 155,115 2.0% 212,693 1.4%
2030 1158,217 1 2.0% 215,795 1 1.4%
Notes: 2010 is the base year for all projections in this table
( }Annual Estimates by Planning &Development Services Department
10
Table 5 summarizes the status of the Water System (Impact Fee eligible) Capital
Improvement Projects included in the November 2020 Impact Fee Analysis.
Table 5
Completed Water Projects Completion Impact Fee Report Actual Cost
Estimated Cost
Creek Bend 12"Waterline 2016 $415,000 $415,000
Arterial H Waterline 2017 $856,400 $162,460
BCRUA Water Treatment Plant- Ph 1 B 2018 $34,000 $31,000
South 81 Elevated Storage Tank Pump Station 2019 $157,000 $1,070,900
Arterial H Phase II 2020 $1,470,500 $1,375,045
BCRUA Phase 1 C -WTP Expansion to 32MGD 2020 $4,465,000 $3,635,540
Water Dist. Master Plan & Impact Fee 2020 $66,000 $220,570
GR-05: University Blvd extension from end of 36- 2022 $1,150,000 $775,481
inch main to CR-110
$8,613,900 $7,685,996
Water Projects In Progress Completion Impact Fee Report Actual Cost
Estimated Cost
GR-01: E Liberty Ave, N Shephard St& Fannin 2022 $500,000 $938,983
Ave
GR-02: Kenny Fort Blvd from Forest Creek Blvd 2022 $1,570,000 $1,787,073
to SH45
GR-03: Kenny Fort Blvd from Old Settlers to 2024 $2,450,000 $4,325,000
Chandler Creek
GR-04: Sam Bass Rd from FM-1431 to Wyoming 2025 $7,000,000 $9,980,300
Springs Dr
BCRUA Phase 1 D -WTP Expansion to 42MGD 2025 $4,000,500 $5,067,300
GR-06: Redbud Ln from south of Palm Valley 2026 $4,560,000 $4,560,000
Blvd to Gattis School Rd
BCRUA Phase 2- Deep Water Intake 2027 $60,608,500 $76,874,130
$80,689,000 $103,532,786
11
Upcoming Water Projects Estimated Impact Fee Report
Completion Estimated Cost
GR-07: Hester's Crossing &CR-172 from west 971 zone to S-81 2025 $3,270,000
EST
GR-08: FM-1460 toward Westinghouse Rd, east to future road 2027 $2,350,000
GR-09: Palm Valley Blvd (north side) extension to CR-110 2029 $600,000
GR-10: Loop from GR-09 to Westinghouse to University 2030 $2,440,000
$8,660,000
Table 6 summarizes the status of the Wastewater System (Impact Fee eligible)
Capital Improvement Projects included in the November 2020 Impact Fee
Analysis.
Table 6
Completed Wastewater Projects Completion Impact Fee Report Actual Cost
Estimated Cost
Lake Creek 2 2017 $2,652,000 $1,916,000
Lake Creek 3 2017 $591,000 $563,000
McNutt Creek C2 (referred to as C5) 2018 $1,324,000 $1,762,000
Brushy Creek 5 2018 $288,000 $282,618
Brushy Creek 2 2019 $685,000 $349,000
Brushy Creek 4 2019 $173,000 $173,000
$5,713,000 $5,045,618
Wastewater Projects in Progress Completion Impact Fee Report Actual Cost
Estimated Cost
Lake Creek 1 2022 $1,856,000 $3,150,000
$1,856,000 $3,150,000
12
Upcoming Wastewater Projects Estimated Impact Fee Report
Completion Estimated Cost
MC-1: New 6,760LF of 18-in 2022 $1,973,000
BC-1: Upsize 3,015LF to 12-in and 18-in 2023 $831,000
CC-1: Upsize 3,975LF to 12-in and 15-in 2024 $1,026,000
Forest Creek LS and FM - Increase Capacity 2024 $3,168,000
MC-2: New 9,120LF of 12-in 2025 $1,576,000
MC-3: New 5,155LF of 24-in 2026 $1,602,000
Hilton Head LS and FM - Increase Capacity 2027 $1,751,000
CC-2: Upsize 955LF to 12-in and 15-in 2027 $230,000
WWTP Expansion to 40MGD- PER 2030 $2,500,000
$14,657,000
Table 7 summarizes the status of the Reuse Water System (Impact Fee eligible)
Capital Improvement Projects included in the November 2020 Impact Fee
Analysis.
Table 7
Completed Reuse Projects Completion Impact Fee Report Actual Cost
Estimated Cost
Reuse Phase VI 2016 $900,000 $900,000
Reuse Phase IV-B 2016 $3,719,000 $3,013,152
$4,619,000 $3,913,152
Reuse Projects in Progress Completion Impact Fee Report Actual Cost
I Estimated Cost
1.0 MG Reuse Ground Storage Tank 2023 $1,628,400 $3,200,000
$1,628,400 $3,200,000
Upcoming Reuse Projects Estimated Impact Fee Report
Completion Estimated Cost
Reuse Phase V—Stony Point High School 2023 $614,328
$614,328
13
Figure 6 compares Single-Family Residential Utility Rates for Round Rock to
surrounding Central Texas Municipalities and Municipal Utility Districts. As
depicted, Round Rock utility rates remain among the lowest in the region.
Figure 6
Single-Family Residential
Water and Wastewater Rates Monthly Comparison
$200 Assumes 10,000 gallons water&8,000 gallons wastewater usage
$180
$162.40 $159.83
$160 $155.02
$140 $131.30
$12015
$120 5115.60 S11382
$100 $98.22 $96.90 596.45
591.38 $86 70
$80.11
$80
S72S5 $67.43
$60
$40
$20
S0
San Hutto Austin Pflugervile Leander Paloma Walsh Vista Teravista ll Cedar Teravista 10 Fern Round Georgetown Brushy
Marcos 1&2 Randy Oaks Park Bluff Rock Creek
(Annual
■Water a Wastewater Avg)
* assumes 10,000 gallons water and 8,000 gallons wastewater used
14
Table 8 compares Round Rock's Water and Wastewater Impact Fees to
surrounding cities and Municipal Utility Districts. Historically, Round Rock had one
of the highest total Impact Fees charged for new connections to the water and
wastewater systems. However, several surrounding cities have increased their
fees over the past few years and surpassed Round Rock. Round Rock's
philosophy is for new customers and developments to pay for the required capital
improvements due to the growth.
Table 8
ImpactArea • • . •
Last
otal
Updated Water Wastewater T
Brushy Creek MUD 2012 $2,095 $1,804 $3,899
Round Rock 2020 $4,234 $1,799 $6,033
Cedar Park 2020 $3,160 $3,170 $6,330
San Marcos 2018 $3,801 $2,684 $6,485
Leander 2017 $4,309 $2,820 $7,129
Austin 2018 $4,700 $2,500 $7,200
Pflugerville 2020 $7,897 $1,898* $9,795
Georgetown 2018 $6,921 $3,115* $10,036
Hutto 2021 T- $8,832 $2,788 $11,620
*Indicates the City has two different Wastewater Impact Fees, based on service area. The
number in the table above reflects the lowest fee charged by that City.
15
CONCLUSION AND RECOMMENDATIONS
Due to the volatility in growth rates and infrastructure requirements, the City
recommends a review of the Impact Fees every three to four years. The current
Impact Fees were adopted on January 14, 2021, and went into effect on February
1, 2021.
Over the past several years, the population growth in Round Rock has proceeded
slower than projected in the Impact Fee Analysis. However, the number of
connections to the water and wastewater systems has occurred as anticipated.
The next Capital Improvements Plan Progress Report will be presented to the
CIAC and the City Council in approximately six months.
16
Mayor Councilmembers City Manager
Craig Morgan Michelle Ly Laurie Hadley
Matthew Baker
Frank Ortega
ROUND ROCK TEXAS Mayor Pro-Tem Kristin Stevens City Attorney
PLANNINGANDDEVELOPMENTSERVICES Rene Flores Hilda Montgomery Stephan L.Sheets
May 4,2022
Mayor Morgan
Mayor Pro-Tem Flores
Councilmember Ly
Councilmember Baker
Councilmember Ortega
Councilmember Stevens
Councilmember Montgomery
RE: Capital Improvements Advisory Committee—Semi-Annual Meeting
Dear Mayor Morgan and Council Members:
The Capital Improvements Advisory Committee met on May 4,2022,to consider and approve the
semi-annual report to the City Council with respect to the progress of the Capital Improvements
Plan and identification of any perceived inequities in the Impact Fees.The findings are addressed in
Chapter 395.058(c)of the Texas Local Government Code.
After discussion,the Committee found no perceived inequities in implementing the plan or imposing
the Impact Fee.Therefore,a motion was made to approve and forward the report from the Utilities
and Environmental Services Department to the City Council,with updated city comparison data.
Sincerely,
Jeifer Henderson,Chairman
Capital Improvements Advisory Committee