CM-2022-150 - 6/24/2022F rage 1 01' 3 mv, oai6 Department: Project Name: City Project ID Number Vendor 3ustification Contract Quantity Adjustment/Change Order Utilities and Environmental Services South Interceptor Wastewater Manhole Rehabilitation Date: 5/16/22 Change Order/Quantity REGSI Adjustment No. 2 Cruz Tec Inc. 12210 Ann Lane Houston Texas 77064 281-469-2888 Company Name Address Phone No. SUMMARY Original Contract Price: Previous Quantity Adjustment(s): This Quantity Adjustment: Total Quantity Adjustment(s): Total Contract Price with Quantity Adjustment(s): Previous Change Order(s): This Change Order: Total Change Order(s) To Date: Adjusted Contract Price (Original Contract Price Plus Quantity Adjustment(s) Plus Change Order(s)}: Difference between Original and Adjusted Contract Prices: Original Contract Time: Time Adjustment by previous Quan. Adj./Change Order: Time Adjustment by this Quan. Adj./Change Order: New Contract Time: Prepared By: $113,400.00 20% $23,837.67 4% $137,237.67 24% $703,564.67 -$80,962.33 190 0 158 348 ?q"ttt d for Agjari? Kaldyn Saucedo 11 Printed Name, Title, Company Date ContractsAV—, 0 (AN . r y (�VPKAkL- rJ uw�- �tv Pri ted Name, Title, Company Date City Project Manager: f b�l e Printed %me, TitleI Date Manage ity a A.* 4 �/ i! r%� a*A.�'�- e A' ! Signattke l� Prin ed Name, Title J Date ��— Page 3 or Project Name: South Interceptor Wastewater Manhole Rehabilitation Quan. AdWhange Order No. Uwaffmyusarranc vam ;;Time Item [Wcri n Unit UnttPAw Amount Clot Time Adfutstment Adjustment - 0 50.00 $0.00 158 5 Remove and Replace Existing 48-inch Manhole and Replace with New FRP Manhole, 60-inch Dia., W W, Including Surface Restoration to Existing Conditions, per Plans EA As 12.500 S (12,500.00) 6 Pipe. I&inch Die.. SDR26 PVC, Including Excavation and Backtill, W W LF -30 $ 300 S (9,000.00) 7 Cast in Place Drop Manhole 60-inch Diameter, W W EA -I $ 19,500 $ (19,500.00) 8 Abandonment of Existing 18-inch Wastewater Line (Grout in Place) LF -30 S 250 S (7,500.00) 9 Mulch Sock LF -110 S 25 S (2,750.00) IS Rework Bench and Trough (EX MH 1464173) EA -I $ 650 $ 23 24-inch PVC Pipe to Re -Tie to the New Manhole LF .10 S 300 S (3,000.00) 24 Trench Safety Plan LF -50 $ 175 S (8,750.00 25 Siablized Construction Entrances EA -2 S 2.750 S (5,500.00) 28 Tree Protection LF -100 $ 25 S (2,500.00 3 32" Standard Framc and Cover EA -9 S 1.500 S (13,500.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 ases.158.081 1; 11agc 2 of 3 Project Name: South Interceptor Wastewater Manhole Rehabllltation Quan. Adj./Change Order No.: Chenoe Order Data f Item d Itern DescAption Unit Qty. Unit Price Amount Contract Time Adjustment CO 2-1 Restocking Fee Cast in Place Drop Manhole 60-inch Diameter, WW EA 1 $1.205.69 $1,205.69 CO2-2 Remove and Replace Existing 48-inch Manhole and Replace with New FRP Manhole, 60-inch Dia., WW, including Surface Restoration to Existing Conditions, per Plans LA l $9.131.98 $9,131.98 CO2-3 Furnish All Materials, Equipment, fools & Labor Necessary for Installation of Fiberglass Manhole Liners (48-inch Diameter Manholes) per Technical Specifications V111 10 $1.350.00 $13,500.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 S0.00 $0.00 S0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 City of Round Rock JROU ND ROCK �+SAgenda Item Summary Agenda Number: Title: Consider executing Quantity Adjustment/Change Order No. 2 with Cruz Tec, Inc. for the South Interceptor Manhole Rehabilitation Project. Type: City Manager Item Governing Body: City Manager Approval Agenda Date: 6/24/2o22 Dept Director: Michael Thane, Utilities and Environmental Services Director Cost: Indexes: Attachments: Change Order 2—Signed, Map Department: Utilities & Environmental Services Text of Legislative File CM-2022-250 This agenda item is Change Order/ Quantity Adjustment (QA/CO) No. 2 for the construction phase of the South Interceptor Wastewater Manhole Rehabilitation project. The South Wastewater Interceptor was constructed in 1984 and is co -owned by the City of Round Rock and the City of Austin. Recent inspections of the South Wastewater Interceptor indicated deteriorating conditions of the manholes located along the entire length of the wastewater line. Deteriorating manholes can lead to infiltration of water into the wastewater line, and if left untreated, the failure of the manhole. This project consisted of the extensive rehabilitation of 61 manholes which restored the service life of the manholes and wastewater interceptor. This QA/CO No. 2 includes the addition of a 48-inch fiberglass insert and the deletion of an 18-inch wastewater line, a fiberglass manhole, and the abandonment of an 18-inch wastewater line due to a field adjustment. To accommodate production delays and fiberglass procurement issues, an additional 158 days is necessary to complete construction. QA/CO No. 2 constitutes a credit of $61,312.33 to be given to the City of Round Rock. Cost: $-61,312.33 Source of Funds: Self -Financed Wastewater Construction City of Round Rock Page 1