Contract Quantity Adjustment/Change Order
General Services
Round Rods Public Library
Date: 7/28/22
Change Order/Quantity
Adjustment No. 3
ks the project progresses, minor changes incur some costs. Many of these changes were missing on the plan or changes that needed to be
nade in the field. This Change Order represents the largest cost changes not covered by the Owner's Betterment Allowance within the
xonstruction contract. This change order includes the follow OB's: 094 - 093 - 092 - 091 - 088 .
SUMMARY
Original Contract Price:
Previous Quantity Adjustment(s):
This Quantity Adjustment:
Total Quantity Adjustment(s):
Total Contract Price with Quantity Adjustment(s):
Previous Change Order(s):
This Change Order:
Total Change Order(s) To Date:
Adjusted Contract Price [Original Contract Price Plus
Quantity Adjustment(s) Plus Change Order(s)]:
Difference between Original and Adjusted Contract Prices:
Original Contract Time:
Time Adjustment by previous Quan. Adj./Change Order:
Time Adjustment by this Quan. Adj./Change Order:
Amount
Change
0.00
$49,921.00 0.00
$49,921.00 0.00
$29,946,252.00
$149,446.00
578/578
0
0
New Contract Time: 578/578
Prepared By:
., 6-elt
Richard Will, Construction Manager, CORR
Signature
Printed Name, Title, Company
Date
ki A. PrqipJm P
Contractor:
-
g re
Printed Name, Tide, Com any
Date
City Project
�
Manager:
Chad McDowell General Services Director CORK
Mayor/City
Mananar
nature
i
Printed Name, Tide
1 R/n n47q All/ lti �G tr.
Date
ClI2 I2 2-
C,/v)- z b Z -2- - Zb �-
ROIINO ROb[ i i �.t
Project Name:
Quan. Adj. / Change Order No.:
Contract Quatity Adjustment/ Change Order
Change Order Data
Round Rock Public Library
Item #
Item Description
Unit
Qty.
Unit Price
Amount
Contract Time
Adjustment
(Days)
1
OB 094 - COR 145 - Lib Monumental Stair
Diffuser Grille Size
LS
1
$753.00
$ 753.00
0
2
OB 093 - COR 141 - Parking Guidance
Di ital Si na a with Aluminum Angle
L5
1
$8,353.OD
$ 8,353.00
0
3
OB 092 - COR 134 - Staff Service Elevator
Architectural vs Structural Dimensions
LS
1
$12,719.00
$ 12,719.00
0
4
OB 091 - COR 133 - Library and Site
Communications Site Tie-in and Quazite
Box Confirmation and T&M Work
LS
1
$14,276.00
$ 14,276.00
0
5
OB 088 - COR 122 - Lib Duct Insulation
Tvoe at Exposed Ceilings
LS
1
$10,827.00
$ 10,827.00
0
6
$ -
$
7
$
$
8
$
$
9
$
$
10
$
$
11
$
$
12
$
$
13
$
$
14
$
$
15
$
$
Subtotal
$ 46,928
Insurancel 0.759%
$ 356
Subtotal
$ 47,284
Bond 0.55%
$ 260
Subtotal
$ 47,544
Fee 5%
$ 2,377
TOTALS S 49,921
ROUtNO ROdC TEXAS
Gera.. am
Round Rock Library
Change Order # 003 Summary
Date: 07/28/2022
Change Order # 3 to contract with Hensel Phelps Construction Co.
Cost: $49,921.00
Overview:
As the project progresses, minor changes incur some costs. This Change Order represents the largest cost
changes not covered by the Owner's Betterment Allowance within the construction contract.
1. OB 094 - COR 145: Lib Monumental Stair Diffuser Grille Size
2, OB 093 - COR 142: Parking Guidance Digital Signage with Aluminum Angle
3. OB 092 - COR 134: Staff Service Elevator Architectural vs Structural Dimensions
4. OB 091- COR 133: Library and Site Communications Site Tie-in and Quazite Box Confirmation and
T&M Work
5. OB 088 - COR 122: Lib Duct Insulation Type at Exposed Ceilings
Betterment (encumbered in contract)
Original
$750,000.00
Remaining to Date
$0
Change Order 001-002 Total Remaining to Date
$ 99,525.00 $ 52,693.94
hd
u
cc
C
Z
O
Cd
aL
O
s � �
3 G
W �
dy u
u o
W
? Z S
G u "i A i v g w u 0 •I
V C A q
6p m E c Y '_ ' e v o q C
�Ey; ^aSgH v c
b M O Y yl m S FL- C .pp s y�
_ �� 3 a'vmiv6 00� Y •' n�
w� c N n? m E
O
b
m� g m�
M m Y c
a• 6 a� 4 6
�usi Y� c
m g qCq C
F N E L N
r q M L Y C R
e
8 8
h !/1
W
4
Y
N
tYJ Y
C C
E
a
3
�
L'
C
m
Y
o
pp� m
Oil
Z�
x
M_
Sm
7
05
N
N
N
N
G
b
N
Y.
n
rl
N
k
�
A
E
o
-
o
j
J
u
i
S
S
�
q
[
a y
a c
G
8g€
�
Pa
08
Or
N
N
ryH
m
M
y
N
ROUND Roca
TEXAS
City of Round Rock
Agenda Item Summary
Agenda Number:
Title: Consider executing Quantity Adjustment/Change Order No. 3 with Hensel Phelps
Construction Co. for the Library Project.
Type: City Manager Item
Governing Body: City Manager Approval
Agenda Date: 9/2/2022
Dept Director: Chad McDowell, General Services Director
Cost: $49,921.00
Indexes: 2014 General Obligation Bonds
Attachments: Change Order No. 3
Department: General Services
Text of Legislative File CM-2022-207
As the project progresses, minor changes incur some costs. Many of these changes were missing on the
plan or changes that needed to be made in the field. This Change Order represents the largest cost changes
not covered by the Owner's Betterment Allowance within the construction contract.
Cost: $49,921.00
Source of Funds: 2014 General Obligation Bonds
City of Round Rock Page 1 of 1