TB-2020-002 - 2/27/2020 i
RESOLUTION NO. TB-2020-002
WHEREAS, the Round Rock Transportation and Economic Development Corporation
("Owner") and Hensel Phelps Construction Company ("Construction Manager") entered into that
certain Construction Manager at Risk Agreement("Agreement")dated April 26,2018;and
WHEREAS, Owner and Construction Manager have determined that it is necessary to amend the
Agreement;and
WHEREAS, Owner wishes to enter into Amendment No. 1 to the Agreement with Construction
Manager,Now Therefore
BE IT RESOLVED BY THE BOARD OF DIRECTORS OF THE ROUND ROCK
TRANSPORTATION AND ECONOMIC DEVELOPMENT CORPORATION,
That the President is hereby authorized and directed to execute on behalf of the Round Rock
Transportation and Economic Development Corporation, Amendment No. 1 Contract for Construction
Round Rock Convention Center Guaranteed Maximum Price Contract, a copy of same being attached
hereto as Exhibit"A"and incorporated herein for all purposes.
The Board of Directors hereby finds and declares that written notice of the date, hour,place and
subject of the meeting at which this Resolution was adopted was posted and that such meeting was
open to the public as required by law at all times during which this Resolution and the subject matter
hereof were discussed, considered and formally acted upon, all as required by the Open Meetings Act,
Chapter 551, Texas Government Code, as amended.
RESOLVED this 27th day of February, 2020.
By:
— /"o 7
CRAIG ORG , President
Round Rock Trkisportation and Economic
Development Corporation
ATTEST:
JON LOAN, Secretary
0112.20202;00440011
l r
EXHIBIT
«A„
AMENDMENT NO. 1
CONTRACT FOR CONSTRUCTION
ROUND ROCK CONVENTION CENTER
GUARANTEED MAXIMUM PRICE CONTRACT
This Guaranteed Maximum Price Amendment No. 1 (this "Amendment") to the Construction
Manager at Risk Agreement for the Round Rock Convention Center(the"Project") is made and entered
into by and between Round Rock Transportation and Economic Development Corporation ("Owner")
and Hensel Phelps Construction Company("Construction Manager"), (sometimes collectively referred
to as the"Parties"), effective as of the date set forth below.
WHEREAS, Owner and Construction Manager entered into that certain Construction Manager at Risk
Agreement(AIA Documents Al 33—2007 and A201 —2007 as modified by the parties,and all Exhibits
thereto,)dated April 26, 2018 (the"Agreement"); and
WHEREAS, in the Agreement, Construction Manager and Owner have previously approved a
Stipulated Sum for the performance of the Pre-Construction Phase Services,a Construction Manager's
Fee,and a Stipulated Sum for the performance of the General Conditions;and
WHEREAS, in compliance with the Agreement, as amended hereby, Construction Manager has
submitted its final GMP Proposal for the Convention Center, (the "Scope of Work") as required for
completion the Project, including the Cost of the Work, in accordance with the Contract Documents
and as reasonably inferable therefrom;
NOW THEREFORE, on the basis of the analysis, investigations, reports and other work processes
and products developed in the Preconstruction Phase, Construction Manager hereby submits its
Guaranteed Maximum Price ("GMP") Proposal for the completion of the Project pursuant to the
Contract Documents, and Owner and Construction Manager agree to modify and amend the
Agreement, as follows:
1. All terms used herein shall have the same meaning as such terms have in the Agreement,except
as expressly stated otherwise herein.
2. The Scope of Work covered by this Guaranteed Maximum Price Amendment shall include
the Work described in the Contract Documents for the Convention Center Project listed in Attachment
1 and as further described in the Contract Documents.
3. Owner and Construction Manager hereby agree that the Guaranteed Maximum ['rice for the
Convention Center Project is set forth as follows:
1 The General Conditions Lump Sum is $1,902,386.00.
GMP Amendment No. 1 Page 1 of 4
.2 The Subcontracted Work is $44,980,186;
.3 The portion of the Construction Contingency allocated to this Project is
$562,252.00;
.4 The amount for Bonds, Insurance and SDI is $1,158,782.00
.5 The Construction Manager's Fee is $1,336,599.00; and
.6 There is an Allowance to provide LT Light Fixtures at the event barn for$30,000
(the price of which is included in the amounts above, and if not selected will be
credited back to the Owner).
Accordingly, the Guaranteed Maximum Price for the Convention Center Project is Forty-Nine
Million, Nine-Hundred and Forty Thousand, Two-Hundred and Five Dollars ($49,940,205.00),
which includes all Work previously approved by any prior Work Authorization Letter and prior
payments therefor.
4. The Schedule of Values for the Work is set forth in Attachment 2.
5. The GMP is based upon the Clarifications and Assumptions as set forth in Attachment 3.
Attached to the Clarifications and Assumptions is the Convention Center RFI Log, the purpose of
which is to list specifically which RFI items are associated with the Convention Center Project and the
cost of which is confirmed to be included in the GMP.
6. Schedule. The Substantial Completion date for the Project is reaffirmed to be November 1,
2020, and the Project Schedule is attached hereto as Attachment 4. The parties hereto acknowledge
and agree that the Contract Time (including all scheduling) requirements set forth in the Agreement,
together with the Liquidated Damages applicable to the Contract Time requirements as set forth in the
Contract, are hereby affirmed.
7. General Conditions. The amount of General Conditions Costs for the Convention Center
Project as set forth in Exhibit F of the Agreement is increased to $1,902,386.00. This increase of
$148,914.00 is to move all Layout and Control Costs from Cost of Work to the fixed General
Conditions.
8. Effect of GMP Amendment No. 1. The Parties agree that GMP Amendment No. I amends
the Agreement, as set forth herein and that, otherwise, the Agreement, as amended, is hereby ratified,
approved, and confirmed.
9. Construction Manager Designated Representative.Joseph Sanders is added as a Designated
Representative for the Construction Manager as set forth in Exhibit A of the Agreement.
GMP Amendment No. 1 Page 2 of 4
l
10. Execution and Authorized Signatures. By its signature below, Construction Manager
certifies that all necessary corporate acts have been taken to authorize the signing of this Agreement
and to bind Construction Manager.
11. Effective Date. The Parties acknowledge that due to the maximum financial responsibility
of the Round Rock Transportation Authority and Economic Development Corporation as set forth in
Exhibit L to the Agreement, this GMP Amendment shall be effective upon the Effective Date as set
forth herein below. Round Rock Transportation Authority and Economic Development Corporation
is anticipated to execute this GMP Amendment at a later date, but this GMP Amendment shall be
immediately effective upon the execution by KR CC, Inc. and Hensel Phelps and that Construction
Manager shall not challenge the efficacy of this GMP Amendment based upon the timing of execution
by Round Rock Transportation Authority and Economic Development Corporation.
12. Preconstruction Services. The parties entered into a Preconstruction Agreement for the
Preconstruction phase of the Round Rock Convention Center and Kalahari Hotel, Waterparks and
Infrastructure (the "Preconstruction Agreement"). Pursuant to the terms of the Preconstruction
Agreement,if Hensel Phelps was awarded the construction for the Convention Center(the"Convention
Center") and Hotel, Waterparks, and Infrastructure ("Hotel and Waterpark") Projects, then the fee
(total amount) paid by the Owner's, respectively, would be reduced by Twenty-Five Percent (25%).
Due to various reasons, including those raised by Construction Manager in its November 18, 2019
letter, KR Acquisitions, as Owner of the Hotel and Waterpark Project(and the Owner pursuant to the
Preconstruction Agreement), has agreed to the following as full resolution of the issues raised in the
Construction Manager's November 18, 2019 letter which is attached hereto as Attachment 5:
(1) Pay to Construction Manager the remaining balance of $112,963.00 which shall total
$765,000.00 paid in full to Construction Manager pursuant to the Preconstruction Agreement;
(2) If Construction Manager reaches Substantial Completion of both the Convention Center and Hotel
and Waterparks Project by November 1,2020,then Owner will waive the Twenty-Five Percent(25%)deduction
owed by Construction Manager. If, however, Substantial Completion is not reached by November 1, 2020 for
both Projects, then Construction Manager will return the Twenty-Five Percent (25%) paid pursuant to this
Section 12 of GMP Amendment No. 1, via deductive Change Order.
The foregoing is a full settlement of the issues raised in Construction Manager's November 18, 2019 letter,
neither party acknowledging any liability regarding same, but rather for the purposes of avoiding any disputes
related to the statements contained therein.
GMP Amendment No. 1 Page 3 of 4
Effective Date of this Amendment is December 24, 2019.
AGREED:
Hensel Phelps
A Delaware efe al-Partnership
B ra mans Its: Vice President
KR CC,Inc.,
A Delaware Company
By: Todd R.Nelson Its: President
ROUND ROCK TRANSPORTATION
AND ECONOMIC DEVELOPMENT
CORPORATION
By:
Its:
GMP Amendment No.1 Page 4 of 4
GMP Amendment No. 1 - Attachment 1
KALAHARI CONVENTION CENTER
Z =
DRAWING LOG
u u
O W O 0 W V
O O O Q J
Y a K
O Y O V O N
V
Z
U a U A J = O
Z
J J i U
o 0 0 0 0
� O � 2 2 2 2 2
Z 2N W
O o O y b ry n O J w J
U Z U W W O W
O
GENERAL
CAO 000 COVER
CAO 001 SHEETINDEX J J
A0.002 PROJECT INFORMATION
AO 003 BUILDING SUMMARY
JA0.010 OVERALL SECTOR PLAN
CA0.020 CITY OF ROUND ROCK PLAN REVIEW COMMENTS
CA0.101 CONVENTION CENTERAREA PLAN LEVEL 01
CA0.102 CONVENTION CENTER AREA PLAN LEVEL 02
LIFE SAFETY
CALS.101 CONVENTION CENTER-LIFE SAFETY PLAN-LEVEL 01
'I -7ffff
CALS.102 CONVENTION CENTER-LIFE SAFETY PLAN-LEVEL 02
ARCHITECTURAL
A1.000 OVERALL SITE PLAN
A1.001 OVERALL SITE PLAN-SOUTH PORTION
A1.100 DIMENSIONAL CONTROL PLAN
CA2.101 CONVENTION CENTER-OVERALL LEVEL 01 FLOOR PLAN
7A2.102 CONVENTION CENTER-OVERALL LEVEL 02 FLOOR PLAN
CA2.103 CONVENTION CENTER-OVERALL ROOF PLAN
CA2.201.A CONVENTION CENTER LEVEL 01-SECTOR'A'
CA2.201.6 CONVENTION CENTER LEVEL 01-SECTOR'B'
CA2.201.0 CONVENTION CENTER LEVEL 01-SECTOR'C' > 19 10 0 0. In a 0 Ml I M
CA2.201.0 CONVENTION CENTER LEVEL 01-SECTOR'D'
CA2.201.E CONVENTION CENTERLEVEL01-SECTOR'E'
CA2.201.F CONVENTION CENTER LEVEL 01-SECTOR'F'
CA2,202.A CONVENTION CENTER-LEVEL 02-SECTOR'A d B' Ml I 1 101
CA2.202.0 CONVENTION CENTER LEVEL 02-SECTOR'C'
72.202.D CONVENTION CENTER-LEVEL 02-SECTOR'D'
CA2.202.E CONVENTION CENTERLEVEL02-SECTOR'E'
CA2.202.F CONVENTION CENTER LEVEL 02-SECTOR'F'
CA2.203.A CONVENTION CENTER-ROOF-SECTOR A'
CA2.203.B CONVENTION CENTER-ROOF-SECTOR'S'
CA2.203 C CONVENTION CENTER-ROOF-SECTOR'C'
CA2203D CONVENTION CENTER-ROOF-SECTOR'0'
CA2.203.E CONVENTION CENTER-ROOF-SECTOR'E'
CA2.203 F CONVENTION CENTER-ROOF-SECTOR'F'
101 1
CA2.221 SINGLE-PLY ROOFING DETAILS
CA2.222 SINGLE-PLY ROOFING DETAILS
CA2.301 LEVEL Ot ENLARGED RESTROOMS
GMP Amendment No. 1 - Attachment 1
oNx
KALAHARI CONVENTION CENTER
= Z
WW 2
DRAWING LOG ano � W
_ Z a
O U O < O h
Z
U S U 1 = Z O
Z J J 1 U o 0 o e o
Y Z 2 2 2 Z
2 O =
N N N 0 Z 2 Z 2 2
O as O
U Z U W O yi J J J J
a O K C p _ O J
p O O _ N > ? R 7
CA2.303 LEVEL 01 ENLARGED RESTROOMS 101 101
CA2.305 LEVEL 02 ENLARGED RESTROOMS IN I Mi
CA2.306 LEVEL 01 ENLARGED RESTROOMS IN I MI
CA2.307 LEVEL 02 ENLARGED RESTROOMS 101 1 01
CA2.308 LEVEL 02 ENLARGED RESTROOMS 1 101 101 1 Mi
CA2.401.A CONVENTION CENTER FINISH PLAN LEVEL 01 SECTOR'A'
CA2.401.B CONVENTION CENTER FINISH PLAN LEVEL 01 SECTOR'B'
CA2.401.0 CONVENTION CENTER FINISH PLAN LEVEL 01 SECTOR'C'
CA2 401.13 CONVENTION CENTER FINISH PLAN LEVEL 01 SECTOR'D'
CA2.401.E CONVENTION CENTER FINISH PLAN LEVEL 01 SECTOR E'
CA2.401.F CONVENTION CENTER FINISH PLAN LEVEL 01 SECTOR F'
CA2 402 C CONVENTION CENTER FINISH PLAN LEVEL 02 SECTOR'C'
CA2A02.13 CONVENTION CENTER FINISH PLAN LEVEL 02 SECTOR'D'
CA2.402.E CONVENTION CENTER FINISH PLAN LEVEL 02 SECTOR'E'
CA2.402.F CONVENTION CENTER FINISH PLAN LEVEL 02 SECTOR'F'
CA3.001 PARTITION TYPES
CA3.002 PARTITION HEAD AND FRAMING DETAILS
CA3.003 GYP.BOARD DETAILS
CA3,004 GYP.BOARD DETAILS
CA3.100 METAL FABRICATIONS
CA3.101 METAL FABRICATIONS
CA3.200 BOH ADAAG/ANSI TOILET LAYOUTS AND STD.ACCESSORIES
CA3,201 FOH ADAAG/ANSI TOILET LAYOUTS AND STD.ACCESSORIES
CA3.202 ACCESSORIES,WALL PROTECTION EQUIPMENT
CA3.300 DOOR,SAFETY GLAZING.AND LOUVER INFORMATION
CA3.301 DOOR SCHEDULE
CA3.302 DOOR DETAILS
CA3.304 PARTITION HEAD DETAILS
CA3.401 FLOOR TRANSITIONS
CA3.500 STD.CABINET DETAILS
CA3.501 BOH INTERIOR ELEVATIONS
CA3.600 INTERIOR FINISH SCHEDULE
CA3.601 INTERIOR FINISH SCHEDULE
CA3.602 BOH ROOM FINISH SCHEDULE Mi
CA3.603 PLUMBING FIXTURES
CAJ 604 PLUMBING FIXTURES
CAJ 605 PLUMBING FIXTURES
CA3.606 PLUMBING ACCESSORIES
CA3.607 PLUMBING ACCCESSORIES
CA3.608 DOOR HARDWARE SELECTIONS
CA3.611 INTERIOR ELEVATIONS
GMP Amendment No. 1 - Attachment 1
KALAHARI CONVENTION CENTER
z z
DRAWING LOG
f f 2
J � �
U V W
O O O W V
❑ O O Q J
Z Z U
O U O Q N
UQa U 6 J Z 2
❑ J � i O o 0 0
= u e o
O _ = Z Z Z 2 2
Z Q Z OW 2 2 2 2 Z
O ❑ O b w ry ry
J rc rc p J w
CA3.612 INTERIOR ELEVATIONS
CA3.617 INTERIOR ELEVATIONS El NJ
CA3.615 INTERIOR ELEVATIONS 01
CA3.616 INTERIOR ELEVATIONS
CA3.617 INTERIOR ELEVATIONS
CA3.730 MILLWORK DETAILS
CA3.735 MILLWORK DETAILS
A4 001 CEILING DETAILS
CA4002 CEILING DETAILS
CA4.101 CONVENTION CENTER-RCP-LEVELW
CA4.102 CONVENTION CENTER-RCP-LEVEL 02
CA4.201.A CONVENTION CENTER-RCP-LEVEL 01-SECTOR'A'
CA4.201.B CONVENTION CENTER-RCP-LEVEL 01-SECTOR'B'
CA4.201.0 CONVENTION CENTER-RCP-LEVEL 01-SECTOR'C'
CA4.201.D CONVENTION CENTER-RCP-LEVEL 01SECTOR'D'
CA4.201.E CONVENTION CENTER-RCP-LEVEL 01 SECTOR'E'
CA4.201.F CONVENTION CENTER-RCP-LEVEL 01SECTOR'F
CA4.202.0 CONVENTION CENTER-RCP-LEVEL 02 SECTOR'C'
CA4.202.D CONVENTION CENTER-RCP-LEVEL 02-SECTOR'D'
CA4.202.E CONVENTION CENTER-RCP-LEVEL 02-SECTOR'E'
CA4.202.F CONVENTION CENTER-RCP-LEVEL 02-SECTOR'F'
CA4.203 CONVENTION CENTER-RCP-KILIMANJARO BALLROOM > 101 MIN Mi
CA4.204 CONVENTION CENTER-RCP-KILIMANJARO BALLROOM
CA4.205 CONVENTION CENTER-RCP-KALAHARI BALLROOM > IMI 0101
CA4,300 ENLARGED RCP
CA5001 EXTERIOR MATERIALS SCHEDULE
CA5010 OVERALL PERSPECTIVES AND IMAGES
CA5.101 CONVENTION CENTER ELEVATIONS
CA5.102 CONVENTION CENTER ELEVATIONS
CA5.210 ENLARGED ELEVATIONS
CA5.211 ENLARGED ELEVATIONS
CA5.212 ENLARGED ELEVATIONS
CA5.213 ENLARGED ELEVATIONS
CA5.240 ENTRY PORTE COCHERE
CA5.250 ENTRY TRELLIS
CA5.251 ENTRY TRELLIS DETAILS
CAS.301 WINDOW AND LOUVER TYPES
CA5.302 WINDOW AND LOUVER TYPES
CA6.001 BUILDING SECTIONS
CA6.101 CONVENTION CENTER-WALL SECTIONS
CA6.102 CONVENTION CENTER-WALL SECTIONS
CA6.103 CONVENTION CENTER-WALL SECTIONS
GMP Amendment No. 1 - Attachment 1
7
g
KALAHARI CONVENTION CENTER
z z
W W Z
DRAWING LOG °U
U U W
O O O
Z ,
z a a
U O H
O Q a Z z
U y U O o0
F z w a 6 0 e z
O = = z z i
z i
N N N N 2 Z 2 2 Z
2 Q zH -
z U W W W W W J J J
U j O
O O O ¢ - - H > > IJ > >
CA6.104 CONVENTION CENTER-WALL SECTIONS
CA6.105 CONVENTION CENTER-WALL SECTIONS
CA6.106 CONVENTION CENTER-WALL SECTIONS
CA6.107 CONVENTION CENTER-WALL SECTIONS im
CA6.108 CONVENTION CENTER-WALL SECTIONS
CA6.109 CONVENTION CENTER-WALL SECTIONS
CA6.110 CONVENTION CENTER-WALL SECTIONS
CA7.000 TYPICAL FOUNDATIONS DETAILS
CA7.001 BELOW GRADE WATERPROOFING DETAILS
CA7.011 STONE DETAILS-RIGID INSULATION
CA7.012 STONE DETAILS-RIGID INSULATION
CA7.021 EIFS DETAILS
CA7.022 EIFS DETAILS
CA7.031 CEMENT PANEL DETAILS
CA7.101 SECTION DETAILS
CA7.102 SECTION DETAILS
CA7.103 SECTION DETAILS
CA7.104 SECTION DETAILS IN in NJ
CA7.201 PLAN DETAILS
CA7.202 PLAN DETAILS
CA7.203 PLAN DETAILS
CA7.204 PLAN DETAILS
CA8.001 TYPICAL STEEL STAIR PLANS,SECTIONS,AND DETAILS
CA8.002 METAL SCREEN GUARDRAIL DETAILS
CA8.101 STAIR CST-01-PLANS AND SECTIONS
CA8.201 ELEVATOR DETAILS
CA8.202 ELEVATORS CS-01,-02.AND-03-PLANS AND SECTIONS
CA8.301 TYPICAL ESCALATOR DETAILS
ELECTRICAL
CE0.00 NOTES,SYMBOLS.LEGEND&ABBREVIATIONS
CE1.100 ELECTRICAL DETAILS 7 19
CE1.300 LIGHT FIXTURE SCHEDULE
CEU2.101 CONVENTION CENTER-UNDERFLOOR PLAN-LEVEL 01
CEU2.201.A CONVENTION CENTER-UNDERFLOOR PLAN-SECTOR'A'
CEU2.201.B CONVENTION CENTER-UNDERFLOOR PLAN-SECTOR'S'
CEU2.201.0 CONVENTION CENTER-UNDERFLOOR PLAN-SECTOR'C'
CEU2.201.0 CONVENTION CENTER-UNDERFLOOR PLAN-SECTOR'D'
CEU2.201.E CONVENTION CENTER-UNDERFLOOR PLAN-SECTOR'E'
CEU2.201.F CONVENTION CENTER-UNDERFLOOR PLAN-SECTOR'F'
CE2.101 CONVENTION CENTER-FLOOR PLAN-LEVEL 01
GMP Amendment No. 1 - Attachment 1
KALAHARI CONVENTION CENTER
z z
DRAWING LOG JJ °
U U
0D Q
V W j
Z 2 U Y G rc
H
O V O u
O
S Z
a
J 2
Z o l o e G
2 i 2 2 Z
O O O K J J J J J
CE2.102 CONVENTION CENTERFLOOR PLANLEVEL02
CE2.103 CONVENTION CENTER-OVERALL CLERESTORY PLAN
CE2.104 CONVENTION CENTER-ROOF PLAN
CE2.201.A CONVENTION CENTERLEVEL01-SECTOR'A'
CE2.201.B CONVENTION CENTER-LEVEL 01SECTOR'B'
CE2.201.0 CONVENTION CENTER-LEVEL 01SECTOR'C'
CE2.201.D CONVENTION CENTER-LEVEL 01 SECTOR'D'
CE2.201E CONVENTION CENTER-LEVEL 01SECTOR'E'
CE2.201.F CONVENTION CENTER-LEVEL 01-SECTOR'F'
CE2-202A CONVENTION CENTER-LEVEL 02-SECTOR'A'
CE2.202.B CONVENTION CENTER-LEVEL 02-SECTOR'S'
CE2.202.0 CONVENTION CENTER-LEVEL 02-SECTOR'C'
CE2.202.D CONVENTION CENTER-LEVEL 02-SECTOR'D'
CE2.202.E CONVENTION CENTER-LEVEL 02-SECTOR'E'
CE2.202.F CONVENTION CENTER-LEVEL 02-SECTOR'F'
CE2.203 A CONVENTION CENTER-ROOF-SECTOR A'
CE2.203.B CONVENTION CENTER-ROOF-SECTOR B'
I MIN
CE2203.0 CONVENTION CENTER-ROOF-SECTOR'C'
CE2.203.D CONVENTION CENTER-ROOF-SECTOR'0
72.203.E CONVENTION CENTER-ROOF-SECTOR E'
CE2.203.F CONVENTION CENTER-ROOF-SECTOR'F'
CE3.100 ENLARGED LEVEL 01-GRAND BALLROOM-POWER
CE3.101 ENLARGED LEVEL 02-JUNIOR BALLROOM-POWER
CE3.102 ENLARGED FLOOR PLANS-POWER
CE/.101 CONVENTION CENTER-RCP-LEVEL 01
CE/.102 CONVENTION CENTER-RCP-LEVEL 02
CE4.201A CONVENTION CENTER-RCP-LEVEL 01 SECTOR'A'
CE1.201.B CONVENTION CENTER-RCP LEVEL 01SECTOR'B'
CE4.201.0 CONVENTION CENTER-RCP-LEVEL 01-SECTOR'C'
CE4.201.D CONVENTION CENTER-RCP-LEVEL 01-SECTOR D'
CE4.201 E CONVENTION CENTER-RCP-LEVEL 01-SECTOR'E'
CE4.201.F CONVENTION CENTER-RCP-LEVEL 01-SECTOR'F'
CE4.202.0 CONVENTION CENTER-RCP-LEVEL 02-SECTOR'C'
CE4202.D CONVENTION CENTER-RCP-LEVEL 02.SECTOR'D'
CE1.202.E CONVENTION CENTER-RCP-LEVEL 02-SECTOR'E'
CE1.202.F CONVENTION CENTER-RCP-LEVEL 02-SECTOR'F'
CES.000 ELECTRICAL FEEDER SCHEDULES
CE5.010 SCHEMATIC ONE-LINE DIAGRAM-CONVENTION CENTERir
CES 011 SCHEMATIC ONE-LINE DIAGRAM-CONVENTION CENTER
CE5.012 SCHEMATIC ONE-LINE DIAGRAM-CONVENTION CENTER ,ffilu
GMP Amendment No. 1 - Attachment 1
KALAHARI CONVENTION CENTER
W W Z
DRAWING LOG 00
U U
O OO W U
o O O Q J
2 Q 2 IL R
ICO
� O U O
-6, 0 0 0
rZ � J J � U � � o � o
O f = N Z 2 2 Z 2
Z
2 Q Z n W F H
O O O O J J
V 2
J p K 1 O J
Q O O K - - N J J J J J
CE6.010 ELECTRICAL PANEL BOARD SCHEDULES
CE6.011 ELECTRICAL PANEL BOARD SCHEDULES
CE6.012 ELECTRICAL PANEL BOARD SCHEDULES
CE6.013 ELECTRICAL PANEL BOARD SCHEDULES
CE6.014 ELECTRICAL PANEL BOARD SCHEDULES
CE6.016 ELECTRICAL PANEL BOARD SCHEDULES
CE6.016 ELECTRICAL PANEL BOARD SCHEDULES
CE6.W7 ELECTRICAL PANEL BOARD SCHEDULES
CE6.018 ELECTRICAL DIMMING SCHEDULES
CE6.019 ELECTRICAL DIMMING SCHEDULES
CE7.010 CONVENTION CENTER-LIGHTING CONTROL RISER DIAGRAM
CE8.100 FOOD SERVICE CENTRAL STORAGE PLAN-ELECTRICAL
CE8.1005 FOOD SERVICE CENTRAL STORAGE PLAN SCHEDULE
CE8.101 FOOD SERVICE BANQUET STAGING SERVICE STATIONS-ELECTRICAL
CE8.101 Sa FOOD SERVICE BANQUET STAGING SERVICE STATIONS-SCHEDULES
CE8.101 Sb FOOD SERVICE BANQUET STAGING SERVICE STATIONS-SCHEDULES
FOOD SERVICE
CFS1.000 CONVENTION CENTER-LEVEL 01-OVERALL LAYOUT
CFSI.IOO CENTRAL STORAGE-LAYOUT
CFS1.101 STAGING KITCHEN/BEVERAGE STATIONS/COFFEE SERVICE ROOM LAYOUTS
CFS1.200 CENTRAL STORAGE-PLUMBING
CFSI 201 STAGING KITCHEN/BEVERAGE STATIONS I COFFEE SERVICE ROOM-PLUMBING
CFSI.300 CENTRAL STORAGE-ELECTRICAL
CFS1.300S CENT RAL STORAGE-ELECTRICAL SCHEDULE
CFS1.301 STAGING KITCHEN/BEVERAGE STATIONS/COFFEE SERVICE ROOM-ELECTRICAL Mi M 1 01
CFS1.400 CENTRAL STORAGE-SPECIAL CONDITIONS 1 01
CFS7.401 STAGING KITCHEN/BEVERAGE STATIONS/COFFEE SERVICE ROOM-SPECIAL CONDITIONS
CF 52.100 BEVERAGE STATION-LAYOUT
CFS2.200 BEVERAGE STATION-PLUMBING
CFS2.300 BEVERAGE STATION-ELECTRICAL
CFS2.400 BEVERAGE STATION-SPECIAL CONDITIONS
TECHNOLOGY
TELECOMMUNICATIONS
CTO.000 ICOVER SHEET
CT1.100 CONVENTION CENTER-LEVEL 01 ACTIVE SHOOTER FLOOR PLAN
CTI.101 CONVENTION CENTER-OVERALL LEVEL 0I FLOOR PLAN
CT1.102 CONVENTION CENTER-OVERALL LEVEL 02 FLOOR PLAN
CT1.103 CONVENTION CENTER-LEVEL 0I RCP PATHWAYS
CTI A04 lCONVENTION CENTER-LEVEL 01 WAP LAYOUT
CT2.201-A CONVENTION CENTER-LEVEL 01-SECTOR'A'-DATA COMM Iff
CT2.201-8 CONVENTION CENTER-LEVEL 01-SECTOR'B-DATA COMM
CT2.201-C CONVENTION CENTER-LEVEL 01-SECTOR'C'-DATA COMM
GMP Amendment No. 1 - Attachment 1
KALAHARI CONVENTION CENTER
w
DRAWING LOG 0 0
U U
O O [7 w U
O O O Q O
2
U
O _ = 1 Z
N N N N N Z Z Z 2 Z
Z Q 2
Q b b J
i w w u w
O
CT2.201-D CONVENTION CENTER-LEVEL 01-SECTOR'D'-DATA COMM
CT2.201-E CONVENTION CENTER-LEVEL 01-SECTOR'E'-DATA COMM
CT2201-F CONVENTION CENTER-LEVEL 01-SECTOR'F'-DATA COMM
CT2.202-C CONVENTION CENTER-LEVEL 02-SECTOR'C'-DATA COMM
CT2.202-D CONVENTION CENTER-LEVEL 02-SECTOR D'-DATA COMM
CT2.202-E CONVENTION CENTER-LEVEL 02-SECTOR'E-DATA COMM
CT2.202-F CONVENTION CENTER-LEVEL 02-SECTOR'F'-DATA COMM
772.301-A CONVENTION CENTER-LEVEL 01-SECTOR A-ACCESS CONTROL
CT2.301-B CONVENTION CENTER-LEVEL 01-SECTOR'B'-ACCESS CONTROL
CT2.301-C CONVENTION CENTER-LEVEL 01-SECTOR'C'-ACCESS CONTROL
CT2.301-D CONVENTION CENTER-LEVEL 01-SECTOR'D'-ACCESS CONTROL
CT2.301-E CONVENTION CENTER-LEVEL 01-SECTOR'E'-ACCESS CONTROL
772.301-F CONVENTION CENTER-LEVEL 01-SECTOR'F'-ACCESS CONTROL
CT2.302-C CONVENTION CENTER-LEVEL 02-SECTOR'C'-ACCESS CONTROL
CT2.302-D CONVENTION CENTER-LEVEL 02-SECTOR'D'-ACCESS CONTROL
CT2.302-E CONVENTION CENTER-LEVEL 02-SECTOR E'-ACCESS CONTROL
CT2.302-F CONVENTION CENTER-LEVEL 02-SECTOR F'-ACCESS CONTROL
CT3.100 CONVENTION CENTER-LEVEL 01-TECHNOLOGY SPACES
CT3.101 CONVENTION CENTER-LEVEL 01-TECHNOLOGY SPACES
CT3.200 CONVENTION CENTER-LEVEL 02-TECHNOLOGY SPACES
AUDIO I VIDEO
CAVO 001 AV COVER PAGE MIN
CAV1.001 AV REFERENCE PAGE MIN
CAV2.201 BD AV 1ST FLOOR PLAN SECTORS B/D MIT
CAV2 201 EF AV i ST FLOOR PLAN SECTORS E/F min
CAV2.202E AV 2ND FLOOR PLAN SECTOR E min
CAV3.101 AV EQUIPMENT DETAILS MIN Mi
CAV36102 AV EQUIPMENT ELEVATIONS
CAVO 201 BD AV 1 ST FLOOR RCP SECTORS B/D
CAV1.201EF AV 1ST FLOOR RCP SECTORS E/F
CAV1.202E AV 2ND FLOOR RCP SECTOR E
CAV4.202F AV 2ND FLOOR RCP SECTOR F
STRUCTURAL
CS1.001 GENERAL NOTES AND TYPICAL DETAILS
CS1.002 SPECIAL BUILDING INSPECTION PLAN
CS1.011 WIND LOADING DIAGRAMS
CS2.101 CONVENTION CENTER-FOUNDATION PLAN-LEVEL 01
C S2.102 CONVENTION CENTER-FRAMING PLAN-LEVEL 02
CS2.103 CONVENTION CENTER-FRAMING PLAN-LOW ROOF
CS2.104 CONVENTION CENTER-FRAMING PLAN-HIGH ROOF
CS2.201A CONVENTION CENTER-LEVEL 01-SECTOR'A'
CS2201.H CONVENTION CENTER-LEVEL 01-SECTOR'B'
GMP Amendment No. 1 - Attachment 1
KALAHARI CONVENTION CENTER
z z
W W Z
DRAWING LOG 0O 0
U U W r
O � gO W J
Z Z U a0
a i Qe o r
'' Z rc J a 0 0 0 0 0
H O = = y i Z i Z i
y H y y y V1 0 2 Z Z 2 Z
O O Otl C ry J J J J J
U Z U W W O M W
J K C O _ _ J
O O O C N J J J J J
CS2.201.0 CONVENTION CENTER-LEVEL 01-SECTOR'C'
CS2.201.0 CONVENTION CENTER-LEVEL 01-SECTOR'D'
CS2.201.E CONVENTION CENTER-LEVEL 01-SECTOR'E'
CS2.201.F CONVENTION CENTER-LEVEL 01-SECTOR'F'
CS2.202.A CONVENTION CENTER LEVEL 02-SECTOR'A'
CS2.202.B CONVENTION CENTER LEVEL 02-SECTOR'B'
CS2.202.0 CONVENTION CENTER LEVEL 02-SECTOR'C'
CS2.202.D CONVENTION CENTERLEVEL02-SECTOR'D'
CS2.202.E CONVENTION CENTER-LEVEL 02-SECTOR'E'
CS2.202.F CONVENTION CENTER-LEVEL 02-SECTOR'F'
CS2.203 A CONVENTION CENTER-LOW ROOF-SECTOR'A'
CS2.203.8 CONVENTION CENTER-LOW ROOF-SECTOR'B'
CS2.203.0 CONVENTION CENTER-LOW ROOF-SECTOR'C'
CS2.203.0 CONVENTION CENTER-LOW ROOF-SECTOR 0'
CS2.203.E CONVENTION CENTER-LOW ROOF-SECTOR'E'
CS2.203.F CONVENTION CENTER-LOW ROOF-SECTOR'F'
CS2.204 A CONVENTION CENTER-HIGH ROOF-SECTOR'A'
CS2.204.13 CONVENTION CENTER-HIGH ROOF-SECTOR B'
CS2.204.0 CONVENTION CENTER-HIGH ROOF-SECTOR'C'
CS2.204.0 CONVENTION CENTER-HIGH ROOF-SECTOR'D'
CS2.204.E CONVENTION CENTER-HIGH ROOF-SECTOR'E'
CS2.204.F CONVENTION CENTER-HIGH ROOF-SECTOR'F'
CS3.001 FOUNDATION SECTIONS AND DETAILS
CS3.002 FOUNDATION SECTIONS AND DETAILS
CS3.003 FOUNDATION SECTIONS AND DETAILS
CS3.004 FOUNDATION SECTIONS AND DETAILS N I IN 101
CS5.011 COLUMN SCHEDULE
CS7.001 STEEL SECTIONS AND DETAILS
CS7 002 STEEL SECTIONS AND DETAILS 101
CS7.003 STEEL SECTIONS AND DETAILS
CS7.004 STEEL SECTIONS AND DETAILS
CS7.011 STEEL FRAMING ELEVATIONS
CS7.012 STEEL FRAMING ELEVATIONS
CSL020 STEEL SECTIONS AND DETAILS(BALLROOM) NJ
CS7.021 STEEL SECTIONS AND DETAILS(BALLROOM)
CS7.022 STEEL SECTIONS AND DETAILS(BALLROOM)
MECHANICAL
CM0.00 NOTES,SYMBOLS.LEGEND&ABBREVIATIONS
CM2 201,A CONVENTION CENTER LEVEL 01-SECTOR'A'
CM2.201.8 CONVENTION CENTER LEVEL 01-SECTOR'B'
GMP Amendment No. 1 - Attachment 1
KALAHARI CONVENTION CENTER
Z
f
°
Z Z
DRAWING LOG J
V U1.
O �< D Q W J
Z Y Z Y K
U pQ �
O UU
pJ Z
O as 4 Z U O
FZ F J J 1 U Co C o 0
p = 2 0 Z 2 Z 2 2
N N VI N � 2 2 2 Z Z
V Z V W O $ W
O O O T N J J J J J
CM2 201,C CONVENTION CENTER LEVEL 01SECTOR'C'
CM2.201.D CONVENTION CENTER-LEVEL OI-SECTOR'D'
CM2.201.E CONVENTION CENTERLEVEL01-SECTOR'E'
CM2.201.F CONVENTION CENTER LEVEL 01-SECTOR'F'
CM2 202A CONVENTION CENTER-LEVEL 02-SECTOR'A'
101 1
CM2.202.8 CONVENTION CENTER-LEVEL 02-SECTOR'S' MI I
CM2.202.0 CONVENTION CENTER LEVEL 02 SECTOR'C'
CM2.202.D CONVENTION CENTER LEVEL 02-SECTOR'D' 01
CM2.202.E CONVENTION CENTERLEVEL 02 SECTOR'E' s 11
CM2.202.F CONVENTION CENTER-LEVEL 02-SECTOR'F'
CM2.203.B CONVENTION CENTER-ROOF-SECTOR'B'
CM2.203.0 CONVENTION CENTER-ROOF-SECTOR'C'
CM2.203.D CONVENTION CENTER-ROOF-SECTOR'D'
CM2.203.E CONVENTION CENTER-ROOF-SECTOR'E'
CM2.203.F CONVENTION CENTER-ROOF-SECTOR'F'
CM6.01 MECHANICAL SCHEDULES
CM6.02 MECHANICAL SCHEDULES
CM7.01 MECHANICAL DETAILS
CM7.02 MECHANICAL DETAILS
CM7.03 MECHANICAL DETAILS
CM7.04 MECHANICAL DETAILS
PLUMBING
CPFO.000 NOTES.SYMBOLS.LEGEND 8 ABBREVIATIONS
CPF2.100 CONVENTION CENTER UNDERFLOOR PLAN-LEVEL 01
CPF2I01 CONVENTION CENTER FLOOR PLAN LEVEL 01
CPF2.102 CONVENTION CENTERFLOOR PLAN LEVEL 02
CPF2.104 CONVENTION CENTERROOFPLAN
CPF2.200 A CONVENTION CENTER-UNDERFLOOR LEVEL O1-SECTOR'A'
CPF2.200.8 CONVENTION CENTER-UNDERFLOOR LEVEL 01-SECTOR'8' s NI in
CPF2.200.0 CONVENTION CENTER-UNDERFLOOR LEVEL 01-SECTOR'C'
CPF2.200.D CONVENTION CENTER-UNDERFLOOR LEVEL 01SECTOR'D'
In
10
CPF2.200.E CONVENTION CENTER-UNDERFLOOR LEVEL 01-SECTOR'E'
CPF2.200.F CONVENTION CENTER-UNDERFLOOR LEVEL 01-SECTOR'F'
CPF2.201 A CONVENTION CENTER-LEVEL DI-SECTOR'A'
CPF2.201.B CONVENTION CENTER-LEVEL 01-SECTOR'8'
CPF2.2010 CONVENTION CENTER-LEVEL 01-SECTOR'C'
CPF2.2011) CONVENTION CENTER-LEVEL 01-SECTOR'D'
CPF2.201.E CONVENTION CENTER-LEVEL 01-SECTOR'E'
CPF2.201F CONVENTION CENTER-LEVEL 01-SECTOR'F'
CPF2.201A CONVENTION CENTER-LEVEL 02-SECTOR'A'
GMP Amendment No. 1 - Attachment 1
KALAHARI CONVENTION CENTER
= z
w w
DRAWING LOG °
ono0wlu
z
V O Q N
U Q U 1 J z ZO
a i 0 0 0 0
z
O z z° z° z z
Z < z
U
O
Z
U O W
J
rc z O J
vE O O O R' - - N J J J J J
CPF2.202.8 CONVENTION CENTER-LEVEL 02-SECTOR'11
CPF2.202C CONVENTION CENTER-LEVEL 02-SECTOR'C'
CPF2.202.D CONVENTION CENTER-LEVEL 02-SECTOR'D'
CPF2.202.E CONVENTION CENTER-LEVEL 02-SECTOR'E'
CPF2.202.F CONVENTION CENTER-LEVEL 02-SECTOR'F'
CPF2.203.A CONVENTION CENTER-ROOF-SECTOR'A'
CPF2.20113 CONVENTION CENTER-ROOF-SECTOR'B'
CPF2.203.0 CONVENTION CENTER-ROOF-SECTOR'C'
CPF2.203.D CONVENTION CENTER-ROOF-SECTOR'D'
CPF2.203.E CONVENTION CENTER-ROOF-SECTOR'E'
CPF2.203.F CONVENTION CENTER-ROOF-SECTOR'F'
CPF3.100 ENLARGED RESTROOM UNDERFLOOR PLANS
CPF3.101 ENLARGED RESTROOM PLANS 01
CPF3.102 ENLARGED RESTROOM PLANS
CPF3.103 ENLARGED RESTROOM UNDERFLOOR PLANS
CPF3.110 ENLARGED WATER HEATER ROOM PLAN
CPF4.100 ENLARGED KITCHEN UNDERFLOOR PLANS
CPF6.01 SCHEDULES
CPF7.01 PLUMBING AND FIRE PROTECTION DETAILS
GMP Amendment No. 1 - Attachment 1
CONVENTION CENTER SPECIFICATIONS LOG
ISSUES
2017-10-27 50% Design Development
2018-01-26 Final Design Development
2018-03-30 30% Construction Documents
2018-03-30 Foundation Package
2018-06-01 60% Construction Documents
2018-06-05 Shell and Core Package
2018-07-27 75% Construction Documents
2018-08-10 Shell and Core Update 1
2018-08-10 Progress Print
2018-10-05 Issued For Construction
DIVISION 00 - PROCUREMENT AND CONTRACT REQUIREMENTS
2018-03-30 31000 Available Project Information
2018-03-30 52000 Agreement Form
2018-03-30 72000 General Conditions
2018-03-30 73000 Supplementary Conditions
DIVISION 01 - GENERAL REQUIREMENTS
2018-03-30 12100 Allowances
2018-03-30 12200 Unit Prices
2018-03-30 12300 Alternates
2018-03-30 12500 Substitution Procedures
2018-03-30 12600 Contract Modification Procedures
2018-03-30 12900 Payment Procedures
2018-03-30 13100 Project Management and Coordination
2018-03-30 13200 Construction Progress Documentation
2018-03-30 13300 Submittal Procedures
2018-03-30 14000 Quality Requirements
2018-03-30 14200 References
2018-03-30 14323 Special Inspections
2018-03-30 14326 Testing Laboratory Services
2018-06-05 14339 Visual Mockup Requirements
2018-06-05 14516 Field Test for Water Leakage
2018-03-30 15000 Temporary Facilities and Controls
2018-10-05 15639 Temporary Tree and Plant Protection
2018-03-30 16000 Product Requirements
2018-03-30 17300 Execution
2018-03-30 17700 Close Out Procedures
2018-03-30 17823 Operation and Maintenance Data
2018-03-30 17839 Project Record Documents
2018-03-30 17900 Demonstration and Training
DIVISION 03 — CONCRETE
2018-07-27 31000 Concrete Formwork
2018-03-30 32000 Reinforcing Steel
2018-03-30 33000 Cast In Place Concrete
GMP Amendment No. 1 - Attachment 1
2018-03-30 33500 Concrete Finishing
2018-06-05 35300 Concrete Toppings
DIVISION 04 — MASONRY
2018-06-05 42100 Masonry Veneer
2018-06-05 42200 Concrete Unit Masonry
2018-10-05 44216 Site Stone Blocks, Boulders and Slabs
2018-06-05 47500 Adhered Masonry Veneer
DIVISION 05 — METALS
2018-03-30 51200 Structural Steel
2018-06-05 51213 Architecturally Exposed Structural Steel
Framing
2018-03-30 52100 Steel Joists and Joist Girders
2018-03-30 53123 Metal Roof Deck
2018-03-30 53600 Composite Metal Floor Deck
2018-06-05 54000 Cold Formed Metal Framing
2018-06-05 54300 Slotted Channel Framing
2018-06-05 55000 Metal Fabrications
2018-10-05 55013 Site Miscellaneous Metal Fabrications
2018-06-05 55100 Metal Stairs
2018-06-05 55213 Pipe and Tube Railings
2018-10-05 55214 Site Guard and Hand Railings
2018-06-05 55300 Metal Gratings
2018-06-05 57000 Ornamental Metal
2018-06-05 57300 Ornamental Handrails and Railings
DIVISION 06 — WOOD, PLASTICS AND COMPOSITES
2018-03-30 61000 Rough Carpentry
2018-06-05 61053 Miscellaneous Rough Carpentry
2018-10-05 61063 Site Exterior Rough Carpentry
2018-03-30 61300 Heavy Timber Construction
2018-03-30 61600 Sheathing
2018-06-05 61643 Exterior Gypsum Sheathing
2018-03-30 61753 Prefabricated Wood Trusses and Bracing
2018-03-30 61800 Glue-Laminated Construction
2018-10-05 62013 Exterior Finish Carpentry
2018-10-05 62023 Interior Finish Carpentry
2018-10-05 64023 Interior Architectural Woodwork
2018-10-05 66400 Plastic FRP Paneling
2018-06-05 66813 Plastic Gratings
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
2018-06-05 71352 Modified Bituminous Sheet Waterproofing
2018-06-05 71413 Hot Fluid Applied Rubberized Asphalt
2018-07-27 71616 Waterproofing
Crystalline Waterproofing
2018-06-05 71800 Traffic Coatings
2018-08-10 72100 Thermal Insulation
GMP Amendment No. 1 - Attachment 1
2018-06-05 72400 EIFS
2018-06-05 72423 DEFS (Direct Applied Exterior Finish System)
2018-06-05 72617 Below Slab Vapor Retarder
2018-06-05 72726 Vapor Permeable, Fluid Applied Membrane
2018-06-05 74114 Metal Roof Panels
2018-06-05 74213 Formed Metal Wall Panels
2018-06-05 74343 Composite Fiber Cement Panels
2018-06-05 75013 Single Ply Membrane Roofing
2018-06-05 76200 Sheet Metal Flashing and Trim
2018-06-05 77200 Roof Accessories
2018-06-05 78116 Sprayed Fire Resistive Materials
2018-08-10 78413 Penetration Firestopping
2018-08-10 78446 Fire Resistive Joint Firestopping
2018-06-05 79200 Joint Sealants
2018-10-05 79500 Expansion Control
DIVISION 08 - OPENINGS
2018-06-05 81113 Hollow Metal Doors and Frames
2018-06-05 81416 Prefinished Flush Wood Doors
2018-06-05 81426 Stile and Rail MDF Doors
2018-06-05 81433 Stile and Rail Wood Doors
2018-06-05 81613 Fiberglass Doors and Frames
2018-06-05 83113 Access Doors and Frames
2018-06-05 83213 Sliding Aluminum Framed Glass Doors
2018-06-05 83313 Coiling Counter Doors
2018-08-10 83323 Overhead Coiling Doors
2018-06-05 83326 Overhead Coiling Grilles
2018-10-05 83813 Traffic Doors
2018-06-05 84229 Automatic Entrances
2018-06-05 84400 Glazed Aluminum Framing Systems
2018-10-05 87100 Door Hardware
2018-06-05 88800 Glazing
2018-06-05 88300 Unframed Mirrored Glazing
2018-06-05 89100 Wall Louvers
DIVISION 09 - FINISHES
2018-10-05 92600 Veneer Plastering
2018-10-05 92900 Gypsum Board Assemblies
2018-10-05 93000 Tiling
2018-10-05 95113 Acoustical Panel Ceilings
2018-10-05 96340 Stone Flooring
2018-10-05 96400 Wood Flooring
2018-10-05 96500 Resilient Flooring
2018-10-05 96513 Resilient Base and Accessories
GMP Amendment No. 1 - Attachment 1
2018-10-05 96800 Carpeting
2018-10-05 97200 Wall Coverings
2018-10-05 97500 Interior Stone Facing
2018-10-05 97713 Stretched Fabric Wall Systems
2018-06-05 99100 Painting
2018-10-05 99300 Staining and Transparent Finishing
2018-06-05 99600 High Performance Coatings
2018-06-05 99639 Epoxy Containment Coating
2018-06-05 99663 Textured Acrylic Coatings
DIVISION 10 — SPECIALTIES
2018-10-05 102113 Toilet Compartments
2018-10-05 102213 Wire Mesh Partitions
2018-10-05 102238 Operable Panel Partitions
2018-10-05 102613 Wall and Corner Guards
2018-10-05 102813 Toilet Accessories
2018-10-05 103116 Manufactured Fireplaces
2018-10-05 104400 Fire Protection Specialties
2018-10-05 105113 Metal Lockers
DIVISION 11 — EQUIPMENT
2018-08-10 111300 Loading Dock Equipment
2018-06-05 112400 Building Maintenance Equipment
DIVISION 12 — FURNISHINGS
2018-10-05 122113 Horizontal Louver Blinds
2018-10-05 122413 Roller Window Shades
2018-10-05 123640 Stone Countertops
2018-10-05 123661 Simulated Stone Countertops
2018-10-05 124843 Entrance Floor Mats
2018-10-05 129300 Site Furnishings
DIVISION 13 — SPECIAL CONSTRUCTION
2018-10-05 132640 Prefabricated Modular Bathrooms
2018-10-05 133100 Tensile Membrane Structures
DIVISION 14 — CONVEYING EQUIPMENT
2018-10-05 142100 Electric Traction Elevators
2018-08-10 143100 Escalators
DIVISION 21 — FIRE SUPPRESSION
2018-10-05 210001 Basic Fire Protection Requirements
2018-10-05 210002 Fire Protection
DIVISION 22 — PLUMBING
2018-10-05 220501 Basic Plumbing Requirements
2018-10-05 220505 Plumbing
DIVISION 23 — HEATING, VENTILATION, AND AIR CONDITIONING
2018-10-05 230501 Basic Mechanical Requirements
GMP Amendment No. 1 - Attachment 1
2018-10-05 230510 Basic Materials and Methods
2018-06-05 230540 Vibration Isolation
2018-06-05 230593 Testing, Adjusting, And Balancing
2018-10-05 230701 Insulation
2018-10-05 230901 Building Control System
2018-10-05 230993 Sequence of Operations for HVAC Controls
2018-06-05 232500 HVAC Water Treatment
2018-08-10 232923 Variable Frequency Drives
2018-10-05 233113 Metal Ducts
2018-06-05 233300 Air Duct Accessories
2018-10-05 233401 HVAC Equipment—Air Side
2018-06-05 235110 Breechings, Chimneys and Draft Control
Devices
2018-10-05 235201 Heating Equipment
2018-08-10 237413 Packaged, Outdoor, Central-Station Air
Handling Units
2018-06-05 238126 Split System Air-conditioners
DIVISION 26 — ELECTRICAL
2018-10-05 260501 Basic Electrical Requirements
2018-10-05 260510 Basic Materials And Methods
2018-08-10 260526 Grounding And Bonding For Electrical
Systems
2018-08-10 260553 Identification for Electrical Systems
2018-08-10 260573 Overcurrent Protective Device Coordination
Study
2018-08-10 260920 Lighting Control Systems
2018-10-05 260936 Digital Network Lighting Control
2018-06-05 261116 Secondary Unit Substation
2018-06-05 261216 Substation Transformers
2018-06-05 261317 Metal Enclosed Load Interrupter Switchgear
2018-10-05 262000 Electrical Distribution
2018-08-10 263213 Engine Generators
2018-10-05 263356 Single Module Uninterruptible Power System
2018-08-10 263623 Automatic Transfer Switches
2018-06-05 264113 Lightning Protection For Structures
2018-10-05 265100 Architectural Lighting Fixtures
2018-06-05 265101 Lighting
2018-03-30 266000 Electrical Testing
DIVISION 27 — COMMUNICATIONS
2018-11-01 270000 Low Voltage Communications
2018-11-01 270100 Operation and Maintenance Of
2018-11-01 270200 Communications Systems
2018-11-01 270300 Systems
Pathways for Communications Systems
GMP Amendment No. 1 - Attachment 1
2018-11-01 270400 Underground Ducts and Raceways For
2018-11-01 270500 Communications Systems
Identification for Communications Systems
2018-11-01 270600 Schedules for Communications
2018-11-01 270700 Telecommunications Spaces
2018-11-01 270800 Telecommunications Backbone Cabling
2018-11-01 270900 Telecommunications Horizontal Cabling
2018-11-01 271000 Server Room Sr and Demarc
2018-11-01 271100 Communications Connecting Cords Devices
2018-11-01 271200 and Adapters
Data Communications Wireless Access Points
2018-11-01 271300 Data Communications Cameras
2018-11-01 271400 Data Communications Parking Lot Cameras
2018-11-01 271500 Distributed Antenna System Das
2018-11-01 271600 Appendix 1
2018-11-01 271700 Appendix Ii
2018-11-01 273000 Audio Visual Overview
2018-11-01 274000 Audio Visual Systems
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
2018-11-01 280000 Electronic Safety and Security
2018-11-01 282000 Access Control and Cctv Overview
2018-11-01 282040 Cctv Devices
2018-06-05 283163 Digital,Addressable Fire-alarm System
2018-11-01 284000 System Integration
2018-11-01 285000 Cctv Project Completion
DIVISION 31 — EARTHWORK
2018-06-05 313116 Termite Control
2018-03-30 316100 Spread and Continuous Footings
2018-03-30 316329 Drilled Piers
DIVISION 32 — EXTERIOR IMPROVEMENTS
GMP Amendment No. 1 - Attachment 1
DIVISION 33 — UTILITIES
SUPPLEMENTAL INFORMATION
2018-05-18 Marrakesh Market—Lighting Fixture Schedule
Data Sheets
2018-10-05 Mondo Sortinos—Plumbing Fixture Data Sheets
2018-10-05 Mondo Sortinos—Lighting Fixture Schedule
Data Sheets
2018-10-05 B-Lux Burgers—Plumbing Fixture Data Sheets
2018-10-05 B-Lux Burgers—Lighting Fixture Schedule
Data Sheets
SUPPLEMENTAL INFORMATION — FOOD SERVICE
2018-08-07 Convention Center- Data Sheets
GMP Amendment No. 1 - Attachment 2
Farm PC603
R-121&09
e -i Hensel Phelps
Co. Financial Status Report Summary
Project: Kalahari Resorts&Conventions-Round Rock,TXConvention Center Project Manager: Joe Sanders
Project Number: 7018142 Date: 12/18/2019
Bid PackageDescription Esameta Completed emaining Gain or(Loss) Remarks
0.05.A Prefabricated Metal Stair Systems Amencan Stair 73,205 73,205 0 0
0.05.8 Prefabricated Metal Stair Systems(Erection) Patnot 40,445 40,445 0 0
0.06 Elevators&Escalators Oes 585,226 580,396 4,830 0
0.08 Testing Arias 0 Not Bought 0
2.03 Earthwork Ranger 240,000 240,000 0 0
3.01 Turnkey Concrete Hensel Phelps 3,691,655 3,691,855 0 0
4.01 Masonry/Stone Veneer Brazos 309,500 309,500 0 0
4.02 Structural&Miscellaneous Steel Alemo 6,261,158 6,175,296 85,662 0
4.05 Timber Framed Event Berri Sand Creek Post a Beam 316,191 171.191 145,000 0
4.06., Waterproofing(Below Grade) GHM Ktatherguard 64,578 64.576 0 0
4.06.8 Waterproofing(Above Grade) Alpha 304,316 282.041 22.275 0
4.07 EIFS Galindo 6 Boyd 825,788 825,788 0 0
4.08 Roofing Rain King 1,667,701 1,645,600 22,101 0
4.10 Fireproofing Alpha 472,752 434.158 38,594 0
4.12 Loading Dock Equipment Miner 32,134 32.134 0 0
4.14 Exterior Glass Haley Greer 1,108,018 935,357 172,661 0
4.17 Drywall Standard 6,215,152 6,141,450 73,702 0
4.20 Fire Protection Casteel 638,489 528,489 110,000 0
4.21 Mechanical&Plumbing TDI 7,449,344 6,879,190 570,154 0
4.23 Building Control System Automated Logic 340,850 333,350 7,500 0
4.24 Electrical Bergelec0lc 4,306,986 3,830.560 476,426 0
6.00 Operable Panel Partitions Hutcor 1,016,486 1,016,486 0 0
6.01 Ornamental Metals Metalink 88,240 58,240 30,000 0
6.02 Carpentry - 63,960 Not Bought 63.960
6.04 Architectural Millwork ISEC 473,612 502,574 (23.9621 0
6.06 Metal Panels National Parcel Systems 156,602 156.602 0 0
6.07 Doors,Frames&Hardware LeForce 703,116 562.116 141,000 0
6.08 Overhead Coiling Doors&Grilles OverheadD-I'Austin 245,452 235.452 10,000 0
6.09 Overhead Fire Doors w/6.06 0 Not Bought 0 Contracted Math 6.08
6.10 Interior Glass&Glazing Anchor Ventana 84,356 81,856 2.500 0
6.12 Acoustical Ceilings Heartland 586,997 596.536 13.5391 0
6.13 Tile&Stone Centex Floonng 270,546 274,246 ;3 7001 0
6.14 Carpet&Resilient Flooring Flooring Solutions Group 1,198.755 1,025.378 173,377 0
6.16.3 Paint&Wall Coverings Hagler&Kerr 1,322,736 1,387,852 f6f,1161 0
6.19 Public Area Toilet/Shower Partitions&Accessories Spectrum 121.815 121,515 0 0
6.20.7 Building Specialties Alpha 15,611 15,611 0 0
6.20.2 Building Specialties Spectrum 14,532 11.032 3,500 0
6.20.3 Building Specialties OFOI 0 Not Bought 0 CHO per 10123/2019 Meeting
6.25 Countertops ISEC 235,177 190,277 44,900 0
6.26 Testing,Adjusting&Balancing TAB Technologies 170,000 Not Bought 170,000 -
6.27 Decorative Site Fencing OFOI 0 Not Bought 0 OFIO per 10/23/2019 Meeting
6.31 Fire Alarm Johnson Controls 208,700 207,300 1,400 0
8.01 Communications Structured Cabling Infrastructure&Equ Brycomm 654,651 654,651 0 0
8.02 Distributed Antenna System(DAS) - 0 Not Bought 0 Scope has been deleted from project by Owner
8.03 Audio Visual CTI 1,151,636 1,151,636 0 0
8.04 Electronic Safety&Security Brycomm 48,415 48,415 0 0
8.05 Low Voltage System Pathways Bergelecinc 429,400 421,400 8,000 0
9.01 Final Clean TBD 154,650 Not Bought 154,650 Remaining:Issue Bid Package
cow Cost of Work - 621,253 621,253 0 0
GENERAL CONDITIONS 1.902.386 1,902.386 0 0
INDIRECTS 1,158,782 1,158,782 0 0
CONTINGENCY&RESERVES 562,252 Not Bought 562,252 -
CONTRACTOR'S FEE 1,336,599 Not Bought 1.336.599
APPROVED DE I N TRENDS/CHANGES(Temp Placeholder) 0
TOTAL $49,940,208 1 $45,616,279 $4,323.9261 s0
PERCENT 191.34% 1 8.66% 0.00%
GMP Amendment No. 1 - Attachment 2
Column A Column B Column C Column D Column E Column F Column G Column H
Bid Package Cost Gain or
Subsystem Control# Description Estimate Purchasing (Loss)
0.05.A 7018142-0552000 Prefabricated Metal Stair Systems American Stair
C2010 Prefabricated Metal Stair Systems(30%Construction Documents) 80.205 80,205
Issued for Construction Documents No Change No Change
Bulletin 01 No Change No Change
Bulletin 02 No Change No Change
Internal Change-Stair CST-01 Landing Revisions(To 0.05B Patriot) 7 0007
Subtotal 73,205 73,205 0
0.05.8 7018142-0550000 Prefabricated Metal Stair Systems(Erection) Patriot
C2010 Prefabricated Metal Stair Systems(30%Construction Documents) 33,445 33.445
Issued for Construction Documents No Change No Change
Bulletin 01 No Change No Change
Bulletin 02 No Change No Change
Internal Change-Stair CST-01 Landing Revisions(From 0.05A American Stair) 7,000 7 000
Subtotal 40,445 40,445 0
0.06 7018142-1400000 Elevators&Escalators Otis
D1010 Elevators&Escalators 582,476 582,476
CS-01 Passenger Elevator(Pre-Function)4500 LBS,200 FPM(Front/Rear Entry) w/Above w/Above
CS-02 Service Elevator(Loading Dock)4500 LBS.200 FPM w/Above w/Above
CS-03 Service Elevator(Loading Dock)4500 LBS,200 FPM w/Above w/Above
Elevator Finish Allowance(Passenger Elevator) w/Above w/Above
CE-01 Escalator(Pre-Function)100 FPM w/Above w/Above
CE-02 Escalator(Pre-Function)100 FPM w/Above w/Above
Bulletin 01 No Change No Change
Bulletin 02 No Change No Change
Internal Change-Crane Invoice(To Cost of Work) 12 0301
Subtotal 580,396 580,396 0
RFI#0273-Diamond Plate Flooring at Service Elevators 4,830 4.830
0.08 7018142-0202000 Testing Arias
A1010 Material Testing w/cost of work w/cost of work
Bulletin 01 No Change No Change
Bulletin 02 No Change No Change
Subtotal 0 0 --
2.03 7018142-3100126 Earthwork Ranger
G1020 Building Pad Preparation 240,000 240,000
Excavate to Required Elevation w/Above w/Above
Moisture Condition to Site Material and Fill w/Above w/Above
Select Fill Top 12" w/Above w/Above
Bulletin 01 No Change No Change
Bulletin 02 No Change No Change
DJ le 2019 12 18 Page 1 of 12
GMP Amendment No. 1 - Attachment 2
Column A Column B Column C Column D Column E Column F Column G Column H
Bid Package Cost Gain or
Subsystem Control# Description Estimate Purchasing (Loss)
Subtotal 240,000 240,000 0
3.01 7018142-0300000 Turnkey Concrete Hensel Phelps
A1030 Turnkey Concrete(30%Construction Documents) 3,433,496 3,433,496
Event Barn Foundations&Slab on Grade 139,000 139,000
Issued for Construction Documents&Bulletin 1/2 128,820 128,820
Internal Change-CE 30,31 32(to 4.02-Alamo) 9 661 (9.661;
Subtotal 31691,655 3,691,655 0
4.01 7018142-0400000 Masonry/Stone Veneer Brazos
B2010 Masonry/Stone Veneer(30%Construction Documents) 309,500 309,500
Bulletin 01 No Change No Change
Bulletin 02 No Change No Change
Subtotal 309,500 309,500 0
4.02 7018142-0500000 Structural&Miscellaneous Steel Alamo
B1010 Structural&Misc.Steel(30%Construction Documents 5,731,754 5,731,754
Internal Change-CE 30,31 32(from 3.01-HP Concrete) 9,661 9,661
Issued for Construction Documents(60%to 100%) 431,599 431,599
RFI#0596-Delete Rigging Points i 113 400; c 113 400:
RFI#0733-Curtain Wall Steel 7,904 7,904
RFI#0891-Expansion Joint Plate Steel 16,898 16.898
RFI#0933-Escalator Truss 6,394 6,394
Bulletin 01&Bulletin 02 76,322 76,322
RFI 955-Skid Plate Credit 12610; (2,610)
RFI 1438-Hoist Beam at Elevator 10,774 10,774
Subtotal 6,175,296 6,175,296 0
RFI 1426-Loading Dock Finish Changes Added C Channel at Loading Dock Door 5,862 5,862
Miscellaneous Metals not scheduled or detailed 80.000 80.000
4.05 7018142-0613000 Timber Framed Event Barn Sand Creek Post&Beam
81020 Timber Framed Event Barn(30%Construction Documents) 147,142 147.142
6 Pair Sliding Doors&Additional Access Doors(Add Aft) 12,049 12,049
Wind Loading Engineering(Add Aft) 12,000 12,000
Subtotal 171,191 171,191 0
Installation Including Additional Doors&Interior Framing(Texas Timber Frame Separate Contract to be
4.05B) 140,000 140 000
Support Beam for Light Fixtures 5,000 5.000
4.06.A 7018142-0700000 Waterproofing(Below Grade) CHM Weatherguard
A2020 Below Grade Waterproofing(30%Construction Documents) 63,361 63,361
Date 2019.1218 Page 2 of 12
GMP Amendment No. 1 - Attachment 2
Column A Column B Column C Column D Column E Column F Column G Column H
Bid Package Cost Gain or
Subsystem Control# Description Estimate Purchasing (Loss)
Bulletin 01&Bulletin 02 1.217 1.217
Subtotal 64,578 64,578 0
4.06.13 7018142-0702000 Waterproofing(Above Grade) Alpha
81010 Above Grade Waterproofing(Progress Set dated 8/13/18) 282,041 282.041
RFI 320 Fluid Applied Air-Barrier @ Metal Panels(Screen Walls) 33,000 Not Included
RFI 847 Back of Wall Change to DEFS(Screen Walls) (33,000) Not Included
Subtotal 282,041 282,041 0
Event Barn-Cavity Insulation(Final Pricing from Alpha) 10 692 10,692
Event Barn-Air Barrier(Final Pricing from Alpha) 11 583 11.583
4.07 7018142-0704000 EIFS Galindo&Boyd
82010 EIFS 842,800 842.800
RFI#0847-Eliminate EIFS at Screen Walls 166 8501 (66.850
RFI#0847-Add DEFS at Front/Back of Screen Walls 57,366 57,366
RFI 1426-Loading Dock Finish Changes (7 528) t 7.528
Subtotal 825,788 825,788 0
4.08 7018142-0703000 Roofing Rain King
B3010 Roofing(Progress Set dated 8/13/18) 1,497.107 1.497.107
Roofing-Event Barn 148,493 148.493
Bulletin 01 &Bulletin 02 No Change No Change
Subtotal 1,645,600 1,645,600 0
RFI#0847-Add Coping Cap at DEFS Screen Walls to match roof perimeter 14.310 14,310
RFI 1107-Porte Cochere Vapor Barrier 7,791 7.791
4.10 7018142-0702000 Fireproofing Alpha
81010 Fireproofing(Progress Set dated 08/13/18) 434,158 434.158
Subtotal 434,158 434,158 0
Silicon Firestopping at Perimeter slab edge 7,438 7,438
Fireproofing Patching Excluded from Contract.Budget to Be Tracked via T&M 1 26 156 26.156
Fireproofing of Elevator Shaft Steel Supports and Stair Overrun(Required per CoRR Inspector) 5 000 5.000
Date. 2019.12.18 Page 3 of 12
GMP Amendment No. 1 - Attachment 2
Column A Column B Column C Column D Column E Column F Column G Column H
Bid Package Cost Gain or
Subsystem Control# Description Estimate Purchasing (Loss)
4.12 7018142-1113000 Loading Dock Equipment Miner
E1030 Loading Dock Equip-Levelers/Bumpers(30%Construction Documents) 32,134 24,900
Loading Dock -Seals and Shelters wl above 7.234
Issued for Construction Documents No Change No Change
Bulletin 01&Bulletin 02 No Change No Change
Subtotal 32,134 32,134 0
4.14 7018142-0880000 Exterior Glass Haley Greer
82020 Exterior Glass(Haley-Greer)-Progress Set dated 08/13/18 935,357 935,357
Subtotal 935,357 935,357 0
IFC Documents-Extended face caps at vertical accent bands,mullions and flashing 85,478 85,478
AMF-01-Metal Panel(Steel Column Covers)w/IFC number 72,600 72,600
IFC-Bronze Anodized Finish 1250) i X507
Bulletin 01&Bulletin 02 15,833 15,833
4.17 7018142-0900000 Drywall Standard
B2010 Drywall,Fiber Cement Panels&Vapor Barrier(Progress Set dated 08113/18) 6,087,685 6,087,685
IFC Documents 42,130 42,130
Bulletin 01&Bulletin 02 (5,289) 15.289'
RFI 840-Eliminate Light Coves at Prefunction Area (1 593) (1 593)
Add Sheathing at back side of screen walls 20:000 11,588
RFI 847-Add Sheathing at back side of screen walls(Delta between actual and budget) (8 412} w/above
Blocking for Downspouts 20,000 6,929
Blocking for Downspouts(Delta between actual and budget) (13,071) w/above
Subtotal 6,141,450 6,141,450 0
Bulletin 03 1,575 1,575
RFI 1426-Loading Dock Finish Changes-Rework of Door Openings 3,587 3,587
RFI 1509-2 Hour Fire Rated Ceiling at Elevator Shaft 3,502 3,502
RFI 1435-Drywall Ceiling at Deleted T&G Wood Ceiling at Pre-Function(Part of Millwork VE) 7,323 7,323
RFI 1190-Bulletin 2 Swap for Glassmat 7,003 7,003
RFI 1593-Porte Cochere and Loading Dock Venting 5,026 5,026
Bulletin 05 10,266 10,266
RFI 1287-GFRC Column Wrap increase at Porte Cochere 10 000 10,000
Event Barn 25 420 25,420
4.20 7018142-2210000 Fire Protection Casteel
D4010 Fire Protection-30%Construction Documents 507,000 507,000
IFC Documents No Change No Change
Bulletin 01&Bulletin 02 No Change No Change
MDF FM 200 system 21,489 21,489
Subtotal 528,489 528,489 0
Event Barn Fire Protection 41 000 41.000
Dry Pipe System at Porte Cochere 30.000 30.000
Upgrade Hazard Requirements(per Kalahari Insurance)(reduced from$50,000 to$39,000 at 8/13/19 1 39.000 39,000
Date. 2019.12.18 Fuge 4 of 12
GMP Amendment No. 1 - Attachment 2
Column A Column B Column C Column D Column E Column F Column G Column H
Bid Package Cost Gain or
Subsystem Control# Description Estimate Purchasing (Loss)
4.21 7018142-2200000 Mechanical&Plumbing TDI
D3040 Mechanical&Plumbing (30%Construction Documents) 6 879.190 6,879 190
Subtotal 6,879,190 6,879,190 0
IFC Documents 97,900 97,900
Bulletin 01/Bulletin 02 90.174 90,174
Perimeter Drainage System 92,705 92,705
Event Barn Mech/Plumbing Incl.Radiant Heat&Fans 198.819 198,819
Bulletin 03 3,877 3,877
Bulletin 04 39,748 39,748
RFI 1282 Mop Sink 7,018 7.018
RFI 1289 Hose Bib 3,847 3,847
Bulletin 5 25,066 25.066
RFI#0820-Porte Cochere Drains 11000 11 000
4.23 7018142-2301000 Building Control System Automated Logic
03060 Building Control System(30%Construction Documents) 323,350 323,350
IFC Documents 10,000 10.000
Subtotal 333,350 333,350 0
Event Barn(Add A/C to BAS/Control System) 7 500 , 50C
4.24 7018142-2601000 Electrical Bergeiectric
05020 Electrical(30%Construction Documents) 3.968,300 3.968,300
IFC Documents 333,408 333,408
IFC Lighting Clarification-Prior to VE 53,605 53,605
Generator Package(IFC) 1215.570) 15 570;
Savings-Combined Electrical Gear Package/Generators(IFC) ;52.475; (52 475;
Savings-VE Lighting Package and Lighting Controls(IFC) 11100.0061 1100.00&
Bulletin 01&Bulletin 02 35,915 35,915
RFI 0596-Deletion of Rigging Points !97747,, (97 747;
RFI#0840-Eliminate Light Coves at Prefunction Area (11.5621 1 1 562:
RFI#0617A-Location of Lighted Mirrors and Power Information 5,942 5,942
LT Fixture Credit(Berg Mat'I Only) (89.250) ;89 250,
Subtotal 3,830,560 3,830,560 0
Event Barn 217,000 217.000
RFI 1244-Mech Equipment Power Change 17,380 17,380
RFI 1080-Power for Signage 7,154 7,154
RFI 1281-Elephant Sign Power Requirements(Includes lighting controls) 8,810 8,810
RFI 1397-Forklift/Pallet Jack Charging Station 3,176 3,176
(2)Additional 1 1/2"Conduits to floor boxes per IT Underground Coordination 71,039 71,039
Bulletin 03 (27 555) (27 5551
Bulletin 05 21,411 21,411
Installation of Light Fixtures,Raceways to Freezers/Coolers(Excludes Fixtures) 8,011 8,011
Power from Electrical Room to FA Panels 20 000 20.000
FSD Power,Misc Power 100.000 100.000
Allowance-Event Barn LT Fixtures if not Furnished by Kalahari 30,000 30.000
Dat, 2i/1�1'2 18 Faye 5 of t:
GMP Amendment No. 1 - Attachment 2
Column A Column B Column C Column D Column E Column F Column G Column H
Bid Package Cost Gain or
Subsystem Control# Description Estimate Purchasing (Loss)
6.00 7018142-1022000 Operable Panel Partitions Hufcor
C1010 Operable Partitions(IFC Documents) 1.022,250 996,986
Approved VE by Kalahari""STC 52 Wall Panels ILO STC 55 5 E;4; w/Above
BiFold Doors at Kilamanjaro Ballroom 19,500 19,500
Subtotal 1,016,486 1,016,486 0
6.01 7018142-0550100 Ornamental Metals Metalink
C1030 Ornamental Metals(IFC Documents) 58,240 58,240
Subtotal 58,240 58,240 0
Revised Handrail to cover stringers and layout at Escalator/Stair Detail 3G 000 30 000
6.02 Carpentry
B2010 WD-02-Wood Tongue-Groove Soffit(Porte Cochere)(ISEC and Texas Timber pricing) 63 960
Misc.Blocking not shown on documents(removed per meeting w/DH 10/23/2019)
Subtotal 63,960 0 --
6.04 Architectural Millwork ISEC
C3010 Millwork(IFC Documents) 502,574 502,574
Subtotal 502,574 502,574 0
RFI 879A-Deleted Wood Wallcovering at Ceiling L2 ;11.991> {11.451;
Delete BI-fold Doors at Kilamanjaro Ballroom 12.195) 12.195;
Approved Millwork VE Items(Meeting with Kalahari 4/10/19) (132 776) 132J76i
RFI 1554-Liquor Display Cabinet Revisions 3,000 3.000
Bulletin 01&Bulletin 02 100 000 100.000
Acceleration Due to limited crew/labor resources 25,000 25.000
6.06 7018142-0705000 Metal Panels National Panel Systems
B2010 Metal Panels(IFC Documents) 156,602 156.602
RFI#0320-MTL-02-Backside of Screenwall 123,540 Not Included
RFI#0847-Eliminate-MTL-02-Backside of Screenwall f 123.540; Not Included
Subtotal 156,602 156,602 0
6.07 7018142-0891000 Doors,Frames&Hardware LaForce
C1020 Doors,Frames&Hardware(IFC Documents) 547.958 547.958
Event Barn 14,158 14,158
Subtotal 562,116 562,116 0
Dale 2015.12.16
Page 6 of 12
GMP Amendment No. 1 - Attachment 2
Column A Column B Column C Column D Column E Column F Column G Column H
Bid Package Cost Gain or
Subsystem Control# Description Estimate Purchasing (Loss)
Bulletin 01&Bulletin 02 25.000 25 000
Convention Center Ballroom Doors 96 000 96 000
Automatic Openers(Not Specified or Scheduled) 20.000 20 000
6.08 7018142-0833000 Overhead Coiling Doors&Grilles Overhead Door of Austin
82030 Overhead Coiling Doors&Grilles(IFC Documents) 134,237 134.237
Change OH Coiling Shutters at Registration Desks to Wood 101,215 101.215
Subtotal 235,452 235,452 1 0
Controls Wiring and Conduit(Final number from Berg) 10 000 1 0.G00
6.09 Overhead Fire Doors w/6.08
BUDGET w/6.08
Subtotal 0 0 --
6.10 7018142-0870000 Interior Glass&Glazing Anchor Ventana
C1020 Interior Glass&Glazing(Anchor Ventana)-IFC Documents 80.462 80.462
Event Barn-Full Length Mirror&Restroom Mirrors 1,394 1.394
Subtotal 81,856 81,856 0
RFI 1390-Door into Sales Office 2 500 2 500
6.12 7018142-0903000 Acoustical Ceilings Heartland
C3030 Acoustical Ceilings(Heartland Acoustical)-IFC Documents.Bulletin 01&02 596.536 596,536
High Impact Resistant Tackable Wall Panels-WP-101 17.484 Not Included
Eliminate per Kalahari-High Impact Resistant Tackable Wall Panels-WP-101 Not Included
Subtotal 596,536 596,536 0
FOH Finish Revisions
Event Barn-ACT(MA2.301 Unknown Type) 1 665 1 565
6.13 7018142-0904000 Tile&Stone Centex Flooring
C3020 Tile(IFC Documents) 244.950 244.950
Event Barn-T-140 Floor Tile/T-141 Wall Tile 7.546 7.546
Bulletin 01&Bulletin 02 21,750 21,750
Subtotal 274,246 274,246 0
RFI#0862-No Quarry Tile at Freezers
6.14 7018142-0905000 Carpet&Resilient Flooring Flooring Solutions Group
C3020 Carpet&Resilient incl.RC-101 Chair Rail(FSG)-IFC Documents 1,025.378 1,025.378
'Date 2J1y 12 1ti Pageof 12
GMP Amendment No. 1 - Attachment 2
Column A Column B Column C Column D Column E Column F Column G Column H
Bid Package Cost Gain or
Subsystem Control# Description Estimate Purchasing (Loss)
Subtotal 1,025,378 1,025,378 0
Bulletin 01&Bulletin 02 16 084; f6 084)
Carpet Tile at BOH Corridor 60,335 60,335
Credit for Service Elevator Flooring 11.000; (1 000)
RFI 1190R-Finish Revisions
Added Protect-All 61,880 61,880
Change of Resiient Flooring Type 13,868 13,868
Floor Protection 44.378 44,378
6.16.3 7018142-0991000 Paint&Wall Coverings Hagler&Kerr
C3010 Paint and Wall Coverings(Hagler&Kerr) 1,377,773 1,377,773
Event Barn-Finished Spaces Interior Paint 10,079 10,079
Subtotal 1,387,852 1,387,852 0
Sprayed Texture ilo Roller 121,600 121,600
Bulletin 01&Bulletin 02 (7.550) (7550]
RFI 1190R1-BOH Finish Clarifications (38.786; ;38 786)
FOH Finish Revisions (184 74,1) 184 748)
RFI 1426-Loading Dock Finish Changes 2,440 2,440
RFI 1504-LT 912 Light Fixture Details(Rework) 1,307 1,307
RFI 879A-Deleted Wood Walk:overing at Ceiling L2 10,621 10,621
Painters Caulking and Paint Touch-up Outside of Contract Requirements 20.000 20.000
Stain/Seal Event Barn(Board&Batten Siding)(Need final pricing H&K and Cherry) 10,000 10.000
6.19 7018142-1010000 Public Area Toilet I Shower Partitions&Accessories Spectrum
C1030 PP6.19-Toilet Partitions&Accessories(Spectrum)-IFC Documents 118,610 120.382
PP6.19-Event Barn-Toilet Partitions&Accessories(Spectrum)-IFC Documents 1,772 w/Above
PP6.19-Bulletin 01&Bulletin 02 3,657 3,657
RFI 1525-Credit to Remove Trash Grommett 12224`. (2.2245
Subtotal 121,815 121,815 0
6.20.1 7018142-0702000 Building Specialties Alpha
0030 PP6.20-Bldg Specialties-Expansion Joints(Alpha)-IFC Documents 15,611 15,611
Subtotal 1 15,611 1 15,611 0
6.20.2 7018142-1010000 Building Specialties Spectrum
C1030 Bldg Specialties-AED's&Cabinets(Spectrum)-IFC Documents 6,634 6,634
Fire Protection Specialties(Spectrum)-IFC Documents 5,039 6,039
Event Barn-Fire Protection Specialties(Spectrum)-IFC Documents 1,000 w/Above
Bldg Specialties-Corner Guards(Spectrum)-Bulletin 02 478 478
Fire Protection Specialties(Spectrum)-Bulletin 02 218 1 218
RFI 1238-Deletion of 2 AED's (2.3371 r2,3371
Dale 2019.12.18 Page 8 of 12
GMP Amendment No. 1 - Attachment 2
Column A Column B Column C Column D Column E Column F Column G Column H
Bid Package Cost Gain or
Subsystem Control# Description Estimate Purchasing (Loss)
Subtotal 11,032 11,032 0
RFI 1338-Knox Box Locations >OG 2 500
Column Protection at BOH Columns 1 006 1 000
6.20.3 Building Specialties OFOI
C1030 PP6.20-Remaining to Buy Signage ICooel Or 01
Subtotal 0 0 --
6.25 Countertops ]SEC
E2010 Countertops(ISEC)-IFC Documents 183,777 183,777
RFI 1525-Trash Gromment Removal 6,500 6,500
Subtotal 190,277 190,277 0
Approved Countertop VE Items(Meeting with Kalahari 4/10/19) iU0,
Bulletin 01&Bulletin 02 20 000 20 000
Acceleration Due to limited crew/labor resources 25.000 25 000
6.26 Testing,Adjusting&Balancing TAB Technologies
D3070 BUDGET w/Below
Test&Balance 170,000
Subtotal 170,000 0 --
6.27 Decorative Site Fencing OFOI
G2040 Event Barn-Screening Fence BOH(HP RFI) OFO1
Subtotal 0 0 --
6.31 7018142-2810000 Fire Alarm Johnson Controls
05030 Fire Alarm 207 3D 207.300
Subtotal 207,300 207,300 0
Event Barn Conduit 1,400 1.400
8.01 7018142-2700000 Communications Structured Cabling Infrastructure i BryComm
D5030 PP8.01-Communications Structured Cabling Infrastructure&Equip(BryComm)-Event Barn 601,596 654.651
Event Barn 53,055 w/Above
Subtotal 654,651 654,651 0
8.02 Distributed Antenna System(DAS)
Date 2019.12 18 Faye 6 of 12
GMP Amendment No. 1 - Attachment 2
Column A Column B Column C Column D Column E Column F Column G Column H
Bid Package Cost Gain or
Subsystem Control# Description Estimate Purchasing (Loss)
D5030 Deleted by Owner(Pathways Remain with 8.05) Deleted Deleted
Subtotal 0 0 --
8.03 7018142-2830000 Audio Visual CTI
D5030 PP8.03-Audio-Visual Sys-Pathways,Cabling,Devices and Equipment 1,038,647 1,055,547
Event Barn 16,900 w/Above
Bulletin 05 96,089 96,089
Subtotal 1,151,636 1,151,636 0
8.04 7018142-2800000 Electronic Safety&Security BryComm
D5030 PP8.04-Security-Pathways,Cabling and Devices 12,211 48,415
PP8.04-Security(Camera Purchase per direction from Kalahari)(Review Breakdown between Hotel and
CC) 18,442 w/Above
PP8.04-Security(NVR Servers&Licenses Purchase per direction from Kalahari)(Review Breakdown
between Hotel and CC) 19,506 w/Above
PP8.04-Security(Camera VE accepted by Kalahari) i 74-1 w/Above
Subtotal 48,415 48,415 0
8.05 7018142-2601000 Low Voltage System Pathways Bergelectric
D5030 PP8.05-Low Voltage Pathways(Bergelectric) 421.400 421,400
Subtotal 421,400 421,400 0
PP8.05-Low Voltage Pathways(Bergelectric)-Event Barn 8.000 8.000
9.01 Final Clean TBD
C1030 Final Clean 150.900
Event Barn 3,750
Subtotal 154,650 0 --
COW Cost of Work
Layout&Control 182,006 182,006
Layout&Control i 182 0051 (1820M
Arias-Testing 74,650 74,650
Dumpsters 49,651 49,651
Weekly Clean 81,000 81,000
Temp Toilets 21,807 21,807
Sump Pit Grating 434 434
Water Truck 11,000 11,000
Temp Weather Protection 12,500 12,500
Temp Access Protection 15,000 15,000
Temp Signage 3,000 3,000
Dumpster Backhoe 0 0
Date 2019.12.18 Page 10 W 12
GMP Amendment No. 1 - Attachment 2
Column A Column B Column C Column D Column E Column F Column G Column H
Bid Package Cost Gain or
Subsystem Control# Description Estimate Purchasing (Loss)
Support Cranes-Material&Other Cost 100,211 100,211
Support Cranes Equipment 0 0
Forklift Operator-Labor 150,000 150,000
Forklift Fuel Oil Gas 0 0
Forklift Monthly Rental 80,000 80,000
Equipment Insurance 2,000 2,000
Backhoe for Dumpster Management 20,000 20,000
Subtotal 621,253 621,253 0
Date 2019.12.18 Page 11 of 12
GMP Amendment No. 1 - Attachment 2
Column A Column B Column C Column D Column E Column F Column G Column H
Bid Package Cost Gain or
Subsystem Control# Description Estimate Purchasing (Loss)
GENERAL CONDITIONS
General conditions 1,753,472 1,753,472
Layout&Control 148,914 148,914
Subtotal 1,902,386 1,902,386 0
INDIRECTS
Contractors Bonds(.55%of GMP) ($49,667,789'0.0055)(GMP Less Bond) 273,173 273,173
SDI(1.35%COW and Contingency)($44,358,933'.0135)(All costs above COW) 598,846 598,846
Insurance(.59%of GMP less Fee)($48,603,872'.0059) 286,763 286,763
Subtotal 1,158,782 1,158,782 0
CONTINGENCY&RESERVES
Bidding&Construction Reserves(1.25%of Cost of Work less GC's) 562,252
($44,980,186-0.0125)
Subtotal 562,252 0 --
9099000 CONTRACTOR'S FEE
Contractor's Fee(2.75%) 1.336,599
($48,603,606'0.0275)
Subtotal 1,336,599 0 --
CO# APPROVED DESIGN TRENDS/CHANGES(Temp Placeholder)
TOTAL $49,940,205.00 $49,940,205.00 $45,616.279 $45,616,279 $0
Percent Purchased: 91.34
Percent Gain/;Loss) 0.00%
Date 2019 12.18
Page 12 of 12
i
GMP Amendment No 1 Attachment 3 December 18, 2019
Kalahari Resorts and Conventions
Round Rock Convention Center Guaranteed Maximum Price Proposal
Clarifications & Assumptions
General Comments
1. This proposal is based on the Kalahari-Round Rock,Texas—IFC Documents Package dated October
5,2018 prepared by HKS, Inc.and their sub-consultants, inclusive of Bulletin 01 dated November 1,
2018, Bulletin 02 dated January 22, 2019, Bulletin 03 dated April 24, 2019, Bulletin 04 dated June
7,2019 and Bulletin 05 dated September 12,2019.
2. This proposal includes all Convention Center costs associated with Requests for Information as
defined in the attached log(RFI Summary Log). The items in gray are not applicable to this proposal
and not included,the items in green are included in this proposal and the items in red have not been
included in this proposal and will be addressed on an individual basis via the change estimate process.
3. We have not included any costs for hazardous remediation of soil or water. If contaminated materials
are encountered,Hensel Phelps will notify the Owner.
4. The Convention Center has been included as tax exempt.
5. Special payment terms, such as deposits and up-front payments, that differ than those in the prime
agreement that cannot be negotiated for overseas suppliers or specialty vendors are assumed to be
billable at the time the expense is incurred and at the same value.
6. Per owner direction, no standalone (sacrificial) mockups have been included. References to
standalone mockups within specification sections have been excluded.
7. Per the meeting held between Hensel Phelps and Kalahari on October 23,2019 code required signage,
that is not shown in the plans and specifications,will be OFOI and therefore all costs associated with
this scope have been removed.
8. The cost of permits and City of Round Rock inspection fees have been assumed to be waived or by
the owner, including any City required third party inspections and water meter impact fees.
9. The following items have been included as allowances:
a. Event Barn LT Fixtures-$30,000
10. Cost associated with costs highlighted in the attached document, "2019.12.18 —Kalahari CC GMP
Cost Back-up," are budgets for items that remain to be bought or changes to the original contract
documents that have not been fully reviewed,confirmed or approved by the Owner. These costs will
be presented to Kalahari in accordance with the contract.
11. The following IFC specification sections or materials have been excluded as they could not be found
in the documents or do not apply to the Convention Center portion of the project:
a. 015639-Temporary Tree and Plant Protection
b. 033800—Post Tensioning
c. 034100—Precast Structural Concrete
d. 044216—Site Stone Blocks, Boulders and Slabs
e. 055013—Site Miscellaneous Metal Fabrications
f. 055214—Site Guard and Hand Railings
g. 061063—Site Exterior Rough Carpentry
h. 071800—Traffic Coatings
i. 073113—Air and Water Barriers Asphalt Shingles
j. 073213—PVC Thatch Shingle Roofing
k. 083326—Overhead Coiling Grilles-
1. 084500—Translucent Insulating Panel Assemblies
m. 085113—Aluminum Windows
Page 1 of 6
Kalahari.
® HENSEL PHELPS RESORTS
Manap CONVENTIONS
GMP Amendment No 1 Attachment 3
December 18, 2019
n. 096400—Wood Flooring
o. 096623 —Thin Set Terrazzo Flooring
p. 099639—Epoxy Containment Coating
q. 101443 —Photoluminescent Exit Path Marking System
r. 102213—Wire Mesh Partitions
s. 102819—Shower Doors and Enclosures
t. 103116—Manufactured Fireplaces
u. 105113—Metal Lockers
v. 107500—Flagpoles
w. 111213—Turnstiles and Gates
x. 112400—Building Maintenance Equipment
y. 129300—Site Furnishings
z. 122113—Horizontal Louver Blinds
aa. 132640—Prefabricated Modular Bathrooms
bb. 133100—Tensile Membrane Structures
cc. 149100—Chutes
dd. 232123 —Hydronic Pumps
ee. 236416—Centrifugal Water Chillers
ff. 236514—Open Circuit, Mechanical-Draft Cooling Towers
gg. 312219—Landscaping and Fine Grading
hh. Division 32—Exterior Improvements
ii. Division 33—Utilities
12. Fire Watch or other temporary measures that may be required by City of Round Rock AHJ for
temporary stocking or owner move in prior to permanent FA/FP systems being active have not been
included.
13. Any coordination required above and beyond standard permit requirements, with the Authority
Having Jurisdiction(AHJ) for operational sign-off for final opening is by Kalahari.
14. The Owner intends to utilize the Kilimanjaro Ballroom within the Convention Center for staging
and storage of Owner Furnished items prior to completion. Owner and Contractor will develop the
punch list prior to the start of Owner staging and storage activities. It is assumed that Owner
vendors and suppliers will be responsible for their own wall and elevator protection, daily cleanup
and loading into dumpsters, and labor; as well as any rework or repairs due to damages by the
owner, their vendors or suppliers. Coordination with the AHJ for approval of the use of this area as
storage/stocking is assumed to be by Kalahari.
15. In order to finalize the Convention Center finishes in the ballroom,all OFOI, OFCI and FFE will
need to be removed from the Kilimanjaro Ballroom 30 days prior to final completion.
16. Materials are being provided per specifications. The selections are best value and may vary from
Hotel, Parks and Site materials. Costs associated with requiring single source across all
projects/buildings has not been included.
A 10—Foundations
A20—Basement Construction
1. Crystalline waterproofing is included at Convention Center escalator pits. No other locations are
identified and are therefore not included.
Page 2 of 6
wicalahaft
HENSEL PHELPS --- -
RESORTS &
P13n Po 0 Manage CONVENTIONS
GMP Amendment No 1 Attachment 3
December 18, 2019
B 10—Superstructure
1. Square and rectangular tube steel is priced as ASTM A500-B instead of A501 as stated in the
specifications.
2. Any long span steel members longer than 69'-0"have been priced as spliced members.
3. One coat of rust inhibitive primer has been included where AESS steel is indicated.
4. Fireproofing of roof structural members are excluded where every part of the roof construction is 20
feet or more above any floor immediately below. The structural columns and brace frames in these
conditions will be fireproofed up to the roof deck.
5. Fireproofing of metal decking is not included where 4.5"NW concrete is on 3" metal decking. Floor
beams and columns are included.
6. Fireproofing has not been included at trellises,the Event Barn or screen wall framing.
7. A 5-year extended warranty for the area where light weight mix design was placed at Level 2 Sector
C has been included.
B20—Exterior Closure
1. All exterior stone veneer corners will be a return using butt joints; L-shaped corner stones have not
been included.
2. Thermal spray insulation is included at the Convention Center loading dock soffit only where the
above slab is occupied interior space. This product was listed in specification section 07 21 00 —
Thermal Insulation.
3. Fluid applied weather barrier per specification section 07 27 26 is included all exterior applications
in lieu of self-adhered weather barrier per specification section 07 27 13.
4. The 08 8000 Glazing specification indicates an ETA membrane to be utilized at all aluminum framing
systems perimeters to seal the air barrier. Standard sealant details are indicated in the documents and
have been included in lieu of ETA membrane.
�. Manufacturer warranty for Anodized Aluminum has been included as 10 year.
B30— Roofing
C 10—Interior Construction
1. In reference to part 3.5 of specification 10 22 38 for Operable Partitions, no field testing of the
partitions has been included. Manufacturer test data has been included in our proposal. Similarly, no
field testing of rated walls has been included; walls will be constructed per contract documents and
details.
2. Per 1.12.A.2.a of specification 10 22 38, we have included the 2-year base bid warranty period for
the operable partition panels.
3. Per 2.7.b finish facing of specification 10 22 38,we have included vinyl-coated fabric wall covering.
4. Operable partitions have been included at STC 52 ILO STC 55 per the drawings
5. We have included 4' tall unpainted plywood at all BOH corridors (on drywall partitions) and
electrical/IT room walls.
6. The following items are assumed to be Owner Furnished:
a. Paper Towel OFCI
b. Toilet Paper Dispensers OFCI
c. Decorative Mirrors and Lighted Mirrors OFOI
d. Loose Lockers and Benches OFOI
e. Mop& Broom holders OFOI
Page 3 of 6
Kalahari.
Q HENSEL PHELPS RESORTS &
Mmilp CONVENTIONS
GMP Amendment No 1 Attachment 3
December 18, 2019
f. LT Light Fixtures OFCI
g. Loose furniture,curtains,trash bins,artwork, clocks, loose planters OFOI
h. Attendance time clock OFOI
i. Office furniture and equipment OFOI
j. Trash compactors and plates OFOI
k. Oil System and fill boxes OFOI
1. Code Required Signage(not identified in the plans and specs)OFOI
7. Masonry cell insulation has not been included as it does not apply to the project.
8. Flooring system sound reduction membranes have not been included.
9. Custom Vinyl Graphics on Coiling Counter Doors have not been included.
10. Acoustical Wall Panels(WP-101 and WP-102) have not been included per owner direction.
11. Wood Door casings over HM frames have not been included per Owner direction.
C20—Stairs
1. We have assumed and included an American Stair Endura system at all exit stairs. These stairs will
include a fadeaway post and rail system as well as preplaced treads.
C30—Interior Finishes
1. The following owner accepted VE items have been incorporated within the Interior Architectural
Woodwork value:
Location Item Color Description ISEC Amount Accepted Y7N Canniest Cor n*Ma
60 cc Purple CA3.616,Come.Ca.Req.Desks.-Use file backer and
flaVpkwd on nominal Y16'trim at face(trim should overlap the provide 1x6 trim 130 of build up.Tile backer
backer and stand proud so finished file is recessed sightly) 4$7,5831 Yes 17.583) should be covered by tile subcontractor?
61 cc Bite Delete all Wood door casi;;j at Conv Ctr 16.17W13.302 $12.756 Yes x12758)
62 CC Yelow Oi/CA3.617.Defile wood bifoldirg doors at both sides of
elevation $12,1f S1 W 0 loovering rollup doors
delete WD-135 at soffit and portal vertical surfaces
63 CC Pink 02/CA4-002,delete WD-135 wood soffit at arnwl $15.1W. Yes (15,194) this location
64 cc Red Delete all WD-128 ceiling planking in pre•funion lobby t$93.1.6ri Yes :93,267)
cc Green Delete light coves at pre-fun ctlon corridors per RFI 00840 $0 Yes 0 Berg&Standard
65 CC Orange CA4-202-D&F:Remove 4at WD-134(or 148)at Prefunction
03 ($3.976) Yes (5.976)
$0 0
$0 0
Total Proposed To Date: t$144,971.00) ACCEPTED TO DATE:'($02,71`6)
D 10—Conveying
1. Plexi-glass cut out for card readers and Auxiliary car operating panel in passenger elevators have not
been included per Owner direction.
D20—Plumbing
1. Plumbing fixtures have been included per owner selection which has been documented via RFI 812.
D30—HVAC
1. Vibration isolation for ductwork is limited to fabric duct connections at motor-driven equipment and
the first 4 hanger locations on each side. No other ductwork has vibration isolation.
Page 4 of 6
VICalahan.
QHENSEL PHELPS RESORTS &
PILI B 1 C "dale.?"? CONVENTIONS
GMP Amendment No i Attachment 3
December 18, 2019
2. Duct cleaning per 23 3113, 3.12.13 and 3.13 has been excluded. Commercial standard duct cleaning
for a facility of this type has been included.
D40—Fire Protection
1. We have included the design and installation of a code compliant system with the City of Round
Rock Standards.
D50—Electrical
1. Light fixtures have been included per the attached Light Fixture Matrix which includes owner
selections for manufacturer alternates.
2. Lighting control system has been included per owner selection for a Lutron system across the
resort.
3. Taylor Power has been selected as the Generator and ATS provider for the entire project,they will
supply a 5-year extended warranty.
4. GE has been selected as the Gear provider for the entire project.
D50—Low Voltage, AN and Communications
1. The following have not been included as they have been identified to be OFOI or OFCI;this
proposal does include conduit and raceways as required:
a. Digital Signage servers and software
b. Digital Signage display monitor framing(meeting rooms/ballrooms)
c. Pagers and cell phones
d. Computers, network servers, POS system electronic components
e. Main switches, software and telephone handsets
f. MATV system satellite dish, monitors, software and installation
g. Two-way radio equipment, devices, software
h. Rack mounted UPS units for Owner provided equipment/devices(included as OFCI)
i. Wireless Access Point devices and equipment(included as OFCI)
j. Distributed Antenna system(DAS) for cellular DAS equipment and cabling
k. SFP POE Units
1. Access Control equipment, Vingcards, software devices, and programming
2. Empty pathways for cellular DAS system have been included above hard ceilings only.
3. Security cameras,NVR servers and licenses have been included per owner direction.
D50- Fire Alarm
1. Fire Alarm system has been included as an open spec which complies with minimum requirements
for City adopted codes of NFPA 72 and IFC 2015. Some specific items within the issued
specification that have not been included,due to being manufacturer specific or above code
requirements for a facility of this type,are:
a. 100%amp power backup
b. Seismic performance requirements
c. 100%conduit pathways
d. Firefighter's phone
e. Pre-action panels
f. Positive alarm sequencing
Page 5 of 6
Kalahari.
QHENSEL PHELPS RESORTS &
-iI-, i `I'n 11, CONVENTIONS
GMP Amendment No i Attachment 3
December 18, 2019
2. Design and install of an emergency first responder wireless radio communications(DAS) is
included and based on readings of-60.51 dBm @ 857.962 500 MHz taken on site at the Convention
Center Level 2 entrance.
E10—Equipment
1. All Food Service Equipment, Kitchen Equipment, Walk-in Coolers and Freeze are assumed to be
furnished and installed by the Owner's Food Service Equipment contractor.
Page 6 of 6
Kalahari.
0 HENSEL PHELPS RESORTS &
Plan VI Id P.hnajP. CONVENTIONS
TV
c, g�mCgm c � �mm�m � mRm� mem mm § m ��m�� msm ' m�
a"a aaaaaa aaa aa�-a Baa 5 �a �m
C o
O
E
/UR pp
TT v m mO mo m m N s m m.o m m m m b m m m m mU m m s m m m m m m m s m m m m'_T m O m O m'S O m p m S V m m m VZ m m TV m m
Q mc��M iR ssRsI�-,v,Qsmsasmws�m cccc!!Qc ccccccr r�cccacCccc2ecc'"I' �����Ua�H m
�— ����aaaa a aaaaam"a aeamaaaaoazaa�aaN �- ,. � ���,.
0
O
Z
c
E 8
Q � aId 0 � o
ggEg�'3` ��'� ��5��'L'��'°ii.�
Ca a`ixxxxxxxxx xxxxxxx xxxx2mxmxxxx3s3xixxxxsrxxxx=x xxxxxxxxxxxxxxxxxxxixxxI xxiixxxixxxx
G
d d d d d 6 d d 6 6 d d 6 d 6 d d d d d d d d tl U d 6 d d d V d d d d d d d d d d d d d d d d d d d U U 6 d d d d d 6 dUUVUVUUUUUUUUUU U uuUuoUUUuuUuUVUV
V UUUVU
U U U u V U U
€ € 5 § € §fi fib € 5 § € S � fifrfi � fififi fi � fi € fi € 5s ` fi fi bfi 6 € 5 fififi € 55fr
IL
Z76
o
Q
F
Z
W
Z
O
V
G
�S
a`
a 4 0 3 a a m x fr Ef N E Ti
a p cioNLL Q u p vu 3 N s E'
W � m� a - XXX$ np � fi g
g8$ �F_3 'S r3 �0Q Ez
CL =_ C u m o `�� w �$ x �s d
u'w E U v o `s w i
a e $ o g ry 9�� LLa S
W us 3i� ¢o Sao z�N R� �' °�� xf oW P�rA"s =rw5u a $�S s3 ; Fit 664 a ;
�y-� _ ¢�
Z m am Ytl 3o€ g3m �a� o�a� �g � $ a� 8 °nSy §Ga°� �� maE ; F�C `-S gm3 +E?$ �a 'o3uduuN�
n NNn 2> g gg §Pggo �°az no 't 2! u� grN
W � v uciyd3 0 �R'� � `s�44 `s �S��� ����ppyy� a��
y S Z L S ul V S Z I a R a,n w 2 2 I x in S 2 2 2 h a 2 a N Z i a m a S a Z V x Z 0 0 0 U U U U N n as i x x a n 2 i a N d i u I i I n i 2 u v u a m N 2 2 I a U U I w77 Z 2 Z u
rTTR PI AX F'M^�MFtM�� o�NMfND�mP
sssssssas"sssr,
--------------------------
--------------------------------------------------
E
TV T V T TmmQQm TmT TrmVcV VOcf TRV` V V T V T T T�6sV�c��� m�m '�m����� �W m�� m �����
C�4 C"'�^��a,a`���v�1
a a� ai
L
U
(II
Q 8mm mmmmsmmmmmmm S So �mmmmob m0��0bo` SSo00 mbomb-----SSSS ^�mmOmom m moms
or�cSrSSR"ahg�mmomcmac��ccSmIcc ccc& ccc� $Cc �ocRSaam�a
Z
c
E
c
a�
E
Q E
E g g 12ik8 1 2 g Ig I i 1 9 1 ie21
7 77
/n a zxxxxsxxxzxssY`xxrxizixxxxsxxx' xxzrxiii .zzxzx ii zzzrrxrxx' xzxxx£ xxsxxxxxxxxzxxzxx
V
u U U U U oyU d d d 6 d d d d d d dU d d 6 d d d d d d o 6 d, o d d d d d,.d d d 6 d d d o d o d o d
UUUUUUUUUUUUUUuUU UUUUUUUVUUUUUUUoUUUUUVUUUUUUUUuUUUUUUUUU
U U U Qu U U U U U U U U U U U U
S O O S QQ O S O O O tl a O O O O O O O O O O O� O O O p O O O S o O
00- U U
Z a s n a n n a n a n a n a a a n n n n n n a n a a n a a n a G n a a a a n n n n n n n n n a n n a n a a a a a a n n n n n n n a n a n n n n n a 6
� a
a
z
W
Z
0
CL
V
a N3� !� E
W m ys
m �F mm
ry ¢ s`g ro 4 pp o. 19 o E B m yy
g m m a o Dal
E 4 a°
WEy3 � �agw4a a - mw E wmu „oe maaua � S ggsa-£m
R � LLm urra`� s m
od °
g v
w 8 a m of g Y c3 ma- m
�louU ��� � � �5 ��.-80�� E
W
3 Yva wi Cc9 u�[72G
3 ---- -.-- -- -.-- -.- .-
? U
O
r
U
(B
Emm m m
QV m m m m m m mmmm m m............ma m m� m m m s m m m m mU m m m�m m mO m m m S S O m m m m m m m m m m m m
O
Z
c
N
c -
Q o
U
U d d d o d d o d UU d d d 6 d d d d d d d d d d d d d d d d d d o d 6 d d d 6 6 V 6 6 d d d d d d d d d 68 '
U U Quo.
.UN�vuNNOuo�a
W od
Za s n a a a a n a a a s a`a a a a a a a a a a a a a a a a a s n a a a a a a n a a a a a s a a a a a s b a a a a n a a a n a aaa a
Lu
F $ € ea
S=________'T'2=Z x=I=__
0
z
Lu
z
0
U
e
L
m
U
W �O �` 'K y k Y c 5 m C c F ° Yx� y�3y�P mF }i °G Y ani$ a U t3 sq @ i-, W Kb N
3 S 3Y 65 I bay
_ saa °kiaN %�Fw2m° o' `aoo°mm?u �� Bea$ �rs� zms5o�� L� u�a` aFEF�� mgugR
o
Wmwg� ci E$ �i $a u q qE s Sw�? � u'aN ..N4 ' pie �yso � 4 y `�� _ �J p�wuYuw if 8
3�71a m Z
NN
2
LU n � o ° €� # N�
d 9 `
E ...
N N m a rc
m S a�U a a a u a SSI Z 6 U I a 2 Z S Z Z N N a as 1 U u a 2 x 6 a y U u x g x I x g a x a 2 a 2 a 2 Z Z a Ogg.a d ay a a m g x a x x o 1 2 2 S U i I I I I x 2 m x x R n .g o iy,a
I a
g�$n`00000000S0000000S�oo��bo�000`$mo'orb"g$b"o`��&'oS'b"�&og'S'og&'�&'o�g���S'���o��Yb���m"�d' �Sg�&'o�o��o�b"oElmS'�b
E �r__ -_ --- -_
U
C m a� �a ���a�a �?aaaaa aaam�5a?aaaa"aae �aa� _ as a "� aaaaaaa �aa
E
L
U
CB
.........................................................mm�
Q m mmmmmm mmm mmm� m -
o o'o o o s o S S o o n S o S
��cCc�rr�����r cr&c
O °
Z
c
a�
E
c
� o �
G a`x xYx=ixi zT xiiiT r T xx x xziiixxi iiiixi xxixxxxxii'ixxzixxx'xiixixii=i x iiTxxai
dU U U U U V U U U Ud Vd U U U U Vd Ud U U U U Ud U U Ud U Vd U U Ud Ud U Ud U UdU U Ud U UUd U Vd U U U U Ucc d U U U U U U d d U d d d U U ' d U tc U U U d
4 UUU UVUUUUUUUUUUUU
U UccUCCCCCU U44 U U
ix
Lu
Z
LU
mmmmmmmmmmmmmmmmm mImmmmmmmmmmmmmmmmmmmmmmTzmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmm�mmmmmmm T
O
z
Z
w
Z
0
U
E
a
m �
E
a. m a ffi Y 4 a cp m
= 8ag $E $ SNa ` 8aN jppa" �ffiw� � pa fi3$ $p Y 4v &�
W m Y
w € s a � mgg E5a a �� Um � g4 5�z�,
� EI_4 �� �fi �w�8ta3 & g@x 8=m�ngm' szg $� aUq grffiLL� Sys€24gmg€�
W #mr « �xg� $UE� F a � f'a8�� mwE § " � ffia� fi� $ E$ �caem �- qFE
L�aUUU � �waa > E ¢ $ v� �".� a�
-U v gip a aAt = w �'w N�w a m� m Nat z u� ffi uuzE�
Z a g w "°x =a '� E,`$ m '� m g a w m- m J $ 3 x x a 3 r g z z
a 8 a o. "� ' N n w m Y
® eE ��o E '�
W ��N� a��m� s �7A '� � o yy � tq�s� o U� E � r � �a��� yy�3 t NF
naU�n 1u 13u'r o cia3u91w u�t¢m�cl ul Ua3�gt�i c33 min a�LL �mi$w'w a Ut3v>w�Y�iw aa� aa.a'x'nao�uuw cS
z4aoaasoo oas0000aosss�soossss o
B
8a aaaaaa ? aaaa �aaaaaaaaaaaaaaa�aaaa a5 -a---aa -- -- aa aS ' ss
� o
E
L
U
< $aV VmV VTdcvmT vcrT v TmSTVaTrmvmmVT TV mf T TT V fVffrV TFT V TV VT Tr$VT Vssm��w������
sma ,c� a$ a�aa a §a� a �aaa5aaaaaaaaaaaaaaaaaaaaaaaaaaaaaa'aaaaaaaaaa aaaa
Z
c
a�
E
c
aD
^Qwo a gg J yy �y y y y y y y ,} �y , g
LL'n Q w o O'd_w=y=_ =i 2 0�5 Y'o 0 S 5 0 XT XXXS 2 S I.L S.I Z h Y 2 S 2 S I S 2 2 S I S 2 S S S S 2 F Z 2'S 2 S Y Z=S 2 2 2 2 2 2 2 2 Z S Z I=
�../ mmz2 Z 2 I
' d d d d d tl d 6 d d d d d dd d d d pp d d d d - d - d d tl tl d d d d
U V U V V U U U U U U U V U U U U U U U V U U U U V U U U V U U U V V U U U U U U V U U U U U U V U U U U U U U U U U U V U U U U V U U U U U U U V U U U U U U U U U U
o
UUU U UUUUU UUUUU UUVUJ UU U U U U U U U U U U U U
z aP� �
0
z
Z
W
Z
0
U
c�
w
gg�
y
� W a
3 4 gg
� a a
N E
E >
uQQu Ax 9a d=gym$$ �0 Y` w u 418
J m S g p G 6 g 3 LL S 2 3 Y d
_
¢poZ
E 3 N x1'$ I�I�1 � 5i €. 2°3 m LU
a g
^
_ d "gOk�ga; vw$sma � oo� �$F ��i �aYaYmu�� n3ase $ g ?€ LL2 � � ° gEQQ� g A
I p J p 0 m
N a=Z S I I I I S L I U 2¢¢III¢¢U>¢U U 12 S S I I¢¢N N S L¢I U N T Q•m V Z 1 12 i 2 I Q.2 a as U U 12 2 2 S 2 S L I U U a¢a S S>a a 2¢N Z 2 2 2 S U
E-- ... 2 ..... ..........218 2,o"sa^s8o o ...s^sS..^$$ s ss aassasaaaaas"asaaaga�
4 0 00 0 0 18 aooaooa0000a
e
M
t�
s
U
Q .m m. mm mm mmm m m m .cmc&. ccm.mm.. . mm...
Enos s o s
p s� ' a"a 8 iialI111a a a a a a � ect � MO
e'
Z
c
a)
E
c
a
E
Q E
a x YZ x 2 x S S Z r r S Z x S S S S S.r r S r S Z 2 S x S S S S r S r XXXIXZZX Z XXX 2 TI z
U
pp dd U U U U U U U U U V tJ U O U V U V U U U tdi u U U U V U V U U U U U U U
U C3 d 6 V 0 0 0 d c6 U U U U U U U U U U U V U U U U U U U U V U U U U V U U U U U U U U 8 S U tJ V
J5 �€ fifi 5 5fi€ fi€ 6fi565 € � fi5fi fi€ § fi & fi$5 fr fi fi fi€ § € €fiS58 5 § fi5
UQI �U�UUUUU�U±{'U UU UUUUU�U$gUUUU.U�UU-!y�ppJ�$UUUUUUUCJ�U��UUUU�g+�U@?V V UUUUU�VUUUUUcegUUUUUg@U�Ugp?'tg Ug+000UUUUU�p^'gU$�UUUUV UUxg+}Uy;
Z Uyyppa�ryryppaay yypyyap a agy9 'g§i yyp '§py�pa@@pyp 'yyZg(yt �Eyyggp �Ep gpa$ paapFyyypQ g^ �ryua?
O
H
Z
W
Z
O
U
15 0
8
O g
� pp ggy
n u g $ 5a $ $ o s o
a. g
s 3° a N ti fi m r"o s a g ffi g u Y
� uu gy�+ pma � [$� ` ya9y� mm S 3 mwgd wpo $T'. r�e � m�
CL
LU
m 'o ua s >o U vii E U
a.i ct 4 u n `� ` y '{ a d o ` i LL 3 w ° o E z ffi m o$E u o=__
s` $' P �a ° aso u$ gga` �wc� o° N um � � m
Pa O u E g E o � y w a
4 N U U S' O qq;; U U (7 O S
W a u ~J " �' s@ a `s d `-�I 7i 9 8 >
.P $ :n'x Y g E o o "
Z m °a �LLm3��,;13N .o� 53ao8J ���wC.4xzusayNs° � & �a�� � SN� ��m�mag$� g.€ $ u=�
w LU
$ o
d
o8> �
EP
w$m vm,am+$��iNo$a'a u� � a aNEu3��C�a�ww ou3aa am �e.i a m aacfi u� n°9oaw o°�na
N�S i S U U U U U i z m g 2g
E8888aS8SSS8SS�SES�S88SSSSSSSS88838S8SS�SSBg�s $ sssassssg�g �� �o�g
4 =
o
B
`o We � o �� sm��� �m� Vsm v�� mc��
N o
L
U
Qcrrc E E?
Z
E
E
Q o
C aiixixzx xiI mmm ixx zxiiIi' i£ i xxxi xi rimfi`xxr' rxmmmx=mrmmm ixx' xix x' i' zx xxx:
uuuuusuuuuQuuuUuuuQ QO U°uU$ UouQouQfjQoQ4vuouUuo°U° u�uuuuQuu°uuuouc°�uc°�uUouui&uuuuuo°Uu°uuvu
€ I € fifi €fi € 5 fi fi § § fi € € fi € §€fi fi fi§ fi € fififi6 € 5fi § €fi
MI
W a �
Z o a a a a e a a a a a a a a a n a a a a a a a a a a n a a a n a a a a a a a a a a a a a a a a a a a a a s a a a a a a a a a a s 3 a a n a a a a
uj
I1�111111TIIITI¢ 111111111111111zIIIIIIIIIIIIIIIIIIIII IIImIII 111111111111111111
0
z
z
w
Z
0
U
N
w
p �
wE} g�q a w E S 3 S €',@ u Z ppgps� € 'ggEi6
W w m k' 8 P t
, $ F o f my n n u ��Q m,�u u `s b
CL
o
W a ndN8� ag N£ N �g �a �8g�g86 � 6ffiE3f@m$ av y8�gggwg aNU
R ag m ^oo$ g UB �zm � gw9wa� $s` 5 ` -uo�3cj °¢Y $ >=UxxN_x .¢$E3gc�nS��cTr
Wuarr���Sn
it
ainmNUa�iw#m �i$$ $a
t�1
A
W 8P < �&it �aF o� ° ` moi u ; 7z � � � �a xy33 ala e ° E� 21 Is o°
a9� go�E fFv �a €a
'ri.6 a33gNaN.9 u°�n F- ua�u¢u5=wn,3adeN aNO3N�Ia myu mu�i3Na g ,n u� uNmcl;3 ins 1u��un�a eu�i
N U Z S S Z S a N a N N N a N N N N N N N Z N N a N a N N a N 2 2 I S 2 2 n a N 2 2 S 2 x 2 2 a I Z Z a a 2 I Z m I I a u 2 2 N 2 2 6 U N N S N N N N N N I a N a a Z S a 2
gmaVermmR oC� ��� 3Ro� o n R�� 3! SR 2om� 4 rgmso�Fn
Fm _ mo mow mow � o wmo m mm m m m m wom
c
O
L
U
�mm mwm........ .w.m w ow w
r
------------------ 65a aaaaaAaaaaa a'aaaaaaaaaaaaaaa------a-------aaa'aaa?aa^S rra S
a
O
Z
c
E E
Q a a
=_i_
c�
U S V S U V U U U V V U U U S V U U U U S V U U U U V SUSS V U U U S S U U S U S U S S S S U U S U S S U S S U U U U()U U U U U V S S U S V U J V5 U U U S(S U V U S S
S fi S fi fi fi fi S fi fi fi S fi S S fi fi �¢ fi S S fi S fi S S fi. o S S r5 S y fi S§fi fi fi fi
TU�RU$,Ug$U UggUUU Ug UOgU:J.V�-p U.O�000<.yJq,U Uyg�U U UU�U O�U.U��V-s U.UpgO O.Ug.0 Uppg U+�O stt#UggU{!UppO O�UgO UgUU U U UU U U UUV UU'U¢$O lS'Ugg).]:J,.iU UppgO O#+p U
Z a Ix
0
z
Z
w
z
0
U
Uri
Z � ❑ pp n
Q � W � = j = $U ��p❑
N
S L v U
Eo�
°�� j if ❑ S� $ gV'
4 � ma3g sS
3 � oa `s°o�ug ��� � g ��mgA
�n° o� � damvpev x �ym�Yv�' se 4'm ° ppm f iu�SO�gfi az � y$ f
�� w uI� $
�F E u
� <
W ° $�� EEa xo°zm8om�s❑ o��oogx � v�as�r $ g3 uyau3 � aNS ogLLg � 3❑� $ z ��de#
Z m m u E a o m N o o Y a X Q.�z 8 m,e$u i a a m um, u a a v 8$m $ g z m 3 ?u LD cD�' x s ati x ° a a
�o a � ny� c a u ° 3'gi egg ' AE _ O � N �3 �=o y v�w� �
W "g� }� 5�`g+ 3t°�8 $� � s ® � o - 8��yagb ; Eo �xo vAg � n aE
u m u u �"$ m i x$w a s u o m ❑>O fi v¢ V a$ w:p°
N i Nn UUCI RCt6ai(]ugg Vld vli Usti B..i a iC�U UUNRxR S 5222 U ad 2S gTg xZ Sa S comity agg i i0ii 4liiii2Ui Zi S Si�i S 2 d x a i2m as iVti d a u.
E �� oa � 8 $ �88�S�g �g8g8�8g888 $g8888g8�88�$ � 888 88 2 � 8888 8
z
$ --r -----« ---------------�
"o
u
8
N °
L
U
(O
Q u�����o wrnawmap w � mQ wmmmm a''oPSS `o 'SpS QQQQ S S mw SpSSq ao, a @ 'oSQp'QpSp p® S'm
ss � ------ _ _ _� ,mc&a_'cCr& L c rcNC Cc Ccc&'ccr
O
Z
c
E
C:
0)
Qyo 5� YY L U J
Cyy� Vi Vi Ji ieAN� �Ic xa�b!y5 yW�N fA VY)Ny Vi t�yNyyNy� N N•y4��N yN w.0 ii w 6 Vi 0u) NVi tti Vi uJ dyi NOr N [NVi �y[
(D
a Z.x S I x I z x S x S ZZMT Z 2 2 S x i 1 2 S X7 1 2 2 S 2 I S 2 x x x I x I S x S x I S x x S 2 1 2 S S S 2 I 2 S x x 2 x I I Z I S I x 2 I x
V
d o d o d d o d o o d o
Ur oU d U U UU U U U UUUUUUUUUUUU UU U UUUUUUUUU U UUUUUUUUUUUUUUUUUUUUUUUUUUUUUU UUUUUUUVUU U U U U U U U U U U U
oG�� p � oG 0 000 ,
V U UU U UU:]V U UU U U UU U UU )UUU Uq UU U 11 U U 0 U U U�U.U�U UUU.Upg.U� V U U U�U.U�.U�UU U�.�U.U'�'.U�UU �U-V U U U �Upp.0.U�-'U$g'Uyg U'{U¢gUU UUgU
Z o
a gg7g a$ay$Ia ayQaaygnK7p, ° a$ yaygaaaFR'an $apaan �taaa aay� nyay+ aCS yS_aypap_a 7p
&_ S b ID i a
Z a S Z x S Z Z Z S S Z 12 I S S S I..z 2 2 2 2 2 2 I S S S S S z S Z I Z z Z S 2 Z S 2 S S S 2 2 2 S S 2 I i.I I I Z 2 S S I Z Z Z Z Z i I Z I I I Z I I Z S Z I S
O
H
Z
W
Z
O
U
� t U
Ln 3 s r m ¢ 0 5 a 33 p o 0
l°03 $S 8a U 5
= o cy0 � � oN �3 ° SLL s o° a m � 9 ale o3 ��� g � 08 a' ' e� ❑ o
CL m 8imu E eg �N gESa
'�m 8 8 gx A v 3�v E m ° YDS,s LL _ 4 m o Q a e"°s S E F.
S � R V Y $ U 4 N E E EO b U U?� m J x U S LL >�w J K $ o°w_ Q41
N G N 5 LL N
va> 58a8�®1w au�6Na3 �m �Lg ¢° $ +ups g,�N Fp , a�
W
�
a E � 3� r $� °�S �Sgmmgm°� u�a cc a �c°v� ��ppo3 a�38u ���
R9N�R� E ° gao=� °� °i
°�� a3£ »�+ �
E a oma oa 8 N
Lil 8 a$ � aRJR ° $a � ° °3an% � ooEy �udULL � �. m�`; m w$ $� yJca� 9QN $}
= a flolo!ouz�U853uN� ..+NN 3�'e�u'3mN. 3N>c9 o.. �N ua� Na>w mN �uu°� iaLLN3a3w� a " N� � �
'o
i N Nay 1 a Z z a N a z W I x 2 2 2 z Z o.6 a S I I I I i z I U 2 I Z U I a Z N N n I a z S z S M.: mu N N x U Z
1. s1.1.z1.11
E$88888 � 88$$8888888^0 o aoa0000000^00000600000aoa000000000000a0000a000000ooo^0000
= S
a
C o°
O
L
U
$- ° m
Q amsnccMcc �c� s � g����ccnss
m�LCacC------ - �ee`_,e aaaaa aaaaaaaaaaaaa as a a aaaaaaa as a as a as aa`�aarvaaaaaaa
O
Z
C:
a)
E
c
E a
Q °y
N yyN y myY Y Y Y Y Y Y y my Y myy Y Y Y Y Y Y Y Y Y Y�Y Y�Y�x Nx X x Nx Y Y�Y Y Y Y Y Y Y Y Y Y.Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y mY Y Y Y Y Y Y Y Y
Y
d o d 0 6 d o 6 0
U U U U U U U U U U Vd U Uh U"U U U0 V6 Ud Ud U U6 Ud Ud Ud U6 Ud U Ud Vd Ud Ud Vd Uo d 6 d d 6 d d d o d d 6 d d U d 6 d o d 6 d d tl.U U U U U U U d il d o UU UU d o
6 0UUUUUUUVUVVUUUUUVUUODUUUUUVU UUUU UUUuVU
0
Z
W
Z
0
U
o, g33 n' ¢_ LL �'c3gwIU0� a t25w5 u w a
u3�sm
8
�� m'°oa¢>�' EW��
W
=m � y"§ E°zE�Eg E d o g w� $XreLLys sSa "a �ram ge��M°oP
a
E 3
W
= d n a LL $ m LL m g J 2 w uw W b N n u 2 f g o u u S$ a LL u o m a a O a m u a w
� qq
�RrJJ�goRm^�Cm ��
E O O O O O O O o O P p O O P 0 O O O O o 0 0 0 g Q o 0 o O O o 0 0 0 0 0 o O O o O P 0 o O mP o E o c�o B P S o 0 0 P 92 o O o a
4 =
o-------------------------------------------------------------------------------------
B
MIA ,3"5'�'A"� ��SA�3 epi AA SI AA
O °
E
L
U
(0
8„
oSgSS'��mSSSSP S �qS" S ..mS ' SS'�S'�'oSS Sim SSSS SSS' m So ao�m S ' rn � S mo
� �aaaAaa�aaaaa`aaa�aa�Aa�aaa5aaa�S�S����"aSSS��SSS�� �S�S�r"asr"a��S�a"�"�Q'aS�" �aA�AA�S�� �����
O °
Z
c
m
c
a�
� o
� my�my�� mm�yykYY�3�.y,�yyT�y�.��k[kY�my�������kyy��Y�������y���y��3�.Y��sY3�y�r���Yy��� ���Y�y�3�Ykky�4Y�k���
.L 2 2 2=
V
d o d d d d 6 d d o d d d d o d d d d d d d o d d d d o d d 6 d d 6 d o 6 d d d 6 o d o d d o d d o d d d d o 6 d o d d o d d o d d o d 6 6 d
000u!i ci v°ci.....u.UU.u..V.u..uUUUUu.000.uuuoQu..u...uuu.u....u0.u.uu Vuu uoUUUUVUVU U UVUUUU
000 0 � o
�u 00uooua og au�aouu o�ouo ugou agoo3ou°0004000'ug�uao8°uu oogo g8o �000qu83guu000 ug� 000 0�0000..8�
z � aaaaaaaaaaanaaaFaaaaaayaaaaaaa
o
Z
W
Z
0
U
90 g
a P E
o a
2 y � eta g
tf1
m m 5
JLU
_ a 14�SN eB ° oA,
>��Y3m� g�
i-
mad 9i n
Pa
W
Juu ° x�$� € 8 €�� m a0 _ o u - �3 'I 9
3 m LL g� a #' `d °G m G L g L G U� 'm 3 5 m
tn
u == {y ¢
m 4�im a �;yLy 'dw eum N C7 SGV Ew W= '� gyi 4��y L'�NuWilag n�iN �'oZ� `� o �p € n V 2 0 8��O ga m Z
u u ?v g a ab < -g
W EE
=a d89�gwaa�w�u�wm�°aYax� uaa m�u�a°ani<5�����4��aLL��o��,�u mimauow aaa a�`&LLup3p3¢a��ma3m��w
i S n U as U U Z S a m Z 12 m V m x I m i u R R x 2 x Z x x i
z U
limit
imit zm
QtA
INS
OM
Eaf n wit �n
6qg ' 3v
� � � � RN� � e fr 3 � � �� a �$v An$�v� �, •°
A�mal m Tmp mn {`i.�� �xNm n Nig 3. t a�ES cid e 8 Via ' s 5� v 3!" .K' N
D S ^ m
cn � m
n
O
z
m
z
1
�@{ gggq�gy $ yg gp �$tl gy ag{ gy Aga yg{ $ yg ,j, gg gq l� gg aa� gg pg O
0000 nt�n000000000�000a�'O �'Q n�oouooao onon0000c,0000n000ngonoo no�oono�0000nn0000n0000� �
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
2222222ZZ22222522SFF F F x JZC Fx itF SJZCF F F�X7cxF FFFF 'ST.F 7�S x F F x F X r1FiNN U.OFi N.r/Fi(n fAN fFiiN N(F/r+IrN fxhN NV�N NNNtF/iN Nm
F F F F FF yNNN-FU.N[Fe W NNNNN fJ1 NfAN N!l(/1 lAN Nb(Ii Nft N Nl/�fm,N N N(A LIQ NNNN;b Nfn NN U
N N Vi N N
rM
On
E
CD
0-
3 3
CD
Z
0
O
�5��a�a���a�a5�a � a
a aaas 0. .0000so.00.ooo....Qoo..o.. .o ..e1—11H H H H H 11 D
bmmbmmmmmmm�
b .......................................m b m m m m m m m
3
o CD
m mn mm bb� mm s m�e�m bbmb�mmmmbmmmmmmnom mmmmmb mmmmmmmmmmm b ,mmm m mm m�
g
n
8 - - -------I-------- --_---- -
8
a'a5S"a aaa <aaa5a'aa"aaaaa as"aa'a "a "a a5a"a5aa a aS a55 SHS a a Sa< a al
L
U
8 �a QS
9op,m����y��i�R CL�'��"Cs'�le��CC
♦P O S Y Cv? S v v v c
0
Q
Z
C
Q)
C
C
C�
C a
E
CLLC G Z I x i S Z z I Z I Z 2 2 2 I 2 Z 12 Z I S 2 S 2 L 1 2 Z S 2 I S 2 S S 2 x S 2 2 1 2 2 2 Z Z S S S S Z I Z x Z Z Z S 2 Z i z Z l I 1 2 Z Z S x i S I m 2 Z Z Z I Z
/G
V
U U UQU U d o duuVUuuUUOUuUUV uUVuuUUVUUVuUUUVuV UUV UuUUVVUVuVuVUUUUVuVUuVuUVuVVuVUuUUUODUUuU V
U V
yLL
� � � � � �
J UV u U<,uU0:]O V Q:]V u0 s u U u�UU V�J,�kJr.u�U.V.0 °U V V UODUO(:°U:,.0.�pU¢v000'J{UU J.ysp�usUU V U<i ppp Ugp U.UpgU V U.UyG Upppg ii 30 UO V U V
U
Z a x x x x x x x z x x x x x x z x x z z x z 2 x z x z x x x z x z z_z x x z z z z x z x x x x z x x x x x x x x x x z z x x z x z x x-I x x x z x z x x x x x x z z z
O
r
z
w
z
O
U
S Q E
> a
n x o
(n 73:
a s Q � �
o EsB s J d
LU 9s" 3 �un34 �3a a 8 � ma "31 � are � $$ 4LL8 �$r � € °
FE t ` a 9° LZ 3 ` w IS
g, g y �p �yS
V1a °� gF > � gSzwg�9 � we3® $ � gro8m �figoy� gw Nm pLL �
_ �. §zm ri7,-:
p gg
mu1�:�w�uw¢9, � g
m p Z i vI Z Z to x x a Z I Z I i Z I R G a I 6 2 Q a V 2 2 6 2 2 U i d a¢n n n C as d a a a 2 I Z 2 I a m I U U Z Z U I Z I Z I Z Z Z U Z Z 2 N Z a S a Z d Z 12 I I a u
s--a-ae------ -------------------o-ss_"--------- ����� _o-------------
X----------- --------- -.----- ------ --------------------------------------------
o -----W-D--e-.----------.-------.--- ---O-.---O.--
0
E
F S W W W W W W W T W W W P W W Q W
C� o
C
U
C�
m W m W a w W w W W a a W W W w W w w W w w W w m W W W rn W m w W W Wmam m W�WWa m WaW W W � a� �.
� P�a�a ������ ���a���aS$�S�S�S�S��aa�aaa��affia��aa���haaaa�aaaaaa`a�a��aa�aaaa�a�'a SSa��
O
Z
C:
a)
E
C:
m
F a
LSL y ��Ypp yy v�Y Y r� u� rr!!�� y cc�� X NN Y y y Y ttJyyJ}}
` <ixxxiiiixxxii xiliZxl£xxxx xx x xxZiixxxxxxx xiiix xMxx
0
O °
L
U
cz
$�mmammam�ammb�am�� mammam�a�ammamwa�� aw
a.mgg
Os S SSaM H §a a Na aSS a as aaaaa aaa a era ��� a�����aaaa�aa��aaaama as
O °
Z
c
O
E
c
m
lCCl 3 Suud�11ec�h�[[ y i b4iN byyyy YNY,,ao�yN�[Notyy�j 0N'60 J.y.w 6 'aw y55INyyyv�0.l(�a�yNm'6.6 N�i'nYY.N.y6m yyY m .lmmv��m 6[N Y]w mm 0tySty��£
S Z 2 2 I S I I Z I 12 I S Z S S I I S S x 2 2 2 S I 2.YT S S Z Z I
mm Z TIM 2 2 2 Z Z I S x S x i
V
d o d d d d o d d o d o 6 d 6 d d d d d 6 d o 6 d d d d o d o d d 6 d ��44 d Co d d o d d d d d d d o 68 d o d d o d d d d d d o d 6 d d 6 dd dd '
u u u u u U U u U u U U UO U 00.0 U U u U U U U U U u V U U U U U U U U U U J u U Qu U U U U V U 00 U U U u u U UO U U U U u u U U U U V u U U u u U U u U u
0
uj
z
w
z
0
U
aNy
N
a
'u A
gn y U
dNN§ aI a s§ ys`S a g,g $�'gp3 4 $ g m €Ya
J § g 114 mx �� E g� s 8 F a e 3o3ua� s
W s�uy 68 zs IZ u� u
Z u 3 V a N J fr 9 i u
w � i9aafi5_ 5 of 5 5k
f u
8 + 3 w 2 m a m 3 r u N N LL a¢ a LL S a
W � moa x� $`�� g g��o�� E� � ����$3�m � � Nm�- US � 9a
u wwA'w gg y R u-
m E¢ V a I S i p4p k y N i a m
5 LL a 5 N u m a u i u I n LL gx a a w zgz a LL V V 4 g a a a n sg& 3 g a a!o
W Au �a u���u um T gs6sgpig� �7u8�� uuuL� 3C u u 5y ciu
T. d au nXM3bxm�=w m' y N'naaNS3fusi N� 3LLImaN 3emau'1 wiN�a¢@o�uf�"a JigN�a`aiaaN ¢°E ni
I
immix I Z S U V U N d x Z Z I I I a 2 x Z x I Z Z x N 2 2 I 2 n N N U X2
�Sm3o{�m��8n mS2b66^mo°4$S < g o ANR A�B:am:......N.e$` `A
8 -______.-______.-.-______.-____ ___o_.-_"___o___o<________.-.-_- -_ _.._________.-__a_.-
wma
°
E
U
(0
B m .............. w m a w m a a w a a m a w a w...........
m w a w w w w w w w a w w w w w w w w w w a m
m s 5� s� RHooImnpII INPIPIZIP�P§Z§p X61_
Ee"aa�aaaaaaaeaaa•"aa�aaamaaea �m m� � �m VHF -Ira�FE�r_z�
O °
Z
c
O
E
c
a�
E a
Q °
'Tx If
C�
'd o d d d d o d GG 'd d d tl d d d d d d d d d d 6 d d o 6 tl 6 d o 68.. d8 d d d o 6 d d d d d d d 6 d d d d d d 6 d o d d d 6 d 6 d'
0 U U U U U U U o U U o U U U U U U U�U U O o U o 0 0 0 o U o U o o Q0.0 U u U U o U U J U U U U U U U U U O U o U 0000000 U U U U U❑U V U U U U U U U V U O
° 8
J
92
ui
<< ��������� � ��U�� ������ U����❑�°�Us� �������UUU ❑�❑,���������s����UUU��U�a.»��������
= a a a a a a a a a a a a a a a a a a a a a n n s n a a a a a a
°
z
W
Z
°
U
U U
aP �R�
W � g E afi�g 8 $ '� g$ w„d, 8 8$ u 8 a ' g s �' m S ❑ " °' ° °@
�' � t8 � 3 a� c � �� �' Ng � ❑ m.� aV d � w
a3np 2=wbT� aa � a oa5a c�m
�' c���� ❑� u8 �'�4—� ffi0�'� 8�a: �a o o`u_$O � m' �o
J z E $ga �g $�oa❑�a�nSo � �ug.$ ��um 8' nS`�. ea m� �' � �� o�'E $��� � 2� a's �❑ � roJF9K z
Wtilin - ❑ � S no �c3� 8 w m 5 o z m��` gu � z �£xw $ :n'
N t❑ m g w b $V u $ u Y u�u n E $N ; �,m❑ Z
�5 5 ti 5$ m oRY tau � �b qF u yam �$ �❑ 8@
=m z �'��.p�m�xmr=g�$��€ €E3 ��.$y rgc,5upy; � 7, A $ Q'�ao �3s�,.gge����
d a� aLLb � Baa p� aaaw V a �; LL�uaLL�` m3d � �d �LL� �d^So ?� a9aa3
................... �"�'��V V---------- --------" _
.-.-.-o--_---- -.---- --.--o----•---•-- --•------•----------•---o---o- ---- --------- ----
p _
U
(p
QB w w o 0 0 0 o w w m w o w w w w w w w o w w w o w o w o w w o w o w o w o 0 0 o w o
p
Z
c
a�
E
a
c
a�
Q E
Ca
C axxxxx'x�xxxxixxxxxxxxxxxiixifiixxx'xxxx'xxxxx�txxxxxixxx 'xixixxixxxxtxixx3xxxxx
d dU5 U U U U U U UfrUbU U�U6U UdU U U U U Ufid
Vd5 UdU Ud U Vd U U U d d U d U U U U d U d U d 'U dU dU d U d tl U U d d U d U dUU-U d
` UVUuUuU uUUUUUUUU UuVUUuU UUVUUUU U
U U
o
5 55 5 55555555 5 fi
u
ro0 0 u o u �U06
u dg U�o ug�u o U ��o 0�ci S oU o u ug o u 3 3 0�a 8 u u u o u$ u u o 0 o u� �o u u o u 3 u v u"1
Zan]gg[ F $ g £ fFF #ga
LLJ
_$ygS�6+7ap�a n_$aga ayaaa a_ya aR�n_Tag ap aaq_ayy aV ynpa a_4 nyp a_$_a aK nZpa n_naaa ay��nyg ,1�_a ZEpan5a_n_air_a a_a_a a_a:��[c aTp a_$n_aa9t a_a Rn _ ya3� aszy gpa aapS
W
U
Z Q I SSI S L L S S Z S S Z S L i I Z L S Z 2 S i I Z 2 i 2 2 I Z Z Z S 2 Z S S 2 2 2 I 2 2 S I 2 Z L I I Z S I Z S S x S S S S L S S 2 S S Z Z S S Z x 2 I S 2 I 2 2
O
f
Z
W
Z
O
U
16
q c
U o
a
1E
LP `y U 8 U }( 7R5 g 4 U U
CL
g Y t gg ��� 2 $ m 0 g P'9 .q m a O ` YI
W 52� 8��, � au6aS U£ q � gs � m p7F - qa Pgz&ga �Q z2 � so 8 d s
uE
r= gp � 8 s wm 5 �a u° c u oaa r e iR3 i LQa•P`
�n
6
W -' �, +': NEps : R€a s°u � RnSx -mgwg€ ai �$gbs " 38 � � 5 Zu 3?EEE 00' 88€ 7
� 5 '4� ' u�g p �R4 a 3_n� 8 �p � u � �
= 6 -b' N,� wa �= 6 � i�UE�°_wbbNiP?k , "a<a� LLruTUYo � � go°c3go°°u�y �
w x x Ci I a x a I I a 2 2 x x 2 2 6 x a x x Z n U n u Z x x 2 2 x as x Z U I x U I Z�I U Z x I I I a 2 I I I m I x Z i vi U m u U I Z I 2 a a a as x 2 2 2 Z x a Z U I 6 2 Y
8o
s o $�sso <Qsoas�na;r ����R
4 =- - --_- - ----- - ---- --- - -- - -- - -------
a gju ills s JAN§lm § gg�jgu p§
`aa� � a a a� p a
L
U
(B
Q a w m o w
p ��a� aaamama�'aaa w"a aaw�aaaamaaaas�w�maaaw�ammwaaamaaama�a�Sa�aaoaaa mm�w SS S�w�Sos 1
Z
c
N
c
Q a
9 13
d
U U U UUUU UVUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUVUoUUUUUUUUUUUUUUUUUUUUUUUUUVUUoUUUUUU U U U U U
�� uuouu°voauouuc�o uu u u000gv�ouuso �uu ooS�uuouc�o�uoU�U$ugu ouuuciUoou ovaoUUu go
z gFlaana4nanaaaQQaaaaaaa!
°
Z
w
Z
°
U
x € s a m q tt
�
ME€
E u yyyyy. A
ICL t�scc� oy � � `§
Joh --- ;o u a" g
W � u 'vm 3 $ a u.t fix
W
1-Em
��//�� pyp� 3y aYOQ u $u z Eggff 8 Wg u�
Y• � � 9 E U�� � �2 .2p � � p#p�� U mU �8 5 �W K U F $m m U 2
m bP Obi yj w O � �W W W y 3 O
WB ,(gy�ona� a �.$
1 N 7 I w W Z vi s� VI xu-10 W O U N Y �j w N Iz u��n N O O 2 N N ¢a a m W a U N V J N 9 CL 5 LL a N U a Y
NSI S U U U U a U T 2 i S a a 4 2 2 2 i T 2 2 I Z Z 12 S 2 2 i a 2 Z 6 2 Z I Z T 2 a 2 i T 2 2 T 2 2 2 2 I a Z 6 2 T N U S 2 a N LL m S N S S a 2 U U S U T 2 U T S V
-o a--.-o.--- -----o- o-- -----------------------------------
-
.-.-- - --o-- -- o---m
QAmo S mombq a mmo moo mmmmm mmmm m °' .m Sm o'mm`ow �a mo'S Sbmb SP Sw
O oSSS 5"ama � saaaaaa aaa a� se se�sseesessese�sasseaae�a� ��ee"m am"a
Z
c
a�
c
a�
Q a
<Z= =Z=t== Z x ====rr _= = �tZ xxxxx_xxxx mxmxm rm m = mrrrrzrrrr€rr=rrMZX
C�
U U Vd o d d d U d d UU d d d d 6 U UU U d o 6 d d d UJJU d Uo d d 6 d o d U Ud d Uo 6 d Uo d d d d d d d d Uo d d o d 6 d pU d 6 6 d d d Uo 6
UVUUUUUUUUUUUUUJ UUUUUUUUUUUUUUU VUUUUUUUUUUUUUUUVUUU UUUUUUUUUV
U
z Q _ Tim e milmill m
0
z
w
Z
0
U
16
S
� 9
" 8
s E
t
C
333E a
U � a
m B = b a ffi �E$
'b u a € ,g'o3 g =3 g yu �s E § §� s 'u Y €m YSN rc 2 E fF
J 8 = fr pp a N sy Yre �xPa � ^bPeI
W p9a3® R a_ � g 'am Ede r � uyy5 rp$U°$ < i uG �LLR 39us �wEE � m �
$ g ffi
a € ys 3 si8a ; 1ffi7 � xfE" rims 9
3Qalm
W _o ksauo � $� wffi ` Uy �a$=9o °siZE �2e $� � t� � a �'LLx � frg48 � �
v• _ frat' �-2 oNBad p�LL �m a' a q®w a $m' U 5a It XS'au m `d+� A� gin tt55 �3 a E€rc
3�a"a� u aaum o��,p�9mamw"uu��BEaa¢ x u „ � wao Vin°
m a 2 I a I 2 as I Z 2 2�Z Z S Z Z Z Z x a 2 a n as 2 Z 2 2 S N Z 2 Z wYY 2 U"2 Z I 2 U I I I�Z Z Z Z U U S U a i N i I a i ui I Z x S a a a Z a Vi 2"Z Z m a N 2 ui u i 2
-----------"--------------s„aw�g
c
1 HENSEL PHELPS tuts tz
Plan. Build. ManageGMP Amendment No 1 Attachment 3
.
CONVENTION CENTER RFI LOG
Number Sublect Author Company Answer Company Date Created Date Responded Closed?
1596H-Level 4 Sector J Mssi g Sovent Sleeve el DO Hem"Pteps Corctrucbon Co. HKS,nc 9/252019 W302019 1
157 H•SM,tor Llaael 3-7PresidrtW Sias Shumar Panl�Mf[epon Hrsai Pfteps Conshcton Co. HKS.Ito. 9252019 1017520t9 1
1698 H.P,C-Cssrg Deletion Abova Wak4n Cadre.FrsesWs and Hoods Harem Phelps C ndrucbw Co. HKS,Io. 9252019 10r1o2019 1
1601 H.EAWior Tower Pall Calor Clankallon Fa GreatiO e"Phelps Art HarConstrulo.
im C ... W.8,Inc 262
9019 1
1602 H,C-Expamon J.W Roofrg Delaat Hotel and Core .—Center Hensel Phelps Cor4lnutial Co. HKS,tee. 9262019 9/902019 1
1603 H-5 Nmoe Entry WAR Clarll BUon H—si Phis"C—truclron Co. HK$,Inc. 97262019 10142019 1
1604 H-Las 86.Carly Shop becumy Gn1e Hemel Pheips Coneft-bon Co. HKS,nc 9262D19 1
1605 H-Rood's Pun.Metal Deckng Fs,3pr—Wij Confinnaton Hens"Phelo C.rwtmctlal Co- HKS,Inc, 926=19 10!32019 1
1606 H-Receptacle a1 IDF Room HIK-24 Hera"Phe"
C---Co. HKS Io, srwole 101152919 1
1607 P-Spray Foam Skyfgiss H-1 Phelps Constr ution Co. HKS Inc - 9262019 10/32019 1
1608 H-iC Suppon Roam Bonawed Lae and CM g Clalftw— Hamel Phelps Corstrucs.n CO- HKS,nc. 9272019 1waam9 1
spd
1609 H-Hoally Sulo Fborbox Lccalwn Hens"Phelps CorstrucUon Co. HKS,nor 9272019 10132019 1
1610 H-J3 Wal Conflabng with Hua Duct P.1hway m Eletnwl Room H4K-08 Hos"Phelps Con ixtron Co. HKS,len. 9272019 1002019 1
1611 H-Level 4 Sector J&K HF3 Lghi Feature HWw"N alps Corstrulion Co. HKS,Inc. 9272019 14172019 1
1612 H-Corwerong'lector File For E denor GMPMC Art Hemel Phelps Corstruclron Cn HKS,Ric 9282019 1
1613 H-Marrakesh Knee Wal Sill F—h CtarR+calion Hensel Phelps Cchsd n Co. HKS.Vic. 9262019 9(302019 1
1614 H-Cooler Mathis n Room HiK-09 Receptacle ClarNorman Hemsi Phelps Combudran Co. HKS,Inc. 9282019 102(2019 1
1615 P-Retail Entry from FEC Display Arses Doors Addition Hensel PhWs Co nWnct on Co. HKS,W- 9!302019 9130/2019 1
1616 P-BLUX(B-PL-5)Confirmation Hensel Phelps CorstruAon Co. HKS,ft. 9/302019 16/12019 1
1617 H-Piaster Coknrn Added FleSltirgs to RFI 1429 Hemel Phi Cense—ban Ca HKS,Ina 9rl4we 10142019 1
1618 P-LasW Tag Wal Layat Hensel Phlets Comtnlctldl Co HKS,Inc. 10112019 11142019 1
1620 H-Deletdn of Chef Rail W Desert Queen Ouestraoms Hensel Phelps Construction Co. HKS,li c 10/12019 101152019 1
1621 P-8-L-(&W P-1)Fre Rbng Her"Pups Cmatnct on Co. HKS,Inc. 10112019 1011&r2019 Y
1622 P-Crack Cowrss Detail Cnntcaton Hera Phelps C.muucucn Co. HKS,Inc. Iwwol9 0
1623 H-5 News Timor Frame Conrscaon Hers"Phelps Corw—,con Co. HKS,Inc 10122019 1
1624 H-P-Sector N 8 P Lgfa Fortue HoUls Clanhcatwn Hemel Phelps Cors[nulon Co. HKS,Ore, 10(42019 16/112019 1
1625 P-Bartel Ceiling Cl.'rf—ton Hensel Phelps Corwtrucbon Co. HKS Inc. 10132019 0
1626 H-TWV Paper Haler Location Cfanficatoa at AQ Bathroom Hersel Phelps Comtncbon Co HKS.Ina 10132019 0
1627 H-Addito+a1 Dupimc at Afroan queen Bedroom Heal"Phelps Comtruchoh Ca HKS.nc. 1D(32019 1672019 1
1628 P-Coroealed Dish—her Du t Material FatYKabon Hemel Phelps Corsi—ton Ca, HKS,Inc 10142019 101142019 1
1629 P-W"Wparl,Every SIA Diffuser&Duct Suing Conhrm"dn Helsel Phelps Comtncoon Co. HKS,Inc. 10H2O19 IGM 2019 1
1630 P-BulaUn 95-EP-1 Sump Pump Schedule(,ala Claw"— Hemel Phelps C.--I—Ca HKS,W. 10142019 1002010 1
1631 P.
Redrnptwn Store Light Fw.o Ebvalwrw Hereat Phelps Comtrutlon Co. HKS.Ino. I0Af2019 101162019 0
1832 H-Level 2 Sector K Ersrenca EJevawn Cladc— Hers"Phelps Comtnucbon Co. HKS.Inc. 10/72019 10/152019 1
1633 H-Metal Parol Z Fumng Waterproofing Csnf ton Hr"Phelps Canots-ion Co. HKS,nc 10182019 10,821119 1
1634 H.P-Laucidry Compressor Raom Mlodificaoons Hamill Phrps CorMtuoBWn Co. HKS,Inc. 10/82019 I
1636 S-Ewnt Bonn SAO.Raom Clieftesion Hem"PhepsColshuptlon Ca HKS,Inc 1011/1099 101152019 0
aroo
1837 H-KEntrance Screen Door H—W Phelps Co sMcaon Co. 10/92019 0
1638 S-Removal of Grass Below W"arpark Sodas Hensel Phelps Corer—Ca HKS,Inc- 10/92019 0
1639 Hers"Phelps CotstncUon Co. 10192019 1
1840 P-Trash Comp.d— Hers"Phelps Comburtron Co. HKS.th, IW WG19 0
1842 B.HP-South Hot"and Psit a D—sipat L"— Hreel Phelps Corea—don Co. HKS,fr.. 101102019 101142019 1
1643 H-HDMI Pstl—y at HoarMeMy Suter He1o"Phelps Coretructiai Ca HKS,Inc. 101102019 0
1644H-SPA R—paon Area Clore-b- Here"Phelps Combutlon Ca HKS,Inc, 10/10/2019 901152019 1
1645H-Level 1 Sector H BOH Corridor Finches Clanfoason Hensel Phelps Const—bon Ca HKS,Inc. 101112 20
019 10/1519 1
1646 H-Lobby Tragi Lgtt Fmue Support Cit rRcahon Hemel Phelps Ccreon uuclC. HKS,Iia 101112019 101152019 1
1647 H-Coffee&Gelato Bump Out Clwic"on Here"Peeps ConstrucUwl Co. HKS,IIc 16/142019 10772019 1
1048 S-C.RR Sdewelk Camel J "SP-9 Hensel Phelps Comth on Co- HKS.Inc. 10"112919 0
1849 P,FF-C Restroom(Sector N)Celag Cel f short Hemel Phelps Corotrtwum Ca HKS,Inc 10/112019 0
1651 H.P-N"AulWZone BWvnen FECerd Hot" Hems Phelps Construction Co. HKS,Io. 10/122019 0
1653 H-BOH&FOH Fairs CNrifkation Harrel Phelps Comtrueson Co. HKS.Inc. 10742019 101152019 1
1654 P-Seta O Exterior Com,Mot-el Confirmation Hensel Ptwpa Colrhuchon Ca HKS-Inc 1011412D19 101152019 1
1655 P-lWP Baro Grease Were Code Ciard'w— Hr19el Phelps 1;—Aruct1on Ca. HKS,Inc. 1011412019 101152019 1
1656 P-EJ at Sateen Wal Hemel Phelps Coretrucaon Co- HKS,Inc. 101140119 0
1857 P-Fit.Pump Room Ede-L—,Hekpceaon Hama Phelps Corslruccon Cn HKS,Inc 16'142019 0
1658 H-Marriage,H21,i-24&PDX 0whit.m H2J-01 CeMrg Hegta Cartfirm"ion Hemel Phelps Comlm.bon Co. HKS,It- 101142019 16/152019 1
1859 H-Ceilug G dl Athw hr rens For Saismo C.W wn D-0 CwAsmman Hard Phelps C.,tacuton Ca HKS.Iic, 10/152019 101172019 1
1660 H-Level 1&2 Seta J&K Elevator Entry Framing Geta/ Hr"Phelps Corst—ton Co. HKS,I— 101152019 101152019 1
1861 H-Bunk Room Soffl Co--bort Mensal Pups Construction Co. HKS.Inc 101752019 0
1663 C-Slot DIM—L.caoom He-"Phelps Con"ruction Co. HKS,Ina 14+162019 10/162019 1
1864 P-Level 2 PST-5 CMU Clerdication Hensel Phelps Coretnlctim Co. HKS.Inc. 101162019 0
1665 P-Office Wndow Claidicamn Hemel Phelps Corwbuction Cn HKS,Inc 101162019 0
1666 P-Poly—b—o Parapet CordRron Hamm Ph."Consncaal Co. HKS,Iw 101172019 1W172079 1
1067 C-Added Macre far Registration Doors Herod Phelps C.,samcton Co. HKS,Inc. 10117/2019 0
1668 H-Level 9 ecs
Sector J BOH Rplecle&Data Jack CleraKatwn Here"Pups ComUu#ion C. HKS,Ila 101172019 0
1869 H-Spa Condor Scale Lot FUdto.Elevation ClrewWnon Hereat Phelps C-9—tion Co. HK$;,Inc. 10/172019 0
1673 P-FEC Er"PIO-09 Dor Oprugs CoArevi n Hers"Phots CatshucOM CQ we,Ila 10110=9 0
1874 P-Ewell 3ky1pH Detail zHe "Phelps Combustion Co. HKS,Inc. 10MBF2019 0
1878H-Starts to MadPorW'CaPrrD"MCWMlemew ... .-,... "Hra"Ph*$Cm*nx#-Ca MKS:tn 102212019 - 0
IWO P-Escalator PR Parmelar,Drawn Requtamenis Her"Phets Corrhwtion Co, HKS,Ina 111232019 0
1680P-Liu Gres Urdsrgmurd 0—Waste Pipe Material Type Re"o—A Hem"Phel s Coretnstion Co- HKS,Ina 10232019 0
1681 P-Ptywoal a BOH Candor Hero"Phelps Construction Ca HKS,nor 101232019 0
1882 H-Leas11 8e16or J CRooms Mirror d P 7ovd Conflmwprr Hens" Crrhucb-Ca HKS,Ma 104142019 0
HENSEL PHELPS
Plan. Build. Manage. GMP Amendment No 1 Attachment 3
CONVENTION CENTER RFI LOG
Number Sublect A—Company Answer Company Date Created Date Respontletl Uosetli
1685 P-6—Lnes SchaddW Hansel Phelps Cpnetrucban Co. HKS,he 10242019 0
1688 P-Detad at B-Lw Beek arw Glazing Hensel Phelps Co R ton Co. HKS,Inc 1024 2019 0
1687 P-CMU M Locker Ram 3 Hamel Phelps Construdwn Co. HKS Inc 1025/2019 0
1I P-Btu.Gas PvV for CR se Mater*358: HerneI Phetps C—strudwn Co HKS.Inc 10252019 0
1689 P-Sector Z-AMU-1 5uppty eno Return Dud F1oar Penetralan Damper Requre N, H-4 Phelps Coretrucnon Co. HKS,Inc 10r25t2o19 0
1690 P-FEC 8 IW P Flonazzp Tee Herne)Phelps Cor4nructon Ca HKS,Inc 1025/2019 0
GMP Amendment No 1 Attachment 3
ATTACHMENT 3 (continued)
The Guaranteed Maximum Price as set forth in this GMP Amendment No. 1 to Round Rock
Convention Center Construction Contract includes costs associated with Requests for Information
("RFIs") as set forth in the RFI Log attached (highlighted in green) and as listed herein below:
0001 0072 0182 0345 0495 0733 0835 0906 1071 1190 1286 1406 1 1511
0003 0077 0195 0345A 0496 0737 0838 0922 1080 1190R 1287 1407 1523
0004 0078 0196 0353 0497 0738 0840 0923 1087 1190R1 1288 1409 1525
0006 0084 0203 0364 0513 0752 0841 0933 1096 1203 1289 1426 1542
0026 0085 0204 0365 0558 0756 0844 0933A 1107 1204 1301 1430 1546
0030 0086 0230 0379 0565 0764 0844A 0938 1112 1205 1310 1431 1548
0037 0088 0235 0384 0570 0773 0846 0940 1120 1206 1315 1435 1554
0039 0095 0255 0397 0577 0777 0846A 0945 1127 1217 1329 1436 1558
0040 0096 0260 0398 0596 0787 0847 0950 1127R 1232 1338 1437 1563
0041 0097 0261 0408 0597 0795 0855 0953 1128 1238 1339 1438 1563R
0042 0100 0271 0409 0598 0796 0860 0955 1130 1244 1340 1440 1565
0043 0105 0276 0426 0604 0797 0861 0956 1131 1248 1341 1443 1583
0044 0106 0279 0430 0610 0800 0862 0957 1132 1249 1348 1472 1592
0045 0111 0284 0431 0611 0801 0871 0985 1144 1250 1355 1491 1593
0046 0112 0287 0432 0616 0803 0876 1007 1158 1251 1368 1492 1598
0050 0113 0296 0433 0617 0806 0879 1008 1 1159 1257 1370 1497 1602
0061 0114 0314 0434 0617A 0808 0879A 1015 1166 1260 1382 1499 1663
0062A 0130 0320 0439 0618 0810 0889 1020 1167 1261 1385 1504 1667
0064 0145 0321 0446 0626 0811 0891 1037 1170 1273 1390 1504R
0065 0152 0326 0447 0651 0812 0895 1043 1172 1277 1391 1506
0067 0159 0327 0449 0661 0815 0898 1067 1174 1 7 1 1393 1509
0068 0165 0328 0460 0697 0821 0902 1068 1175 1281 1397 1510
0069 1 0171 0338 0461 0699 0833 0902R1 1069 1187 1282 1405 1510A
QHENSEL PHELPS GMP Amendment No. 1 - Attachment 4
Plan B6:la. Manage.
2019 2020
line unique Task ID Name Dura tan Start Finish D E March oaoeor wren E
9 23 6 2D 3 17 2 16 30 13 7 11 25 6 22 16 120 13 17 31 14 26 IIZ 126 19 23 7 21
1 0910 Executive Milestone Summary 685d5/15/2018 A 1/26/2021 ----
2 1050 Convention Center 563d 7/17/2018 A 10/1/2020 C"w"cvw
3 1430 Exterior Skin&Roof 2044 3/14/2019 A 1/2/2020 E>seaswo&Roof j
4 30360 West Elevation-North End 185d 3/25/2019A 12/13/2019 Wedgy liEm I I I
5 68930 Install CFCP Panels-West Elevation-Nath End-Pate Corhere 10d 12/2/2019 12/13/2019 DOW CFO PVA-Wet&MW-ram EW-Pme CDC"
6 30400 East Elevation 1 5/31/2019 A 1/2/2020
7 30960 Install CFCP Panels @ Restroom Bump-ads-East Elevation 1 11/13/2019 A 12/5/2019 i sal oa Ped o Restroom&M,is•eau Ekwim
8 30950 Install Canopy-East Elevation-North 7d 12/2/2019 12/10/2019 1ta1�•Ent 8—-Norm
9 30970 Instal Trews Canopy-East Elevation South 1 12/11/2019 1/2/2020 111511111 Trek crag Tre -East Ekrwm Boum
10 30440 Roof5ls0ani&EqulpmW 13 6/3/2019A 12/18/2019 System&EWPnw
11 68970 Rough-in Roof Piping&Test-Roofing Seq.3 C9 >C18 1 10/14/2019 A 12/4/2019 Ro*-Rao1 Paw&Test-Rodrsg Seq.3 c9->ci&
12 68990 Rough-in Roof Piping&Test-Roofing Seq.5 Cl >C9 1 11/4/2019 A 12/9/2019 b#w Rod Pan&Test•Roarng sea.s a->cn I
13 59720 Instal Lightning Protection 10d 11/11/2019 A 12/3/2019 >� P demur
14 68980 Insulate&Heat Trace Roof Piping-Roofing Seq.4 C9 >C18 7d 12/5/2019 12/13/2019 lnsuhee&keu Trace Roof agog-Roorng se4 t c9->a&
15 69000 Insulate&Heat Trace Roof Piping-Rcoging Seq.5 Cl >C9 7d 12/10/2019 12/18/2019 ®U&Le&He*Trace Roof aping-RoWq 54 5 Cl•>c9
16 59710 Dry-in-Convention Center 12/13/2019 12/13/2019 �D"-cwmtwCelt" I I I
17 1440 Interior Build-out&Rough-in 220d 4/15/2019 A 2/25/2020 &
18 2560 Build-out-Levell 22 4/15/2019A 2/25/2020 -- - ------�Z09waou-LCdt 1
19 59370 Build-out-Level 1-Pr;w#Was/Roads-Noahlluio-at•teM 1-a my Wyk f Rams•ram IAm 1111"JIM711111.
I
20 46710 Buildout Electrical Rooms-Level 1-North 6 7/31/2019 A 12/4/2019 6Wsaa eeco-a Roans•teM 1.1am I I I
21 46730 Buildout MDF&IDF Rooms-Level 1-Nath 41 8/5/2019 A 12/4/2019 Brut MF&IDF Roan•tCM I-Nam
22 58520 Terminate Electrical Branch Circuits-Level 1-North 1 12/2/2019 12/20/2019 Ten.Ra EleMo1&mm Gm&•Led 1•No* I I
23 58550 Energize Main Equipment-Level 1-North 5d 12/16/2019 12/20/2019 &ew run 4whiat•terd 3-Ram I I I
24 58560 Energize Branch Parnels/Circuits-Level 1-North 5d 12/23/2019 12/30/2019 DOW&Vel Pwee f omwa•LeM i-ram I I
25 58440 Terminate Data Wiring @ MDF/IDF Rooms-Level 1 Nath 1 2/5/2020 2125/2020 ®Twmxe our Win 0 aff I eE Roans•serd 1 ram&
26 56380 Build-out-Level 1-
Ptioritp Walk/Rams-South 8/23/2019 A 1/14/20?A araat•nerd 3•army wdk i Roass-seam 1 1
27 45520 Set Electrical Equipment&Panels•Level 1-South 5d 11/25/2019A 12/3/2019 SdBernsdamnax&Pwek-nerdI-Seth l I 1
28 46780 Buildout IDF Rooms-Level 1-South 1 12/2/2019 12/20/2019 l rsau mE Roans-terd 1-SRM I I I
29 46770 Pull&Terminate Main Feeders -Level 1-South 10 12/2/2019 12/13/2019 Pd&f Ton Poedem•teal 1-south] I I
iLn58530 Terminate Electrical Branch Circuits-Level 1-South 1 12/2/2019 12/20/2019 Termiete Bsunl6rwan reois-nerd 3-sasm I I
Kalahari Covention Center- November 2019 GMP Update
DATA DATE 12/1/2019 JOB# 7017134 VIEW Kalahari
REV.DATE 12/12/2019 2.0710 PM PAGE 1 of 17 FILTER:In Progress/Not Started Tasks
No Text
QHENSEL PHELPS GMP Amendment No. 1 - Attachment 4
Plan. Bu:tO. Manage.
-2020 _
Line Unique Task ID Name Duration Start Finish oecemwr r _i ole N� oeamoer
9 23 6 20 3 17 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 12 26 9 23 7 21
- lord 1•Restroom tate I I I
62 41390 Fit up Carriers&Plumbing Racks Level l Restroom Center 5d 11/21/2019 A 12/2/2019 �ws& Raks-Lem 1-Rewwm conn I I
63 41420 Frame Remaining Walls-Level 1-Restroom Center 4d 11/26/2019 A 12/11/2019 'fame Rlmumnq Wak-Level I-Rewoom CVW I I
-- 1._ 1 1
_......
64 41450 Rough-in Wal Electrical Drops-Level 1-Restroom Center 3d 11/26/2019 A 12/2/2019 Rw�rn w1I edtr of Level 1 Restroom eons '
65 41340 Rough-in OH Electrical-Level 1•Restroom Center 3d 12/2/2019 12/4/2019 Rage oR Fkctrd-Level I-Reur m cent= I
66 41410 Insulate Carriers&Plumbing Racks-Level 1-Restroom Centel 3d 12/2/2019 12/4/2019 Mudge Cass&Aw&V Rads-Led I-Restroom cern
67 41400 Test Carvers&Plumbing Racks-Level 1-Restroom Center 3d 12/3/2019 12/5/2019 rest candy&Rumtry Racks•teal I•Restroom cents
68 41350 Rough-in OH Sprinkler-Level I-Restroom Center 3d 12/4/2019 12/6/2019 1 Roman atl Sial We-teed I-Raroom coma j
69 41430 Wall Cloe-in-Level 1-Restroom Center 5d 12/5/2019 12/11/2019 ■Wa&a"-Lem I-Raman card I I I
70 41360 Rough-in OH Controls-Level l-Restroom Center 2d 12/6/2019 12/9/2019 1 Rom ole Cwhis-Led I-Rest=conn I I I
71 41370 Rough-n OH Fire Alarm-Level 1-Restroan Center I 2dl 12/6/2019 12/9/2019 1 Rou$h m ole Fn Nam-Lend I-Remo carer
72 41440 Install c—a" e�Pl_-Ret cm I 4d 12/12/2019 12/17/2019 1wwsealbn/aro-Levd1-Restroomcen<c
I I
1-Restroom. Lem I-Restroom south I I I
74 41540 yet Tamers a Plumbing Rados-Level 1-Restroom South 21d 10/31/2019A 12/2/2019 std Cam&PlnbN Racks-Lend l-Restroom Boum
75 41500 Rough-in OH Electrical-Level 1-Restroom South 3d 12/2/2019 12/4/2019 Rou"a+rlectrral-teed I-Restroom Boum '
76 41550 Fit-up Lamers&Plumbing Racks-Level 1-Restroorn South 5d 12/2/2019 12/6/2019 Fr-op cards&ILmtanq Rads-Lad 1-Restroom sour
77 41510 Rough-in OH Sprinkler-Level l-Restroom South 3d 12/4/2019 12/6/2019 0 Rotm pl SMWu-Lad I-Remoom South I I I
78 41520 Rough-in OH Controls-Level 1-Restroom South 2d 12/6/2019 12/9/2019 Rout"aM crow&-L&d I-It woore south
_._.._.__.. ........ ___.........� _.f.. _I-_..
79 41530 Rough-in OH Fire Alarm-Level 1-Restroom South 2d 12/6/2019 12/9/2019 oM Fire Nam-Leal I-Restroom xunl I I
80 41560 Test Carriers&Plumbing Racks-Level 1-Restroom South 3d 12/9/2019 12/11/2019 1 rest cam-&--Tony Racks-Lad I•R-soon I I
81 41580 Frame Remaining Walls-Level 1-Restroom South 4d 12/12/2019 12/17/2019 ®r* Rewmy Vials•Leal I•Raman soon I I
82 41610 Rough-in Wal Electrical Drops-Level 1-Restroom South 3d 12/16/2019 12/18/2019 Rout war 91erRd Drop.•Lad I-Restroom South
83 41570 Insulate Carriers&Plumbing Racks-Level 1-Restroom South 3d 12/16/2019 12/18/2019 0 In:uale mimes&%a*Rads-Leal I-Restrom south
84 41590 Wag Close-in-Level 1-Restroom South 5d 12/19/2019 12/26/2019 ®vw aos"•Lad I•Resor m South j 1 r
85 41600 Instal Sheathing/Gyp-Level 1-Restroom South 4d 12/27/2019 1/2/2020 Instal sham ro r Gyp-Lend 1-Restmom South
86 58360 Build-out-Leven-Testing&Insulation _ 23d 12/12/2019 1/15120 &rbw•ted I-Tang&Fns mm
87 39840 Test Mechanical Duct-Level 1 10d 12/12/2019 12/26/2019 ®la Necnaad bud-Led 1 I I
88 39850 Test Mechanical Piping-Leven 10d 12/12/2019 12/26/2019 ®ra Metwew FOV-Lad L
89 39880 Insulate Mechanical&Plumbing Systems-Level 1 20d 12/17/2019 1/1512020 Isuhte me&aiid&nmam&51mdm-Lena I I I
90 39860 Test Sprinkler Piping Level 1 1 12/23/2019 1/7/2020 ra spuaa •Ievd I
Kalahari Covention Center- November 2019 GMP Update
DATA DATE.12/1/2019 JOB M:7017134 VIEW.Kalahari
REV.DATE.12/122019 2:07 10 PM PAGE 3 of 17 FILTER:In Progress/Not Started Tasks
HENSEL PHELPS GMP Amendment No. 1 - Attachment 4
Plan. Build. Manage
2019 20'10
Line Unique Task ID Name Duration Start Finish DeamDer Awaary Felinjaiy &knell Me , O*W Moveria&er DeanW
9 23 6 20 3 17 2 :16 30 13 27 11 ;25 :6 ;22 6 M 3 :17 .31 14 26 112 126 ig 23 :.7 21
91 39870 Test Plumbing Piping-Level l 8d 12/27/2019 1/8/2020 10
Teo nr&9PM-L-A 1 I I I
92 2570 Build-out-Level 2 117d 7/2912019A 1/14/2020 Mq Bu"-LrM2 1 I I
!_44W1,JL_ Build-out-Level 2-Priority Walls/Rooms Bu"-Level 2-ft*W*;Rooms
94 47020 BUII6-OU[Plumoing Room-LeVel 2 44c 9/20/2019A U418/2019 M Buraae ftneiN Room-Level2
95 46980 Pull&Terminate Main Feeders-Level 2 4 9/23/2019 A 12/2/2019 M&TvmY*ran reek -Level 2
% 46970 Build-out IDF Roans-Level 2 15( 12/2/2019 12/20/2019 Llualdaut>oF Rooms Led 2 I I 1
.............
97 58960 Terminate Bectrical Branch Circuits 15d 12/2/2019 12/20/2019 hnaute9xiricswooKuts
98 58910 Energize Main Equipment-Level2 5d 12/3/2019 12/9/2019 arnegaeL7an4.pnent-Level2 1 I 1
99 58430 Terminate Data Wiring Ca)lDF Rooms-Level 2 15d 12/23/2019 1/14/2020 Temnat,wup Wkoq@ Il1F Rom-Led 2 1
100 58920 Energize Branch Circuits-Level 2 5d 12/23/2019 12/30/2019 ®Bierwe firm muds-Levd 2 I I I
10140130 Build-out-Level 2-BOH 102d 7/29/2019 A 12/20/2019 keuou Level 2-�+
102 46240 Pull Electrical Branch Circuits-Level 2-BOH 15d 9/16/2019 A 12/4/2019 Ral BedrrA Branch CrC AS-Level 2-eon
103 46140 Rough-in OH Sprinkler-Level 2-BOH 10d 11/25/2019 A 12/10/2019 Rw$jOKSi nat,-Level 2.11011 I I I
10446260 Pull Main Data/AV Wire-Level 2 BOH 1 1212/2019 12/20/2019 WiM.WWAvvrae-Lerd2-Bon I I I
10546250 Pull Main Fire Alarm Wire-Level 2-BOH 10d 12/2/2019 12/13/2019 Nr Man Fre Alarm vne-Level 2-90H
106 46270 Pull Main Control Wire-Level 2-BOH 5d 12/2/2019 12/6/2019 RI Man Cued Wee-Level 2.908 I I
Bulld-out-Level 2-Meeld"Room&Corridors 89 8/1212019 A 12(17/2019 X19 Wdd«a-Level 2-IIeetng Rid CwxtiR
108 46400 Pull Electrical Branch Circuits-Level 2-MTG Rooms&Corridors 15d 10/1/2019 A 12/4/2019 1 Pull Oed of Branch Cnats-Level 2-MIG Rooms&Corrdon
109 46330 Rough-in OH Sprinkler-Level 2-MTG Roams&Corridors 10d 11/11/2019 A 12/2/2019 Raagn-m on*ri*-Level 2.MTG Rooms&Cwdm i
110 46430 Pull Main Data/AV Wire-Level 2-MTG Rooms&Corridors 18d 11/20/2019 A 12/17/2019 SO Nl mam dawpv wn-Level 2-MTG Rooms&commis I I
111 46440 Pull Main Fire Alarm Wire-Level 2-MTG Rooms&Corridors 10d 11/22/2019 A 12/9/2019 L.Ra Kari we Alarm swe-Level 2-rftG Rooms&rnndas I
112 46460 Pull Main Control Wire-Level 2-MTG Rooms&Comdors 5d 12/2/2019 12/6/2019 PLA Mam CWM Noe-Level 2-KTG Room&CieWi s
133 40150 Bind-oUt-L,xMlld 2-xallah i Bid 8/26/2019 A Buidae-Level 2-Kahhan earoan
114 46570 Pull Electrical Branch Circuits-Level 2-Ballroom 15d 10/24/2019 A 12/11/2019 N aatr d Branch Gcuils-Level -Ba&oom l I I
115 46590 Pull Main Data/AV Wire-Level 2-Ballroom 15d 11/20/2019 A 12/12/2019 iw Mao dawAV Wee-Level 2-Bahn
116 46490 Rough-in OH Electrical-Level 2-Ballroom 15d 12/2/2019 12/20/2019 Ro+-n on Bedixal-Lew 2-earoom
._.._ .....
117 46600 Pull Main Fire Alarm Wire-Level 2-Ballroom 10d 12/2/2019 12/13/2019 I'd Men Fit Alive Wh Level2 6*w I I I
__..
118 46620 Pull Main Control Wire-Level 2-Ballroom 5d 12/2/2019 12/6/2019 ry nay comd was-LEM 2.61111.n. I I I
119 46510 Rough-in OH Sprinkler-Level 2-Ballroom lOd 12/12/2019 12/26/2019 ®Rough n OH sprNly-Level2-Baraem. I I
— ---
12040160 Budd-out-Level 2-Restrooms 8/28/2019A 12/20/2019 edo-o. Level 2-Reltiticift
Kalahari Covention Center- November 2019 GMP Update
DATA DATE:12/1/2019 JOB#:7017134 VIEW.Kalahari
REV.DATE12/12/2019 2:0710 PM PAGE 4 of 17 FILTER:In Progress/Not Started Tasks
QHENSEL PHELPS GMP Amendment No. 1 - Attachment 4
Fl,n Bc I0 Manage.
2019 2020
Line Unique Task I Name Duration Start Rnistl oer.1 FeWary Mac .Ane Odit W"Inber Demft
9 23 6 20 3 17 2 16 130 113 27 11 25 8 22 6 120 13 17 31 14 28 12 25 9 23 7 21
42530 L.eW 2-Women's owtt LILLevd 2•Women's Remove
12242590 Rough-in OH Sprinkler-Level 2-Women's Restroom 3d 12/2/2019 12/4/2019 RDu�+iOMspneb-Lem!2-womm5Restmad I
123 42600 Rough-in OH Controls Level 2-Women's Restroom 2d 12/4/2019 12/5/2019 Rwoq i caRSDk-Led 2-Warms Restroom
124 42610 Rough-in OH Fire Alan-Level 2-Women's Restroom 2d 12/4/2019 12/5/2019 Rooghn a1 Fie Alarm-teM12-Wow's Restroan
42540 Level 2-Men's Restroom level 2 Men's ReAmom I I I
126 42740 Rough-in OH Mechanical-Level 2-Men's Restroom 3d 11/4/2019 A 11/3/2019 oM Meda-LeM 2-Men's Rin
127 42830 Frame Remaining Walls-Level 2-Men's Restroom 4d 12/2/2019 12/5/2019 ftft Remamg Wdh-levd 2-rims Reshom,
128 42750 Rough-In OH Electrical-Level 2-Men's Restroom 3d 12/3/2019 12/5/2019 Ram ox Ild"-tevd 2-Men's Remoom
129 42840 Rough-n Wal Drops-Level 2-Men's Restroom 3d 12/4/2019 12/6/2019 �Rw*m veal aoRs-levd 2-Mars Reshom I I I
130 42760 Rough-in OH Sprinkler-Level 2-Men's Restroom 3d 12/5/2019 12/9/2019 Rauq+off 6pml*-Lem!2-Men's Reshom
131 42850 Insulate Canners&Plumbing Racks-Level 2-Men's Restroom 3d 12/5/2019 12/9/2019 tiro Gmers&Wribrig Rads.LM 2-Mms Rstr m
132 42770 Rough-In OH Controls-level 2-Men's Restroom 2d 12/9/2019 12/10/2019 Rough-el off Caua6-level 2-Mens Rewoan�
133 42780 Rough-in OH Fire Alarm-Level 2-Men's Restroom 2d 12/9/2019 12/10/2019 Rss#j OM Fie Ah--Leve 2-Mm s ReshaD i
134 42860 Wall Close-in-Level 2-Men's Restroom 5d 12/10/2019 12/16/2019 ,wal cks&m-Led 2-Men's Ress m
135 42870 Install Sheathing/Gyp-Level 2-Men's Restroom 4d 12/17/2019 12/20/2019 ,tmgE sheahaw/Gyro.Levd 2-Men's aesUoom
62600 wwout-Lew 2-Tau"&Insulation 2M 9 rsac-led 2-Te:ow a hum. i
137 50140 Test Mechanical Piping-Level 2 10d 12/2/2019 12/13/2019 Tut ftm1dvaw-Levd2 I I 1
138 50130 Test Mechanical Duct-Level 2 10d 12/2/2019 12/13/2019 Test MLW Duct-Lesd 2
139 50160 Insulate Mechanic&Plumbing Systems-Level 2 20d 12/5/2019 1/3/2020 6sdxe Mfttavol&Nwmhng Wm-tevd 2 I �
140 50150 Test Plumbing Piping-Level 2 8d 12/16/2019 12/26/2019 ®Test aanbrw ROPw-Lesd 2 I I I
141 50170 Test Sprinkler Piping-Level 2 10d 12/27/2019 1/10/2020 Test so was PPV-«vel 2
w6m Build-out-Roof-Mechanical Systems 89d 8/26/2019A 1/2/2020 &Adw-Rad-MtdanaWAma �.
143 63470 Rough-in Mechanical Duct to Equipment Roof 24d 8/26/2019 A 12/2/2019 M to Eqi"m Roo I I I
144 63480 Rough-in Mechanical Piping to Equipment-Roof 46d 8/30/2019 A 12/5/2019 1 Rwo-irn Medw`ral Raw to Ewpnent-Rod I I I
145 63490 Rough-in Natural Gas Piping to Equipment-Roof 20d 11/25/2019 A 12/24/2019 =Rw Lotrel Gas PpV to eRvanem-and
146 63520 Test&Insulate Mechanical Systems-Roof 15d 12/6/2019 12/27/2019 ®Test a tmdale Med ayal systens-Rod
147 63500 Rough-in&Terminate Power to Equipment-Roof 10d 11/11/2019 12/24/2019 ®RougRn is TW.Ae Po M tD Ewomem-Rod
148 63510 Rough-in&Terminate Controls to Equipment-Roof 10d 12/18/2019 1/2/2020 Rw"&Teamewe Cmb-&to Ewasae-Rod I I
E141450 Finishes 209d 8/1912019A 6/12/2020 32810 Finishes-L&W 1 19 8/19/2019 A $/18/2020 --T- ' "- - Rwsim-tevd 1'
Kalahari Covention Center- November 2019 GMP Update
DATA DATE.12/1/2019 JOB#:7017134 VIEW:Kalahari
REV.DATE.12/122019 2 07 10 PM PAGE 5 of 17 FILTER:In Progress/Not Started Tasks
HENSEL PHELPS GMP Amendment No. 1 - Attachment 4
Plan. Build. Manage
-- - -- 2019 - 2020
Line Unique Task ID Name Duration Start tv
oet F March OMkr Nwwbw Dember
9 33 6 20 3 17 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 12 26 9 23 7 21
rushes•Level I•BOH I I
15247050 Instal Ceding Grid LevdI-BOH 5d 12/2/2019 ImaceingGrid-IevelI-BOH I I I
---.... ...... __...._.
153 47070 MEP Drops to Ceiling Grid-Level 1-BOH Sd 12/2/2019 WP Daps to reig raid•level I-eon I I I
_..... _ �.... ...... ... ..._.. ........
154 47100 Drop Ceiling Tile-Level 1-BOH 5d 12/2/2019 oay king Tie-level I-�1155 47170 Install Dods Levelers-Level 1-BOH 5d 12/2/2019 In"Dod Lenin•Level
1-BDH156 47190 Appty EIFS Soffit @ Loading Dock-Level 1-BOH 5d 12/2/2019 Ap*ms slit o/many Dock-Level I•Bon.._...... _ __157 47200 Install Windows-Level
1-BOH 5d 12/2/2019 rrsGl vdndaas•Level I•Bon
158 47080 Above Ceiling Inspection-Level 1-BOH 5d 12/9/2019 12/13/2019 ■Aeov c*q bwecbm•Lend 1•BOH
.......... __ I __
159 47180 Install OH Doors&Specialties-Level 1-BOH 5d 12/9/2019 12/13/2019 ®Insw OH Doan 6 spa aE[s-Level I-li I
160 47520 Paint EIFS Soffit @ Loading Dods-Level 1-BOH 5d 12/9/2019 12/13/2019 ■Pant Brs soft 0 wom Dmk-Levo I-hwH I I
161 47110 Trim-out Electrical Devices-Level 1-BOH 5d 12/16/2019 12/20/2019 ®Tmrade eleftal Devin-Level 1•BOH
162 47120 Trim-out Data/AV-Level 1-BOH 5d 12/23/2019 12/30/2019 rinout D"Av•Lend I-WH I I I
163 47130 Trim-out Fire Alarm-Level 1-BOH 5d 12/31/2019 1/7/2020 Trm A Fu Alum-level I-MH I I I
16447210 Install Doors&Hardware-Level 1-BOH 5d 1/8/1020 1/14/2020 ®WWD.&ffirdaere-Level i-BDH I I
16547160 Install Flooring-Level I-BOH 10d 1/15/2020 1/28/2020 ®trsGlrh -Levell-80H
166 47140 Install Plywood Wainscott&Specialties-Level 1-80H 5d 1/29/2020 2/4/2020 e Install%w dva�c &Si aaees-uwi 1-BM
16747220 Final Coat Paint-Level 1-BOH 5d 2/5/2020 2/11/2020 FrWWPad-Level 1-a011 I I
I I I
16847230 In-house/Contractor Punch List-Level l-BOH 5d 2/12/2020 2/18/2020 ®In-law l rmaadw Rade lst-Lewd I-0011
cK, "` ':"a. I Wo-IeM1-Comdors-NOMI I
170 47280 Frame Soffits/Ceiling-Level 1-Corridors-Nath 5d 12/2/2019 12/6/2019 Raw saris I reig-lewd I-ramM•Ibdh I I I
171 47290 MEP Drops to Ceiling-Level 1-Corridors-North 5d 12/9/2019 12/13/2019 !MEP Drros to Gell•lead 1.Cwr4m-NOM! I I
172 47300 Above Ceiling Inspection-Level 1-Condors-North 5d 12/16/2019 12/20/2019 Ab relln 4spttUon•Level I_r ndm-Nam
173 47310 Instal Gyp Ceiling-Level 1-Corridors-North 5d 12/23/2019 12/30/2019 Install Wv calling-level 1-Umdom•/IOM
174 47320 T/F/P Ceilings&WaBs-Level 1-Corridors-North 5d 12/31/2019 1/7/2020 TIFR C*9&walls-Levo 1•ramdm•W 1 I
175 47410 Install Specialty Ceilings-Level 1-Corridors-North 5d 1/812020 1/14/2020 ®insa saaatr ceiv-Lend l=cmndZ-form I I
176 47420 Install Wall Coverings-Level 1-Corridors-North 15d 1/15/2020 2/4/2020 ®1md wall rmeeg;-tewl I-comdas-lad
177 47430 Install Millwork/Specialties-Level 1-Corridors-North 5d 2/5/2020 2/11/2020 0 Install N1an4I syr-Level 1-CMM•Homs I I
178 47470 Trim-out Mechanical-Level 1-Corridors-North 5d 2/10/2020 2/14/2020 ®Tw M Lee wva -lend I-nus mrs-form I I
179 47440 Trim-out Electrical-Level 1-Corridors-North 5d 2/13/2020 2/19/2020 Tana,tem of•Level 1-sand.-Norm I I
180 48890 Trim-out Fire Protection-Level 1-Corridors-North 5d 2/18/2020 2/24/2020 ®TW M Fre Aoteroon•tend I-rondos-tarn
Kalahari Covention Center- November 2019 GMP Update
DATA DATE.12/1/2019 JOB#:7017134 VIEW:Kalahan
REV.DATE:12/12/2019 2:07.10 PM PAGE 6 of 17 FILTER:In Progrr 'ot Started Tasks
QHENSEL PHELPS GMP Amendment No. 1 - Attachment 4
Ptnr, BLJA. blsnage
— — — —
_.2019 _. __ 2020 -
Line Unique Task I Name Duration Start Finish Dewift AW F9WM uyrn April may h- - Od-
9 23 6 20 3 17 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 12 26 9 23 7 21
181 47450 Tnm-out Fire Alarm-Level 1-Corridors-North 5d 2/21/2020 2/27/2020 .Tanaot Fre.6 •tnd I-Camas-WM I I
182 47460 Trim-out Data/AV-Level I-Corridors-North 5d 2/26/2020 3/3/2020 ®TtmmA 01h/AV-Led I-C.M-Nam I I
183 47490 Install Doors&Hardware-Level 1-Corridors-North 5d 3/4/2020 3/10/2020 ®Imtar doors a wmraxe-lord I-WI&as-Nam
184 47480 Install Floors-Level 1-Condors-North 10d 3/11/2020 3/24/2020 ®lmw Pan-LNd I-caroms-Nam '
185 47500 Final Paint-Level 1-Condors-North 5d 3/25/2020 3/31/2020 FM PW-Led I-ruedms-Nam I 1
186 47510 In-house/Contractor Punch list-Levet 1-Corridors-North 5d 4/1/2020 4/7/2020 WOR n CaArxta wRe USt-u d I-Ca,mn-nam 1
18740100 Finishes-Level 1- --_ _ _---
t4eetingRootns 15 8(28/2019A 4(13(2020 -------r-----=---- %kite-L&dl•MN"
�
188 47540 Frame Soffits-Level 1-Meeting Rooms 15d 11/11/2019 A 12/3/2019 F�Ase 51-Led I-*etM Room
189 47550 MEP Drops to Soffits-Level 1-Meeting Rooms 5d 11/20/2019 A 12/2/2019 ISP omos to soires-ted I-NedAro Rom I I I
190 47570 Instal Gyp Soffits-Levet 1-Meeting Rooms 8d 12/3/2019 12/12/2019 Imo cypSo%-led 1-Meda;Roam 1 I 1
191 47580 T/F/P Soffits&Walls-Level 1-Meeting Rooms 5d 12/13/2019 12/19/2019 0 T/Fn soma a wars-Ind 1-14MM Roam
192 47700 Instal Ceding Grid-Level 1-Meeting Rooms 5d 12/20/2019 12/27/2019 ®wtj sero rya-Led I-Mldnq Roam
193 47710 Instal MEP Drops to Ceding Grid-Level 1-Meeting Rooms 5d 12/30/2019 1/6/2020 Imo NFP sops to cert'W-Ina I-MMA;Raann 1 I
194 47560 Above Ceding Inspection-Level 1-Meeting Rooms 5d 1/1/2020 1/13/2020 Mose 0.18 NNpdoai-tnd I'M"Roam
195 47590 1 Instal ACT Ceilings-Level 1-Meeting Rooms 5d 1/14/2020 1/20/2020 ®bar Aa cdM-Ind I- Roam
196 47600 Instal Wal Coverings-Level 1-Meeting Rooms 10d 1/21/2020 2/3/2020 ®I.W will CM-.0-L;M I-Medrro Roam I t
197 47610 Install Millwork/Specialties-Level 1-Meeting Rooms 5d 2/4/2020 2/10/2020 ®hW Mak/SpKak d-Ind I-ne"Roam I I
198 47650 Trim-out Mechanical-Level 1-Meeting Rooms 5d 2/7/2020 2/13/2020 ®Tan-out Mediawal-ted I-ft"Room
199 47620 Tnm-out Electrical-Level 1-Meeting Rooms 5d 2/12/2020 2/18/2020 ®TanaA Be= lord I-ftUN Roam I I
200 48880 Trim-out Fire Protection-Levet 1-Meeting Rooms 5d 2/17/2020 2/21/2020 ®Tw oA In PmteMon-lord I-"Roam I I
201 47630 Trim-out Fire Alarm-Levet 1-Meeting Rooms Sd 2/20/2020 2/26/2020 ®TdnaA Foe ikm-Leal I-*Wq Roans I I
202 47640 Tnm-out Data/AV-Level I-Meeting Rooms 5d 2/25/2020 3/2/2020 Twod DNwAV-led I-ftVq Roam
203 47720 Install Operable Partitions-Level 1-Meeting Rooms Sid 3/312020 3/9/2020 ®9tstar ondaue Panom-Lem!I-Meepoq Roam i
204 47670 Instal Doors&Hardware-Levet 1-Meeting Rooms 5d 3/10/2020 3/16/2020 ®ww noon 8 Narawm-Led I-Pt"Roam I
205 47660 Instal Floors-Level l-Meeting Rooms 10d 3/17/2020 3/30/2020 ®!L.W rival-Ind I-M"Roam 1
206 47680 Final Paint-Level 1-Meeting Rooms 5d 3/31/2020 4/6/2020 Feld PaaA-Led I-Mede;Rom
20747690 In-house/Contractor Punch List-Level 1-Meeting Rooms 5d 4/7/2020 4/13/2020 i InAmm/CaAaxtaRah tst-LedI-I*"Rum i
208 40110 Finishes-Levet 1-Corridors-South 1 1219/2019 5/1/2020 AD"-Lod I•rnndas-South I
209 47940 Tape&Bed Walls-Level 1-Condors South 5d 12/9/2019 12/13/2019 ®Tape&I w wak-Lem 1-o ndod sorb
210 47950 Frame Soffits/Ceding-Level 1-Corridors South 10d 12/16/2019 12/30/2019 Frame 5drb/Cerro-tad 1-came South
Kalahari Covention Center - November 2019 GMP Update
DATA DATE 12/1/2019 JOB#.7017134 VIEW.Kalahan
REV.DATE 12/12/2019 2.07.10 PM PAGE 7 of 17 FILTER:In Progress/Not Started Tasks
HENSEL PHELPS GMP Amendment No. 1 - Attachment 4
Plan. 9cld. Manage.
2019 M20
Line Unique Task ID Name Duration Start Finish December January Fekisary kkirch April May Mme Aust SeOrbils Odobw Novw&r r
9 :23 6 20 3 17 2 16 30 13 27 11 25 8 22 6 20 3 17 31 11 28 12 26 9 23 7 21
211 47960 MEP Drops to Ceiling-Level 1-Corridors South 5d 12/31/2019 1/1/2020 W I)W to king-Levd 1-cond,M swm i
212 47970 Above Ceiling Inspection-Level 1-Corridors South 5d 1/8/2020 1/14/2020 ®Above CeiM Y M•Level I•Com sw I I
213 47980 1 Install Gyp Ceiling-Level 1-Corridors South 8d 1/15/2020 1/24/2020 ®IsM Gyp Cein9•Level 1 So Ah
214 47990 T/F/P Ceilings&Walls-Level 1-Corridors South 5d 1/27/2020 1/31/2020 ®TIF/P C*9 a wals-Level I-Cwwors south
215 48000 Install Specialty Ceilings-Level 1-Corridors South 5d 2/3/2020 2/7/2020 ®Imo spay ubN -Level 1•Cnnimr:sD I I
216 48010 Install Wall Coverings-Level 1-Corridors South 15d 2/10/2020 2/28/2020 hW WA cwe ngs-Le d 1-Cnnidm6 SRO
217 48020 Install Millwork/Specialties-Level 1-Corridors South 5d 3/2/2020 3/6/2020 ®msw Ml of i slow"-Lewd I-candm SaAh
218 48060 Trim-out Mechanical-Level 1-Corridors South 5d 3/4/2020 3/10/2020 ®Tana:Wwed-Level l-Comdors soot
219 48030 Trim-out Electrical-Level 1-Corridors South 5d 3/6/2020 3/12/2020 ®T"eKbXA-Level I-ur&M so& I I
220 48110 Trim-out Fire Protection-Level 1-Corridors South 5d 3/10/2020 3/16/2020 ®Tmruut Fre Notedim-Level I-Canards soon
221 48040 Trim-out Fire Alarm-Level 1-Corridors South 5d 3/12/2020 3/18/2020 ®TmraA F-Alan-Lewd 1-Camdas SOA!,
222 48050 Trim-out Data/AV-Level 1-Corridors South Sid 3/16/2020 3/20/2020 ®Tm,"A CaWAV-Level 1-Camams SOO I
223 48080 Install Doors&Hardware-Level 1-Corridors South 5d 3/23/2020 3/27/2020 ®"ooas Is Kv"re-Lewd 1-Civsic s sa O I
224 48070 Install Floors-Level 1-Corridors South 15d 3/30/2020 4/17/2020 I,.M eons•Level I-C.4swm
225 48090 Final Paint-Level 1-Corridors South 5d 4/20/2020 4/24/2020 ®RW Put Lewd I-Combo SOA
226 48100 In-house/Contractor Punch List-Level 1-Corridors Soutr 5d 4/27/2020 5/1/2020 ®kAM I Corerader Punch uu-Level 1-COMM mouth i
22740120 Finishes-Levell-Restrooms 92d 12/2/2019 4/9/2020FrOes-Ldd l-ReMM
I I
Lewd 1- man RestNorth
229 41050 Tape&Bed Walls-level 1-Restroom North 2d 12/2/2019 12/3/2019 Tape&em wak-Level 1-Reshanm Nam
230 41060 Frame light Coves&Ceilings-Level 1-Restroom North 4d 12/3/2019 12/6/2019 anise IgA Coes&Cels-Lewd 1-Reser Borth
231 41070 Instal MEP Drops to Ceilings-Level 1-Restroom North 4d 12/6/2019 12/11/2019 ®In MEP aovs to Ce&O-Lewd 1-Restroom NoM 1
232 41080 Above Ceiling Inspection-Level 1-Restroom North Sd 12/12/2019 12/18/2019 ®AbT Ce&V Kwdsw-Lewd 1-ReM=North
233 41090 Instal GYP Ceilings-Level l-Restroom North 4d 12/19/2019 12/24/2019 ®hsW GW Ceingt-Level t-Restroom 1,100 I 1
234 41840 T/F/P Walls&Ceilings-Level 1-Restroom North 5d 12/26/2019 1/2/2020 TiRp w*&Ceigs-Level 1-Rewoao North I 1
235 41850 Instal Lights-Level 1-Restroom North 3d 1/3/2020 1/7/2020 ®Insw Lgu-Level I-Rewoan Norm I 1
236 41860 Instal Countertops-Level 1-Restroom North 3d 1/7/2020 1/9/2020 0 ww Countertops-Lerd I•Restroom Noma
237 41870 Instal Tile-Level i-Restroom North 15d 1/10/2020 1/30/2020 M WW Tit-Lrrd I-Restroom Norm i
238 41910 Trim-out Cehings-Level 1-Restroom North 3d 1/31/2020 2/4/2020 ®Tmrod Cei¢-Level I-Restroom Norm I I
239 41920 Set Plumbing Fildures-Level 1-Restroom North 8d 2/3/2020 2/12/2020 ®set&in*rvmea-Level I-Restroom North I I
240 41930 Instal Partitions&Specialties-Level 1-Restroom North 6d 2/13/2020 2/20/2020 0 insw Partrfpns&5petld6es-lewd 1-Rewoom NM '
Kalahari Covention Center - November 2019 GMP Update
DATA DATE:12/1/2019 JOB#:7017134 VIEW.Kalahari
REV.DATE:12/12/2019 2'.07'.10 PM PAGE 8 of 17 FILTER:In Progress/Not Started Tasks
HENSEL PHELPS GMP Amendment No. 1 - Attachment 4
Plan Scala Manage.
2020
Line Unique Task I Name Duratan start Knish Dewriter Fetwuary Maras Apd May Jere My r rrov°rrow oe r
9 23 6 20 3 17 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 12 26 9 23 7 21
241 41940 Clean-Level 1-Restroom North 3d 2/21/2020 2/25/2020 1 aew-Level 1-Ratri:w NDo I
242 41950 In-house/Contractor Punch List-Level 1-Restroom North 10d 2/26/2020 3/10/2020 Ir house/comndor Pwr^Let-Level I-Restroom NOO
Level 1-Restroom Center - c.- 7 1211812019 4 Level 1-R6Wom Ceiter
244 41960 Tape&Bed Walls-Level 1-Restroom Center 2d 12/18/2019 12/19/2019 0 Tax&Bed wit-Level 1-Ram^
245 41970 Frame Light Coves&Ceilings-Level 1-Restroom Center 4d 12/19/2019 12/24/2019 ®Fame lent CM& -Level 1-Restroan Gena I 1
246 41980 Instal MEP Drops to Ceilings-Level 1-Restroom Center 4d 12/24/2019 12/30/2019 ®wear W or*to CahV-Led 1-Res&oom Gaiter I 1
247 41990 Above Ceiling Inspection-Level 1-Restroom Center 5d 1/8/2020 1/14/2020 ®Wove 0e&o9 wxd w-Level 1-Restroom Cena
248 42000 Instal GYP Ceilings-Level 1-Restroom Center 4d 1/15/2020 1/20/2020 ®ww lire Cery,-Level 1-Restroom cans i
249 42010 T/F/P Wals&Ceilings-Level 1-Restroom Center 5d 1/21/2020 1/27/2020 ®T/RP Wak&c*9-revel 1-Reow center I i
250 42020 Instal Lights-Level 1-Restroom Center 3d 1/27/2020 1/29/2020 ww Ly&s-Level 1-aesuoom Cera I I
251 42030 Instal Countertops-Level 1-Restroom Center 3d 1/29/2020 1/31/2020 1 ww C ter rs-Level I-RWnam Lena
252 42040 Instal Tile-Level 1-Restroom Center 15d 2/3/2020 2/21/2020 DswTie-Level 1-Rah.caw i
253 42050 1 Trim-out Ceilings-Level 1-Restroom Center 3d 2/24/2020 2/26/2020 Tmeq&Cde9-Level 1-ReMw cert I I
254 42060 Set Plumbing Fixtures-Level 1-Restroom Center 8d 2/25/2020 3/5/2020 ®set ftarw Lem.a-Level 1-RWM Cana
255 42070 Instal Partitions&Spedal ies-Level 1-Restroom Center 6d 3/6/2020 3/13/2020 ®ww Pitons&sOanRla-Level 1-Restroom cat
256 42080 Clean-Level 1-Restroom Center 3d 3/16/2020 3/18/2020 1 oe -Lem 1-R.U.0 anter I 1
257 42090 In-house/Contractor Punch List-Level 1-Restroom Center 10d 3/19/2020 4/1/2020 uNwne r Comactor Puom Leu-Lew!1-ReOM Ceuta 1
I I
Lend 1-Ratroan soon
�225�941"130Tape&Bed Walls-Level 1-Restroom South 2d 1/3/2020 1/6/2020 1 Tax&aces Wali-level 1-Restroom Sash
260 42100 Frame Light Coves&Ceilings-Level 1-Restroom South 4d 1/6/2020 1/9/2020 ®Fame Lot coves&U6*-LeM 1-Restroom Soak I I
261 42110 Instal MEP Drops to Ceilings-Level 1-Restroom South 4d 1/9/2020 1/14/2020 ®InsW W or*to Celligc-Level L-RWM soar i
262 42120 Above Ceiling Inspection-Level 1-Restroom South 5d 1/15/2020 1/21/2020 .Abwe Cei9> 1-Reitman swth �
263 42130 Instal GYP Ceilings-Level 1-Restroom South 4d 1/22/2020 1/27/2020 ®Inst GYP Geb-9-Lewd I-Restroom sown I i
264 42140 T/F/P Wags&Ceilings-Level 1-Restroom South 5d 1/28/2020 2/3/2020 ®T/F/P Wab&Genas-Level L-Resuoom soah I 1
265 42150 Instal Lights-Level 1-Restroom South 3d 2/4/2020 2/6/2020 1 wwto%-Lem I-Reww 6a&n I 1
26642160 Instal Countertops-LevelI-Restroom South 3d 2/6/2020 2/10/2020 lwwcounaLoPs-ledl-Rite nom Sun
267 42170 Instal Tile-Level 1-Restroom South 15d 2/11/2020 3/2/2020 ®ww Tie-.Levd l-aesuoom sab
268 42180 Tnmout Ceilings-Level 1-Restroom South 3d 3/3/2020 3/5/2020 1 Tema&cdel9-Level 1-lteww stn I I
269 42190 Set Plumbing Fixtures-Level 1-Restroom South 8d 3/4/2020 3/13/2020 ®sd P4mdng Fauna-Level 1-Rewm stn
270 42200 I Instal Partitions&Specialties-Level 1-Restroom South 6d 3/16/2020 3/23/2020 ®ww Prows&sxca&es-Levd L-Rwi m San
Kalahari Covention Center - November 2019 GMP Update
DATA DATE.12/1/2019 JOB#:7017134 VIEW.Kalahari
REV.DATE 12/12/2019 2:07.10 PM PAGE 9 of 17 FILTER.In Progress/Not Started Tasks
HENSEL PHELPS GMP Amendment No. 1 - Attachment 4
Plan. Build. Manage.
2019 2020
Line Unique Task ID Name Duration Start Finish WwW Avg Feli ri.ai Jur �+ octoDe :DKmft
9 23 B 20 9 .17 2 48 j30 113 27 11 25 ;8 :22 15 12D 13 .17 :31 :14 :28 IIZ 9 23 7 21
271 42210 Clean-Leve 1-Restroom South 3d 3/24/2020 3/26/2020 6W-Levd 1-Reswan sow1F I
27242220 In-house/Contractor Punch List-Level 1- 10d 3/27/2020 4/9/2020 mfiotse/CmIrador Punch List-Lewd l-
-, t I
"Eiger r FVisnes-Leve•"mom 8lilan
274 47730 Tape&Bed Walls-Leve 1-Kilimanjaro Ballroom 5d 12/2/2019 12/6/2019 Tape&Bed warn-Level-Klmanlam Bauoan '
275 47740 Frame Soffits-Level 1-Kilimanjaro Ballroom 20d 12/9/2019 1/7/2020 Fr ft sofa-Level 1-Ui )am B&i=
276 47930 Black-out Ceilings Above Soffits-Level 1-Kilimanjaro Ballroom 10d 116/2020 1/1712020 0 1 r-eings Ahwe sorts-Levell-Wlmmlam Bakm
277 47750 MEP Drops to Soffits-Leve 1-Kilimanjaro Ballroom 8d 1/8/2020 1/1712020 0 MEP Dmix to Sara-Lend 1-K&manlam BAm0m
278 47770 Install Gyp Soffits-Leve 1-Kilimanjaro Ballroom 10d 1120/2020 1/3112020 0 Imml cnv soffits-Level i-Kirwiam Bafoan
279 47780 T/F/P Soffits&Walls-Leve 1-Kilimanjaro Ballroom 10d 213/2020 2/14/2020 T/F/P Sofa&wak-Level I-Kimwtam Bafoan I
280 47900 Install CeilingGrid @ Registration/Offices-Level 1-Kilimanjaro Ballroom 6d
] 2/11/2020 2/24/2020 Imtal Ce&9 Cale 0 Regstratun I gfices•Leve I-Kwanym Ballow ,
281 47910 Install MEP Drops to Ceiling Grid-Level 1-Kilimanjaro Ballroom 5d 2/19/2020 2/25/2020 ®Imtal ler�to C*q cad-Leal I-Kkwjam Bafoom
282 47760 Above Ceiling Inspection-Leve 1-Kilimanjaro Ballroom 5d 2/26/2020 3/3/2020 ®Ahme cr>z,"Unarm-Level I-KwanWo Bafoan
283 47790 Install ACT Ceilings-Leve 1-Kilimanjaro Ballroom 5d 3/4/2020 3/10/2020 Irmai A T Ceigs-Level I-Kimanlam Baba. I
284 47800 Install Wall Coverings-Leve 1-Kilimanjaro Ballroom 1 3/11/2020 3/31/2020 Install war coven
9 1 ng-leve l-KLnanlam Balmom
285 47920 Install Operable Partitions-Level 1-Kilimanjaro Ballroom 15d 4/1/2020 4/21/2020 Instal Owatk Partitom-Level I-Kimenlam Ballroom
286 47810 Install Millwork/Specialties-Leve 1-Kilimanjaro Ballroom 5d 411/2020 4/7/2020 Imlal M"*/SWAM Level 1.""n)am Balmom i
287 47820 Trim-out Mechanical-Leve 1-Kilimanjaro Ballroom 5d 4/3/2020 4/9/2020 I®TmroA McCM Keil-Level I-(imanlam Baioom
288 47830 Trim-out Electrical-Leve 1-Kilimanjaro Ballroom 5d 4/7/2020 4/13/2020 T—W 9emnl-Level I-")am eaiwm
289 48870 Trim-out Fire Protection-Leve 1-Kilimanjaro Ballroom 5d 4/9/2020 4/15/2020 i ®Tnmwt he Roledim-Leve 1-Klirunlam lidm
290 47840 Trim-out Fire Alarm-Leve 1-Kilimanjaro Ballroom 5d 4/13/2020 4/17/2020 I ®Trtnout Fire Awn-Level 1-Kimrjam Bakoom
291 47850 Trini Data/AV-Leve 1-Kilimanjaro Ballroom 5d 4/15/2020 4/21/2020 I ®TrmpA UWAV-Leve 1-Kimani m 8a&man
292 47860 Install Doors&Hardware-leve 1-Kilimanjaro Ballroom 10d 4/22/2020 5/5/2020 ®'W Door:&HaNw e-Levo I-Kimanlam Balmw
293 47870 DO NOT Install Floors-Leve 1-Kilimanjaro Ballroom ld 5/5/2020 5/5/2020 Do NOT Instal Roars-Level I-K nwfam Bafoan i
294 47880 Final Paint-Leve 1-Kilimanjaro Ballroom 5d 5/5/2020 5/11/2020 1 ®Few Pairtt-Level 1-K Mtvam Ballroom I
295 478% In-house/Contractor Punch List-Leve 1-Kilimanjaro Ballroom 5d 5/12/2020 5/18/2020 I ®Ir'b./Contracts Roth List-Lem I-K..w Baioan
29632820 Finishes-Level 2 137 12/2/2019 6/12/2020 11 Rds&a-Level 2
29740170 Finishes-Level 2-BOH 4W 12/2/2019 1/2812020 1 Rnshee-Level 2-BOH I I I
298 48910 Tape&Float Walls-Level 2-BOH 5d 12/2/2019 12/6/2019 1 Tape&Float was-Level 2-BOH I I
I I I
299 49110 Trim-out Mechanical-Level 2-BT.nW Akaervcal-Level 2-BOHOH 5d 12/912019 12/13/2019 ® ,
300 49020 Install Plywood Wainscott&Specialties-Levd 2-BOH 12/9/2019 12/13/2019 1 Imw NAtim wamon&swam-Lem 2i BOH
Kalahari Covention Center- November 2019 GMP Update
DATA DATE:12/1/2019 JOB*7017134 VIEW.Kalahari
REV.DATE.12/12/2019 2.0710 PM PAGE 10 of 17 FILTER In Progress/Not Started Tasks
0 HENSEL PHELPS GMP Amendment No. 1 - Attachment 4
Flan BD-Id H;nage
---- —-
- 2019 2020
LineUnique Task I Name Duration Start Finish December Fouiry Marro Aod May !rte AugLd Seplembef OdDW M01'mbw �bef
9 23 6 20 3 17 2 16 30 13 R7 11 25 8 22 6 20 3 17 31 14 28 12 26 9 23 7 21
301 48990 Trim-out Electrical Devices-Level 2-BOH 5d 12/16/2019 12/20/2019 Tw,"8WU rA Deevces-Level 2-WH
302 49000 Trim-out Data/AV-Level 2-BOH 5d 12/23/2019 12/30/2019 rmma WWAY-Lend 2•WH
303 49010 Trim-out Fire Alarm-Level 2-BOH 5d 12/31/2019 1/7/2020 Trm-M fire Ahm-Levo 2•WH
304 49080 Instal Doors&Hardware-Level 2-BOH 5d 1/8/2020 1/14/2020 ®tnM Doan a ft*mm•Level 2•&DR
305 49030 Apply Flooring Treatment-level 2-BOH 5d 1/15/2020 1/21/2020 ®"p*"T -Led 2-WH
306 49090 Final Coat Paint Doors&Frames-Level 2-BOH 5d 1/15/2020 1/21/2020 FW Coat rim Doan&k+"6-Level 2.80H
301 49100 In-house/Contractor Punch List-Level 2-BOH 5d 1/22/2020 1/28/2020 0 lr,q i camadm w«fi Lot-Level2•&oM
30840180 Finishes-Level 2-Meeting Rooms 91d 12/2/2019 4/8/2020 I Fnehes-levd2-Meta5R1 I •�
309 48150 Tape&Bed Walls-Level 2-Meeting Rooms 5d 12/2/2019 12/6/2019 TW&Bea wok•Level 2-Mxd q Roam 1 1 I
310 48160 Frame Soffits-Level 2-Meeting Rooms 8d 12/5/2019 12/16/2019 N ft ne sones•Level2-Mee"Roans
311 48170 MEP Drops to Soft-Level 2-Meeting Rooms 5d 12/12/2019 12/18/2019 ®MEPPW 10 Sofia-Level 2-ft"Roans
312 48190 Instal Gyp Soffits-Level 2-Meeting Rooms 5d 12/19/2019 12/26/2019 N j sW Wv suets-Level 2-ft"Rows
31348200 T/F/P Soffits&Walls-Level 2-Meeting Rooms 7d 12/27/2019 1/7/2020 TlrRSoft&wds-LrM2-MR"Rom
314 48320 Instal Ceiling Grid-Level 2-Meeting Rooms 5d 1/8/2020 1/14/2020 1AW C&Q GN-Level 2-Meeaw R.
315 48330 Instal MEP Drops to Ceiling Grid-Level 2-Meebng Rooms 5d 1/15/2020 1/21/2020 WW W DW to ce&o9 ael-Level 2-retro"Roans
316 48180 Above Ceding Inspection-Level 2-Meeting Rooms 5d 1/22/2020 1/28/2020 ®M..T&q lns cbm-Lrid 2-Meean RM.
317 48210 Instal ACT Ceilings-Level 2-Meeting Rooms 5d 1/29/2020 2/4/2020 imW X7 coh9s-Level 2-Medni;Roans
318 48220 Instal Wal Coverings-Level 2-Meeting Rooms 5d 2/5/2020 2/11/2020 ®Ingo waycow. -Level 2-tre.y Roars
319 48230 Instal Millwork/Specialties-Level 2-Meeting Rooms 3d 2/12/2020 2/14/2020 1 hW M&wt 1 s I,-•Lena 2-W"Rom i
320 48240 Trim-out Mechanical-Level 2-Meeting Rooms 3d 2/17/2020 2/19/2020 'T..Lt MLdun,d•Level 2-meetm Ram 1 I
321 48250 Trim-out Electrical-Level 2-Meeting Rooms 3d 2/19/2020 2/21/2020 Twat Bxma-Level 2-MMM limes
322 48860 Trim-out Fire Protection-Level 2-Meeting Rooms 3d 2/21/2020 2/25/2020 Tme"rn Raamoe-Level 2-Med"Roans 1
323 48260 Trim-out Fire H �Ali.Alarm-Level 2-Meeting Rooms 5d 2/25/2020 3/2/2020 ®T"M a-Level 2- Rea"'
324 48270 Trim-out Data/AV-Level 2-Meeting Rooms 5d 2/27/2020 3/4/2020 0 TW"A Dews•Led 2-Mearq Roans i I
325 48340 Instal Operable Partitions-Level 2-Meeting Rooms 5d 3/5/2020 3/11/2020 1lrshl4Lw+uevrmons-Level 2-MedNRoans
326 48280 Instal Doors&Hardware-Level 2-Meeting Rooms 5d 3/12/2020 3/18/2020 BmR boas&Wdwe•evel 2-Meta q R1om
327 48290 Instal Floors-Level 2-Meeting Rooms 5d 3/19/2020 3/25/2020 ®1�w Roos-Level 2-Meetrq Roans i 1
328 48300 Final Paint-Level 2-Meeting Rooms 5d 3/26/2020 4/1/2020 ®r+w rant-Level 2-Meta v&vans i 1
32948310 In-house Contractor Punch List-Level 2-Meeting Rooms 5d 4/2/2020 > 1cWbadwanonUit-Livel 2-MR"Ram
. 09 Rns&e-Level 2-KAim6avoao '
Kalahari Covention Center - November 2019 GMP Update
DATA DATE.12/12019 JOB 8:7017134 VIEWKalahan
REV.DATE 12/122019 2.0710 PM PAGE 11 of 17 FILTER:In Progress/Not Started Tasks
QHENSEL PHELPS GMP Amendment No. 1 - Attachment 4
Plan. Build. Manage
- 2019 2020
Line Unique Task ID Name Duration Start Finish I>etunber AyM Februivy AarM Ld Sepbi oamer rwremoer Dewtbet
9 23 16 20 3 17 2 16 130 113 127 ,11 25 8 22 16 120 13 17 31 14 28 112 s26 19 23 7 21
331 48350 Tape&Bed Wags-Level 2-Kalahari Ballroom 5d 12/2/2019 12/612019 ITW&&ea wab-trd 2-RahW ea=
332 48360 Frame Soffits-Level 2-Kalahari Ballroom 20d 12/5/2019 1/3/2020 Frame Saab-heW 2-n*hua&*oao I 1
333 48370 MEP Drops to Soffits-Level 2-Kalahari Ballroom 8d 1/6/2020 1/15/2020 ®W onP to so%-Ind 2-n�lw U n 1
334 48390 Install Gyp Soffits-Level 2-Kalahari Ballroom 10 1/16/2020 1/29/2020 ®IWA OVR Sara-Level 2•K*tw&*aom
335 48400 T/F/P Soffits&Walls-Level -Kalahad Ballroom 10d 1/30/2020 2/12/2020 ®T/FIPWits&wars-LeM 2-Wtw 11*90m
336 48520 Instal Ceiling Grid-Level 2-Kalahari Ballroom 10d 2/13/2020 2126/2020 ®WW rein9 Grid•hrd 2•K.Ii fi*aam I 1
337 48530 Install MEP Drops to Ceding Grid-Level 2-Kalahari Ballroom 10 2/20/2020 3/4/2020 ®&aw WIDW m Cda9 W•Lrd 2-UWan&*smn
338 48380 Above Ceiling Inspection-Level 2-Kalahari Ballroom 5d 3/5/2020 3/11/2020 Amrc U"inspec m-Lewd 2-UWW Ilaioom j
33948410 Install ACiCeilings-Level 2-KalahadBallroom 10 311212020 3/2512020 ®>WAcTCA*-Lem 2-luld�ae�ro� I
34048420 Install Wag Coverings-Level 2-Kalahari Ballroom 15d 3/19/2020 4/8/2020 Inv*whl Foremg.lewd 2-aihlwi 8*oom I
341 48430 Install Milhvolk/Specialties-Level 2-Kalahari Ballroom 5d 4/9/2020 4/1512020 ®Rism t i sRea:Iaes-Led 2-KAOW 8*wn
342 48440 Trim-out Mechanical-Level 2-Kalahari Ballroom 5d 4/13/2020 4/17/2020 j .Tunwt nxlnnnl-Led 2-;owl a*=
343 48450 Trim-out Electrical-Level 2-Kalahari Ballroom 5d 4/15/2020 4/21/2020 1 ®rmmW De ad-Leed 2.UaW B*oan I
344 48850 Trim-out Fire Protection-Level 2-Kalahari Ballroom 5d 4/17/2020 4/23/2020 ! ®T.Iwt F.Rotedim-Lrd 2.14"B h.
345 48460 Trim out Fire Alarm-Level 2-Kalahari Ballroom 5d 4/21/2020 4/27/2020 ®Tm,wt Fn Alarm-LeM 2-Manan B*aom
346 48470 Trim-out Data/AV-Level 2-Kalahari Ballroom 5d 4/23/2020 4/29/2020 I ®Tim-mit NoJAV-Lewd 2-Ka"8*oan I
347 48540 Install Operable Partitions-Level 2-Kalahari Ballroom 10 4/24/2020 5/7/2020 I ®Instal!*a*PwMws-LeM 2-I da&n 0*oan
348 48480 Install Doors&Hardware-Level 2-Kalahari Ballroom 5d 5/8/2020 5/14/2020 l ®Inv*Doan&ftm-Lewd 2-raWwi I3*0am
349 48490 Install Floors-Level 2-Kalahari Ballroom 10d 5/15/2020 5/29/2020 j ®ImW R ,-Led 2-e*ean naiad"
350 48500 Final Paint-Level 2-Kalahari Ballroom 5d 5/1/2020 6/5/2020 i ®W linvi-U-M 2-KM.8*aom 1
35148510 In-house/Contractor Punch Ust-Level 2-Kalahari Ballroom 5d 6/8/2020 6/12/2020 l �rn6aeelcmmdorwduv-L&d2-n*gaa&-1
Fines-Level2-Restroom 92d 12/2/2019 4!9/2020 An"-Lewd 2•R
-ImI wamm's Restroom j ..
354 42250 Tape&Bed Wags-Level 2-Women's Restroom 2d 12/2/2019 12/3/2019 Tape&Bed wad-lewd 2-www's Restroom I 1 I
355 42260 Frame Light Coves&Ceilings-Level 2-Women's Restroom 4d 12/3/2019 12/6/2019 Frame Ljg Coms&0*9-trd 2-wama's Rjsuoom !
356 42270 Instal MEP Drops to Ceilings-Level 2-Women's Restroom 4d 1216/2019 12/11/2019 lass W I)mp m CdW-Ind 2-W.',Bemoan
357 42280 Above Ceiling Inspection-Level 2-Women's Restroom 5d 1/1312020 1/17/2020 ®am c bq Yis e w-Leal i-wamee's Reo m 1
358 42290 Instal GYP Ceilings-Level 2-Women's Restroom 4d 1/20/2020 1/23/2020 ®hw W CdW-Lend 2-Www's Retimn I
359 42300 T/F/P Walls&Ceilings-Level 2-Women's Restroom 5d 1/24/2020 1/30/2020 ®TMP Wallis&C*9-Lead 2-women's Rem=
36042310 Instal Lights-Level 2-Women's Restroom 3d 1131/2020 2/4/2020 16var Lights-Led 2-women's Reslmom
Kalahari Covention Center- November 2019 GMP Update
DATA DATE:12/1/2019 JOB#:7017134 VIEW Kalahari
REV.DATE.12/12/2019 2'07'10 PM PAGE 12 of 17 FILTER In Progress/Not Started Tasks
QHENSEL PHELPS GMP Amendment No. 1 - Attachment 4
Plan BLA d Manage.
2019 2020 _ _ _
Line Unique Task 1 Name Duration Start Finish E Marro caber NumberDeawber
11 9 23 6 20 3 17 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 12 26 9 23 7 21
361 42320 Instal Countertops-Level 2-Women's Restroom 3d 2/4/2020 2/6/2020 1IrewC"Wtops-Level 2-women'sReslow. j j
362 42330 Instal Tile-Level 2-Women's Restroom 15d 2/7/2020 2/27/2020 ®Ifw TEe-Levd 2-WMoe's Restroom I I
363 42340 Tnm-out Ceilings-Level 2-Women's Restroom 4d 2/28/2020 3/4/2020 ,Tnncia C;kq-Level 2-wo,na's Restroom
364 42350 Set Plumbing Fixtures-level 2-Women's Restroom 8d 3/2/2020 3/11/2020 ®set lkm"rte-Level 2-Wormers Restroom
365 42360 Instal Partitions&Speaakies-Level 2-Women's Restroom 8d 3/12/2020 3/23/2020 ®u.w Paro ms&spec"-Level 2-W.;.'s Restroom j
366 42370 Clean-Level 2-Women's Restroom 3d 3/24/2020 3/26/2020 1 dw-uvd 2.Wonw s Regrow
367 42380 In-house/Contractor NO List-Levd 2-Restroom North 1 3/27/2020 4/9/2020 whouse I coovxw KNO L!1-Levo 2-Regrow No*
Men's Resuoam j I
369 42390 Tape&Bed Wals-Level 2-Men's Restroom 2d 12/23/2019 12/24/2019 f Tex&Bed Wa!-Leed 2-Men's Regrow I I
370 42400 Frame Light Coves&Ceilings-Level 2-Men's Restroom 4d 12/24/2019 12/30/2019 Frave Lift coves It coos-Level 2-fn's Rem I
371 42410 Instal MEP Drops to Ceilings-Level 2-Men's Restroom 4d 12/30/2019 1/3/2020 Irad W Drops to Cakgs-Levo 2-Mens Restroom
37242420 Above Ceiling Inspection-Level 2-Men's Restroom 5d 1/6/2020 1/10/2020 ®Above Ce&ng>rsvvmn-LeM2-Men's Regrow
373 42430 Instal GYP Ceilings-Level 2-Men's Restroom 4d 1/13/2020 1/16/2020 1 WW GYP caws-LrM 2-Men's Regrow I I
374 42440 T/F/P Wals&Ceilings-Level 2-Men's Restroom 5d 1/17/2020 1/23/2020 tl TTrP VIA&CdV-L-M 2-Mm's Restroom
375 42450 Instal Lights-Level 2-Men's Restroom 3d 1/24/2020 1/28/2020 /9eoE L".uvd 2-Pr's Rte^
376 42460 Instal Countertops-Level 2-Men's Restroom 3d 1/28/2020 1/30/2020 1 WW Coixtertog-Level 2-Men's Regrow i I
377 42470 Instal Tile-Level 2-Men's Restroom 15d 1/31/2020 2/20/2020 ®LVA Tit-Level 2-men's Resom
378 42480 Tnm-out Ceilings-Level 2-Men's Restroom 3d 2/21/2020 2/25/2020 /Trm-MR trigs-L&d 2-Men's Regrow
379 42490 Set Plumbing Fixtures-Level 2-Men's Restroom 8d 2/24/2020 3/4/2020 ®Set Munit�g mss-Level 2-Men's Restrw I
380 42500 Instal Partitions&Specialties-Level 2-Men's Restroom 6d 3/5/2020 3/12/2020 ®I sGl Parroom&speuaoes-Level 2-Mens Revoeo i
381 42510 Clean-Level 2-Men's Restroom 3d 3/13/2020 3/17/2020 1 OBy-Levd 2-Men's Regrow I I
382 42520 In-house/Contractor Punch List-Level 2-Men's Restroom 10d 3/18/2020 3/31/2020 19&Horse I conrnoa Palin ust-Level 2-Men's Restroom
383 40210 F -Level 2-Cortidors 87d 12/9/2019 4/912020 I kWvs-nerd 2•Corr'mrs I I
384 40220 Tape&Bed Wals-Level 2-Corridors 5d 12/9/2019 12/13/2019 ®Tax&em grab•Level 2-condors I I I
385 48550 Frame Soffits/Ceiling-Level 2-Comdors 10d 12/16/2019 12/30/2019 sones I Ceig•Level 2•Ca EMs I I
386 48560 MEP Drops to Ceding-Level 2-Corridors 5d 12/23/2019 12/30/2019 0 MEP Drops to cefn9-Level 2-condors!
387 48570 Above Ceiling Inspection-Level 2-Corridors 5d 12/31/2019 1/7/2020 Prove cerw Irep M-Level 2-Conchs I I
388 48580 Instal Gyp Ceiling-Level 2-Corridors 8d 1/8/2020 1/17/2020 ®uow*cdrw-Lad 2-CMrdMs I I
389 48590 T/F/P Ceilings&Wals-Level 2-Corridors 5d 1/20/2020 1/24/2020 B T/EiP caws&Way-Level 2-Corridors I I
NW Instal Spedalty Ceilings-Level 2-Corridors 5d 1/22/2020 1126/2020 u&taEp�r�
s - 2-Untors
Kalahari Covention Center - November 2019 GMP Update
DATA DATE 1211/2019 JOB#:7017134 VIEW:Kalahari
REV.DATE:12/122019 2:07.10 PM PAGE 13 of 17 FILTER.In Progress/Not Started Tasks
QHENSEL PHELPS GMP Amendment No. 1 - Attachment 4
Plan. BLiId. Manage.
- - - — -- - -
2019 - - 2020
Line Unique Task ID Name Duration Start finish oemm&et AyM F Mucti AM OWW November December
9 23 6 20 3 17 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 12 26 9 23 7 21
391 48610 Install Wad Coverings-level 2-Corridors 15d 1124/2020 2113/2020 M ww'wj •Lead 2•cwn i i
392 48620 Install Millwork/Specialties-Level 2-Corridors 5d 2114/2020 2120/2020 WW M kwk/spw"-Ina 2-Coeurs I I
393 48630 Trim-out Mechanical-Level 2-Corridors 5d 2/1812020 2/24/2020 ®Tr mea Medwnd-Lead 2-Calors
394 48640 Trim-out Electrical-Level 2-Corridors 5d 2/20/2020 2/26/2020 .Two Bmkal-Ina 2-Umbs
395 48840 Trim-out Fire Protection-Level 2-Corridors 5d 2/24/2020 2128/2020 Tmaa F.ftW.•LtM 2-canmrs i 1
396 48650 Trim-out Fire Alarm-Level 2-Corridors 5d 2126/2020 3/3/2020 .Tr mmit Fee Airm-lad 2-CM&M I I
397 48660 Trim-out Data/AV-Level 2-Corridors 5d 2/28/2020 3/5/2020 ®Tmaa o WAV-lead 2-commis
__.... ... _ ......... } r....... r..
398 48670 Install Doors&Hardware-Level 2-Corridors 5d 2/28/2020 3/512020 O Inswil ons&Hutloom-L&d 2-U10o s I I
399 48830 Install Ornamental Guardrail @ Escalators-Level 2-Corridors 15d 2/28/2020 3119/2020 ®ww Dow"&wda 0 babe rs-lead 2•candor
400 48680 Install Floors-Level 2-Corridors 15d 3/6/2020 3/26/2020 ®! rs-Lad 2-Cxmtm I I
40148690 Final Paint-Level 2-Corridors 5d 3/27/2020 4/2/2020 W hkt-Lee!2•Cm dos
402 48700 In-house/Contractor Punch List-Level 2-Corridors 5d 4/3/2020 4/9/2020 j®mMe/CmVa ar nwd u t•Level 2-tmidmt j
rsksMs•Led 2-ha lahq I I
404 48710 Tape&Bed Walls/Soffits-Level 2-East Lobby 5d 12/2/2019 12/612019 Tape&&ed wa&s/soft-Lad 2-fa#Lo* I I 1
405 48730 Frame Ceilings @ Rafters-Level 2-East Lobby 10d 12/9/2019 12/20/2019 ®Rr Gd*a Ra&es-lad 2-Ewt tobM
406 48750 MEP Drops to Ceiling-Level 2-East Lobby 6d 12/23/2019 12/31/2019 W DW to ce in-Lad 2-lost Lobb/ I I
407 48760 Above Ceiling Inspection-Level 2-East Lobby 5d 11212020 1/8/2020 AbweCrikV bW mt-Lad 2-East 1a* I I
408 48770 Install Gyp Ceiling-Level 2-East Lobby 6d 1/9/2020 1/16/2020 ®lnsw tap ce&a9-Ind 2-rasi Lobb I I
409 48780 T/F/P Ceilings-Level 2-East lobby 5d 1/17/2020 1/23/2020 ®TLFIr Cd*-Ind 2-East' I
41048720 Install Wood Rafters-Level 2-East Lobby 15d 1124/2020 2/13/2020 ®bswWOW Rams-load2-FntL0* I I
411 48790 Trim-out Mechanical-Level 2-East Lobby 5d 2114/2020 2/20/2020 ®Tmw"ftwiiw-Lad 2-W lomr I I
41248800 Trim-out Electrical-Level 2-East Lobby 5d 2/18/2020 2124/2020 Tmoeteamol-Lad2-East Lobby
413 48820 Trim-out Fire Protection-Level 2-East lobby 5d 2/2012020 2126/2020 Tmaa In wat«ms-Lad 2-Fora lomr
414 48810 Trim-out Fire Alarm-Level 2-East Lobby 5d 2124/2020 2/28/2020 ®Tmeaut Re Nem-Lad 2-Fast Lo* I 1
415 48900 In-house/Contractor Punch List-Level 2 East Lobby 5d 3/16/2020 3/20/2020 ®m-;./Cmtrxmr R.0 Lit-Lnd 2 East Lamy
4161470 Conveyance 2294 5/24/2019 A 4/17/2020 game
41737330 ServimEkvator 48d 12/10/2019 2/17/2020 Sam Bram
418 37370 Install Elevator Rails-Service Elevator 10d 12/10/2019 12/23/2019 ®Lmw Baata wk-Sault,Baamr
dI I I
419 37380 Set Equipment-Service Elevator 5d 12/24/2019 12/31/2019 sdeawwt-santeBMW
I I
420 37390 Set Door Frames-Service Elevator 1/2/2020 1/8/2020 se bur kames Sarre ewxa'
Kalahari Covention Center- November 2019 GMP Update
DATA DATE:12/1/2019 JOB#:7017134 VIEW:Kalahari
REV.DATE.12/12/2019 2:07:10 PM PAGE 14 of 17 FILTER:In Progress/Not Started Tasks
QHENSEL PHELPS GMP Amendment No. 1 - Attachment 4
Flan 6u:10. Mznage.
-- -- – – — _2019
Task Une Unique TaName Duration Start Fini5h oemmtt Jmm Feft" N� k� May J^- A August SeP"'bw 00ft NDW&Tbw DKwriw
9 23 6 20 3 17 2 16 30 13 27 11 25 8 22 6 20 3 17 31 14 28 12 26 9 23 7 21
421 37400 Close-up Moist Way-Service Elevator 5d 1/9/2020 1/15/2020 �4 iw�+r serm B"O, i i
422 37410 Budd Cab-Service Elevator 8d 1/16/2020 1/27/2020 ®BWa arme&
b-swater
423 37420 Wiring&Testing-Service Elevator 15d 1/28/2020 2/17/2020 ®vraaa&Testa9-Sewe aerates
424 37340 Pas>oengeralevator 43d 1/28/2020 3/26/2020 E
425 37450 Install Elevator Rails-Passenger Elevator 5d 1/28/2020 2/3/2020 imW Elt awr8ak-PatteaeFkraw
42637460 Set Equipment-Passenger Elevator 5d 2/4/2020 2/10/2020 se EWPM-Pain Ekwxa
427 37470 Set Door Frames-Passenger Elevator 5d 2/11/2020 2/17/2020 ®Set ow Fames-Passenger EkvaW
428 37480 1 Close-up Hoist Way-Passenger Elevator 5d 2/18/2020 2/24/2020 ®aasew twat War-Passer%,Berxa j j
429 37490 Build Cab-Passenger Elevator 8d 2/25/2020 3/5/2020 ®BW Cab.Pamw w Bew W 1 1
430 37500 Wiring&Testing-Passenger Elevator 15d 3/6/2020 3/26/2020 ®wawa 6 Tessa-Paseo&wxar 1 1
431 37350 EscalaEonc 2M 5/24/2019 A 4/17/2020 lEscallim
43237520 Escalator-Hook-up&Fit-up 1 3/2/2020 3/13/2020 ®Esoller-Xmtw6R-W
433 37530 Escalator-Trim 1 3/16/2020 4/3/2020 ®BGMW-Tan 1 1
434 37540 Escalator-Start-up&Testing 10d 4/6/2020 4/17/2020 -s-waT"
4351460 Commissioning 1924 12/3/2019 9/1/2020 P ■a
436 66710 Convention Center-Commissioning Complete 9/1/2020 9/1/2020 j j U tw C me-cc.Uwaa amaee
437 37550 Conveyance 15d 6/10/2020 6/30/2020 1 PM9C°"ej"`° i
438 37620 Escalator QEI 5d 6/10/2020 6/16/2020 1 ®Es QEI
439 37600 Service Elevator QEI 5d 6/17/2020 6/23/2020 j ®s"ami QB j
440 37610 Passenger Elevator QEI 5d 6/24/2020 6/30/2020 I 11 W-w&,"QB I
441 66660 Elevator&Escalator QEI Complete 6/30/2020 6/30/2020 I +EIN.W&Erarmr QS Cw*1
442 37560 Mlechancial Systems 17 12/30/2019 9/1/2020 taslweWsrstemr �!
443 75920 Rip&Hush CHW System 7d 12/30/2019 1/8/2020 av a Ren Cnw system
44437630 Factory Start-up Air Handling Equipment-CC 5d 1/15/2020 1/21/2020 Faday Stator a Moria Ep prise•CC 1 1
445 37650 Point to Point Controls-CC 30d 2/26/2020 4/1/2020 Pon to Pa.n comms-a 1
446 37660 Pre-functional Equipment&System Checks-CC 30d 4/8/2020 5/19/2020 ®P a iu cmw FAQ a sruan awes•a
447 66750 Test&Balance-CC 50d 5/20/2020 7/30/2020 j Test a saw"-a j
44831670 Functional Equipment Testing-CC 23d 7/31/2020 9/1/2020 I I ®ftKwWEyrvmemT"-CC
44937570 Electrical Systems 150d, 12/3/2019 7/2/2020 a dsr
450 37750 Power 5 12/3/2019 2/14/2020 --- =1P-
i
Kalahari Covention Center - November 2019 GMP Update
DATA DATE:12/1/2019 JOB u.7017134 VIEW:Kalahari
REV.DATE.12/12/2019 2.07 11 PM PAGE 15 of 17 FILTER:In Progress/Not Started Tasks
HENSEL PHELPS GMP Amendment No. 1 - Attachment 4
Pian 8c:id. Manage
2019 2020
Line Unique Task ID Name Duration Start Finish Demyte Fetwoy March April May in td oaoDe laeeme Elesntter
9 :23 6 20 3 17 2 16 30 13 27 11 25 8 :22 6 20 3 17 31 14 28 12 26 9 :23 7 21
451 37790 Start-up Main Electrical Gear-Level 2 Main Electric Room 5d 1213/2019 12/9/2019 0 sump Iqn Berm al rear-Level 2 Man earn 1tocen
452 66060 UL Test Grounding System-Convention Center 5d 12/4/2019 12/10/2019 1 u1 Test'G uwang Systew-Comato Geste 1 I
453 59270 Power Available-Convention Center 12/9/2019 12/9/2019 ♦Powe tlailaW-caws tan yenta
454 76050 Set Emergency Generator-Loading Dock Exterior 5d 1/13/20201/17/2020 ,set Enagmcy G&MW-Loa*Dock Edd
455 50320 Start-up Emergency Generator-Loading Dods Exterior 5d 1/20/2020 1/24/2020 0 surtwo Etegmty Ge est -twaolw9 ood El. j I
456 50330 Load Bank Test Emergency Generator-Locading Dock Exterior 5d 1/27/2020 1/31/2020 ®loan Band Tet Emagm[r Geneator-1o^9 Doo Edw I I
457 37800 Test Automatic Tasnfer Switches-Level 2 Emergency Electrical Room 5d 2/3/2020 2/1/2020 ®Test kWmt[Tr&sr a swildlies-Lend 2 cmayety 9etnl Iimm
458 37810 Test Emergency Power Functionality-Convention Center 5d 2/10/2020 2/14/2020 ®Tat Emagaty via Rmdarally,-Coma om Cate
459 59290 Power Complete-Convention Center 2/14/2020 2/14/2020 Pow cewgkte-rometm rente I I
460 37760 Fire Alarm 35 4/18/2020 6/16/2020 I runes I
461 37820 As-built Fire Alarm Documents&System Programming 15d 4/2812020 5/18/2020 ®M-bimitr*eAlarm oxwoauseSystem v ramm 9
462 37830 In-house Fire Alarm Functionality Testing 15d 5/19/2020 6/9/2020 i ®lenese In www rwt6mafly Testis j
463 37840 AM)Fire Alarm Testing 5d 6/10/2020 6/16/2020 I ®Ake ru www T." I
Doti/&y
465 5Data Wire Terminations Complete-Level l-North 3/3/2020 3/3/2020
8400 Data Tewninaeaw CWft trd I-Nath;
466 58410 Data Wire Terminations Complete-Level 1-South 4/21/2020 4/21/2020 j Data wee Tmnnadaw Cwm 10-4M 1-5.6 j
467 58420 Data Wire Terminations Complete-Level 2 4/29/2020 4/29/2020 I Dau vee Tawwuows Cw0de-teed 2
468 38710 Ring-out&Verify Data Drops-Conventlon Center 15d 4/30/2020 5/20/2020 I ®RmtM&va*IDra coos-cawmCm Cewte
469 38720 Test&Document Data System Functionality-Convention Center 15d 5/21/2020 6/11/2020 ®rex a-unem Dau system rmmoraQy-CanK tnn[enter
470 38730 Verity/Test AV DeviceFuncionality-ConventionCenter 15d 6/12/2020 7/2/2020 I very/Test AvD.liedi.uity-Ccmm&wwCenter
47137580 Pltwobing5ytr>bm 75d 12/19/2019 4/3/2020 &-WVsysats
472 37700 Certify Bark-flow Preventers-Convention Center 5d 12/19/2019 12/26/2019 ®Cindy Back-lim 7rerentm-rawaoww late
473 76060 Purge Natural Gas System-Convential Center 3d 12/26/2019 12/30/2019 Re9e NAran Gas system-rwmmam knta j j
474 37690 Factory Start-up Plumbing Equipment&Pumps-Convention Center 5d 1/15/2020 1/21/2020 ®rxVy Swt-w ftn.o Ewcw ent&IV*-rwwretan Center I I
475 37680 Chlorinate&Flush Plumbing System-Convention Center IM 3/16/2020 3/27/2020 ®aroaate&Rush wnaw System-Canvmeww Cate
476 37710 TAB Plumbing&Adjust Fixture flows-Convention Center 5d 3/3012020 4/3/2020 TIB%i&@&Aiust Potae mows•cwmmdm center
477 65160 Plumbing Complete-Convention Center 4/3/2020 4/3/2020 Kroev cowvlete-Cwmmdm Corte j
47837590 Fire Protection 25d 5/27/2020 6/30/2020 I Feevmeanw I
479 37720 Start-up&Test Dry-ppe Systems 10d 5/27/2020 6/9/2020 ®sung a rex D y ope sysuww
480 37730 Adjust Stand-pipe Flows 10cl6/10/2020 6/23/2020 ®just stand-w mows
Kalahari Covention Center - November 2019 GMP Update
DATA DATE:12/1/2019 JOB#:7017134 VIEW:Kalahari
REV.DATE.12/12/2019 2:0711 PM PAGE 16 of 17 FILTER In Progress/Not Started Tasks
QHENSEL PHELPS GMP Amendment No. 1 - Attachment 4
Ftdn B610 M�s3ge.
2019 2020
Line IUnique Task I11 Name Duration Start Finish DecemberJyRaq FebRary Marct — may ane Aujual---- 0dober iDeceMet
9 23 6 20 3 17 2 16 130 113 27 11 25 8 22 16 20 13 17 31 14 28 12 26 9 23 7 21
48137740 Final A.H.)Walk 5d 6/24/2020 6/30/2020 j NHN1W0walk j
4821480 FFE&OSE 1044 5/6/2020 10/1/2020 1 WE&OSE
14831490 FFE&OSE-Level 1 1041 5/6/2020 10/1/2020 RE&OSE-Lerdl
484 50230 Deliver&Install OFCI Items-Level 1 1 5/6/2020 5/27/2020 ® e I�Ui ora I em Ird I '
485 66800 Staging for Hotel FFE-Level 1-Kilimanjaro Ballroom 6/17/2020 9/10/2020 I s,Wq la Itdd RE•urd I•K6wgWm
486 50220 Deliver&Instal FFE Items-Level 1 1 6/19/2020 7/10/2020 1 Dtere&Imte1RE Items-Lad 11
487 66810 Install Flooring-Level 1-Kilimanjaro Batraoom 15d 9/11/2020 10/1/2020 1WA%w"
4881500 FFE&OSE-Level 2 6/1/2020 8/10/2020 j 1 reos6•ee2 j
s
489 50240 Deliver&Install OFCI Items-Level 2 15d 6/1/2020 6/19/2020 1 ®Dl .&1,9AOFO Item-Lerd 2 I
490 1510 Deliver&Install FFE Items-Level 2 15d 7/21/2020 8/10/2020 1 I ®Dare&WW FIT eem-lewd 2
9166520 Punch list 89d 5/27/2020 10/1/2020 wdLst
49266470 Convention Center Complete 10/1/2020 10/1/2020 j j *conraem tate Cnmpkte
493 66530 Punch List-Level 1 20d 5/27/2020 6/24/2020 1 PM=9 ranch ust-L&d I
494 59570 In-crouse/Contractor Punch Complete-Level 1 5/27/2020 5/27/2020 I�aee fonvanu Cade-LM I I
495 50280 0/A/E Punch List Walk-Level 1 4d 5/28/2020 6/2/2020 01AR wKh Iet Wet-Ierd I
4%50290 Correct Punch List Items-Level 1 12 6/3/2020 6/18/2020 j ®rw�d win ua Il m-Inr1 I j
497 66550 Final Sign-off Punch List-Level 1 4d 6/19/2020 6/24/2020 1 Fed sgtte wvn Let-Lewd I
49866540 Punch List-Level 2 20d 6/19/2020 7/20/2020 1 ` w[h utt-Level 2
499 59580 In-house/Contractor Putsch Complete-Level 2 6/19/2020 6/19/2020 j Io-lro /canraa vetch cw0ete-Lewd 2
500 50300 O/A/E Punch List Walk-Level 2 4d 6/22/2020 6/25/2020 I ®oiAX i tet wax•Ierd 2 1
501 50310 Correct Punch List Items-Level 2 12d 6/26/2020 7/14/2020 1 ®caw win IA Item-Lewd 21
502 66560 Final Sign-off Punch List-Level 2 4d 7/15/2020 7/20/2020 w sgser wat Lu-1eqi 2
I I 1
I i I
I 1 i
I I I
� 1 I
I 1 I
06 RESPONSIBILITY
MASONRY SUB
Kalahari Covention Center - November 2019 GMP Update
DATA DATE.12!1/2019 JOB#.7017134 VIEW.Kalahari
REV.DATE.12/122019 2.07.11 PM PAGE 17 of 17 FILTER.In Progress/Not Started Tasks
GMS Amendment No. 1 Attachment 5
HENSEL PHELPS
Plan. Build. Manage.
JOBSITE OFFICE
501 South Kenny Ft.
Round Rock, Texas 78665
November 18, 2019
KR Acquisitions, LLC
P.O. Box 590
Wisconsin Dells, WI 53965
Attention: Dale Hensen
Subject: Kalahari Resort and Convention Center—Extended Preconstruction Services
Mr. Hensen,
Hensel Phelps anticipates executing the Guaranteed Maximum price for both the Convention
Center and the Hotel, Parks and Site within the next few weeks. When these GMP's are executed
it will bring closure to the preconstruction phase of the project and as a result Hensel Phelps is
looking to resolve our extended preconstruction services cost.
Preconstruction Schedule- The original RFP schedule indicated that preconstruction would begin
on June 12, 2017 with construction starting on November 3, 2017. Design would be completed in
phases with final Construction Documents issued on May 25, 2018. The actual dates were
significantly different with preconstruction starting as scheduled on June 12, 2017 followed by
construction starting on May 15,2018 and final Construction Documents being received on October
5, 2018. These documents required major Bulletin's 1,2, and 3 to incorporate and correct design
issues found by the project team taking the actual completion of the Construction Documents to
April 24, 2019. These dates resulted in 6.5 additional months of preconstruction services before
construction began and an additional 5-12 months of extended design time depending on your
interpretation of when actual final completion of Construction Documents was achieved.
MEP Preconstruction- Hensel Phelps has been informed verbally that you have been unsatisfied
with our efforts to manage the design assist MEP subcontractors that were brought onto the project
early. We understand that our management of the cost to complete budgets established as part of
their procurement process leaves some area for improvement on our part. The project was able to
procure 4 Mechanical and 4 Electrical subcontractors for a single project in the busiest market
central Texas has ever seen ensuring the project had the craft resources needed. Those
subcontracts did assist with an unanticipated complete redesign of the electrical system and the
pricing effort associated with it. In addition they were crucial to understanding the cost implications
of design changes late in the Construction Document process that allowed for Value Engineering
to help bring the cost closer to the original budgets established by these early MEP subcontractors.
Design Completion- The impact of the fall out between HKS and Kalahari resulted in additional
work for the Hensel Phelps preconstruction team beyond what would be anticipated on a typical
project. The request for Hensel Phelps to assist with the development of finish schedules in the
public spaces, back of house spaces, restaurant spaces, and the redesign efforts associated with
the exterior amenity areas, and other critical areas of the resort has resulted in additional
preconstruction services from Hensel Phelps and in particular Kelli Mitchell and the resources that
support her.
j t
GMF Amendment No. 1 Attachment 5
HENSEL PHELPS
Plan. Build. Manage.
Guaranteed Maximum Price Proposal process- Hensel Phelps has also been asked to submit
multiple GMP's as part of the preconstruction process which takes a significant effort on our part to
prepare, internally review, assemble, submit and review with Kalahari. This process has been
repeated multiple times with numerous meetings held to review pricing that has been developed
as a result of design modifications to the Construction Documents and specifically core and shell
aspects of the project along with the finishes throughout the resort.
Hensel Phelps has attached to our letter email correspondence from March 14, 2018 outlining our
extended preconstruction services concerns a year and a half ago. Our organization to date has
incurred over $2.5 million in preconstruction service cost on this project and only proposed to
provide $765,000 in preconstruction cost.
In lieu of Hensel Phelps submitting for our entire cost as a result of the key issues above we request
that Kalahari allows us to bill for the outstanding preconstruction balance of$112,963 and to retain
permanently the agreed upon 25%give back if awarded the Construction phase.
Hensel Phelps appreciates the compliments made by Mr. Nelson and members of the Kalahari
Team who recognize and appreciate the expertise, hard work and dedication the Hensel Phelps
team has put forth to get the project in the position it is today. We appreciate your continued
support and the efforts of the entire project team to bring this project to a successful completion.
Should there be any questions regarding the above, please contact the undersigned.
If you concur with our proposed resolution to the extended preconstruction services please sign
and process the attached pay application.
Sincerely,
HENSEL PHELPS CONSTRUCTION CO.
Michael Orlowski
Project Executive