CM-2023-268 - 11/3/2023�IQ T4l[!1s —. 01l16 Department: Project Name: Lake Creek Wastewater Line Replacement Date: 2/23/23 Change Order/Quantity LC1P1 Adjustment No. 2 Austin Underground, Inc. P. O. Box 5650 - Lago Vista, Texas 78645 (512) 535-3285 Company Name Address Phone No, Contract Quantity Adjustment/ Change Order City Project 1D Number Vendor Page 1 0173 UES iustiflcation Change Order/Quantity Adjustment No. 2 is for asphalt and sidewalk repair across and along Round Rock West Drive SUMMARY original Contract Price: Previous Quantity Adjustment(s): This Quantity Adjustment: Total Quantity Adjustment(s): Total Contract Price with Quantity Adjustment(s): Previous Change Order($): This Change Order: Total Change Order(s) To Date: Adjusted Contract Price (Original Contract Price Plus Quantity Adjustment(s) Plus Change Order(s)): Difference between Original and Adjusted Contract Prices: Original Contract Time: Time Adjustment by previous Quan. Adj./Change Order: Time Adjustment by this Quan. Adj./Change Order: New Contract Time: 0 Amount % $0.00 $0.00 $22,764.20 1% $15,981.63 OMo $38 745.83 1% $3 629 915.83 $38,745.83 Valentin 1 Contractor: Gomez,lr. «. """'" Valentin Gomez, Project Manager,Austin Underground , Inc_. Signature Printed Name, Title, Company Date City Project Manager: nature Mang er ignature _ Eddie Zapata, Senior Project Manager Printed Name, Title _ Laurie Hadlt�, City Manager Printed Name, Title Date Date I'Agc � Ol .1 Contract Quantity Adjustment/Change Order fly. 4'J li Project Name: Lake Creek Wastewater Line Replacement Quan. Adj./Change Order No. Chamne Order Data Item A Item Descri tion Unit Unit Price Amount Contract Time Adjustment CO 2-1 Asphalt Repair SY 42 $108.00 4 S36.00 CO 2-2 Sidewalk Replacement 4' SY 5 $308.00 $1 540.00 CO 2-3 Sidewalk Replacement 5' SY 6 $301.00 $1,806.00 CO 2-4 Curb and Gutter LF 22 $98.00 2 156.00 CO 2-5 Asphalt M! ling SY 34 $52.00 11,768.00 CO 2-6 VXlDinQ Double Yellow Thermoplastic LF 10 $180.00 1800.00 CO 2.7 Trudtin LS 1 $395.63 $395.63 CO 2-8 Traffic Controls LS 1 1580.00 5.80.00 CO 2-9 Mobilize Paving Equipment LS 1 $1,400.00 $1,400.00 TOTALS: 15 9a1.63 0 Fait i ui A Po— Contract Quantity Adjustment/Change Order .;... Ul i Project Name: Lake Creek Wastewater Une Replacement Quantity AdjustmentData 1 Iu 1 1 �