Project Name: Brushy Creek Regional Water Treatment Plant, Phase 1A
Contractor: Pepper-Lawson Construction(PLC) Date: 3/14/2013
Engineer: CDM Smith, Inc. Change Order No. 6
Justification
Change Order #6 captures costs associated with CPRs #32, #49, #51, #63, #64, and #68; the contract time extensions associated
with these changes; and, amounts associated with Base Bid Items#7, #8,and #10,
SUMMARY Amount %Chan e
Original Contract Price: $47,323,000.00
Previous Quantity Adjustment(s): $0.00
This Quantity Adjustment: $0.00
Total Quantity Adjustment(s): $0.00
Total Contract Price with Quantity Adjustment(s) $47,323,000.00 fah + ?
Previous Change Order(s): $335,821.81 0.710/a
This Change Order: $0.00 0.000/0
Total Change Orders)To Date: $335,821.81 0.71%
Original Contract Price Plus Change Order(s) Plus
Quantity Adjustment(s): $47,658,821.81
Original Contract Time(Substantial Completion): 840 Calendar Days March 21, 2012
Original Contract Time(Final Completion): 930 Calendar Days June 19, 2012
Contract Time Prior to this Change Order(Substantial Completion): 938 Calendar Days June 27, 2012
Contract Time Prior to this Change Order(Final Completion): 1,095 Calendar Days December 1,2012
Contract Time with All Approved Change Orders(Substantial Completion): 938 Calendar Days June 27, 2012
Contract Time with All Approved Change Orders:(Final Completion): 1,104 Calendar Days December 10, 2012
- •s�F.yH , �. c vim.:
Sign4tures 200.AP�jvVals.
Pre ared B P l:.. 1 <
ret Printed Name,Title and Company Date
Contractor Jason Lawson, President
Approval: ,rte Pepper-Lawson Construction L.P May i5 2013
//�Signature Printed Name,Title and Company Date
BCRUA 1
Approval:
igna r Printed Name,Title Date
BCRUA
Approval:
Signature Printed Na e,Title Date
w
BRUSHY CREEK
REGIONAL UTILITY AUTHORITY
A Parcnersn+p rxf C eda r Park. Leander. —d gt—d R u[k
CHANGE ORDER NO. 6
DATE OF ISSUANCE: March 14. 2013 EFFECTIVE DATE:
OWNER: Brushy Creek Regional Utility Authority (BCRUA)
CONTRACTOR: Pepper-Lawson Construction(PLC)
PROJECT: Brushy Creek Regional Water Treatment Plant- Phase I Project
ENGINEER: CDM Smith, Inc.
The Contractor is hereby directed to make the following changes in the Contract Documents:
L CPR No. 32 Revision I - Additional Sample Pump at Clearwell, Pipeline, and Chlorine
Analyzer(Owner Request)
ADD $485380.00
ADD 7 CALENDAR DAYS TO FINAL COMPLETION
2. CPR No. 49 Revision 1 - TSC Laboratory Sink Faucet Modifications (Engineer
Recommendation)
ADD $348.00
3. CPR No. 51, Revision I - Sodium Hypochlorite Discharge Piping Modifications (Owner
Request)
ADD $3,679.00
ADD I CALENDAR DAYS TO FINAL COMPLETION
4. CPR No. 63 - Sludge Pump Station Level Indicating Transmitter Device (SLSP-LIT-001)
(Owner Request)
ADD $3,690.00
5. CPR No. 64 -- Modifications to Booster Pump Warning and Alarm Relays (Contractor
Recommendation)
ADD $3,557.00
ADD I CALENDAR DAYS TO FINAL COMPLETION
Brushy Creek Regional Water Treatment Plant, Phase 1A
Change Order No. 6
Page 1 of 3
W Ab
EBRUSHYCREEK
REGIONAL UTILITY AUTHORITY
A Partnership of Cedar Park, Leander. and Aound Rock
6. CPR No. 68 .. Sell Office Furnishings used in the BCRUA Trailer(Owner Request)
*Note that the specified cleaning and trash disposal requirements in
Section 0150012.01.B.5 shall be transferred to the Administrative Level of the Treatment
Structure.
7. Base Bid Item No. 7 — Additional Miscellaneous Site Improvements Per Section
01026/1.06.E, this amount reflects partial amount due to Contractor for work performed.
DEDUCT $31,859.00
8. Base Bid Item No. 8 Additional Landscaping Improvements. Per Section 0I026/1.07.B,
this amount reflects actual amount due to Contractor for work performed.
DEDUCT $26,297.00
9. Base Bid Item No. 10 - Natural Gas Line Extension. Per Section 01026/1.09.B, this
amount reflects actual amount due to Contractor for work performed.
DEDUCT $1,498.00
TOTAL (Items 1 - 9)NO COST CHANGE
ADD 9 CALENDAR DAYS TO FINAL COMPLETION, REVISED DATE:
DECEMBER 10, 2012
Brushy Creek Regional water Treatment Plant,Phase I
Change Order No.6
Page 2 of 3
0 W*b
XBRUSHYCREEK
REGIONAL UTILITY AUTHORITY
A Partnership of Cedar Park. Le—der. and Round R o c k
CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIME:
Original Contract Price: Original Contract Times:
Substantial Completion(Days):840 Calendar Days
47,323,000.00 Substantial
Completion (Days): 930 Calendar Days
Substantial Completion (Date): March 21 2012
Final Completion(Date): June 19,2012
Net Increase(Decrease) from previous Change Orders Net change from previous Change Orders No. 1 to No. 5
No. 1 to No. 5 Substantial Completion(Days): 98 Calendar days
Final Completion(Days): 165 Calendar days
$ 335.821.81 Substantial Completion(Date): June 27,2012
Final Completion(Date): December 1,2012
Contract Price prior to this Change Order: Contract Times prior to this Change Order:
Substantial Completion (Days):938 Calendar Days
$ 47 658 821.81 Final Completion(Days): 1,095 Calendar Days
Substantial Completion(Date): June 27 2012
Final Completion(Date): December 1,2012
Net increase/decrease of this Change Order: Net increase(decrease)this Change Order:
Substantial Completion(Days): 0 Calendar days
$ 0 Final Completion(Days): 9 Calendar days
Substantial Completion(Date): fune 27,2012
Final Completion(Date): December 10,2012
Contract Price with all approved Change Orders: Contract Times with all approved Change Orders:
Substantial Completion (Days):938 Calendar Days
$ 47„658,821.81 Final Completion(Days): 1,104 Calendar Days
Substantial Completion(Date):June 27,2012__
Final Completion (Date): December 10,2012