Loading...
GM-15-07-16-056 SUPPLEMENTAL CONTRACT NO.1 TO THE CONTRACT FOR ENGINEERING SERVICES FIRM: HDR Engineering,Inc.("Engineer") ADDRESS: 4401 West Gate Blvd,Suite 400,Austin,TX 78745 PROJECT: Re-Commission of the Floating Pump Station This Supplemental Contract No.1 to Contract for Engineering Services is made by and between the BRUSHY CREEK REGIONAL UTILITY AUTHORITY,INC.,hereinafter called"BCRUA"and HDR Engineering, Inc.,hereinafter called the"Engineer". WHEREAS,BCRUA and Engineer executed a Contract for Engineering Services,hereinafter called the "Contract",on the 9h day of December,2014 for Re-Commission of the Floating Pump Station in the amount of$49,800;and WHEREAS,it has become necessary to amend the Contract to modify the provisions for the scope of services and to increase the compensation by$18,700.00 to a total of$68,500.00;and NOW THEREFORE,premises considered, BCRUA and the Engineer agree that said Contract is amended as follows: I. Article 2,Engineering Services and Exhibit B,Engineering Services shall be amended as set forth in attached Addendum to Exhibit B. II. Article 4,Compensation and Exhibit D,Fee Schedule shall be amended by increasing the$49,800.00 amount payable under the Contract for a total of$68,500.00 as shown in the attached Addendum to Exhibit D. IN WITNESS WHEREOF,BCRUA and Engineer have executed this Supplemental Contract in duplicate. OWNER: Brushy Creek Regional Utility ENGINEER: HDR Engineering,Inc. Authority,Inc. 01 By: Tort 6,qUier By. 4"Oyl / Title: General Manager Title: L _l' Date Signed: 07/16/2015 Date Signed: elm', 5-0-7,I ta6FCv ADDENDUM TO EXHIBIT B ENGINEERING SERVICES BASIC SCOPE OF SERVICES Task 1.0—Design Phase 1.21 Incorporate the City of Round Rock Agreement(00500),General Conditions (00700),and Supplemental General Conditions(00800)into the Construction Specifications. Review and modify these documents as required for implementation of a BCRUA project. Prepare additional Supplemental General Conditions as required for the Project. Include project-specific insurance requirements for equipment owned by BCRUA but being transported,stored,and recommissioned by the Contractor.Modify Specification Sections 00020,00100, and 00301 to correctly reference the adopted City of Round Rock front end specifications. Coordinate review of all modifications to the project front end specifications with BCRUA legal counsel. 1.22 Coordinate with Owner for the development and review of proposals from Neltronics and CH2MHill to support start-up and commissioning of SCADA and control elements of the Project. Owner shall contract with these contractors separately. 1.23 Prepare Drawings to replace the low voltage power and control conductors that were buried and submerged and are not recoverable as part of the project. The conductors will be replaced from the manhole adjacent to the City of Cedar Park WTP and BCRUA electrical building to the floating raw water barge. Task 3.0—Construction Phase 3.10 Shop Drawings and Samples. Review and approve shop drawings for the replacement of the low voltage power and control conductors. 6/25/2015 ADDENDUM TO EXHIBIT D FEE SCHEDULE The total compensation for services under Supplemental Agreement No. 1 is estimated to be$18,700. OWNER shall pay ENGINEER for Basic Services described in Addendum to Exhibit B on the basis of Direct Labor times a factor as described in Paragraph Al of Exhibit D of the Contract. Total compensation shall be adjusted to be$68,500. 6/25/2015 ��� Brushy Creek Regional Utility Authority Raw Water Intake Barge Recommissioning Supplemental Amendment No.1 Labor Summary Project Senior OC Senior Admin Total Manager Engineer Reviewer Technician Support Hours TASK DESCRIPTION -- 1.0 Design Phase 1.21 40 d 4- 12 _ 60 1.22 6 2 - ------~ --2^ 10 1.23 2 8 8 4 22 TASK SUBTOTAL J48 14 4 8 18 92 3.0 Construction Phase 3.1 1 4 2 7 TASK SUBTOTAL 1 4 0 0 2 7 Total Hours 49 18 4 8 20 99 Fee Summary Total Fee TASK DESCRIPTION - 1.0 Design Phase 1.21 $ 10,_500 1.22 -.__-------------- $ ---._2.200 1.23 $ 4.500 TASK SUBTOTAL $ 17,200 3.0 Construction Phase 3.1 $ 1.500 TASK SUBTOTAL $ 1,500 Total Fee S 18,700