GM-20-04-03-0871 Supplemental Contract Rev. 03/2011 0140.4634-40; 00443170 215829 SUPPLEMENTAL CONTRACT NO. 10 TO CONTRACT FOR ENGINEERING SERVICES FIRM: WALKER PARTNERS (“Engineer”) ADDRESS: 804 Las Cimas Parkway, Suite 150, Austin, TX 78746 PROJECT: Phase 1C Water Treatment Plant Expansion and Phase 2 Land Rights and Stakeholder Coordination This Supplemental Contract No. 10 to Contract for Engineering Services is made by and between the BRUSHY CREEK REGIONAL UTILITY AUTHORITY, INC., hereinafter called “BCRUA” and Walker Partners, hereinafter called the “Engineer”. WHEREAS, BCRUA and Engineer executed a Contract for Engineering Services, hereinafter called the “Contract”, on the 19th day of April, 2017 for the BCRUA Phase 1C Water Treatment Plant Expansion in the lump sum amount of $1,763,900.00 and Phase 2 Land Rights and Stakeholder Coordination Project in the maximum amount of $2,012,600.00 for a total Project compensation of $3,776,500.00; and WHEREAS, BCRUA and Engineer executed Supplemental Contract No. 1 on July 19, 2017 to amend the scope of services and to increase the compensation by $14,100.00 for Phase 1C Water Treatment Plant Expansion to a lump sum amount total of $1,778,000.00 and by $212,000.00 for Phase 2 Land Rights and Stakeholder Coordination Project to a maximum amount total of $2,224,600.00 for a total Project compensation of $4,002,600.00; and WHEREAS, BCRUA and Engineer executed Supplemental Contract No. 2 on November 20, 2017 to amend the scope of services and to increase the compensation by $19,600.00 for Phase 1C Water Treatment Plant Expansion to a lump sum amount total of $1,797,600.00 for a total Project compensation of $4,022,200.00; and WHEREAS, BCRUA and Engineer executed Supplemental Contract No. 3 on April 18, 2018 to amend the scope of services and to increase the compensation by $105,200.00 for Phase 2 Land Rights and Stakeholder Coordination Project to a maximum amount total of $2,329,800.00 for a total Project compensation of $4,127,400.00; and WHEREAS, BCRUA and Engineer executed Supplemental Contract No. 4 on October 24, 2018 to add the construction phase services for the Phase 1C Construction Phase Services Project and to increase the compensation by $897,200.00 for a total Project compensation of $5,024,600.00; and 2 WHEREAS, BCRUA and Engineer executed Supplemental Contract No. 5 on April 30, 2019 to modify the provisions for the scope of services and to increase the compensation by $40,300.00 for Phase 1C Water Treatment Plant Expansion to a lump sum amount total of $2,735,100.00 for a total Project compensation of $5,064,900.00; and WHEREAS, BCRUA and Engineer executed amended Supplemental Contract No. 6 on September 25, 2019 to modify the provisions for the scope of services and to increase the compensation by $497,885.00 for Phase 2 Land Rights and Stakeholder Coordination Project to a maximum amount total of $2,827,685.00 for a total Project compensation of $5,562,785.00; and WHEREAS, BCRUA and Engineer executed Supplemental Contract No. 7 on November 15, 2019 to modify the provisions for the scope of services and to increase the compensation by $49,400.00 for Phase 2 Land Rights and Stakeholder Coordination Project to a maximum amount total of $2,877.085.00 for a total Project compensation of $5,612,185.00; and WHEREAS, BCRUA and Engineer executed Supplemental Contract No. 8 on November 20, 2019 to modify the provisions for the scope of services and to increase the compensation by $447,880.00 for Phase 2 Land Rights and Stakeholder Coordination Project to a maximum amount total of $3,324,965.00 for a total Project compensation of $6,060,065.00; and WHEREAS, BCRUA and Engineer executed Supplemental Contract No. 9 on January 22, 2020 to modify the provisions for the scope of services and to increase the compensation by $498,590.00 for Phase 2 Land Rights and Stakeholder Coordination Project to a maximum amount total of $3,823,555.00 for a total Project compensation of $6,558,655.00; and WHEREAS, it has become necessary to amend the Contract to modify the provisions for the scope of services and to increase the compensation by $38,608.00 for Phase 1C Water Treatment Plant Expansion to a lump sum amount total of $2,773,708.00 for a total Project compensation of $6,597,263.00; NOW THEREFORE, premises considered, BCRUA and the Engineer agree that said Contract is amended as follows: I. Article 2, Engineering Services and Exhibit B, Engineering Services shall be amended as set forth in the attached Addendum To Exhibit B. Exhibit C, Work Schedule shall be amended as set forth in the attached Addendum To Exhibit C. II. Article 4, Compensation and Exhibit D, Fee Schedule shall be amended by increasing by $38,608.00 the lump sum amount payable under the Contract for Phase 1C Water Treatment Plant Expansion Project to a total of $2,773,708.00 for a total Project compensation of $6,597,263.00, as shown by the attached Addendum to Exhibit D. 3 IN WITNESS WHEREOF, BCRUA and the Engineer have executed this Supplemental Contract in duplicate. [signature pages follow] 4 WALKER PARTNERS By: Date George E. Walker, Jr., President April 3, 2020 4/3/2020 3/30/2020 ADDENDUM TO EXHIBIT B  ENGINEERING SERVICES    GENERAL  The purpose of Supplemental Amendment No. 10 is to address additional services requested by the  OWNER for the Phase 1C WTP Expansion project. The additional services include design and  construction administration required to change order the proposed improvements into the Phase 1C  WTP Expansion construction contract as described in the Basic Scope of Services.    BASIC SCOPE OF SERVICES  Task 1.0 ‐ Phase 1C WTP Expansion  Insert Task 1.8 as follows:   1.8 Phase 1C Additional Services  1.8.1 Finished Water Booster Pump Station (FWBPS) Pump Control Valve Replacement.  1.8.1.1 Develop  design  documents,  including  drawings  and  specifications,  necessary  to  replace  three  existing  pump  control  valves  with  diaphragm‐style control valves.   1.8.1.2 Provide construction phase services required to complete the proposed  improvements as a change order to the WTP construction contract.  1.8.2 Water Quality Analyzer Replacement  1.8.2.1 Specify  new  chlorine  residual  analyzers  and  turbidimeters  to  replace  aging units at the WTP and reduce the associated waste stream to the  City of Cedar Park sewer system.  1.8.2.2 Provide construction phase services required to procure new analyzers  as a change order to the WTP construction contract. The OWNER will  provide installation and programming required for the new analyzers.  1.8.3 WTP Programmable Logic Controller (PLC) Replacement  1.8.3.1 Assist replacement of three existing PLCs at the WTP, which have been  causing control program issues and are considered obsolete hardware.  The  OWNER  will  select  the  models  for  the  new  PLC  processors  and  associated redundancy modules.  1.8.3.2 Provide construction phase services required to complete the proposed  improvements as a change order to the WTP construction contract.            3/30/2020 ADDENDUM TO EXHIBIT C  WORK SCHEDULE    The engineering services will be provided during the Construction Phase Work Schedule described  in Supplemental Amendment No 4.  ADDENDUM TO EXHIBIT D Fee Schedule Attached Behind This Page 3/30/2020 ADDENDUM TO EXHIBIT D  COMPENSATION    Total compensation for services under Supplemental Amendment No. 10 is estimated to be $38,608.  Total compensation for Task 1.0 – Phase 1C WTP Expansion shall be adjusted to be $2,773,708. Total  compensation for the Project shall be adjusted to $6,597,263.  OWNER shall pay ENGINEER for Task 1.8 set forth in Supplemental Amendment No. 10 on the basis of  Standard Hourly Rates as described in Paragraph 1.0 of Exhibit D of Supplemental Amendment No. 4.