GM-23-01-12-108 W§ 06
EBRUSHYCREEK
REGIONAL UTILITY AUTHORITY
A pd r LI.I I I of Gado, ■a.Y, lea n d e r, and R,un6 Rn,l
SUPPLEMENTAL CONTRACT NO. 1
TO CONTRACT FOR ENGINEERING SERVICES
FIRM: WALKER PARTNERS ("Engineer")
ADDRESS: 804 Las Cimas Parkway, Suite 150,Austin,TX 78746
PROJECT: ErnergeneV Repair of the Phase 1A Contract 2 Raw Water Pipeline
This Supplemental Contract No. 1 to Contract for Engineering Services is made by and between
the BRUSHY CREEK REGIONAL UTILITY AUTHORITY, INC., hereinafter called
"BCRUA" and Walker Partners,hereinafter called the"Engineer."
WHEREAS, BCRUA and Engineer executed a Contract for Engineering Services, hereinafter
called the"Contract," on the 28th day of September,2022 for the Emergency Repair of the Phase
IA,Contract 2 Raw Water Pipeline Project in the amount of$75,200.00; and
WHEREAS, it has become necessary to amend the Contract to modify the provisions for the
scope of services and to increase the compensation by$48,200.00 to a total of$123,400.00;
NOW THEREFORE, premises considered, BCRUA and the Engineer agree that said Contract
is amended as follows:
I.
Article 2, Engineering Services and Exhibit B, Engineering Services shall be amended as set
forth in the attached Addendum To Exhibit B. Exhibit C, Work Schedule shall be amended as
set forth in the attached Addendum To Exhibit C.
11.
Article 4, Compensation and Exhibit D, Fee Schedule shall be amended by increasing by
$48,200.00 the maximum amount payable under the Contract for a total of $123,400.00, as
shown by the attached Addendum to Exhibit D.
IN WITNESS WHEREOF, BCRUA and the Engineer have executed this Supplemental
Contract in duplicate.
[signature pages followl
Supplemental Contract Rev.03/2011
0140.4634-59;4884-8195-9241 215829
WALK R PAR' S
By: -
01/11/23
Date
I
2
BRUSHY CREEK REGIONAL UTILITY AUTHORITY, INC.
By:
Karen Bondy,Ge al Manager
01/12/2023
Date
APPROV S TO FORqe6L—.---
Stephan V. Sheets,BCRUA Attorney
i
3
ADDENDUM TO EXHIBIT B
Engineering Services
GENERAL
The purpose of Supplemental Amendment No. 1 is to assist Owner with claims against W.L. Hailey
and Jacobs regarding damages sustained by Owner due to failure of the Phase 1A, Contract 2
underwater 36-inch diameter pipeline.
BASIC SCOPE OF SERVICES
Task 2—Litigation Support and Expert Witness Testimony
2.1 Project Administration. Manage and coordinate staff resources and project planning and
prepare monthly invoices.
2.2 Project Meetings. Coordinate and attend up to six meetings with Owner and Owner's legal
counsel as required. Provide up to three status presentations to Owner's Board.
2.3 Litigation Support Services.
2.3.1 Respond to production requests during the pre-trial discover process. Information
will be assembled and provided as required by civil procedure. Such information
may include but is not limited to technical design calculations and drawings,
communication and correspondence, and supporting documentation.
2.3.2 Review materials prepared by other parties in the case and prepare responses as
required.
2.3.3 Assist in the development of a direct examination case.
2.3.4 Develop exhibits offered at the hearing as required by Owner's legal counsel.
2.3.5 Prepare for oral depositions and review deposition transcripts.
2.3.6 Prepare for and provide testimony at a judicial proceeding as a consultant or
witness if required.
i
i
1/1112023 QWAer Partners
engineers * surveynrs
ADDENDUM TO EXHIBIT C
Work Schedule
It is anticipated that Basic Services will be required for a duration of approximately nine months.
I
+
1/11/2023 QWAer Partners
engineers • suryeyor-�
i
{
ADDENDUM TO EXHIBIT D
Fee Schedule
Total compensation for services under Supplemental Amendment No. 1 is estimated to be $48,200.
OWNER shall pay ENGINEER for Basic Services on the basis of Standard Hourly Rates as described in
Paragraph 2.0 of Exhibit D Compensation of the original Agreement,
Total compensation for the Project shall be adjusted to$123,400.
J
I
1/11/2023 Eenlker Partners
r ineers* surveyors
I
0140.4634-59
BRUSHY r D r-EK
REGIONAL UTILITY AUTHORITY
A IP In*..Ml• t G.#a. J1 irk, L..na*r, .w1 Ft T.l it-1
LEGAL DEPARTMENT APPROVAL FOR BOARD/GENERAL MANAGER ACTION
Required for Submission of ALL Board and General Manager Items
Emergency Repair of the phase 1A,
Project Name: Contract 2 Raw Water Pipeline ContractorNendor: Walker Partners
Board Action:
Agenda Wording
General Manager Approval:
GMA Wording
Consider executing Supplemental Contract No 1 with Walker Partners for the Emergency Repair of the Phase 1A,
Contract 2 Raw Water Pipeline Project.
Attorney Approval
Attorney m�� Date4Q, �
Notes/Comments
C:IUserslrmcmillin\ND Office Echo1VAULT-D6RSLZUWILAF-SC#1 with Walker Partners-Emergency Repair of
the Phase 1A, Contract 2 Raw Water Pipeline 4893-8072-0457 v.1 Updated 613108