BCRUA_R-11-02-23-7A RESOLUTION NO. R-11-02-23-7A
WHEREAS, the Brushy Creek Regional Utility Authority, Inc. (`BCRUA") has
previously entered into a contract ("Contract') with S.J. Louis Construction of Texas LTD. for
the 78-Inch Treated Water Transmission Line Segment One Project, and
WHEREAS, the BCRUA has determined that it is necessary to make changes to the
quantity of work to be performed or materials, equipment, or supplies to be provided, and
WHEREAS, it has been determined that it is necessary to change said Contract in
accordance with the attached Contract Change Order No. 1,Now Therefore
BE IT RESOLVED BY THE BRUSHY CREEK REGIONAL UTILITY
AUTHORITY,
That the Board President is hereby authorized and directed to execute on behalf of the
BCRUA, Change Order No. 1 to the Contract with S.J. Louis Construction of Texas LTD. for the
78-Inch Treated Water Transmission Line Segment One Project, a copy of same being attached
hereto as Exhibit "A"and incorporated herein for all purposes.
The Board hereby finds and declares that written notice of the date, hour, place and
subject of the meeting at which this Resolution was adopted was posted and that such meeting
was open to the public as required by law at all times during which this Resolution and the
subject matter hereof were discussed, considered and formally acted upon, all as required by the
Open Meetings Act, Chapter 551, Texas Government Code, as amended.
RESOLVED this 23rd day of February, 2011.
MITC FULL R, President
Brushy Regional Utility Authority
TT ST:
Join Cowman, Secretary
Z. CRUA\Board Packets\Packet Documents\022311\Res.BCRUA Change Order_I w-Sl Louis Construction(00214972)[1].DOCtrmc
SRM CREED
REGIONAL UTILITY AUTHORITY
w FI,%a a ralI 4t r*4 At F—u. La as qer.red MevAd Reek
CHANGE ORDER No. 1
DATE OF ISSUANCE: 12/07/10 EFFECTIVE DATE:
OWNER. BCRUA
CONTRACTOR: S.J.Louis Construction
PROJECT: 78-Inch Treated Water Transmission Line Segment One
ENGINEER: Lockwood,Andrews,and Newnam,Inc.
The Contractor is hereby directed to make the following changes in the Contract:Documents:
1. Extension of tunnel at New Hope Drive and New Flope Spur to facilitate water line tunnel installation.
Under underground telephone and gas lines.
ADD OR HE°I'UCT$ 58,664.00
TOTAL(Items t -2) ADD 0R-DkI3UC T$ 58.664.00
Page i
Project:78-Inch Treated Water Transmission:Line Segment One
Change Order No. 1
CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIME:
Original Contract Price: Original Contract Times:
Substantial Completion(Days): 460
$ 8,134.941.13 Final Completion(Days): 550
Substantial Completion(Date): 7/16/11
Final Completion(Date): 8/14/11
Net Increase(Decrease)from previous Change Orders Net change from previous Change Orders No.Oto No._
No. to No. Substantial Completion(Days): N/A
Final Completion(Days): N/A
$ N/A Substantial Completion(Date): N/A
Final Completion(Date): N/A
Contract Price prior to this Change Order: Contract Times prior to this Change Order:
Substantial Completion(Days): 460
$ 8.134.941.13 Final Completion(Days): 550
Substantial Completion(Date): 7/16/11
Final Completion(Date): 8/14/11
Net increase(decrease)of this Change Order: Net increase(decrease)this Change Order:
Substantial Completion(Days): 0
$ 58.664.00 Final Completion(Days): 0
Substantial Completion(Date): 7/16/11
Final Completion(Date): 8/14/11
Contract Price with all approved Change Orders: Contract Times with all approved Change Orders:
Substantial Completion(Days): 460
$ 8.193.605.13 Final Completion(Days): 550
Substantial Completion(Date): 7/16/11
Final Completion(Date): 8/14/11
RECOMMENDED BY: ACCEPTED BY:
By: '" By:
ENGINEER CONTRACTOR
Date: Date:
APPROVED BY: MANAGEMENT REVIEW:
By: By: ---
BCRUA Construction Manager BCRUA General Manager
Date: l-,.I y - fl Date:
K:AWAK020Mexecutionlchange orders\draft change order template.doc
Page 2
Lockwood,Andrews
&Newnan,Inc.
A LEO A QALY COMPANY
December 6,2010
'Org
Mr.Michael Thuss,PE
Brushy Creek Regional Utility Authority
221 E.Main Street
Round Rock, TX 78664
RE: Brushy Creek Regional Utility Authority
Treated Transmission Line Segment One
Request for Deviation#6
Mr. Thuss:
LAN has reviewed SJ Louis' Request for Deviation#6. The proposed tunnel extension is
acceptable with the following exception. Ring beam and lagging outside of the existing
ROW should be removed after the water line has been installed and the extended
tunneled area should be back filled with Plowable fill to eliminate voids.
LAN has also reviewed the cost submitted and finds that it is reasonable for the proposed
change. LAN recommends the BCRUA accept the request for deviation with the
exception noted in the previous paragraph.
Sincerely,
Alisa Gruber,PE
Project Engineer
Attach: RFD#6 dated 1.1/24/10
10101 Peunion Place,Suite 200 • San Antonio,Texas 78216-4165 • 210.499.5082 - Fax: 210-499.5157 • www.lan-inc.00m
BRUSHY CREEK REGIONAL UTILITY AUTHORITY
78°TREATED WATER TRANSMISSION LINE —SEGMENT 1
DATE: November 24,2010 RFD No.: 6
T17: LAN ATTN• JULIE,D.HASTINGS,P.E.
10801 NORTH MOPAC EXPRESSWAY
BUILDING 1,SUITE 120
AUSTIN,TX 78759
Please see the attached letter.
0 ADDITIONAL COMMENTS ATTACHED
November 24 2010
SIGNATURE DATE
CURTIS A.OSTRANDER P.E. PROJECT MANAGER
PRINTED NAME TITLE
k a 3
RESPONSE ATTACHED
A USE ONLY
❑LOGGED IN 13RESQ RECORDED LILOGGED OUT SIGN A RE DATE
DISTRIBUTED TO: ) 0}I "7 7c_Yo I t
RESPONSE DUE BY: PRINTED NAME TITLE
RETURNED TO CONTRACTOR ON:
01800-FORMS.doc A 24-Nov-10
S.J.LOUIS CONSTRUCTION OF TEXAS LTD.
9862 Lorena St.,Suite 200 2101340-9998 office•2101340-9997 Fax
San Antonio,TX 78216 Equal opportunity Employer 1 Contractor
November 24, 20.10
L
Mr.Michael Thuss, P.E.
Brushy Creek Regional Utility Authority
221 E.Main Street
Round Rock,Texas 78664
Re: Brushy Creek Regional Utility Authority(BCRUA)
78-Inch Treated Water Transmission Line Segment One
RFD#6—Utility Conflict C Station 37+30
Mr.Thuss:
Please consider this letter a Request for Deviation regarding the installation of the tunnel located
at Station 37+34.75 on the reference project. SJ Louis conducted a utility investigation which
revealed a gas main and an underground telephone line that are not shown on the plans at
approximate Station 37+30 (see attached utility log). These utilities are in direct conflict with
the bore pit that is required to tunnel across New Hope Road.
Several options have been discussed with LAN and BCRUA representatives to resolve this
conflict. It is believed that the solution that has the least impact to the project involves extending
the tunnel back from New Hope to a point where the bore pit will not be in conflict with the
existing utilities. Other options were presented but they involved damage and repair to City of
Cedar park streets. Based on the response Cedar .Park representatives, these options were not
pursued.
The tunnel. extension process would include standard tunneling in accordance with the contract
documents to a point 53' further than the beginning point shown in the plans. Once the tunnel is
complete, trenching for the installation of the pipe would break into the ring beam and lagging
and the pipe would be installed per plan. The remaining length (approximately 40') of additional
tunnel would then be filled with flowable fill.
The costs associated with this deviation from the plan include additional tunneling, removal of
additional spoils, installation of ring beam and lagging and installation of flowable fill. This cost
is calculated as follows: bid price for 78-Inch Water Line in Tunnel (Gann Ranch) less the cost
of pipe and associated items plus the cost of flowable fill for the abandoned additional tunnel.
The bid price for 78-Inch Water Line in Tunnel (Gann Ranch) is $1.575.00/LF of which$575,00
is. associated with the pipe materials and installation. including welding, weld testing,
rails/spacers and grouting the annular space. This puts the cost of the tunnel at $1,000.00/LF.
Using a length of 53 LF gives a total cost of additional tunnel of$53,000.00. The volume of
flowable fill needed to fill the abandoned additional tunnel can be calculated for the 9-foot
diameter tunnel to be 2.36 CY/LF. Assuming 40 LF of tunnel will require flowable fill and a
unit price of$60:00/CY, this gives a cost of flowable fill of $5664.00.
If approved, the total cost of this Request for Deviation to resolve the existing utility conflict
would be$58,664.00.
Should you have any questions or require additional information, please do not hesitate to call.
Regards,
S.J.LOUIS CONSTRUCTION OF TEXAS LTD.
Curtis A, Ostrander-P.E.
Project Manager
Station De pth Utility Notes Conflict
Plan Field Plan Held (YeslNo
10+36 10+15 7.5' 6.0' WW No
18+4.1 18+42 4:5" 35' 8"W No
18+79 18+67 10.0' 11.0' 6"SS T Clearance Will Not Be Achieved Yes
19+00 3.5' 4"UE CONDUIT No
22+77 3.5' 4"UE CONDUIT N0
27+13 5.0' 24"SD No Apparent Utility At This Locati No
27+85 6"'G,LIT 14'LEFT(RUNS PARALLEL)Not Vertically Feld Located No
29+64 29+64 6.5 8.0' r W T Clearance Will Not Be Achieved Yes
30+20 5.0' 24"SD No
32+00 6"G,UT 9' 'T(RUNS PARALLEL) Not Vertically Field Located No
32+39 7.5' 8"W F13 Branch Not Meld Located No
34+00 WG.UT 25'LEFT(RUNS PARALLEL Not Verticals Field LiKated No
34+64 7.0' 8"W IN.,Marked,Not Fie►d.Located Unknown
37+30 4.0' 6"G,6'SS,4"UT In Bore Pit Yes
37+53 .3.0' UT Not Feld Located
37+83 4.0' 6"G Not Feld Located
37+90 3.0' UE Not Field Located
38+49 38+49 6.5' 8.0' 36"SD No
38+76 5.0' 16"W Not Field Located
39+08 3A' UE Not Field Located
39+1.4 ? 8"W Not Field Located
39+42 39+42 5.0' 6.0' 24"SD No
41+30 15.0' SD MH On Centerline Yes
41+47 3.0' UE Not Field Located
41+80 ? SD MH,UIS 50 UT No Inlets As Shown on Plans
41+92 12.0' SD BOX Does Not Exist 1n Feld
42+75 42+72 ? 4.5' 8"W(ABANDONED'?) No
42+81 (i.0' 81,W Not Field Located
42+83 10.0' 42"SS Does Not Exist In Field No
42+91 42+91 8.5' 8.0" 8"SS No
47+22 7.0' 8"W FH Branch Not Field Uxated No
48+12 3.(Y UE Not I field Located
53+17 7.0' 8"W FN Branch Not field Located No
53+30 53+40 12.0' I I A' 8"SS No
54+53 6.5' 12"W(ABANDONED") Not Field Located No
54+58 54+58 6.51 5.0' 12"W No
i5+32 3.0' UE Not Field Located
59+32 7.0' 8"W FH Branch Not Feld Located No
00+76 6.0' UT,UF.CONDUITS No
61+01 61+02 9.0' 6.0' 24"SD BOX No
61+18 ? UE Not Field Located
61+56 61+55 4.5' 5.0' 8"W No
61+65 4.5' 8"W Not Field Located
61+73 61+73 6.5' 7.0' 8"SS No
64+93 ? MONITORING WELL'? Offset 2'Left Yes
65+20 2.5' 2.5' 18"SD No
67+72 4.5' 1.2"W Not Held Located
68+97 7.012"SS No
69+07 ? 8"W Not Field Located
70+48 ? ?W Not Field located
70+94 ?SS Seiner Service from 12"SS Line No
71+(A ?W Not Field Located
71+16 7.0' 7.0' 18"SD No
72+14 5.0' 12-W Not Held Located
72+15 72+14 10.0' 93' 10"SS No
72+50 72+50 ZO' 8.0' ?SD No
72+65 72+70 11.51 8.0' SD MH/36"SD No
72+91 ?W Not Field Located
73+44 ?W Not Field Located
74+73 74+75 18.0' IS"SD No
7?+50 3.0' U7 No
79+15 IIS' 1 I-W 15"SS No
94+50 4.5' 8'W No
95+(X) 4.5' GAS SERVICE No
95+01 3.O' I;K, No
98+00 2.0' CE No
10(1+01 0.0' TEST STATION On Centerline Yes
Notes:
All smirked utilities were field 1iroated.
Fire hydrant leads were not'field located bceuuse they are to be removed and replaced.
Depths shown are.to top of utility except for MHs and SD boxes-those depths are MH/box inverts.
EXECUTED
DOCUMENT
FOLLOWS
' �• BRUSHY CREEJ�:�REGIONAL UTILITY AUTHOR
A Par n e r a h p o t Cedar Park, L e a n E<r, and 0.o u n U 0.
CHANGE ORDER No. 1
DATE OF ISSUANCE: 12/07/10 EFFECTIVE DATE:
OWNER: BCRUA
CONTRACTOR: S.J.Louis Construction
PROJECT: 78-Inch Treated Water Transmission Line Segment One
ENGINEER: Lockwood, Andrews,and Newnam, Inc.
The Contractor is hereby directed to make the following changes in the Contract Documents:
1. Extension of tunnel at New Hope Drive and New Hope Spur to facilitate water line tunnel installation.
Under underground telephone and gas lines.
ADD OR-BEBtfff$ 58,664.00
TOTAL(Items 1 -2) ADD OWDEDUC T$ 58,664.00
Page 1
Project: 78-Inch Treated Water Transmission Line Segment One
Change Order No.—I
—
CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIME:
Original Contract Price: Original Contract Times:
Substantial Completion(Days): 460
$ 8,134,941.13 Final Completion(Days): 550
Substantial Completion(Date): 7/16/11
Final Completion(Date): 8/14/11
Net Increase(Decrease)from previous Change Orders Net change from previous Change Orders No._to No.
No. to No. Substantial Completion(Days): N/A
Final Completion(Days): N/A
$ N/A Substantial Completion(Date): N/A
Final Completion(Date): N/A
Contract Price prior to this Change Order: Contract Times prior to this Change Order:
Substantial Completion(Days): 460
$ 8,134,941.13 Final Completion(Days): 550
Substantial Completion(Date): 7/16/11
Final Completion(Date): 8/14/11
Net increase(decrease)of this Change Order: Net increase(decrease)this Change Order:
Substantial Completion(Days): 0
$ 58,664.00 Final Completion(Days): 0
Substantial Completion(Date): 7/16/11
Final Completion(Date): 8/14/11
Contract Price with all approved Change Orders: Contract Times with all approved Change Orders:
Substantial Completion(Days): 460
$ 8,193,605.13 Final Completion(Days): 550
Substantial Completion(Date): 7/16/11
Final Completion(Date): 8/14/11
RECOMMENDED BY: ACCEPTED BY:
2..v
By: CXR By:
ENGINEER CONTRACTOR
Date: � Date: 42,
7
APPROVED BY: MANAGEMENT REVIEW:
By: By:
BCRUA Construction Manager BCRUA Giiteral Manager���
Date: fj Date: "1 "' "1 23 2 I
le-
!l•02.23 7�
:\WJ�ecution\change orders\draft change order template.doc
Page 2
Lockwood,Andrews
&Newnam, Inc.
A LEO A DALY COMPANY
December 6, 2010
09
Mr. Michael Thuss, PE
Brushy Creek Regional Utility Authority
221 E. Main Street
Round Rock, TX 78664
RE: Brushy Creek Regional Utility Authority
Treated Transmission Line Segment One
Request for Deviation#6
Mr. Thuss:
LAN has reviewed SJ Louis' Request for Deviation#6. The proposed tunnel extension is
acceptable with the following exception. Ring beam and lagging outside of the existing
ROW should be removed after the water line has been installed and the extended
tunneled area should be back filled with flowable fill to eliminate voids.
LAN has also reviewed the cost submitted and finds that it is reasonable for the proposed
change. LAN recommends the BCRUA accept the request for deviation with the
exception noted in the previous paragraph.
Sincerely,
Alisa Gruber, PE
Project Engineer
Attach: RFD#6 dated 11/24/10
10101 Reunion Place, Suite 200 San Antonio, Texas 78216-4165 210.499.5082 Fax: 210.499.5157 www.lan-inc.com
'er i u kN 4 b
0 0
BRUSHY CREEK REGIONAL UTILITY AUTHORITY
78" TREATED WATER TRANSMISSION LINE — SEGMENT 1
DATE: November 24,2010 RFD NO.: 6
TO: LAN ATTN: JULIE D.HASTINGS,P.E.
10801 NORTH MOPAC EXPRESSWAY
BUILDING 1,SUITE 120
AUSTIN,TX 78759
Please see the attached letter.
Q ADDITIONAL COMMENTS ATTACHED
% -" November 24, 2010
SIGNATURE DATE
CURTIS A.OSTRANDER,P.E. PROJECT MANAGER
PRINTED NAME TITLE
Al
RESPONSE ATTACHED
A USE ONLY
❑LOGGED IN ❑RESP RECORDED ❑LOGGED OUT SIGNA RE DATE
DISTRIBUTED TO: — ��/I 7 4�3t�r'+ ?tiE (.% _,)
RESPONSE DUE BY: PRINTED NAME TITLE
RETURNED TO CONTRACTOR ON:
- - -- . -..__.... ....... ... _._..
01800-FORMS.doc A 24-Nov-10
S.J. LOUIS CONSTRUCTION OF TEXAS LTD.
9862 Lorene St.,Suite 200 210/340-9998 Office•2101340-9997 Fax
San Antonio,TX 78216 Equal Opportunity Employer 1 Contractor
November 24, 2010
Mr. Michael Thuss, P.E. ,
Brushy Creek Regional Utility Authority
221 E. Main Street
Round Rock, Texas 78664
Re: Brushy Creek Regional Utility Authority (BCRUA)
78-Inch Treated Water Transmission Line Segment One
RFD#6—Utility Conflict @ Station 37+30
Mr. Thuss:
Please consider this letter a Request for Deviation regarding the installation of the tunnel located
at Station 37+34.75 on the reference project. SJ Louis conducted a utility investigation which
revealed a gas main and an underground telephone line that are not shown on the plans at
approximate Station 37+30 (see attached utility log). These utilities are in direct conflict with
the bore pit that is required to tunnel across New Hope Road.
Several options have been discussed with LAN and BCRUA representatives to resolve this
conflict. It is believed that the solution that has the least impact to the project involves extending
the tunnel back from New Hope to a point where the bore pit will not be in conflict with the
existing utilities. Other options were presented but they involved damage and repair to City of
Cedar park streets. Based on the response Cedar Park representatives, these options were not
pursued.
The tunnel extension process would include standard tunneling in accordance with the contract
documents to a point 53' further than the beginning point shown in the plans. Once the tunnel is
complete, trenching for the installation of the pipe would break into the ring beam and lagging
and the pipe would be installed per plan. The remaining length (approximately 40') of additional
tunnel would then be filled with flowable fill.
The costs associated with this deviation from the plan include additional tunneling, removal of
additional spoils, installation of ring beam and lagging and installation of flowable fill. This cost
is calculated as follows: bid price for 78-Inch Water Line in Tunnel (Gann Ranch) less the cost
of pipe and associated items plus the cost of flowable fill for the abandoned additional tunnel.
The bid price for 78-Inch Water Line in Tunnel (Gann Ranch) is $1575.00/LF of which $575.00
is associated with the pipe materials and installation including welding, weld testing,
rails/spacers and grouting the annular space. This puts the cost of the tunnel at $1,000.00/LF.
Using a length of 53 LF gives a total cost of additional tunnel of $53,000.00. The volume of
flowable fill needed to fill the abandoned additional tunnel can be calculated for the 9-foot
diameter tunnel to be 2.36 CY/LF. Assuming 40 LF of tunnel will require flowable fill and a
unit price of$60.00/CY, this gives a cost of flowable fill of $5664.00.
If approved, the total cost of this Request for Deviation to resolve the existing utility conflict
would be $58,664.00.
Should you have any questions or require additional information, please do not hesitate to call.
Regards,
S. J. LOUIS CONSTRUCTION OF TEXAS LTD.
Curtis A. Ostrander, P.E.
Project Manager
Station De pth Utility Notes Conflict
Plan Field Plan Field (Yes/No)
10+36 10+15 7.5' 6.0' 30"W No
18+41 18+42 4.5' 3.5' 8"W No
18+79 18+67 10.0' 11.0' 6"SS 2'Clearance Will Not Be Achieved Yes
19+00 3.5' 4"UE CONDUIT No
22+77 3.5' 4"UE CONDUIT No
27+13 5.0' 24"SD No Apparent Utility At This Locati No
27+85 6"G,UT 14'LEFT(RUNS PARALLEL)Not Vertically Field Located No
29+64 29+64 6.5' 8.0' 8"W 2'Clearance Will Not Be Achieved Yes
30+20 5.0' 24"SD No
32+00 6"G,UT 9'LEFT(RUNS PARALLEL) Not Vertical) Field L)ated No
32+39 7.5' 1 8"W FH Branch Not Field Located No
34+00 6"G,UT 25'LEFT(RUNS PARALLEL) Not Vertically Field Located No
34+64 7.0' 8"W Not Marked,Not Field Located Unknown
37+30 4.0' 6"G,6"SS.4"UT In Bore Pit Yes
37+53 3.0' UT Not Field Located
37+83 4.0' 6"G Not Field Located
37+90 3.0' UE Not Field Located
38+49 38+49 6.5' 1 8.0' 36"SD No
38+76 5.0' 16"W Not Field Located
39+08 3.0' UE Not Field Located
39+14 ? 8"W Not Field Located
39+42 39+42 5.0' 6.0' 24"SD No
41+30 15.0' SD MH On Centerline Yes
41+47 3.0' UE Not Feld Located
41+80 ? SD MH,O/S 50'LT No Inlets As Shown on Plans
41+92 12.0' SD BOX Does Not Exist In Field
42+75 42+72 ? 4.5' 8"W(ABANDONED?) No
42+81 6.0' 8"W Not Field Located
42+83 10.0' 42"SS Does Not Exist In Field No
42+91 42+91 8.5' 8.0' 8"SS No
47+22 7.0' 8"W FH Branch Not Field Located No
48+12 3.0' UE Not Field Located
53+17 7.0' 8"W FH Branch Not Field Located No
53+50 53+40 12.0' 11.0' 8"SS No
54+53 6.5' 12"W(ABANDONED?) Not Field Located No
54+58 54+58 6.5' 5.0' 12"W No
55+32 3.0' UE Not Field Located
59+32 7.0' 8"W FH Branch Not Field Located No
60+76 6.0' UT,UE CONDUITS No
61+01 61+02 9.0' 6.0' 24"SD BOX No
61+18 ? UE Not Feld Located
61+56 61+55 4.5' 5.0' 8"W No
61+65 4.5' 8"W Not Field Located
61+73 61+73 6.5' 7.0' 8"SS No
64+93 ? MONITORING WELL? Offset 2'Left Yes
65+20 2.5' 2.5' 18"SD No
67+72 4.5' 12"W Not Field Located
68+97 ? 7.0' 12"SS No
69+07 ? 8"W Not Field Located
70+48 ? ?W Not Field Located
70+94 ? ?SS Sewer Service from 12"SS Line No
71+04 ? ?W Not Field Located
71+16 7.0' 7.0' 18"SD No
72+14 5.0' 12"W Not Field Located
72+15 72+14 l0A' 9.3' 10"SS No
72+50 72+50 7.0' 8.0' ?SD No
72+65 72+70 11.5' 8.0' SD MH/36"SD No
72+91 ? ?W Not Field Located
73+44 ? ?W Not Field Located
74+73 74+75 ? 8.0' 18"SD No
77+50 3.0' UT No
79+15 11.5' 11.0' 15"SS No
94+50 4.5' 8"W No
95+00 4.5' GAS SERVICE No
95+01 3.0' UE No
98+00 2.0' UE No
100+01 0.0' TEST STATION jOn Centerline Yes
Notes:
All marked utilities were field located.
Fire hydrant leads were not field located because they are to be removed and replaced.
Depths shown are to top of utility except for MHs and SD boxes-those depths are MH/box inverts.