BCRUA_R-11-10-19-6ERESOLUTION NO. R-ll-IO-19-6E WHEREAS, the Brushy Creek Regional Utility Authority, Inc. ("BCRUA") has previously entered into a contract ("Contract") with Excel Construction Services, LLC for the BCRUA Interim Floating Intake Facilities Project, and WHEREAS, the BCRUA has determined that it IS necessary to make adjustments/changes to the quantity of work to be performed or materials, equipment, or supplies to be provided, and WHEREAS, it has been determined that it is necessary to adjust/change the quantities in said Contract in accordance with the attached Quantity Adjustment/Change Order No.5, Now Therefore BE IT RESOLVED BY THE BRUSHY CREEK REGIONAL UTILITY AUTHORITY, That the Board President is hereby authorized and directed to execute on behalf of the BCRUA, Quantity Adjustment/Change Order No.5 to the Contract with Excel Construction Services, LLC for the BCRUA Interim Floating Intake Facilities Project, a copy of same being attached hereto as Exhibit "A" and incorporated herein for all purposes. The Board hereby finds and declares that written notice of the date, hour, place and subject of the meeting at which this Resolution was adopted was posted and that such meeting was open to the public as required by law at all times during which this Resolution and the subject matter hereof were discussed, considered and formally acted upon, all as required by the Open Meetings Act, Chapter 551, Texas Government Code, as amended. Z:IBCRUAIBoard PackeuIPacketDocwnentsl\01911IReI. BCRUAQA-CO#5 w-Excel Construction (00235444).DOC/rmc RESOLVED this 19th day of October, 2011. ~ l,k~ _ GEORGE ~, President Brushy Creek Regional Utility Authority ATTEST: 2 Page 1of1 Contract Quantity Adjustment/Change Order ~=JI!k§ttrTY~~ Ii ••",••••••••• C._If' •• , ".lII2DU ~ " Project Name: BCRUA Interim Floating Intake Fadllties Contractor: engineer: Excel Construction 5ervIces, LLC Jacobs Engineering Group, Inc. Date: Olange Order/Quantity Adjustment No. 10/6/2011 5 Justiftcatlon 1 _ SUMMARY Amount ~ Original Contract PrIce: $3,807,500.00_ PrevIous Quantity Adjustment(s): ThisQuantity Adjustment: Total Quantity Adjuslment(s): Total Contract Prlce wtth Quantity Adjustment(s): PrevIous Olange Order(s): $331,590.82 ThIs Olange Order: $141,784.00 TotalO1ange Order(s) To Date: Original Contract Prlce Plus OIange Order(s) Plus QuanUly Adjustment(s): 473,374.82 Or1g\nal Contract l1me: 365 calendar days Contract TIme PrIor to this Olange Order: 400 calendar days Contract TIme wtth All Approved OIange Orders: 400 calendar days Glenn A. BrIdges, P.E., Project engineer Prepar!d By: (DlJSlgnatulMfr.A Jaoobs Engineering Group, Inc. '0· ~ .. It ~re Printed Name, T1tIe and Company Date=-~~ /t4fl ft...... ,t., f..cH t,.,t-/l." SIgnature Printed Name, TItle and Company Date ;..: ~:~~~ #(~4/t!t~4 L7k",," SIgnIbft Prlnted Name, TItle BCRUA AppnMlI: Date Printed EXFf I8IT "/i.' A 'arener.hl, 0' C.dar 'ark. L •• nder, ."" Round Rock CHANGE ORDER No.5 DATE OF ISSUANCE: 10-06-11 EFFECTIVE DATE: _ OWNER: BCRUA CONTRACTOR: Excel Construction Services, LLC PROJECT: BCRUA Interim Floating Intake Facilities ENGINEER: Jacobs Engineering Group, Inc. The Contractor is hereby directed to make the following changes in the Contract Documents: Change Proposal Reguests 1. Add finished water SCADA system improvements, per CPR #9A and the response to CPR #9A from Excel, dated September 2, 2011. ADD $ 141,784.00 2. Revise the substantial completion date to allow Excel to perform emergency work required for City of Cedar Park drought contingency pipeline and barge relocation, as discussed at the recent DOC meeting. ADD 27 calendar days to Substantial Completion Page 1 Project BCRDA Interim Floating Intake Facilities ChangeOrderNo.5 CHANGE IN CONTRACf PRICE: Original Contract Price: $ 3,807.500.00 Net increase from previous Change Orders s 331,590.82 Contract Price prior to this Change Order: s 4.139.090.82 Net increase from this Change Order: $141.784.00 Contract Price with all approved Change Orders: s 4.280,874.82 CHANGE IN CONTRACf TIME: Original Contract Times: Substantial Completion (Days): 334 calendar days Final Completion (Days): 365 calendar days Substantial Completion (Date): November 5. 2011 Final Completion (Date): December 6. 2011 Net change from previous Change Orders: Substantial Completion (Days): 348 calendar davs Final Completion (Days): 400 calendar days Substantial Completion (Date): November 19.2011 Final Completion (Date): January 13. 2011 Final Completion (Date): January 17. 2012 (lor SCADA work only) Contract Times prior to this Change Order: Substantial Completion (Days): 348 glendar daYs Final Completion (Days): 400 calendar days Substantial Completion (Date): November 19.2011 Final Completion (Date): .January 13. 2011 Final Completion (Date): January 17.2012 (for SCADA work only) Net increase this Change Order: (See Note 1 below.) Substantial Completion (Date): December 16.2011 Final Completion (Date): .January 13. 2012 Final Completion (Date): January 17.2012 (for SCADA work only) Contract Times with all approved Change Orders: Substantial Completion (Days): 375 calendar days Final Completion (Days): 400 calendar davs Substantial Completion (Date): December 16.2011 Final Completion (Date): January 13.20U Final Completion (Date): ,January 17.2012 (for SCADA work only) Note 1: SubstantialCompletiondate isextendedto December 16, 2011 to allowExcel to perfonn emergencyworkassociated with City of Cedar Park's project to extend a new raw water pipeline and relocate the City's existing barge. Page 2 CHANGE ORDER #5 ITEMl ISIn Lockwood, Andntwa a~lnc. A LEO A OAl Y COMPANY REa,.:·October 13, 2011 By..."".,L......... Mr. Michael Thuss, PE Brushy Creek Regional Utility Authority 1906 Hur Industrial Boulevard Cedar Park, TX 78613 RE: Brushy Creek Regional Utility Authority Interim Floating Intake Facilities Change Proposal Request #9A / Treated Transmission System Radio System Mr. Thuss: LAN has reviewed Interim Floating Intake Facilities Change Proposal Request #9A Rev2submitted by Excel Construction Services as it pertains to the radio system for the BCRUA Treated Transmission System. The change proposal request includes providing materials and labor for the installation and set-up of the radio and antenna system and appurtenances for the Treated Transmission System. The cost for the proposed revision is reasonable and in accordance with the contract documents. LAN recommends the BCRUA accept the change proposal in the amount of $141,784 with the following revision: • Delete the follOWing statementfrom the coversheet:"This proposal assumes all antenna mountsfor the elevated towers will be provided by others (Landmark)." As acknowledged in a letter from Excel Construction on September 28,2011, the antennamounts will be provided and installed by JTS. Please contact me at (512) 338-4212 if you have any questions. Sincerely, JJi,~ Julie Hastings, PE Team Leader cc: Glenn Bridges, Jacobs LAN File No. 160-10296-202-5.16 Attachments: Excel CPR#9A Excel Letter dated 9128/11 LAN/Jacobs letter dated 8/30/11 2705 BeeCeve Roed.Sun. 300 Austin. Tellis78746U.S.A. 1.512.314.3100 F8111.512.314.3135 July 14,2011 Matt Cannon ExcelConscruction Services. LLC 1201 Leender Drive Leander,TX 78641 Re: B......)' Creek R......Utllit)' AatborUy (DCRUA) I.tat.. noadqlatake "aclDtles Qup Proposal Request t9A Dear Mr.Cannon: Please providea cost ploposal forall materials. labor and equipment to add the finished water SCADA sysIan improvements to the subjectproject The finished wata' SCADA system impccm:ments are cklailcd in the enclosed specification Section 13411 (8 paaes at 8-112" x II" sizeplus 1 pile Radio Equipment Schedule at II" x 17"size)and the following enclosed drawinpat II"x 17" _<signed and sealed on 07-12-11): 1. BCR.UA Radio Si~ Map 2. BCR.UA FiniJhcd WaterRadio System 3. Radjo Antenna Standard Details Please note dJat the above additions are related to CPR #9.which waspreviously issued OIl June 24.2011 (see cacloeed copyofCPR#9). The enclosed Sheet 7Y03 (daeed 07-13-11)_11 replace the pI'CYious Sheet1Y03that wasincluded with CPR#9. Specification section 13411 shaU also apply CO raw watI:r systemSCADA equipmcat referenced in QtR. #9. Please break out the costs separately for CPR. t#9 andCPR #l9A. Ifthe colt ptopwal is acccptcd,a chaqe onIer wiD bei*epared for the work. If youhave any queatioas, pIe8se do DOthesitate to c:oatlct meat S12-314-3182. Sincerely, JACOBS ENGINEERING GROUP,INC. xc Nih 1buss, PA. BCRUA Jean BilbY, EIT,BCR.UA Once Sbl~EIT, BCRUA DUIdn Riley. Wata'Rr:Iource Management J.R.. ToUcs, P.E. w' encIoeures Jacobs Engineering Group InC. §2s.~ Change Proposal BCRUA Floating Intake Request No. 09A Rev2 JACOBS ProjectName: InterimFloatina Inteke Facilities Contractor: Excel Construction Services LLC ProjectOwner: 8CRUA Address: POBox 2260 Leander Texas78646 Address: 221 E. MainStreet Round Rock TX78664 InlUated by: X Enalneer o Contractor Att.ntlon: The followIng changeInthe contract on thisprojectIs proposed. • Workshallnot commence untllauthorizedby the Owner. Description of the Proposed Change' Exr:eI's DI...ed to offer the followlnll chanll. for the owners consideration by the changNlJrOlIOsed by the engineer In CPRltA. This "",lI08a' assumes all antenM mounts for the elevated towww wIN be DrOvided bv others (LandmarlcJ. By I MatthewCannon-Excel Construction Services LLC All wor1c. shall be In accordance with the terms, Jacobs Recommendation: stipulations, and conditions oftheoriginal Contract o Recommand Acceptance Documents. Ifthe worlthereinprovidedfor is Approved by o Do Not Recommend Acceptance Change Order,the time of completion will be: X Increased o Decreased Unchanged By: Jacobs 8y 0 calandar days. This assumes both CPR'sare accepted Date This change will: X Add Deduct 0 No Change Owner'sAction: o Accepted 0 Not AcceptedS 141,784.00 I -::B:-y-:'=B'=CR""U:-:'A.,------------------ExcelConstNction S8rv1ces, LLC I Date September2.2011 I Date Change Proposal Request Fonn BCRUA INTERIM FLOATING INTAKE FACILITIES cpr.doc WORKPROPOSALCOST ITEMIZATION; CPRNo.9A Rev 2 BCRUA Interim Floating Intake Revised Seada September 2, 2011 ~ quantity I unit cost 0 total IA) Materials 1 $ · 2 $ $ $ $ $ ----- 3 4 5 6 7 $ $ · -8 18) LaborlEaulDment 1. $ $ $ $ $ $ $ $ $ $ - -- · · - - - · - 2 3 4 5 6 7 8 9 10 IC} Subcontracts 1. T.Morales LS 1 $125,580.00 $ 125,580.00 2. $ · $ -3. IC) Administration 1. M.Cannon HR 6 $ 75.00 $ $ $ $ 450.00 - · · 2. 3. 4. Sub-Total $ 126.030.00 12.5%OHP $ 15,753.75 TOTAL I $ 141,784 1 Flied: 12-02,.MIrI:!!!L Cc:02-4A Project: Interim Floating Intake Facilities Date: September 2,2011 TMC Change #: COR-QS Rev 02 Owner: Brushy Crk Regional Utility Authority Project Change #: CPR9A Change Order Request Morales Company is pleased to provide change pricing in response to the engineers CPR-9A: This quotation includesthe following services and materials: • Conduits with associated fittings, mounting hardware as required. • Wiring and terminations for powerand control. • Subcontractor servicesfor instrumentation procurement and installation (see attached). • Equipment costs for small tools (benders, drills, saws). • Equipment costsfor highwork (ladders,scaffolds,platform lift,snorkel lift,bucket truck). • Antenna poles/concrete bases for the (2) take point sites are included This quotation does not include any of the following: • N/A. This quotation is qualified uponthe following assumptions: • Ethernet connections to equipment existing or FBOwill be available. Total cost for the additional work associated with this change is $125,580.00. Please see attached pricing summary breakdown. Extension In Time Request for (20) weeks: This extension in timecanrun concurrently with CPR9work,assumingbothchangesare accepted. Thechange'lntime is contingentuponsubmittalsbeing returned approvedas noted. Change Initiated By: Matt Cannon I Excel Canst Change Prepared By: Farrell R. Prewitt I TMC A...._Change Delivered To: Matt Cannon I Excel Canst Response Rqst'd By: ..,A:=;S....P 601 South Patterson Avenue Florence, Texas76527 Florence. Texas 76527 Phone: 254-793-4344 POBox 859 Fax: 254-793-3044 0.54686 Bid;#20• 201037chng08 antennas CPR9A 2011 projectschangeorders T Morales Company Electric Controls LId 0.54686 (Mailing) PO Box 859 2011 projectschangeorders (Pysical) 601 South Patterson Ave 91212011 10;05:05AM Florence. Texas 76527 FP wrp Commlndust TSCfTP... 254-793-4344 F~;254-793·3044 morales 1 0 0.00 2 0 Mise Materials: Malerlal Total 10,150.00 1.00 10.150.00 3 0 Quote#1 calculated 0.00 1.00 0.00 4 0 Quote#2 calculated 0.00 1.00 0.00 5 0 SUBTOTAL 10,150.00 6 0 nUK#«rOCtOnnnnHUDVrX 0.00 7 0 SALEST~; Material Total 10.150.00 0.00 8 0 SUBTOTAL 0.00 9 0 "#~#R~9*##~##UfNIXC## 0.00 10 0 LABOR: 0.00 11 0 StraightTimeLabor Labor Total 224.00 35.80 6,019.20 12 0 OvertimeLabor Calculated 0.00 47.55 0.00 13 0 IC Tech S·TIme calculated 0.00 40.42 0.00 14 0 IC Tech O-Time Calculated 0.00 58.80 0.00 15 0 GooForemanHours Labor Total 224.00 0/0 8.00 17.92 16 0 Gen Foreman Rate Component 15 17.92 41.64 749.n 17 0 Material HndlerHrs Labor Total 224.00 "­3.00 6.72 18 0 Material HndlerRate Component 17 6.72 24.24 162.89 19 0 UpdateAs BuiltDwgs Calculated 1.00 41.64 41.64 20 0 Programmer Calculated 0.00 70.00 0.00 21 0 SUBTOTAL 8.973.71 22 0 uUnUCnCKVXXUNCffiVc:Xa 0.00 23 0 DIRECT JOB EXPENSES; 0.00 24 0 Expendable Tools Material Total 10,150.00 % 3.00 304.50 25 0 Equipment calculated 150.00 1.00 150.00 26 0 Warranty on Material Component 5 10.150.00 % 0.00 27 0 warranty on Labor Component 21 8,973.71 % 0.00 28 0 SUBTOTAL 454.50 29 0 CC&NJCt"Xnuux«ruuaua 0.00 30 0 SUBCONTRACTS: 0.00 31 0 Neltronics ate calculated 87.523.00 1.00 81,523.01) 32 0 Sub#2 calculated 0.00 0.00 33 0 SUBTOTAL 87,523.00 34 0 NY#3.W:1WYnn"Kt~1vC3t 0.00 35 0 JOB SUBTOTAL 107,101.21 36 37 0 0 N#iJlh1ROXHaO#"N1Unyg, MARKUPS; 0.00 0.00 38 39 40 0 0 0 UabilltylBklrs Risk WrIIComp/SSlUnmplymnt OveltJead @ 2.5% Component Component component 35 21 35 107,101.21 8,973.71 107,101.21 0/0 0/0 % 2.00 25.00 2.50 2,142.02 2,243.43 21f17.53 41 0 JOB TOTAL 114,164.19 42 43 0 0 J1J:J::NJNOiJM::JPX:U::tJJ.)CINJ Profit@ 10% Component 41 114,164.19 % 10.00 0.00 11.416.42 44 0 JOB TOTAL + PROFIT Component 43 11,416.42 1.00 125.580.61 45 46 0 0 Perf Payment Bond ADDBOND Component Component 44 45 125,580.61 0.00 % 1.00 0.00 125.580.61 47 0 XX#M##nXMfJKX#UE:#Un 0.00 48 0 BID TOTAL 12U80.81 ; ;,,~ .' '. ' '. ., '!. _;':~_. ~ '::<>C.'···..'Dr".····· CHANGE ORDER REQUEST NELTRONICS, LLC Change Order Request #: 004 415CTexasAvenue Date: 09/01/2011 Round Rock, Texas 78664 Project No.: 2010-034 Project: BrushyCreek Regional Interim Floating Intake Facilities ChangeProposal Request #9A (CPR#9A) To: T. Morales Company Electric & Controls, Ltd. From: Neltronics, LLC P.O. Box 859 415C Texas Avenue Florence, Texas 76527 Round Rock, Texas78664 Attn: Farrell Prewitt Attn: John McClanahan Phone: 254-793-4344 Phone: 512-844-0710 E-Mail: ~ rewitt moralescom an .com E-Mail: ·ohmcc01neltronics.net We propose to provide the following equipment and services as per Change Proposal Request #9: Additional EquipmentasRequired Per Change Proposal Request #9A (CPR#9A} Lot Wireless Backhaul System at Brushy Creek WTP <--->Webster EST <--->Round Rock EST <-->Round RockWTP as Provided and Installed By JTS, Inc. Lot Multipoint Radio System at Webster EST <--> leander Tank Point and Cedar Park Tank Point as Provided and Installed By JTS, Inc. 2ea Nema 12 Radio Enclosures for CedarPark Webster EST &Round Rock EST Including All Required EqUipment 2ea Ethernet Switches at Cedar Park EST & Round Rock EST 2ea 15' Antenna Mast/Hardware light Pole at each Take Point lot ITS Inc. Spare Parts Total Pricefor Change ProposalRequest#9A (CPR#9A} $87,523.00 Note All concrete work for antenna masts by others (GC). JTS providing aluminum poles and hardware at each elevated storage tank and Round RockWTPTower On top of tanks, JTS Inc. providing seal tight flexible conduit to protect cable in walking area's. This price is good for 30 days. If conditions change, this price is void. JohnP.McClanahan 09/01/2011 Author Date The above prices and specifications of this Change Order request are satisfactory and are hereby acepted. All work to be performed under same terms and conditions as specified in original contract unless otherwise specified. 0 Accepted AUTHORIZED SIGNATURE COMPANY DATE September 28,2011 Mr. Glam Bridges, PE 2705 Bee Cave Road,Ste300 Austin,TX 78746 Subject: BCRUA C-3:Response to comments made in refer=ce toCPR#9A Dear Glenn, In response to theletter Excel received on 813012011 from Jacobs, we offer the following elarificatioDS (each COIIlDlCDt corresponds to the same numbering system u seen on the 8130 letter): 1.) Excel and T.Morales has reduced eachofour OH&P toa combined markup of 25tyo. The ~states that the contractor IIDd any subcontr8Ctor be limited to the markups given in this elause and that it doesnot pertain to any 2-or 3111 tier subcontncton. See CPR#9A 1W2 for clarification in howthemarkups were applied. 2.) The rate Biven by Neltronics is a flat rate. 3.) See additional scope breakdown provided by T.Morales, provided to LAN on 912212011. 4.) See note #3. 5.) The antenna mastshavenot been duplicated withinthe respective scopes. 6.) The equipment cost for high work has not been duplicated between T.Morales and ITS. 7.) The anteDna mounts for the elevated tank provided by othersonly pertain to CPR #9, therefore the assumption thatantenna mounts are provided by others on CPR #9Acan be deleted as ITS has included these in their 1COpe. Please cotltKt me lit (512) 259-5005 should you have Illy questions. Sincerely, ~...t< MattCaDnon Bxcel Construction Services Ce:Julie HMtinp, PE-LAN i ~ • ~ . _ ~ rill ".., ~ Ij !fli(flllrWII.r t Iitl !ff~lf ~lftJ i r iifl > , ! i ' i fi ~i !JI [ 1 t~ltt ~ till! ;~II=i Iliti lif~I f II fl.! fi ~ II *1 rllr~ IIl••f: ;:: f~~~ I~J!! I. J~ iii•r I! I II iI' I!f .111 it,ll !~f! :11 ~-~ I~ i It ill - [it ~Ii ;iiit tiii ~Ji ~rrla! !~f ~.I' t:~e e I i rl~a (" ~ I J ~~I I ., ~ DATE: October 14, 2011 SUBJECT: BCRUA Board Meeting -October 19, 2011 ITEM: 6E. Consider a resolution approving Change Order No.5 with Excel Construction Services, llC for the BCRUA Interim Floating Intake Facilities. PRESENTER: Michael F. Thuss, P.E. Program Manager Justification: This change order is required to transition the entire BCRUA Raw Water Telecommunications System to a 4.9 GHz frequency. This will also alleviate any interference with other telecommunication systems in the area. This change order also increases the substantial completion date to allow Excel to perform emergency work requtred for the City of Cedar Park drought contingency pipeline and barge relocation, as requested by the City of Cedar Park. Funding: This change order is for an additional $141,784.00, revising the total contract amount to $4,280,874.82. Funding for this change order is from the project's contingency. EXECUTED DOCUMENTS FOLLOW 10/6/2011 Page 1 of 1 Contract Quantity Adjustment/Change Order rev.9/2011 Project Name: BCRUA Interim Floating Intake Facilities Contractor: Excel Construction Services, LLC Date: Change Order/Qua ntity Engineer: JacobsEngineering Group, Inc. Adjustment No. Justification1'---­ SUMMARY Original Contract Price: Previous Quantity Adjustment(s): This Quantity Adjustment: Total Quantity Adjustment(s): Total Contract Price with Quantity Adjustment(s): Previous Change Order(s): This Change Order: Total Change Order(s) To Date: Original Contract Price Plus Change Order(s) Plus Quantity Adjustment(s): Original Contract Time: ContractTimePriorto this Change Order: ContractTimewith All Approved Change Orders: Glenn A. Bridges, P.E., Project Engineer Jacobs Engineering Group, Inc. Prepared By: Printed Name, Title and Company Date ~ , )..oj I DateSignature Approval: ~4~_ Contractor Approval: BCRUA _ Amount ~ $3,807,500.00_ $0.00 $0.00 $3,807,500.00 $331,590.82 8.71% $141,784.00 3.72% $473,374.82 12.43% $4,280,874.82 365 calendar days 400 calendar days 400 calendar days Si nature Printed Name, Title Date BCRUA Approval: 5 A f'lIr~ners~;p of Cedar Part.. l.allnde,., and Rou,.d flock CHANGE ORDER No.5 DATE OF ISSUANCE: 10-06-11 EFFECTIVE DATE: _ OWNER: BCRUA CONTRACTOR: Excel Construction Services, LLC PROJECT: BCRUA Interim Floating Intake Facilities ENGINEER: Jacobs Engineering Group, Inc. The Contractor is hereby directed to make the following changes in the Contract Documents: Change Proposal Requests 1. Add finished water SCADA system improvements, per CPR #9A and the response to CPR #9A from Excel, dated September 2, 2011. ADD $141,784.00 2. Revise the substantial completion date to allow Excel to perform emergency work required for City of Cedar Park drought contingency pipeline and barge relocation, as discussed at the recent DOC meeting. ADD 27 calendar days to Substantial Completion Page 1 Project: BCRUA Interim Floating Intake Facilities Change OrderNo.5 CHANGE IN CONTRACT PRICE: Original Contract Price: s 3,807.500.00 Net increase from previous Change Orders $ 331,590.82 Contract Price prior to this Change Order: s 4,139,090.82 Net increase from this Change Order: $141,784.00 Contract Price with all approved Change Orders: s 4,280,874.82 I CHANGE IN CONTRACT TIME: I Original Contract Times: Substantial Completion (Days): 334 calendar days Final Completion (Days): 365 calendar days Substantial Completion (Date): November 5, 2011 Final Completion (Date): December 6, 2011 Net change from previous Change Orders: Substantial Completion (Days): 348 calendar days Final Completion (Days): 400 calendar days Substantial Completion (Date): November 19. 2011 Final Completion (Date): January 13,2011 Final Completion (Date): January 17,2012 (for SCADA work only) Contract Times prior to this Change Order: Substantial Completion (Days): 348 calendar days Final Completion (Days): 400 calendar days Substantial Completion (Date): November 19, 2011 Final Completion (Date): January 13,2011 Final Completion (Date): January 17,2012 (for SCADA work only) Net increase this Change Order: (See Note 1 below.) Substantial Completion (Date): December 16,2011 Final Completion (Date): January 13,2012 Final Completion (Date): January 17,2012 (for SCADA work only) Contract Times with all approved Change Orders: Substantial Completion (Days): 375 calendar days Final Completion (Days): 400 calendar days Substantial Completion (Date): December 16, 2011 Final Completion (Date): January 13,2012 Final Completion (Date): January 17,2012 (for SCADA work only) Note I: SubstantialCompletiondate is extendedto December16,2011to allowExcel to performemergencyworkassociatedwith City of Cedar Park's project to extend a new raw water pipeline and relocate the City's existing barge. Page 2 CHANGE ORDER #5 ITEM! 2705 Bee CaveRoad.Suite300 Austin.Texas 78746U.S.A. JACOBS 1.512,314.3100 Fax 1,512,314,3135 July 14> 2011 Matt Cannon Excel Construction Services. LLC 1201 Leander Drive Leander> TX 78641 Re: Brusby Creek Regiollal UtUlty Alltborlty (BCRUA) I.teriaa FloadBg IDtake Facilities C ••Bge Proposal Request #9A Dear Mr.Cannon: Please provide a cost proposalfor a11 materials, labor and equipmenttoadd the fmishedwater SCADAsystem improvementstothe subject project. The finished waterSCADA system improvements are detailedintheenclosed specificationSection 13411 (8 pages at 8-112"x 11" sizeplus 1 page Radio EquipmentSchedule at 11" x 17"size)and the following enclosed drawings at II" x t 7" size (signedand sealed on 07-12-11): 1. BCRUA Radio Site Map 2. BCRUA Finished Water Radio System 3. Radio AntermaStandard Details Please note that theaboveadditionsare relatedto CPR #9, whichwas previously issued on June 24,2011 (see enclosedcopy of CPR #9). The enclosedSheet7Y03(dated07-13-11) shall replace the previous Sheet 7Y03 that was included with CPR #9. Specification Section 13411 shall also apply to raw watersystemSCADAequipmentreferencedin CPR #9. Please break out the costs separatelyfor CPR #9 and CPR#9A. If the cost proposal is accepted, a change order will be prepared forthe work. Ifyou haveanyquestions,please do not hesitate to contact me at 512-314-3182. Sincerely, JACOBS ENGINEERING GROUP, INC. Glenn A Bridges, P . Senior Project Engi XC: MikeThuss,P.E.,BCRUA Jenn Higby, Err, BCRUA Grace Stillman, Err, BCRUA Dustin Riley, Water Resource Management J.R. Tolles, P.E. wI enclosures K:\WJXK020I\Contrxt3'01ange Proposal RequeslS\cPR #9\CPR#9A final.doc Jacobs Engineering Group Inc ~~.§.L» Change Proposal BCRUA Floating Intake Request No. 09A Rev2 JACOBS Proiect Name: Interim FloatinQ Intake Facilities Contractor: Excel Construction Services. LLC Project Owner: BCRUA Address: PO Box 2260 Leander, Texas 78646 Address: 221 E. Main Street Round Rock, TX 78664 Initiated by: X Engineer 0 Contractor AttentIon: The following change in the contract on this project is proposed. • Work shall not commence until authorized by the Owner. I ~:~oomthep~CMnge ". xce ,s p,eased 0 0 er the folloWlnQ chanQe for the owners cons, erat,on IV the c h anQes propose bv the enQineer in b d cPR#9A. This proposal assumes all antenna mounts for the elevated towers will be provided by others (Landmark). By I Matthew Cannon-Excel Construction Services, LLC All work shall be in accordance with the terms, Jacobs Recommendation: stipulations, and conditions of the original Contract o Recommend Acceptance Documents. If the work herein provided for is Approved by o Do Not Recommend Acceptance Change Order, the time of completion will be: X Increased o Decreased Unchanged By: Jacobs By 0 calendar days. This assumes both CPR's are accepted Date This change will: X Add Deduct o No Change Owner's Action: $ 141,784.00 [] Accepted 0 Not Accepted Excel Construction Services, LLC By: BCRUA Date September 2,2011 Date Change Proposal Request Form SCRDA INTERIM FLOATING INTAKE FACILITIES cpr.doc WORK PROPOSAL COST ITEMIZATION: CPR No. 9A Rev 2 BCRUA Interim Floating Intake Revised Scada September 2,2011 ~l quantity I unit cost D total IA) Materials 1 $ $ $ $ $ $ $ $ - - - - - - - - 2 3 4 5 6 7 8 IB) Labor/Equipment 1. $ $ $ $ $ $ $ $ $ $ - - - - - - - - - - 2 3 4 5 6 7 8 9 10 IC) Subcontracts 1. T.Morales LS 1 $ 125,580.00 $ 125,580.00 2. $ - $ -3. IC) Administration 1. M.Cannon HR 6 $ 75.00 $ $ $ $ 450.00 - - - 2. 3. 4. Sub-Total $ 126,030.00 12.5% OHP $ 15,753.75 TOTAL 1 $ 141,784 1 El cct r ic J Controls U Inst ru r-ic nt<JT10n Filed: 12-02 Cc: 02-4A Project: Interim Floating Intake Facilities Date: September 2, 2011 TMC Change #: COR-OB Rev 02 Owner: Brushy Crk Regional Utility Authority Project Change #: CPR9A Change Order Request Morales Company is pleased to provide change pricing in response to the engineers CPR-9A: This quotation includes the following services and materials: • Conduits with associated fittings, mounting hardware as required. • Wiring and terminations for power and control. • Subcontractor services for instrumentation procurement and installation (see attached). • Equipment costs for small tools (benders, drills, saws). • Equipment costs for high work (ladders, scaffolds, platform lift, snorkel lift, bucket truck). • Antenna poles/concrete bases for the (2) take point sites are included This quotation does not include any of the following: • N/A. This quotation is qualified upon the following assumptions: • Ethernet connections to equipment existing or FBO will be available. Total cost for the additional work associated with this change is $125,580.00. Please see attached pricing summary breakdown. Extension in Time Request for (20) weeks: This extension in time can run concurrently with CPR9 work, assuming both changes are accepted. The change in time is contingent upon submittals being returned approved as noted. Change Initiated By: Matt Cannon / Excel Const Change Prepared By: Farrell R. Prewitt / TMC Change Delivered To: Matt Cannon / Excel Const Response Rqst'd By: ~A~S::....:A~P _ PO Box 859 601 South Patterson Avenue Florence, Texas 76527 Florence, Texas 76527 Phone: 254-793-4344 Fax: 254-793-3044 • 0.54686 Bid: #20 - 201037 chng 08 antennas CPR9A 2011 projects change orders T Morales Company Electric .Controls Ltd .0.54686 (Mailing) PO Box 859 2011 projects change orders (Pysical) 601 South Patterson Ave Florence, Texas 76527 9/2/2011 10:05:05 AM 254-793-4344t~i~?~;jJ~11;t$~'J5~ FP WTP Commlndust rscrrs ... FAX: 254-793-3044 ====r;T~R:;===~====---:T::T"':"o:7C~fp:;,;re;;.::w;;,itt;;;@g:,:m;o;;.;ra;:.:le:;:;s;;;;company.co:,:.-m,-,=-~~~=,,"= ....j~'f~t~~t~~\wj~;i~{f;;:~~~;I·~~~i:.;}I ••:·i~i~~~~~f~~~~~~1;71i,T::·.~::;,p7~r::7·;!lt:::}P=:P;:--:~f:""1;,~17/ 7,...:T'i,.T.,.~':'":-'~77""""""---'-'-''''-----' 1 0 MATERIALS 1QUOTES: 0.00 2 0 Misc Materials: Material Total 10,150.00 1.00 10,150.00 3 0 Quote #1 Calculated 0.00 1.00 0.00 4 0 Quote #2 Calculated 0.00 1.00 0.00 5 0 SUBTOTAL 10,150.00 6 0 #1I##lifl/fI#!II#ff##!/fIIl#1f1! 0.00 7 0 SALES TAX: Material Total 10,150.00 % 0.00 8 0 SUBTOTAL 0.00 9 0 ##/ff/#!J!!!fN##/;'O#U##!f/li! 0.00 10 0 LABOR: 0.00 11 0 Straight TIme Labor Labor Total 224.00 35.80 8,019.20 12 0 Overtime Labor Calculated 0.00 47.55 0.00 13 0 tc Tech S-Time Calculated 0.00 40.42 0.00 14 0 tc Tech O-TIme Calculated 0.00 58.80 0.00 15 0 Gen Foreman Hours Labor Total 224.00 % 8.00 17.92 16 0 Gen Foreman Rate Component 15 17.92 41.84 749.77 17 0 Material Hndler Hrs Labor Total 224.00 % 3.00 6.72 18 0 Material Hndler Rate Component 17 6.72 24.24 162.89 19 0 Update As Built Dwgs Calculated 1.00 41.84 41.84 20 0 Programmer Calculated 0.00 70.00 0.00 21 0 SUBTOTAL 8,973.71 22 0 ###1::///#####;;/1//###### 0.00 23 0 DIRECT JOB EXPENSES: 0.00 24 0 Expendable Tools Material Total 10,150.00 % 3.00 304.50 25 0 Equipment Calculated 150.00 1.00 150.00 26 0 Warranty on Material Component 5 10,150.00 % 0.00 27 0 Warranty on Labor Component 21 8,973.71 % 0.00 28 0 SUBTOTAL 454.50 29 0 ##H#liN#UNU#######HK# 0.00 30 0 SUBCONTRACTS: 0.00 31 0 Neltronics Qte Calculated 87,523.00 1.00 87,523.00 32 0 Sub #2 Calculated 0.00 0.00 33 0 SUBTOTAL 87,523.00 34 0 #####I!#ffl!##I!##I!##### 0.00 35 0 JOB SUBTOTAL 107,101.21 36 0 ##//;;##;;;;;:fll;'(/#;;;;;;#### 0.00 37 0 MARKUPS: 0.00 38 0 LiabiJity/Bldrs Risk Component 35 107,101.21 % 2.00 2,142.02 39 0 WrkComp/SS/Unmplymnt Component 21 8,973.71 % 25.00 2,243.43 40 0 Overhead @2.5% Component 35 107,101.21 % 2.50 2,6n.53 41 0 JOB TOTAL 114,164.19 42 0 H#If#IfI!#NH#HHHIIUU#ffffff 0.00 43 0 Profit@ 10% Component 41 114,164.19 % 10.00 11,416.42 44 0 JOB TOTAL + PROFIT Component 43 11,416.42 1.00 125,580.61 45 0 Perf Payment Bond Component 44 125,580.61 % 0.00 46 0 ADD BOND Component 45 0.00 1.00 125,580.61 47 0 #;;#f!t/######;;######## 0.00 48 0 BID TOTAL 125,580.61 CHANGE ORDER REQUEST NELTRONICS, LLC Change Order Request #: 004 415CTexasAvenue Date: 09/01/2011 Round Rock,Texas 78664 Project No.: 2010-034 Project: Brushy Creek Regional Interim Floating Intake Facilities Change Proposal Request #9A (CPR#9A) To: T. Morales Company Electric & Controls, Ltd. From: Neltronics, LLC P.O. Box 859 415C TexasAvenue Florence, Texas 76527 Round Rock, Texas 78664 Attn: Farrell Prewitt Attn: John McClanahan Phone: 254-793-4344 Phone: 512-844-0710 E-Mail: fprewitt@moralescompany.com E-Mail: johmcc01@neltronics.net We propose to provide the following equipment and services as per Change Proposal Request #9: Additional EquipmentasRequiredPer Change Proposal Request#9A (CPR#9A) Lot Wireless Backhaul System at Brushy Creek WTP <--->Webster EST <--->Round Rock EST <--->Round RockWTP as Provided and Installed By ns, Inc. Lot Multipoint Radio System at Webster EST <--->Leander Tank Point and Cedar ParkTank Point as Provided and Installed By ns, Inc. 2ea Nema 12 Radio Enclosures for Cedar Park Webster EST & Round Rock EST Including All Required Equipment 2ea Ethernet Switches at Cedar Park EST & Round Rock EST 2ea 15' Antenna Mast/Hardware Light Pole at each Take Point Lot ns Inc. Spare Parts Total Price for Change Proposal Request#9A (CPR#9A) $87,523.00 Note All concrete work for antenna masts by others (GC). ns providing aluminum poles and hardware at each elevated storage tank and Round Rock WTP Tower On top of tanks, ns Inc. providing seal tight flexible conduit to protect cable in walking area's. This price is good for 30 days. If conditions change, this price is void. John P.McClanahan 09/01/2011 Author Date The above prices and specifications of this Change Order request are satisfactory and are hereby acepted. All work to be performed under same terms and conditions as specified in original contract unless otherwise specified. D Accepted AUTHORIZED SIGNATURE COMPANY DATE