Loading...
BCRUA_R-11-10-19-6FRESOLUTION NO. R-ll-IO-19-6F WHEREAS, the Brushy Creek Regional Utility Authority, Inc. ("BCRUA") has previously entered into a contract ("Contract") with S.l Louis Construction of Texas, Ltd for the BCRUA Raw Water Pipeline Phase One - Contract No.1 Project, and WHEREAS, the BCRUA has determined that it is necessary to make adjustments/changes to the quantity of work to be performed or materials, equipment, or supplies to be provided, and WHEREAS, it has been determined that it is necessary to adjust/change the quantities in said Contract in accordance with the attached Quantity Adjustment//Change Order No.7, Now Therefore BE IT RESOLVED BY THE BRUSHY CREEK REGIONAL UTILITY AUTHORITY, That the Board President is hereby authorized and directed to execute on behalf of the BCRUA, Quantity Adjustment/Change Order No. 7 to the Contract with S.l. Louis Construction of Texas, Ltd for the Raw Water Pipeline Phase One - Contract No.1 Project, a copy of same being attached hereto as Exhibit "A" and incorporated herein for all purposes. The Board hereby finds and declares that written notice of the date, hour, place and subject of the meeting at which this Resolution was adopted was posted and that such meeting was open to the public as required by law at all times during which this Resolution and the subject matter hereof were discussed, considered and formally acted upon, all as required by the Open Meetings Act, Chapter 551, Texas Government Code, as amended. Z:\BCRUA\BoardPackctsIPacketDocumenlll\\O\91\IR••. BCRUA ChUlg. Order # 7 w-S.J. Looi. - Raw WL Pipeline (OO235447).DOCIrmc RESOLVED this 19th day of October, 2011. _~~~ LJLv9.L GEORGE WHItE, President Brushy Creek Regional Utility Authority ATTEST: MIT H~Secretary~"'""' 2 9/14/2011 Page 1 of 1 Contract Quantity Adjustment/Change Order =":JI~~~J;~~ .t•••••.•••••fr; •••• "' ••• ~ . ...wu BCRUA Raw Water Pipeline Phase One • Project Name:,.;;CoI;.;;.;n.;,;;;tra..;;;,ct-..:,l _ Contractor: SJ. louis ConstructIon of Tecas, Ltd. Dale: Olange Order/Quantity EngIneer: Jaoobs Engineering Group, Inc. AdjustmentNo. SUMMARY Amount ~ OrtgInai CortnIct PrIce: $19,371,138.19_ PrevIous QuanIly Adjustmenl(s): ThIs QuanIttY Adjustment: Totli Quantly Adjustment(s): Totli ContrICt Price with QuantllyAdjUstment(s): ~O1Inge Order(s): ThIs O1Inge Order: TOCII Olange ORIer(s) To Dale: Ortglnlll 0JntnIc:t Prtoe Plus Q\ange Otdet(s) Plus QulInlily Adjtatment(s): 0rfgInaI Contract Time: 730calendardays (Rnal) ConlraCll1me Prtor to this Change Older: 734 calendardays (Final) contract 11me with All Approved Change Orders: 794 calendar days (Rnal) Glenn A.8I1dges, P.E., Project EngIneer Jacobs EngIneering Group, Inc. 10-1-1\ Printed Name, TIle and CCllq)Iny ~"".Pf~ ~1&rNIWQ4""'" ~.1". 1.OlI.$ ~., 'IF~, IJR Prtnted Name, TItle ~, 7 r • CHANGE ORDERNo.7 EFFECTIVEDATE: _DATE OF ISSUANCE: 09-14-11 OWNER: BCRVA CONTRACfOR: S..J. Louis Construdion of Texas, Ltd. PROJECI': BCRVA Raw Water PJpeJine Phase One - Contract 1 ENGINBER: Jacobs Engineering Group,Inc. The Contractor is hereby directed to make the following changes inthe Contract Documents: ChanD PrQposal ReQuest m I. Install drop inlets.24"diameter drainage culvertsand headwalls withenergy dissipalors at two locations under Trails End Road. ADD $l2Z,540.oo Page I •I Project: BCRUA Raw Water Pipeline Phase One -ContnlCl I Change Order No. 7 CHANGE IN CONTRACT PRICE: Original Contract Price: $ 19.371.131.1' Net inc:rease from previous Change Orders No. 1 through No.6: SI45.515,H Contract Pricepriorto this Change Order: $ 1?S1§.653,85 Net increase from this Change Order: $ 121,540.00 Contrae1 Pricewith all approved ChangeOrders: $19,639,193.85 CHANGE INCONTRACfTIME: Original Contract Times: Substantial Completion (Day,): 630 eWer daD Final Completion (Days): 730 gJspder diD Substantial Completion (Dale): .Illy 10.2011 Final Completion (Date): Ostober 18. 2011 Netchange from preVious Change Orders: Substantial Completion (Days): • calendar dlYs FinalCompletion (Days): .lilA. Substantial Completion (Date): Jyly 14.2011 Final Completion (Date): October 22. 2011 CODInlCI TImes prior 10 this Change Order: Substantial Completion (Days): §31 ffltndl r elm Final Completion (Days): 734glendlr r Substantial Completion (Date): Jgly 14.2011 Final Completion (Date): OsIober P. 2011 Net inc:rease thisChanae Order: 60days Substantial Completion (Days): July 14. 2011 (/I FinalCompletion (Days): December 2 J. 20ll Contract TImes withall approved Change Orders: Substantial Completion (Days): 63f glmdar elm (I) Final Completion (Days): '194 felspde•• Substantial Completion (Date): July 14,2ttl FinalCompletion (Dale): DetsmMrD, ZOll III Note:Certificate of Substantial Completion established July 8as dale of Substantial Completion. Page2 2705Bee CINeRo.d. SuiIe 300 AuIIIn. Telles 78746 U.S.A. t.St2.314.3100 FAll 1.5123143135 ~ACOBS September 13.201t Miehlel P.'FhaII. N), ) Construction Manager Brushy CreekReaionaJ Utility Authori 1906 HwlDduItriIJ Boulevard Cedar Part. Texas78613 RECEIVED MFT By ./chlle' F. ThUD, P.E. at 4:11 pm. Sep 13, 2011 'ty(BCRUA) APPROVED By Mlcha.1 F. Thuss, P.E. at 9:48 am, Sep 14,2011 Re: BCIll1A Raw Water Plpellae, , .....One· Contnet 1 Mlchae' F.Thuss, Cb....PropoaI Reqa.m A ~. P.E.A • ~.f~2011.09.14 Dear Mr. ThUll: 09:48:33-05'00' Enclosecl i. the reaponae fiom SJ. Louis Construction ofTexu. Ud. (SJ. Louis). dated September 9, 2011, to aR tn.7. Jacobi EqineeriDa Group,lnc. baa reviewed the COlt information submitted by SJ.LouiI. It is our opinion that the toCa1 COlt is fair IDd reuonable for the added KOpe ofwOlk. If BCRUA accepts thiscost proposal,• total of $122,540.00 will be incorporated into the nextchlD&e order. One correction shou1cl be made to the nota &om S.J. Louis included in tile proposal. The 45 day time a;tenlion should be chanaed to 60 clays, as requested in 1M breIkdown ofproposa1 eectioo. Consequently, iftbia it tceepted 1Mfinal completion date for 111 CODInCt work wi]) be a;tended from October 18,2011 to December 17,2011. Ifyouhaveany questions or Deed additional information, pleasecall. Sincerely, JACOBS BNGJNEERJNO GROUP, INC. Glenn A.Briclges, P Senior Project EnBineer XC: Jenn Higby, BCRUA Grace Stillman, BCRUA wi enclosures K:'4)~_trIC( l'CPR'l'OR G7'tCPR tl27ltuer 091311 doe Jacobs Engineering GroupInc. PropOSlll .,.. ",...,­I'W-'­.-w_ PhMe One· Contrect 1 MlM110,..,...", 1taIMINfIIf ", ".,. Glenn 8ItcfgM, P.E S8InueIO.~ JabI!ngIneImg Group, Inc. Prqect Coordnib'......• Bee Cave Roed. SUite 300 ~,T_78748 saMWd. 1). MON:ol1A 11U propOllledm-1IddIlone1 COllI aaoc;iIIed with ~of 24-dlemeelr dralnlgt cu!Yertl. drop ...... end headwlllllII two locItIons lI\CIer TI"IIII End Roed ..requeIIed by JlcobI Engineering 8nd deecribeclln CPR .27 (au.::hed). NOTES; •,.workIn'1IfIMII not tpeCIIIcIIv deecrlbed hIrIIn .... exdlldlcl. •M WICMtt .......til plOpOllllncludlng MItaIalkIn wi be perfotmed bv Bryant & F.., ConllNdlon.lnc ·OIHlte ~.be prvvIcI.cI bf8Iyn & FNY CoMtIucIIon, Inc., Peregreement ..IM EngI"",, 8.J. LouII ConItrucIan " notIWqURd 10prcMde. M tIIM ~for th1I watt. • ThlI PftlPOI'IIIndudeI eddIIIon of..a cIayIlD ..... oompllClon d-. of project CommIncImIrt of IdclIIIonII dIyI 18 nat to.slit unlil. A1lly .-cuted chlnoe ord«• rwctMId by S..L LouIs ConItrudIon. fill""" ... Dllcltpllon unit QIw. UnItS r.... COIIt NIW INSTALLATION Of'DRAINAGI CULV&JtT8". DElCRlIID ..CPR. %r La 1 '111,400.00 • 111.«10.00 8U8I'OTAL • 111,400.00 10'ltPROm • 11.140.00 NET CONTRACT CHANGE • 1Z2,....OO REQUESTED ADDI110NAL CALeNDAR DAYS 10 LJ. &.0.-Couhdorl AcffDft In 1M V. Whlnwl. S.J. LoullConltnJetion of T.... lid. . . BRYANT 6: FREY COKI'IRUCftON CO., INC -_......"CII""'I 204S WASHINGTON LANE WAOO, TEXAS 78708 PH: 254-753-2702 FAX: 254-753-2724 PROPOSAL DATE: __rt."1 Rev 918/201' JOB NAME: BCRUA -Change OrdtrRlq....27 BRYANT. JlRDICOPI 01''-: .....CON1'RACtORICOPI OFWORK A.FURNISH ALL LAlORAND EQWIMENT A.PERMfT8 NECUlAlWTOCCMlLEM 80AES 8. DEWATERItG PLAN 8. SET UP N«J AEMGYAL 01'I!QUIPMENT C. TRN'PIC 00N1R0L PLNI INTO AND OUT OFlORE PIT(a) D. Nt(CLEARI'G OF R.O.W. C.FURtIIH TRENCH IOXESADEQUATE POR BORE PITS D.REMOVE ~PROM lORE PIT e. DEWATIR lOR!PIT F. FUANlH ~PPEA8.ECIFII!D ON THE! PLANS 0It1HCS G.GROUI'INGOF AtlU.ARSPACE BeTWEEN ENCASEMENT IHJ NATURAL GROUND If'REQUIRED :ray D!8CRrP'nON PEltLJIT. MIOUNT " TRMS END DRAINAGE ..EI CULVERT8 _ ATTAaIID POItDITAU '111,400.00 $11 t.400.GO SO.oo so.oo 10.00 $0,00 ALL MAT!RW.818 TOBIAS -AND THEMOYEWORK TO IE PERFORMED INACCORDNCEwnHne DRAWlNB AND IPICFICATION8 ~FOR THE ABOVE WORK AND COIR.E'TED tI A SUBSTANTIAl.WORICMAN UI<E MANNER FOR THE SUM OF: APPROXIMATE DOlLARS: [: '111_10 j WITH PAVMI!NT TOIE MADE M FOLLOWS: • DAft UPON COMPLITION NI'( ALlERAnONl OR~TIONI FROM THE A80W SPECIFICATIONS INVOlVING EXTRA cosr WILle EXECUTED ONLV UPON WRmEN ORDI!R8NmWIU IECOMEM ADDfTtOtW. CHARGE OYER AltO MOW 'M!ESTlMATe. ALL AGREEMEN1I CONTWGENTIJPON aTRl<ES. ACCIDENTS, OR DELAYS BaOND OUR COH'TROL RESPECTFULLV SUBMITTED: IItVANrI,...,CON8TItUCIION CO..IIC PER: .9'9 ..... Nom81Frey NOT!: 1lI8 PAOPOCW. MAV Be WIIMDRAWN IV US.NOT ~wmilN 10DAYI. ACCEPTANCE OFPROP08AL. lHEAIOVE PRICES SPECIFICATIONS MD CONDmoNS ARE SATISFACTORV AND YOU ME HEREBY AUTHORIZED TO DO THE WORK SPECIFED. PAYMENT WILLBe MADE AS0U1\INED ABOVE IDATI!: SlGNATURE:I~=======~COMPANY:[ ____ YourBoring Fdends 8CRUA RlWWaIer PIpeIne• PMH One·ConIract 1 Che".. PrcIpoAI .......t.17 Unit E8L UnI Men. Otx. PrIce $15.000.00 $16,000.00LS ' _ $2.100.00 3 Trench s.ttty 1.....,lIlIon LS ss.ooo.oo $3.000.00 80 '--;,.,;,.-- _ • 2401ftch X.5OOWd....e......ent LF $1Z5.00 "0.000.00 LS t 17,500.00 4 -.,0,000.00EA LF 80 $200.00_ "'.000.00 $10,100.00••••00 -'000.00 2--;".,;..-- 1La t TyITxDot. Drap........ W10tfJllM tnd Aprone EA 2 ""'4)To ..8Ihd In ,.,.SO DaV-01Project TOTAL LS 1 ••800.00 13e.ooo.oo ....1-7) To Be Billed,., LFT TOTAL 80 $&37.50 M1.ooo.00LF ~N) To" a.d Wbeft CoMpte" Total LS S22.,,00.00 122.400.00 TOTAL $111,400.00 FInn: Bryant & FNy Construction By. $f'-r"I NonnaD Frey nile: I pMdent DATE: October 14, 2011 SUBJECT: BCRUA Board Meeting -October 19,2011 ITEM: 6F. Consider a resolution approving Change Order No.7 with SJ louis for Raw Water Pipeline Phase One, Contract 1. PRESENTER: Michael F.Thuss, P.E. Program Manager Justification: This change order is to correct pre-existing drainage issues in two different locations on Trails End Road. The drainage culverts will extend the reliability of the roadway. The change order will not change the substantial completion date and adds sixty (60) calendar days to the final completion. Funding: Change Order #7 is for an additional $122,540.00 to the contract, revising the total contract amount to $19,639,193.85. Funding for this change order is from the project's contingency. EXECUTED DOCUMENTS FOLLOW Page1 of 1 COntract Quantity Adjustment/Change Order BCRUA Raw Water Pipeline Phase One ­ Project Name: ..,;.Con.......;..tra....;..;.ct....;1'--_ Contractor: S.J. Louis Construction of Texas, Ltd. Date: 9/14/2011 Change Order/Quantity Engineer: Jacobs Engineering Group,Inc. Adjustment No. Justification 1 SUMMARY Original Contract PrIce: -­ Amount ...::.=a:.. $19,371,138.19_ Previous Quantity Adjustment(s): this Quantity Adjustment: Total Quantity Adjustment(s): Total Contract Price with Quantity Adjustment(s): $0.00 $0.00 $19,371,138.19 Previous Change Order(s): this Change Order: Total Change Order(s) To Date: OrIginal Contract PrIce Plus Olange Order(s) Quantity Adjustment(s): Plus $145,515.66 $122,540.00 O.15oto 0.63010 OrIginal Contract Time: Contract Time PrIor to this Change Order: contract TIme with All Approved Q\ange Orders: 730 calendar days 734 calendar days 794 calendar days (Anal) (Rnal) (Final) 268055.66 Signature=r w~A.vD/I#7,u--- Glenn A. Bridges, P.E., Project Engineer Jacobs En neerln Grou, Inc. PrintedName, Title and Company ~,o"". Pf~loi SO~ 1£oIAS' fItI.CA ~ ..;.T. U>vl$ ~QlooJ Sf ~~ IJfZ Signature Printed Name, TItleand Company Date BCRUA Approval: PrInted Name, TItle Cr-al-.(,,-F \.sl~~ ~"\.... ~eb ...n. Printed Name, TItle Date (D·t _ 7 CHANGE ORDER No.7 DATEOF ISSUANCE: 09-14-11 EFFECTIVE DATE: _ OWNER: BCRUA CONTRACTOR: SJ. Louis Construction of Texas, Ltd. PROJECT: BCRUA Raw Water Pipeline Phase One -Contract 1 ENGINEER: Jacobs Engineering Group, Inc. The Contractor isherebydirectedto make the following changesintheContract Documents: Change Proposal Request #27 l. Install drop inlets. 24" diameter drainage culverts and headwalls with energy dissipaters at two locations under Trails End Road. ADD $122,540.00 Page I Project:BCRUA RawWaterPipeline PhaseOne -Contract I Change Order No. 7 CHANGE IN CONTRACT PRICE: Original Contract Price: $ 19,371.138.19 Net increase from previous Change Orders No. I through No.6: S 145,s15.66 Contract Price prior to this Change Order: $ 19,516,653.85 Net increase from this Change Order: $ 122,540.00 Contract Price with all approved Change Orders: $19,639,193.85 CHANGE IN CONTRACf TIME: Original Contract Times: Substantial Completion (Days): 630 atlendar days Final Completion (Days): 730 calendar days Substantial Completion (Date): July 10, 2011 Final Completion (Date): October 18, 2011 Net change from previous Change Orders: SubstantialCompletion(Days): 4 calendardays Final Completion (Days): J:Y.A Substantial Completion (Date): July 14,201 I Final Completion (Date): October 22.2011 Contract Times prior to thisChangeOrder: Substantial Completion (Days): 634 calendar days Final Completion (Days): 734 calendar daxs Substantial Completion (Date): July 14,2011 (Ij Final Completion (Date): October 22, lOU Net increase this Change Order: 60 days Substantial Completion (Days): July 14,2011 (11 FinalCompletion (Days): December 21. 2011 Contract Times with all approved Change Orders: Substantial Completion (Days): 634 calendar daYS 11) Final Completion (Days): 794 calendar ~fr"s Substantial Completion (Date): July 14, 2011 Final Completion (Date): December 21, 2011 (I) Note: Certificate of Substantial Completion established July 8 as date of Substantial Completion. Page 2 2705Bee CaveRoad. Suite 300 Auslln.Texas78746 U,S.A,JACOBS '512,314,3'00 Fall 1,5123'43135 Sepkmber13,2011 Miohael F. 'Fhuss. P.B. ) Construction Manager Brushy Creek Regional Utility Authori 1906Hur Industrial Boulevard Cedar Park,Texas 78613 RECEIVED MFT By Michael F. Thuss, P.E. at 4:11 pm, Sep 13, 2011 'ty(BCRUA) APPROVED By Michael F. Thuss, P.E. at 9:48 am, Ssp 14, 2011 Be: BCRUA Raw Water PlpeUDe, PUse ODe -CODtract 1 Michael F. Thuss, Cbaage Proposal Reqaest #'1.7 A • ff ~P.E. ~.r~ 2011.09.14 Dear Mr.Thuss: 09:48:33 -05'00' Enclosed is the response from S.I. Louis Construction of Texas, Ltd. (SJ. Louis). dated September 9. 2011,toCPR#27. Jacobs Engineering Group,Inc.has reviewed the cost information submitted by S.J. Louis. It is our opinion that the total cost is fairand reasonable for the added scope of work. If BCRUA accepts this cost proposal, a total ofS122,540.00 will be incorporated into the next change order. One correction should be made to the notesfrom SJ.Louis included in the proposal. The45 day time extension should be changed to 60 days.as requested in the breakdown ofproposal section. Consequently,ifthis isacceptedthe final completion date forall contract workwill be extended from October 18,2011 to December 17.2011. Ifyouhaveany questions or need additional information, pleasecall. Sincerely, JACOBS ENGINEERING GROUP, INC. GlennA.Bridges. P • SeniorProject Engineer xc. Jenn Higby, BCRUA Grace Stillman, BCRUA wI enclosures K:\OS0844'constrvclion'conll'Kt tICPR's'CPR 127'CPR 127 letlCT 091311 doc Jacobs Engineering Group Inc. Proposal If'roJecIIUme PropoaINo. 01. Raw Water PIpeUne Phese One • Contract 1 10 919111 RequIred By n."."",.,By Mr,Glenn Bridges. P.E Samuel D. Montoya Jacobe Engineering Group, Inc. Project Coordinat<lr 2705 Bee C8\18 Road, Suite300 SlgnlICIn Austin, Texu 78746 SA~..w. D. MO~~A 01CIt.". This proposal addresses addltlonal costs associ8l8d with installation of 241\" diameter drainage culverts. dropInlels. and headwalls at two locations underTrailsEnd Road as requested by Jacobs Engineering and described In CPR #27 (attached), NOTES: • AI workImaterteIa not specifically described herein are excluded. -AI WCIfk auoclatectwMh thispropOl8l including restoration witl be perfonned by Bryant & Frey Construction. Inc • On-site supervision will be provided by Bryent &Frey ConsbUClion, Inc.• Per agreement with the Engineer, S.J. louis Conatrudlon Ie not required to provide a fuI tine 8Upenntendent for this woJ1(. -Thia propoaaIlnctudeleddltion of 45 days to final complltlon dateof prcject. Commencement of additional days II not to startuntil• fully executed change order • reoelved by S.J. Louis Cons1ructlon. afPrapoul 111m DescrIption Unit Qty. UnItS Total Colt NEW INSTALLAnoN OF DRAINAGE CUlVERTS M DESCRIBED IN CPR' LS 1 S 111.400.00 S 111.<400.0027 SU8TOTAt. S 111,400.00 10% PROFIT I 11,140.00 NET CONTRACT CHANGe $ 1%2,140.00 REQUESTED ADDITIONAL CALENDAR DAYS 10 SJ. "",en. eo.trucfIof) Acffon xc I.ea V. Whitman. S.J.Louis Construction of Texas. Ltd. " BRYANT a: FREY CONS-rRUCTION CO., INC ROAD BORIIIO IPI:CU',gY 204S WASHINGTON LANE WACO, TEXAS 76708 PH:254-753-2702 FAX: 254-753-2724 PROPOSAL DATE: Aug .... 27.2111 Rev 9181'201 , JOB NAME: BCRUA • CM", Order Request 27 BRYANT a FREY SCOPE OFWORK: PRIIIIE CONTRACTOR SCOPE OFWORK A. FURNISH ALL LABOR AND ~ A. PERMITS NECESSARY TOCOI.FlETE BORES B.DEWATERING PlAN B.SETUP AND REMOVAL OF EQUIPMENT C.TRAFFIC CONTROL PLAN INTO ANDOUTOF BORE PfT(1) D.Nff Cl.EARJNG OF R.O.W. C. FURNISH TRENCH BO)CE8 ADEQUATE FOR BORE PITS D. REMOVE SPOILS FROM BORE PIT E. DEWA1'I!R BORE PIT F.FURNISH ENCASEMENT PPEAS SPECIFIED ONTHE PLANS ORSPECS G.GROUTING OFANNUlAR SPACE BeTWEEN ENCASEMENT AND NATURAL GROUND IF REQUIRED APPROXIMATELY DESCRtP'nON PERLFT. AMOUNT l' TRAI.S END DRAINAGE PIPE & CULVERTS $111,400.00 $111.400.00 $0.00 SU ATTACHID FOR DeTAILS $0.00 $0.00 SO.OO ALLMATERIALS ISGUARANTEED TOBEAS SPEClFED AND THEASOVE WORK TOBE PERFORMED IN ACCORDANCE WITH THE DRAWlNG AND SPECIFICATIONS SUBfMTTED FOR THEABOVE WORK AND COMPlETED IN ,.,SUBSTANTIAL WORKMAN UKE ~NER FOR THE SUN OF: APPROXIMATE DOLLARS: []111,400.00 WITH PAYMENT TOBE MADE M FOLLOWS: 30 DAYS UPON COMPLETION Nf'( ALTERATIONS OR~nONS FROM THE MOVE SPECIFICATIONS INVOlVING EXTRA COST WILL BE EXECUTED ONLY UPONWRmEN ORDERSAM} Will BECOME AN ADOtTIONAL CHARGE OVER AND ABOVE nE ESTIMAlE. All AOREEMENTS CONTINGENT UPON STRIKES, ACCIDENTS. OR DELAYS BEYOND OUR CONTROl. RESPECTFULLY SUBMITTED: BRYANT & PRQ CONSTRUCTION CO..INC PER: 9fQ,..sp Norman Frey NOTE: THIS PROPOSAl. MAY BEWI1'HDRAWN BY us IF NOT ACCEPTED WlT1iIN 30 DAYS. ACCEPTANCE OF PROPOSAL. THEASOVE PRICES SPeCIFICATIONS AND CONDmONS ARE SATISFACTORY AND YOU ARE HEREBY AUTHORIZED TODOTHE WORK SPECIFIED. PAYMENT WILLBE MADE AS 0IJn1NED ABOVE IDATE: SIGNATURE:!============= COMPANY:1 _ Your Boring FrIends BCRUA Raw Water Pipeine •Phase One• Contract1 Chlnge ~81 Request. 17 Item Unit EsL Unit Item No. OescrIpIIon MeIS. Qty. PrIce AmOUf1:;;.;..t__ MobllzaUon For Protect Incidentals LS $15.000.00 $15,000.00 2 Trench Safety Plan EA 1 $2.500.00_ $2.500.00 3 Trench Safety ImpJementaUon LS $3,000.00 $3,000.00 .. 24-lnch X .500Wei Steel Encasem.nt LF 80 $125.00_ $10,000.00 S TrafIIc Control Plan ImplemlnfBllon LS 1 $7,500.00 $7.500.00 5 Excavate Bore Pits EA 4 $2.500.00_ $10,000.00 6 24-lnch Bores LF 80 $200.00_ $16.000.00 7 Haul orr Excav8ted Matertal From PIts & BONa LS 1 $25.000.00 $25.000.00 EA 2 $5,400.00 $10.800.00 9 Ty I TxDol Drop InletsWlGratMJ and Aprons EA 2 $6.800.00 $11,600.00 (lterna 1-4) To Be Billed In FlNt 30 Days of Project TOTAL LS 1 $25.600.00 $38,000.00 (IteIM 5-7) To Be SWed Per L.FT TOTAL (!tema 808)To Be Blled When Com". Total LF lS 80 1 $637.50 $22,400.00 $51.000.00 $22.400.00 TOTAL $111_400.00 Firm: Bryant & Frey Construction By: ~.....tm h!V I Norman Frey nUt: I President 2705 Bee Cave Road. Svile 300 Austin. Texas 78746 U S.A ..JACOBS' 1.512.3143100 Fa. 1512 3143135 August4, 2011 Samuel D.Montoya S.J. Louis Construction ofTexas Ltd. 9862 Lorene St.,Suite200 San Antonio, Texas78216 Re: Brushy Creek Realoaal Utility Aotlaority (BCRUA) Raw Water PlpeliDe, Phase ODe -CODtnet 1 ClaaDge Proposal Request #27 Dear Mr. Montoya: Please provide acostproposalforthe following additional scope of work: 1. Install dropinlets,24"diameter drainage culvertsand headwalls with energy dissipators attwolocationsunder Trails EndRoad,as shownonthe enclosed drawings. Plan &profileviewsare shown onnewSheetC-43,drop inletisshownon newSheet e-44 (TxDOT Standard OI-TYl-(4) and headwall with energy dissipators is shown onCityof Austin Standard Detail S08S-13. If the proposal is accepted,achangeorder will be preparedforthe work. Ifyouhaveany questions, please do not hesitate to contact me at S12-314-3182. Sincerely, JACOBS ENGINEERING GROUP, INC. Glenn A. Bridges, Senior Project En w/encJosures XC: Mike Thuss, P.E.,BCRUA Jennifer Higby, BCRUA Grace Stillman, BCRUA David Dial, David Dial & Associates K:'D50844\eonstruCtion\cootncl I'changeproposal requeslS\cPR 1127.doc Jacobs Engmeermg Group Inc.