BCRUA_R-11-12-14-6ERESOLUTION NO. R-1l-12-14-6E WHEREAS, the Brushy Creek Regional Utility Authority, Inc. ("BCRUA") has previously entered into a contract ("Contract") with S.l Louis Construction of Texas, Ltd. for the BCRUA Raw Water Pipeline Phase One - Contract No.1 Project, and WHEREAS, the BCRUA has determined that it is necessary to make adjustments/changes to the quantity of work to be performed or materials, equipment, or supplies to be provided, and WHEREAS, it has been determined that it is necessary to adjust/change the quantities in said Contract in accordance with the attached Quantity Adjustment/Change Order No.9, Now Therefore BE IT RESOLVED BY THE BRUSHY CREEK REGIONAL UTILITY AUTHORITY, That the Board President is hereby authorized and directed to execute on behalf of the BCRUA, Quantity Adjustment/Change Order No.9 to the Contract with S.J. Louis Construction of Texas, Ltd. for the Raw Water Pipeline Phase One - Contract No. 1 Project, a copy of same being attached hereto as Exhibit "A" and incorporated herein for all purposes. The Board hereby finds and declares that written notice of the date, hour, place and subject of the meeting at which this Resolution was adopted was posted and that such meeting was open to the public as required by law at all times during which this Resolution and the subject matter hereof were discussed, considered and formally acted upon, all as required by the Open Meetings Act, Chapter 551, Texas Government Code, as amended. RESOLVED this 14th day of December, 2011. tt1 ~~.~ GEORGE WH~esident Brushy Creek Regional Utility Authority ---+--~--------------~ Z:\BCRUA\Board PacketllPackel DoaJrnentsI121411IRes. BCRUA Change Order # 9 w-S.J. Louie -Rsw WL Pipeline (OO239296).DOCInnc ---1 Page 1 of 1 Contract Quantity Adjustment/Change Order rev. 9/2011 BCRUA Raw Water Pipeline Phase One ­ Project Name: _CO_ntr_a_ct_1 _ Contractor: SJ. Louis Construction of Texas, Ltd. Date: 12/5/2011 cnange Order/Quantity Engineer: Jacobs Engineering Group, Inc. Adjustment No. 9 Justification SUMMARY Original Contract Price: Previous Quantity Adjustment(s): This Quantity Adjustment: Total Quantity Adjustment(s): Total Contract Price with Quantity Adjustment(s): Previous Change Order(s): This Change Order: Total Change Order(s) To Date: Original Contract Price Plus Change Order(s) Plus Quantity Adjustment(s): Original Contract Time: Contract TimePrior to this Change Order: Contract Time with All Approved Change Orders: Amount % Change $19,371,138.19 $0.00 $0.00 $19,371,138.19 $297,513.38 1.54% $89,055.83 0.46% $386,569.21 2.00% $19,757,707.40 730 calendar days (Final) 797 calendar days (Final) ~Iendar days (Final) Prepared By: Contractor Approval: BCRUA Approval: ~ BCRUA Approval: Glenn A. Bridges, P.E., Project Engineer Jacobs Engineering Group, Inc. Printed Name, Title and Company t>~II'A'J)~ ~,." ~.1.L.()M~U11.V if Printed Name, Title and Company Date Al~H~I1't. r:~d.:1 p~,.< Printed Name, Title Date Signature Printed Name, Title Date EXHIBIT "Pa' A '.rtnershlp 0' C.dar Park. Leander. and R.ound R.ock CHANGE ORDER No.9 DATE OF ISSUANCE: 12-05-11 EFFECTIVE DATE: _ OWNER: BCRUA CONTRACTOR: S.J. Louis Construction of Texas, Ltd. PROJECT: BCRUA Raw Water Pipeline Phase One ­Contract 1 ENGINEER: Jacobs Engineering Group, Inc. The Contractor is hereby directed to make the following changes in the Contract Documents: 1. Add replacement of vaults for 24-inch air/vacuum valves, per CPR # 30 ADD s 56,546.85 2. Add HMAC Bonus, per CPR # 31 ADD $ 32,508.98 TOTAL (Items 1 - 2) ADD s 89,055.83 Page 1 - ---------------- Project: HCRUA Raw WaterPipelinePhaseOne-Contract I ChangeOrder No.9 CHANGE IN CONTRACT PRICE: Original Contract Price: s 19,371,138.19 Net increase from previous Change Orders No. 1 through No.8 s 297,513.38 Contract Price prior to this Change Order: s 19,668,615.57 Net increase from this Change Order: s 89,055.83 Contract Price with all approved Change Orders: s 19,757,707.40 CHANGE IN CONTRACT TIME: Original Contract Times: Substantial Completion (Days): 630 calendar days Final Completion (Days): 730 calendar days Substantial Completion (Date): July 10,2011 Final Completion (Date): October 18, 2011 Net change from previous Change Orders: Substantial Completion (Days): 4 calendar days Final Completion (Days): N/A Substantial Completion (Date): July 14.2011 Final Completion (Date): October 22.2011 Contract Times prior to this Change Order: Substantial Completion (Days): 634 calendar days Final Completion (Days): 797 calendar days Substantial Completion (Date): July 14,2011 (Ij Final Completion (Date): December 24, 2011 - Net increase this Change Order: 14 days Substantial Completion (Days): July 14. 2011 (I) Final Completion (Days): JanuaI)' 7. 2012 Contract Times with all approved Change Orders: Substantial Completion (Days): 634 calendar days (1) Final Completion (Days): e S S -8l+calendar days Substantial Completion (Date): July 14, 2011 \II Final Completion (Date): .,Janliar f-ff 2012 felt,t40 ...... ~ , (I) Note: Certificate of Substantial Completion established July 8 as date of Substantial Completion. Page 2 EXECUTED DOCUMENTS FOLLOW ---1 Contract Quantity Adjustment/Change Order Page1of 1 rev. 9/2011 BCRUA Raw Project Name: ....;;CO;,;;,n;.;.;tr;;.;a;;.;ct;.;;...;;;.l Water Pipeline Phase One _ - Contractor: Engineer: S.J. Louis Construction of Texas, Ltd. Jacobs Engineering Group, Inc. Date: cnange Order/Quantity Adjustment No. 12/5/2011 9 Justification SUMMARY Amount 0/0 Change Original Contract Price: $19,371,138.19 Previous Quantity Adjustment(s): This Quantity Adjustment: $0.00 Total Quantity Adjustment(s): $0.00 Total Contract Price with Quantity Adjustment(s): $19,371,138.19 Previous Change Order(s): $297,513.38 1.54% This Change Order: $89,055.83 0.46% Total Change Order(s) To Date: $386,569.21 2.00% Original Contract Price Plus Change Order(s) Plus Quantity Adjustment(s): $19,757,707.40 Original Contract Time: 730 calendar days (Final) Contract TimePriorto this Change Order: 797 calendar days (Final) Contract Time with All Approved Change Orders: -&tt-calendar days (Final) Glenn A. Bridges, P.E., Project Engineer Prepared By: Contractor Approval: BCRUA Approval: BCRUA Approval: Date Ito. Partner, hlp of Cedar Park. Leander. and Round Rock CHANGE ORDER No.9 DATE OF ISSUANCE: 12-05-11 EFFECTIVE DATE: _ OWNER: BCRUA CONTRACTOR: S.J. Louis Construction of Texas, Ltd. PROJECT: BCRUA Raw Water Pipeline Phase One -Contract 1 ENGINEER: Jacobs Engineering Group, Inc. The Contractor is hereby directed to make the following changes in the Contract Documents: 1. Add replacement of vaults for 24-inch air/vacuum valves, per CPR # 30 ADD s 56,546.85 2. Add HMAC Bonus, per CPR # 31 ADD $ 32.508.98 TOTAL (Items 1-2) ADD s 89,055.83 Page 1 Project:HCRUA Raw WaterPipelinePhase One-ContractI ChangeOrder No.9 CHANGE IN CONTRACT PRICE: Original Contract Price: s 19.371,138.19 Net increase from previous Change Orders No. 1 through No.8 s 297,513.38 Contract Price prior to this Change Order: s 19,668,615.57 Net increase from this Change Order: s 89,055.83 Contract Price with all approved Change Orders: s 19,757,707.40 CHANGE IN CONTRACT TIME: Original Contract Times: Substantial Completion (Days): 630 calendar days Final Completion (Days): 730 calendar days Substantial Completion (Date): July 10,2011 Final Completion (Date): October 18, 2011 Net change from previous Change Orders: Substantial Completion (Days): 4 calendar days Final Completion (Days): N/A Substantial Completion (Date): July 14.2011 Final Completion (Date): October 22. 2011 Contract Times prior to this Change Order: Substantial Completion (Days): 634 calendar days Final Completion (Days): 797 calendar days Substantial Completion (Date): July 14,2011 (I) Final Completion (Date): December 24, 2011 - Net increase this Change Order: 14 days Substantial Completion (Days): July 14.2011 (I) Final Completion (Days): January 7.2012 Contract Times with all approved Change Orders: Substantial Completion (Days): 634 calendar days (1) Final Completion (Days): & S S -I4+calendar days Substantial Completion (Date): July 14, 2011 (I) Final Completion (Date): ..Janaa.,,:z., 2012 ~1.'Mo.""" ~ \ (1) Note: Certificate of Substantial Completion established July 8 as date of Substantial Completion. Page 2