BCRUA_R-19-09-25-6C RESOLUTION NO. R-19-09-25-6C WHEREAS, the Brushy Creek Regional Utility Authority, Inc. ("BCRUA") has previously entered into a Contract for Engineering Services ("Contract") with Walker Partners for the BCRUA Phase 1C Water Treatment Plant Expansion and Phase 2 Land Rights and Stakeholder Coordination Project, and WHEREAS, Walker Partners has submitted an amended Supplemental Contract No. 6 to the Contract to modify the provisions for the scope of services and to increase the compensation, and WHEREAS, the BCRUA desires to enter into said amended Supplemental Contract No. 6, Now Therefore BE IT RESOLVED BY THE BOARD OF DIRECTORS OF THE BRUSHY CREEK REGIONAL UTILITY AUTHORITY; That the Board President is hereby authorized and directed to execute on behalf of the BCRUA an amended Supplemental Contract No. 6 with Walker Partners for the BCRUA Phase IC Water Treatment Plant Expansion and Phase 2 Land Rights and Stakeholder Coordination Project, a copy of same being attached hereto as Exhibit"A"and incorporated herein for all purposes. The Board hereby Ends and declares that written notice of the date, hour, place and subject of the meeting at which this Resolution was adopted was posted and that such meeting was open to the public as required by law at all times during which this Resolution and the subject matter hereof were discussed, considered and formally acted upon, all as required by the Open Meetings Act, Chapter 551, Texas Government Code, as amended. RESOLVED this 25th day of September, 2019. Z WKUMOvard Packets.Packef Docvmerns12019*92S2019%es BCRUA-approve amended SC u6 w-Walker Panncn(004]1724008F8)Jae M"A�- ANNIfI6UFFY', Prei nt Brushy Creek Regio 1 tility Authority ATTEST: IX51-111- b(!40N'§FIAW, Secretary 2 DATE: September 23, 2019 SUBJECT: BCRUA Board Meeting—September 25, 2019 ITEM: 6C. Consider a resolution authorizing the President to execute an amended Supplemental Agreement No. 6 with Walker Partners for Phase 1C Water Treatment Plant Expansion and Phase 2 Land Rights and Stakeholder Coordination Project. PRESENTER: Karen Bondy,General Manager BACKGROUND/JUSTIFICATION: The original contract was approved on April 19,2017 as follows: Phase 1C Water Treatment Plant Expansion Design (Lump Sum) $1,763,900.00 Phase 2 Land Rights&Stakeholder Coordination(Not To Exceed) $2,012,600.00 TOTAL $3,776,500.00 Five Supplemental Contracts have since been approved, leaving the new contract balances as: Phase 1C Water Treatment Plant Expansion Design (Lump Sum) $1,837,900.00 Phase 1C Construction Phase Services(Not To Exceed) $897,200.00 Phase 2 Land Rights&Stakeholder Coordination(Not To Exceed) $2,329,800.00 CURRENT TOTAL $5,064,900.00 Supplemental Agreement No. 6 includes services for the Phase 2 Land Rights and Stakeholder Coordination effort for areas where improvements are needed to overhead electric in existing easements and includes a limited number of temporary construction easements.These services include project management, right of way and land acquisition efforts, agency and stakeholder coordination, and preliminary design updates. The amounts billed will be based on the cumulative hours charged to the project during the billing period by each class of the engineer's employees, times standard hourly rates for each applicable billing class, plus reimbursable expenses, and engineer's consultant's charges.Amounts payable to the engineer for reimbursable internal expenses and the engineer's consultant expenses,will be subject to a 5%overhead factor.The total compensation for these services is estimated as a not to exceed amount of$497,405.00. If approved,the new project budget totals will be: Phase 1C Water Treatment Plant Expansion Design (Lump Sum) $2,837,900.00 Phase 1C Construction Phase Services(Not To Exceed) $897,200.00 Phase 2 Land Rights&Stakeholder Coordination(Not To Exceed) $2,827,205.00 NEW TOTAL $5,562,305.00 BCRUA staff and the Operations Committee (O.C.) have reviewed the proposed Supplemental Contract#6 with Walker Partners and recommend Board approval.Staff, the O.C., and the consultant will be available to answer any questions or concerns during the Board Meeting. FUNDING: Supplemental Contract No. 6 will be funded by 2018 SWIFT funds for Cedar Park and Leander and by Phase 1A savings for Round Rock. r { - � f :emABRUSHYCREEK REGIONAL UTILITY AUTHORITY A Pa rrn.r ae lP of C.dar Par M, L.an d.r, and A n,,J 0.eek SUPPLEMENTAL CONTRACT NO. 6 TO CONTRACT FOR ENGINEERING SERVICES FIRM: WALKER PARTNERS ("Engineer") ADDRESS: 804 Las Cimas Parkway, Suite 150,Austin,TX 78746 PROJECT: Phase I Water Treatment Plant Ex ansion and Phase 2 Land Ri hts and Stakeholder Coordination This Supplemental Contract No. 6 to Contract for Engineering Services is made by and between the BRUSHY CREEK REGIONAL UTILITY AUTHORITY, INC., hereinafter called "BCRUA"and Walker Partners, hereinafter called the"Engineer". WHEREAS, BCRUA and Engineer executed a Contract for Engineering Services, hereinafter called the "Contract", on the 19th day of April, 2017 for the BCRUA Phase 1 C Water Treatment PIant Expansion in the lump sum amount of $1,763,900.00 and Phase 2 Land Rights and Stakeholder Coordination Project in the maximum amount of$2,012,600.00 for a total Project compensation of$3,776,500.00; and WHEREAS, BCRUA and Engineer executed Supplemental Contract No. I on July 19, 2017 to amend the scope of services and to increase the compensation by $14,100.00 for Phase I C Water Treatment Plant Expansion to a lump sum amount total of$1,778,000.00 and by $212,000.00 for Phase 2 Land Rights and Stakeholder Coordination Project to a maximum amount total of $2,224,600.00 for a total Project compensation of$4,002,600.00; and WHEREAS, BCRUA and Engineer executed Supplemental Contract No. 2 on November 20, 2017 to amend the scope of services and to increase the compensation by $19,600.00 for Phase IC Water Treatment Plant Expansion to a Iump sum amount total of$1,797,600.00 for a total Project compensation of$4,022,200.00; and WHEREAS, BCRUA and Engineer executed Supplemental Contract No. 3 on April 18, 2018 to amend the scope of services and to increase the compensation by $105,200.00 for Phase 2 Land Rights and Stakeholder Coordination Project to a maximum amount total of$2,329,800.00 for a total Project compensation of$4,127,400.00; and WHEREAS, BCRUA and Engineer executed Supplemental Contract No. 4 on October 24, 2018 to add the construction phase services for the Phase I C Construction Phase Services Project and to increase the compensation by $897,200.00 for a total Project compensation of$5,024,600.00; and I Supplemental Contract Rev.03/2011 0140.4634-40;00432249 ll 215829 1 El� Jt WHEREAS, BCRUA and Engineer executed Supplemental Contract No. 5 on April 30, 2019 to modify the provisions for the scope of services and to increase the compensation by $40,300.00 for Phase l C Water Treatment Plant Expansion to a lump sum amount total of$2,735,100.00 for a total Project compensation of$5,064,900.00; and WHEREAS, it has become necessary to amend the Contract to modify the provisions for the scope of services and to increase the compensation by $497,885.00 for Phase 2 Land Rights and Stakeholder Coordination Project to a maximum amount total of$2,827,685.00 for a total Project compensation of$5,562,785.00; NOW THEREFORE, premises considered, BCRUA and the Engineer agree that said Contract is amended as follows: 1. Article 2 Engineering Services and Exhibit B, Engineering Services shall be amended as set forth in the attached Addendum To Exhibit B' Exhibit C, Work Schedule shall be amended as set forth in the attached Addendum To Exhibit C. IL Article 4 Compensation and Exhibit D Fee Schedule shall be amended by increasing by $497,885.00 the maximum amount payable under the Contract for Phase 2 Land Rights and Stakeholder Coordination Project to a total of$2,827,685.00 for a total Project compensation of $5,562,785.00, as shown by the attached Addendum to Exhibit D. IN WITNESS WHEREOF, BCRUA and the Engineer have executed this Supplemental Contract in duplicate. [signalure pages follow] 2 WALKER PARTNERS By: Date BRUSHY CREEK REGIONAL UTILITY AUTHORITY, INC. By: Anne Duffy, President Date APPROVED AS TO FORM: By: Stephan L. Sheets, BCRUA Attorney 4 ADDENDUM TO EXHIBIT B ENGINEERING SERVICES GENERAL The purposes of Supplemental Amendment No. 6 are as follows: - Update prior evaluations of three overhead electric routes starting at the intersection of Nameless Road and FM 1431 and continuing to the intersection of North Rim Drive and Trails End Road. The following is a brief description of each route: Route 1 —The "Preferred Route"from Technical Memorandum(TM)2-8 that contacts an existing single-phase line near the end of North Rim Drive and proceeds east along North Rim Drive to Trails End Road. o Route 2— "Alternative Route 2"from TM 2-8 that follows an existing single-phase line south of and parallel to North Rim Drive before turning north on Lost Ridge Circle to North Rim Drive and east to Trails End Road. a Route 3—Follows FM 1431 from Nameless Road to Trails End Road. - Support OWNER with the acquisition of electric easements associated with rebuilding existing Pedernales Electric Cooperative(PEC)overhead distribution lines from the PEC Nameless Substation to the pump station site; - Support OWNER with the acquisition of temporary construction easements needed for the Phase 2 Raw Water Delivery System Project; - Provide on-call technical support and coordination with PEC(provided by subconsultant M&S). BASIC SCOPE OF SERVICES Task 2.0- Phase 2 Land Rights and Stakeholder Coordination Insert Task 2.2.10 North Rim Overhead Electric Alternative Alignment Evaluation Update as follows: 2.2.10 North Rim Overhead Electric Alternative Alignment Evaluation Update. 2.2.10.1 Develop conceptual designs of the Route 3 in a manner that is consistent with the level of design detail utilized to define the alignment of Route 1 and 2 as documented in TM 2-8. The routing analysis shall be planning level in nature and suitable for development of an opinion of probable cost. Develop a.preliminary map of the route and description of route challenges. 2.2.10.2 Develop planning level opinions of probable cost for each of the three routes. Easement and right-of-way costs shall be estimated and included for each route. 9/24/2019 @WAer Partners engineers • Sulwclyt}r 2.2.10.3 Prepare and present a Technical Memorandum that compiles and presents the conceptual designs and planning level opinions of probable costs. Address OWNER comments and finalize the TM. Insert Task 2.5 as follows: 2.5 Additional Easement Acquisition 2.5.6 Project Management, Coordination and Meetings 2.5.6.1 Attend monthly progress meetings with OWNER for a total of 8 meetings 2.5.6.2 Manage and coordinate staff resources,subconsultants, and project planning. 2.5.6.3 Prepare monthly invoices and project progress reports.As a minimum, monthly progress reports shall include a summary description of tasks completed as of the report date, description of activities planned for the next 60 days, financial status of the project,status of schedule for project, and identification of technical or other issues which may have an impact to the overall project budget and/or schedule. 2.5.6.4 Facilitate document control and document sharing for electronic filing of documents. Maintain project and parcel/easement documents. 2.5.6.5 Prepare, update and maintain initial property owner contact list. 2.5.6.6 Maintain records of all payments to property owners including amount and date paid. 2.5.6.7 Maintain copies of all correspondence and contacts with property owners. 2.5.7 Land Acquisition and Right of Way. Support acquisition of easements and land rights for the Project. The total number of assumed parcels/easements is 48 parcels including 43 parcels/easements for electrical improvements and 5 parcels/easements for temporary construction easements. 2.5.7.1 Surveying. Perform site surveying for 5 temporary construction easements, 43 electric easements. Perform boundary survey and prepare exhibits and field notes of parcels to be conveyed. Complete topographic survey of temporary construction easements. Horizontal and vertical datums for project control will remain on NAD83/NAVD88 Texas State Plane, Central Zone. 2.5.7.2 Negotiation Services. 2.5.7.2.1 Research official public records to update ownership and provide i vesting deeds to surveyor. 2.5.7.2.2 Prepare Broker's Opinion of Value for each easement. 9/2412019 (9 Walker Partners engineers * surveyors f 2.5.7.2.3 Analyze appraisal report and confirm OWNER approved value prior to making offer for each parcel/easement. Submit request for authorization to make offers. 2.5.7.2.4 Prepare and send the letter transmitting the Landowner's Bill of Rights by Certified Mail-Return Receipt Requested (CMRRR). 2.5.7.2.5 Prepare documents required on forms approved by OWNER (i.e., the initial offer letter, memorandum of agreement, instruments of conveyance). 2.5.7.2.6 Send the written offer and appraisal report to each property owner or the property owner's designated representative by CMRRR. Appraisal reports to be prepared under separate contract. 2.5.7.2.7 Maintain follow-up contacts and secure the instruments necessary for the closing upon acceptance of the offer. 2.5.7.2.8 Respond to property owner inquiries verbally or in writing within two business days. 2.5.7.3 PEC Technical Support and Coordination. Support OWNER through coordination with PEC for development of the Temporary Power Project. Attend project coordination meetings and conference calls as needed. ADDITIONAL SERVICES The following Additional Services are not included in the Scope of Services and will not be performed unless specifically authorized by the OWNER: 1. Any changes or modifications to the approved right of way or easement documents because of design changes by Owner. 2. Serving as expert witness in commissioner's hearings or other litigation. 9/24/2019 �,i yWalker Partners engineers * surveyors ADDENDUM TO EXHIBIT C WORK SCHEDULE The work schedule for Task 2.0—Land Rights and Stakeholder Coordination shall be extended from 17 months to 42 months. The Draft TM under Task 2.2.10 shall be delivered within two months of NTP. rPartners 9124/2019 �X/all�eS ADDENDUM TO EXHIBIT D Fee Schedule Attached Behind This Page ADDENDUM TO EXHIBIT D COMPENSATION Total compensation for services under Supplemental Amendment No. 6 is estimated to be $497,885 as shown in Attachment 1. OWNER shall pay ENGINEER for Basic Services on the basis of Standard Hourly Rates as described in Paragraph 2.0 of Exhibit D as described in Exhibit D Compensation of the Agreement dated April 19, 2017. Hourly rates for Engineer's services under Task 2.6 Special Commissioner Hearings for individual providing expert witness testimony are detailed below. Total compensation for Task 2.0— Land Rights and Stakeholder Coordination shall be adjusted to be $2,827,685. Total compensation for the Project shall be adjusted to $5,562,785. 9/24/2419 Walker Partners engineers * suevuyors ORIGINAL EXECUTED DOCUMENT TO FOLLOW... 0 1b WNBRUSHYCREK REGIONAL UTILITY AUTHORITY A •arr..rrhlp sl Coda, 0`41%. Laaed-fr. and Send Aa.k SUPPLEMENTAL CONTRACT NO. 6 TO CONTRACT FOR ENGINEERING SERVICES FIRM: WALKER PARTNERS ("Engineer") ADDRESS: 804 Las Cimas Parkivav,Suite 150,Austin,TX 78746 PROJECT: Phase 1C Water Treatment Plant Expansion and Phase 2 Land Rh!hts and Stakeholder Coordination This Supplemental Contract No. 6 to Contract for Engineering Services is made by and between the BRUSi IY CREEK REGIONAL UTILITY AUTI-IORITY, INC., hereinafter called "BCRUA" and Walker Partners, hereinafter called the"Engineer". WHEREAS, BCRUA and Engineer executed a Contract for Engineering Services, hereinafter called the "Contract", on the 19th day of April, 2017 for the BCRUA Phase I Water Treatment Plant Expansion in the lump sum amount of $1,763,900.00 and Phase 2 Land Rights and Stakeholder Coordination Project in the maximum amount of$2,012,600.00 for a total Project compensation of$3,776,500.00;and WHEREAS, BCRUA and Engineer executed Supplemental Contract No. I on July I9, 2017 to amend the scope of services and to increase the compensation by $14,100.00 for Phase 1 C Water Treatment Plant Expansion to a lump sum amount total of$1,778,000.00 and by $212,000.00 for Phase 2 Land Rights and Stakeholder Coordination Project to a maximum amount total of $2,224,600.00 for a total Project compensation of$4,002,600.00;and WHEREAS, BCRUA and Engineer executed Supplemental Contract No. 2 on November 20, 2017 to amend the scope of services and to increase the compensation by $19,600.00 for Phase I C Water Treatment Plant Expansion to a lump sum amount total of$1,797,600.00 for a total Project compensation of$4,022,200.00; and WHEREAS, BCRUA and Engineer executed Supplemental Contract No. 3 on April 18, 2018 to amend the scope of services and to increase the compensation by $105,200.00 For Phase 2 Land Rights and Stakeholder Coordination Project to a maximum amount total of$2,329,800.00 for a total Project compensation of$4,127,400.00; and WHEREAS, BCRUA and Engineer executed Supplemental Contract No. 4 on October 24, 2018 to add the construction phase services for the Phase I C Construction Phase Services Project and to increase the compensation by $897,200.00 for a total Project compensation of$5,024,600.00; and I Supplemental Contract Rev.0312011 0140.4634-40;00432.49 215829 pyr U,4_ p- nj D1-2 S � WHEREAS, BCRUA and Engineer executed Supplemental Contract No. 5 on April 30,2019 to modify the provisions for the scope of services and to increase the compensation by $40,300.00 for Phase 1 C Water Treatment Plant Expansion to a lump sum amount total of$2,735,100.00 for a total Project compensation of$5,064,900.00;and WHEREAS, it has become necessary to amend the Contract to modify the provisions for the scope of services and to increase the compensation by $497,885.00 for Phase 2 Land Rights and Stakeholder Coordination Project to a maximum amount total of$2,827,685.00 for a total Project compensation of$5,562,785.00; NOW THEREFORE, premises considered, BCRUA and the Engineer agree that said Contract is amended as follows: I. Article 2. Engineering Services and Exhibit B, Engineering Services shall be amended as set forth in the attached Addendum To Exhibit B. Exhibit C. Work Schedule shall be amended as set forth in the attached Addendum To Exhibit C. IL Article 4. Compensation and Exhibit D. Fee Schedule shall be amended by increasing by $497,885.00 the maximum amount payable under the Contract for Phase 2 Land Rights and Stakeholder Coordination Project to a total of$2,827,685.00 for a total Project compensation of $5,562,785.00,as shown by the attached Addendum to Exhibit D. IN WITNESS WHEREOF, BCRUA and the Engineer have executed this Supplemental Contract in duplicate. [signaliti-e pagesfollowl 2 WALKER PARTNERS By: CML era 'ng Qfficer September 26,2019 Date 3 BRUSHY CREEK REG UTILITY AUTHORITY, INC. By: Anne Daffy, resident Date APPROV S TO FO By: w Stephan A. Sheets, BCRUA Attorney ADDENDUM TO EXHIBIT B ENGINEERING SERVICES GENERAL The purposes of Supplemental Amendment No. 6 are as follows: - Update prior evaluations of three overhead electric routes starting at the intersection of Nameless Road and FM 1431 and continuing to the intersection of North Rim Drive and Trails End Road. The following is a brief description of each route: o Route 1—The "Preferred Route"from Technical Memorandum(TM)2-8 that contacts an existing single-phase line near the end of North Rim Drive and proceeds east along North Rim Drive to Trails End Road. o Route 2—"Alternative Route 2"from TM 2-8 that follows an existing single-phase line south of and parallel to North Rim Drive before turning north on Lost Ridge Circle to North Rim Drive and east to Trails End Road. o Route 3—Follows FM 1431 from Nameless Road to Trails End Road. - Support OWNER with the acquisition of electric easements associated with rebuilding existing Pedernales Electric Cooperative(PEC)overhead distribution lines from the PEC Nameless Substation to the pump station site; - Support OWNER with the acquisition of temporary construction easements needed far the Phase 2 Raw Water Delivery System Project; - Provide on-call technical support and coordination with PEC(provided by subconsultant M&S). BASIC SCOPE OF SERVICES Task 2.0-Phase 2 Land Rights and Stakeholder Coordination Insert Task 2.2.10 North Rim Overhead Electric Alternative Alignment Evaluation Update as follows: 2.2.10 North Rim Overhead Electric Alternative Alignment Evaluation Update. 2.2.10.1 Develop conceptual designs of the Route 3 in a manner that is consistent with the level of design detail utilized to define the alignment of Route 1 and 2 as documented in TM 2-8. The routing analysis shall be planning level in nature and suitable for development of an opinion of probable cost. Develop a preliminary map of the route and description of route challenges. 2.2.10.2 Develop planning level opinions of probable cost for each of the three routes. Easement and right-of-way costs shall be estimated and included for each route. 9/24/2019 engineers + survcynrr, 2.2.10.3 Prepare and present a Technical Memorandum that compiles and presents the conceptual designs and planning level opinions of probable costs. Address OWNER comments and finalize the TM. Insert Task 2.5 as follows: 2.5 Additional Easement Acquisition 2.5.6 Project Management,Coordination and Meetings 2.5.6.1 Attend monthly progress meetings with OWNER for a total of 8 meetings 2.5.6.2 Manage and coordinate staff resources, subconsultants, and project planning. 2.5.6.3 Prepare monthly invoices and project progress reports.As a minimum, monthly progress reports shall include a summary description of tasks completed as of the report date, description of activities planned for the next 60 days, financial status of the project,status of schedule for project, and identification of technical or other issues which may have an impact to the overall project budget and/or schedule. 2.5.6.4 Facilitate document control and document sharing for electronic filing of documents. Maintain project and parcel/easement documents. 2.5.6.5 Prepare, update and maintain initial property owner contact list. 2.5.6.6 Maintain records of all payments to property owners including amount and date paid. 2.5.6.7 Maintain copies of all correspondence and contacts with property owners. 2.5.7 land Acquisition and Right of Way. Support acquisition of easements and land rights for the Project. The total number of assumed parcels/easements is 48 parcels including 43 parcels/easements for electrical improvements and 5 parcels/easements for temporary construction easements. 2.5.7.1 Surveying. Perform site surveying for 5 temporary construction easements, 43 electric easements. Perform boundary survey and prepare exhibits and field notes of parcels to be conveyed. Complete topographic survey of temporary construction easements. Horizontal and vertical datums for project control will remain on NAD83/NAVD88 Texas State Plane,Central Zone. 2.5.7.2 Negotiation Services. 2.5.7.2.1 Research official public records to update ownership and provide vesting deeds to surveyor. 2.5.7.2.2 Prepare Broker's Opinion of Value for each easement. 912412019 y V�a�kerPartners engineers . surveyors 2.5.7.2.3 Analyze appraisal report and confirm OWNER approved value prior to making offer for each parcel/easement.Submit request for authorization to make offers. 2.5.7.2.4 Prepare and send the letter transmitting the Landowner's Bill of Rights by Certified Mail-Return Receipt Requested (CMRRR). 2.5.7.2.5 Prepare documents required on forms approved by OWNER(i.e., the initial offer letter, memorandum of agreement, instruments of conveyance). 2.5.7.2.6 Send the written offer and appraisal report to each property owner or the property owner's designated representative by CMRRR. Appraisal reports to be prepared under separate contract. 2.5.7.2.7 Maintain follow-up contacts and secure the instruments necessary for the closing upon acceptance of the offer. 2.5.7.2.8 Respond to property owner inquiries verbally or in writing within two business days. 2.5.7.3 PEC Technical Support and Coordination. Support OWNER through coordination with PEC for development of the Temporary Power Project. Attend project coordination meetings and conference calls as needed. ADDITIONAL SERVICES The following Additional Services are not included in the Scope of Services and will not be performed unless specifically authorized by the OWNER: 1. Any changes or modifications to the approved right of way or easement documents because of design changes by Owner. 2. Serving as expert witness in commissioner's hearings or other litigation. 9/24/2019 ®�r�dI'CIleCS engineers * surveyors ADDENDUM TO EXHIBIT C WORK SCHEDULE The work schedule for Task 2.0—Land Rights and Stakeholder Coordination shall be extended from 17 months to 42 months. The Draft TM under Task 2.2.10 shall be delivered within two months of NTP. 9/24/2019 (D. VA&er Partners engineers * surveyors ADDENDUM TO EXHIBIT D Fre Schedule Attached Behind This Page ADDENDUM TO EXHIBIT D COMPENSATION Total compensation for services under Supplemental Amendment No. 6 is estimated to be $497,885 as shown in Attachment 1. OWNER shall pay ENGINEER for Basic Services on the basis of Standard Hourly Rates as described in Paragraph 2.0 of Exhibit D as described in Exhibit D Compensation of the Agreement dated April 19, 2017. Hourly rates for Engineer's services under Task 2.6 Special Commissioner Hearings for individual providing expert witness testimony are detailed below. Total compensation for Task 2.0—Land Rights and Stakeholder Coordination shall be adjusted to be $2,827,685. Total compensation for the Project shall be adjusted to$5,562,785. 9/2412019 (OVYdPartners engi1�neers • surveyors A11aeApOOt I to EshihPl D Brushy Creak Rasmus"Ubley AvtMrtty PRA$O IC W7P Eapanslan and Phase I Laced Rtlhts aM Stakeholder Coardnawn Sk"Isseental AnraOmrnt Na.t Labor ani Pu Swrwnary Walker PAtttnrs Lager Claaadtcatrns and Haws SONer Sealer Walker Walker Walker aubconsallaM Cast Ptojcct OMOC Process Pryecl Sanlor Adorn Survey 214an P8F%u4M Panan TOW SrCn t TASK DESC10PT1Wr Rovewar r Eo ucer vasgnar Support RPS TOchakaToWHwn Etponsee TeUl Cest Costs Itmillay MAN, Fn Task 23.lard Rights apd Stakeholder COerdrlallen LL16 NOM Ron Overhead EWcMc Aharoattve Alrgneral Upata 6 6 860 12600 m."a 1131,453 2.6 A"al od EOswnardAgWss" 233 PrMef Uaft gar ont.Cowthrmsen.sleeknps 40 a I6 24 12 10 sw6 $20.160 81,375 $41.52S 2S.7 lana A[pasbtn ord RrgtA OI Way 2.5.7.1 swveyets s 4 0 16 200 IN 606 IAN 12.M816.020 $211A20 25.72 Noggos Ora Spokes 6 24 22 6100 $4.oa0 11161Aa0 $165.3s0 23.7.7 PECTedwest Support 16 16 $S6 $4.690 85.060 MAN 5.bmart Fee 551600 613.5w TOTAL HOURS w a u 44212 m660 I.aSs TOTALME 122.200 6L260 $2,160 $Lem .62,100 $76.760 1 Miles $2,1w 86/.610 SIUAII mim $"Ass