BCRUA_R-21-04-28-6B RESOLUTION NO. R-21-04-28-6B WHEREAS, the Brushy Creek Regional Utility Authority, Inc. ("BCRUA") has previously entered into a Contract for Engineering Services ("Contract") with Walker Partners/Freese and Nichols Joint Venture for the BCRUA Phase 2 Raw Water Delivery System Project, and WHEREAS, Walker Partners[Freese and Nichols Joint Venture has submitted Supplemental Contract No. 7 to the Contract to modify the provisions for the scope of services and to increase the compensation, and WHEREAS, the BCRUA desires to enter into said Supplemental Contract No. 7, Now Therefore BE IT RESOLVED BY THE BOARD OF DIRECTORS OF THE BRUSHY CREEK REGIONAL UTILITY AUTHORITY: That the Board President is hereby authorized and directed to execute on behalf of the BCRUA Supplemental Contract No. 7 with Walker Partners/Freese and Nichols Joint Venture, a copy of same being attached hereto as Exhibit "A" and incorporated herein for all purposes. The Board of Directors hereby finds and declares that written notice of the date, hour, place and subject of the meeting at which this Resolution was adopted was posted and that such meeting was open to the public as required by law at all times during which this Resolution and the Subject matter hereof were discussed, considered and formally acted upon, all as required by the Open Meetings Act, Chapter 551, Texas Government Code, as amended. RESOLVED this 28th day of April, 2021. REN FLORES, Presiden Brushy Creek Regional Utility Authority ATTEST: . t-w ANNE UFFY, ct site ec etary httpsalruundnkkteaas.�hawpuint, Admmixtrmiantlkpartmem File MCRUAll9oard PackeWPaeket 1 h>Lumr•nrJIr 2G21AW2X?112IMo.]WRLIA tiC "N WAlker 1'arrner% Frlvw and Nxhok hint Venture-Phase 2 Rain%N'JICr DAA - tem wNIA7eil2lxAn%1`%Ldt>< 5 :e7Z BRUSHY CREEK REGIONAL UTILITY AUTHORITY A Partnership of Cedar Part. Leander rna Rare k.rr SUPPLEMENTAL CONTRACT NO. 7 TO CONTRACT FOR ENGINEERING SERVICES FIRM:WALKER PARTNERS/FREESE AND NICHOLS JOINT VENTURE ("Engineer") ADDRESS: 804 Las Cimas Parkway, Suite 150 Austin TX 78746 PROJECT: BCRUA Phase 2 Raw Water Delivery System This Supplemental Contract No. 7 to Contract for Engineering Services is made by and between the BRUSHY CREEK REGIONAL UTILITY AUTHORITY, INC., hereinafter called "BCRUA" and Walker Partners//Freese and Nichols Joint Venture, hereinafter called the "Engineer". WHEREAS, BCRUA and Engineer executed a Contract for Engineering Services, hereinafter called the "Contract', on the 28th day of November, 2018 for the BCRUA Phase 2 Raw Water Delivery System Project in the lump sum amount of $12,518,037.00 for Engineering Services excluding Task 5.3.1 .. Geotechnical Investigation; and WHEREAS, BCRUA and Engineer executed Supplemental Contract No. 1 on April 24, 2019 to amend the scope of services, specifically, Task 6.0, and to increase the compensation by $75,496.00 to a total lump sum amount of $12,593,533.00 for a total project amount of $13,697,291.00; and WHEREAS,BCRUA and Engineer executed Supplemental Contract No. 2 on August 7, 2019 to amend the scope of services, specifically, Task 5.0 - Special Services, and to increase the compensation by $42,348.00 to a total lump sum amount of $12,635,881.00 for a total project amount of$13,739,639.00; and WHEREAS, BCRUA and Engineer executed Supplemental Contract No. 3 on March 5, 2020 to amend the scope of services, specifically, Task 6.0 - Agency and Stakeholder Coordination, and to increase the compensation by $47,000.00 to a total lump sum amount of$12,682,881.00 for a total project amount of$13,786,639.00; and WHEREAS, BCRUA and Engineer executed Supplemental Contract No. 4 on March 20, 2020 to amend the scope of services, specifically, Task 6.0 - Agency and Stakeholder Coordination, and to increase the compensation by $18,155.00 to a total lump sum amount of$12,701,036.00 for a total project amount of$13,804,794.00; and Supplemental Contract Rev. 03/2011 0140.4634-47;00469998 215829 EXHIBIT "A" WHEREAS, BCRUA and Engineer executed Supplemental Contract No. 5 on May 28, 2020 to amend the scope of services, specifically, Task 5.3.1 - Geotechnical Investigation, by reducing the compensation by $256,761.00 and adjusting the total Time and Materials amount to $846,997.00; and to reallocate $256,761.00 to Task 5.0 - Special Services and Task 6.0 - Agency and Stakeholder Coordination, and to modify the provisions for the scope of services for Task 5.0 by increasing the compensation by $24,212.00 to a total lump sum amount of $12,982,009.00 for a total project amount of$13,829,006.00; and WHEREAS, BCRUA and Engineer executed Supplemental Contract No. 6 on October 22, 2020 to amend the scope of services, specifically, Task 5.0 - Special Services, and to increase the compensation by $27,985.00 to a total lump sum amount of $13,009,994.00 for a total project amount of$13,856,991.00; and WHEREAS, it has become necessary to amend the Contract to modify the provisions for the scope of services, specifically, Task 5.0 Special Services, and to increase the compensation by $137,201.00 to a total lump sum of$13,147,195.00 for a total project amount of$13,994,192.00; NOW THEREFORE, premises considered, BCRUA and the Engineer agree that said Contract is amended as follows: I. Article 2, Engineering Services and Exhibit B, Engineering Services shall be amended as set forth in the attached Addendum To Exhibit B. Exhibit C. Work Schedule shall be amended as set forth in the attached Addendum To Exhibit C. II. Article 4, Compensation (1) Lump Sum and Exhibit D, Fee Schedule shall be amended by increasing by $137,201.00 the lump sum amount payable under the Contract for Engineering Services, specifically, Task 5.0- Special Services to a total lump sum amount of$13,147,195.00 for a total Project amount of$13,994,192.00, as shown by the attached Addendum_to.Exhibit D. IN WITNESS WHEREOF, BCRUA and the Engineer have executed this Supplemental Contract in duplicate. [signature pages follow] 2 WALKER PARTNERSIFREESE AND NICHOLS JOINT VENTURE By: Date 3 BRUSHY CREEK REGIONAL UTILITY AUTHORITY, INC. By: Rene Flores, President Date APPROVED AS TO FORM: By: Stephan L. Sheets, BCRUA Attorney a ADDENDUM TO EXHIBIT B ENGINEERING SERVICES BASIC SCOPE OF SERVICES Task 5.0-Special Services Insert Task 5.14 as follows: 5.14 Re-Design of Jackson Street Extension and other Associated Improvements.Through negotiations with the Village of Volente (Village), as part of the Interlocal Agreement, the current design of the Jackson Street Extension will be re-designed to incorporate specific decisions and guidance from the Village. The Village prefers the Jackson Street Extension not be fully connected to Bernard Street and Terrell Street, but instead be a stub-out from the Bernard Street cul-de-sac. This decision will provide for Bernard Street to be the primary approach route for the proposed Maintenance Building, opposed to the currently designed connecting Jackson Street. Other design accommodations, such as improvements to widening corners at intersections along Bernard Street/Sherman Street and Sherman Street/Lime Creek Road, will be required to allow longer trucks to maneuver and approach along Bernard/Sherman Streets. 5.14.1 Conceptual Project Coordination 5.14.1.1 Attend a Project (re)Kick-Off Meeting to develop and provide an updated typical section and project overview exhibit to be approved by the Village. Village has requested a typical section and plan view layout that does not adhere strictly to City of Austin or Texas Department of Transportation (TxDOT) standards. 5.14.1.2 Development of TM 5-15, Jackson Street Extension Re-Design Variances. 5.14.1.3 Development of conceptual exhibits of typical section, plan view, and Autoturn exhibits for Village coordination and approval. 5.14.1.4 Participation in weekly internal coordination meetings for coordination and progress review to obtain Owner and VOV approval of revised plan and typical section. 5.14.2 Project Coordination and Management. Provide project oversight and the daily management of the project. Frequent and appropriate communications will be maintained between the Engineer and Owner to expedite completion. 5.14.3 Project Design. The Project design criteria will be as follows: 5.14.3.1 The design standards to be used will include but not be limited to the City of Austin Transportation Design Criteria Manual, TxDOT Roadway Design Manual, TxDOT Bridge Design Manual— LRFD,TxDOT Hydraulic Design Manual, Highway Capacity Manual,the American Association of State Highway and Transportation Officials (AASHTO) A Policy on Geometric Design of Highways and Streets (Green Book), AASHTO LRFD Bridge Design Specifications, Texas Manual on Uniform Traffic Control 02,Walker Partners . N�EESE 4/20/2021 engineers * surveyors r' ENOLS Devices,ADA Accessibility Guidelines,Texas Pollutant Discharge Elimination System (TPDES) Guidelines, and applicable Travis County Design Guidelines; and 5.14.3.2 Project specification and Standard Details will be developed using the latest Texas Department of Transportation Standard Specifications for Construction and Maintenance of Highways, Streets, and Bridge, the City of Austin Transportation Design Criteria Manual, and the City of Austin Drainage Criteria Manual. 5.14.3.3 Traffic Control Plan Services. Prepare a Traffic Control Plan (TCP) including Advanced Warning Signs, a Detour Plan if required and a Sequence of Work Narrative.The Traffic Control Plan will be developed in accordance with the most recent version of the Texas Manual of Uniform Traffic Control devices (TMUTCD). 5.14.3.4 Roadway Design Services. 5.14.3.4.1 Design with the approved roadway typical section and plan view utilizing the vertical profile from the previous submission, 5.14.3.4.2 Use the pavement section as specified in the Village Code of Ordinances. 5.14.3.4.3 Prepare Project Layout Sheets that clearly indicate the limits of the entire project and include the horizontal alignment data. 5.14.3.4.4 Revise the Proposed Typical Section Sheets.The proposed typical sections will include all pertinent information for the proposed roadway construction. 5.14.3.4.5 Revise the Roadway Plan and Profile Sheets with the revised horizontal geometry and typical section. 5.14.3.4.6 Develop Intersection Layout Sheets with spot elevations and proposed grading for the intersections of Jackson Street and Bernard Street of Lime Creek Road at Sherman Street. 5.14.3.4.7 Prepare cross-sections at 25-intervals to be included in the pian set. 5.14.3.5 Dry Stack Rock Wall Design Services. 5.14.3.5.1 Prepare dry stack rock wall Plan and Profile sheets as specified by the City of Austin including the following information: 5.14.3.5.1.1 Beginning and ending wall points by station, offset, and roadway alignment. 5.14.3.5.1.2 Additional points as necessary to describe relationship of wall alignment to roadway alignment(s). 5.14.3.5.1.3 Typical Wall section depicting wall control points. 5.14.3.5.1.4 Beginning and ending of top/bottom wall points by station and elevation. 4/20/202, �WalkersPartners r12 NICHOLS 5.14.3.5.1.5 Existing ground line along wall alignment. 5.14.3.5.1.6 Finished grade line at face of wall. 5.14.3.5.1.7 Top of retaining wall grade line. 5.14.3.5.1.8 Prepare dry stack rock wall miscellaneous details as necessary. 5.14.3.6 Drainage Design Services. 5.14.3.6.1 Prepare drainage ditch plan and profile sheets. 5.14.3.6.2 Perform drainage calculations for the drainage infrastructure included in the design according to the City of Austin Drainage Criteria Manual. 5.14.3.7 Signing and Pavement Markings Services. Prepare proposed signing layouts, and proposed pavement marking and delineation layouts for the Jackson Street Extension. The layouts will identify the various types of proposed signing, striping, and delineation. Signing and striping will be in accordance with the latest version of the TMUTCD or applicable TOOT standards. 5.14.3.8 Environmental and Storm Water Management Plan Services. Prepare SW3P Layouts to include the necessary controls to minimize the runoff of sediment during construction. The layouts will include information presented in the WPAP and include permanent storm water features as appropriate. The SW3P control measures will be prepared and designed in accordance with the proposed phasing of construction. 5.14.4 Submittal Requirements. 5.14.4.1 Submit a 90% quality control plan set and address comments. 5.14.4.2 Provide 100% plans including the standard specifications from COA or TXDOT as applicable. 5.14.4.3 Submittal and Review Meetings: Attend an internal 90 percent submittal review meeting. Comments and revisions will be incorporated into the deliverables for the next submittal. 5.14.4.4 90 Percent Submittal: 5.14.4.4.1 Provide digital copies of plan sheets and cross-sections. The plan sheets and cross sections must be prepared and submitted in 11"x17"tabloid paper format. 5.14.4.4.2 The submittal must include the following: 5.14.4.4.2.1 Project Layout and Horizontal Alignment Data Sheet, 5.14.4.4.2.2 Revised Proposed Typical Sections. 5.14.4.4.2.3 Revised Sequence of Work and Traffic Control Plan Sheets. 5.14.4.4.2.4 Traffic Control Standards. 5.14.4.4.2.5 Revised Roadway Plan & Profile Sheet. Walker Partners r'FREESE 4/20/2021 engineers f surveyors AICHOLS 5.14.4.4.2.6 Revised intersection Layouts (Two Sheets). 5.14.4.4.2.7 Revised Driveway Details. 5.14.4.4.2.8 Revised Miscellaneous Roadway Details. 5.14.4.4.2.9 Revised Roadway Standards. 5.14.4.4.2.10 Revised Retaining Wall Plan and Profile. 5.14.4.4.2.11 Revised Retaining Wall Miscellaneous Details. 5.14.4.4.2.12 Revised Retaining Wall Standards. 5.14.4.4.2.13 Revised Drainage Ditch Layouts. 5.14.4.4.2.14 Revised Storm Sewer Layout Sheet. 5.14.4.4.2.15 Revised Storm Sewer Detail Sheet. 5.14.4.4.2.16 Revised Miscellaneous Drainage Details. 5.14.4.4.2.17 Revised Drainage Standards. 5.14.4.4.2.18 Revised Estimated Quantities. 5.14.4.4.2.19 Revised Signing & Pavement Marking Layouts. 5.14.4.4.2.20 Revised Signing& Pavement Marking Standards. 5.14.4.4.2.21 Revised Summary of Small Signs. 5.14.4.4.2.22 Revised Small Sign Details. 5.14.4.4.2.23 Revised SW3P Layout. 5.14.4.4.2.24 Revised Environmental Standards. 5.14.4.4.2.25 Revised Roadway Cross-Sections. 5.14.4.5 100 Percent Submittal:The submittal must include the following: PDF of signed (electronic signatures allowed) and sealed 22"x34"tabloid paper sets of the Final Construction Drawings. Insert Task 5.15 as follows: 5.15 TM 5-13 RWPS Back-up Power Capacity. Prepare a technical memorandum identifying the availability, capacity, timing, and source of back-up power for the RWPS at initial and ultimate build-out. Submit Draft TM, respond to BCRUA comments, and prepare a final, sealed TM. Insert Task 5.16 as follows: 5.16 Design of New Water Quality Related Structures and Retaining Walls per City of Austin. Provided structural design and the preparation of contract drawings for the implementation of two new water quality related structures at the RWPS property, as required by the City of Austin. Structures are inclusive of the Water Quality Basin and Detention Basin. These new structures were designed as cast-in-place concrete structures. Additionally, the City of Austin required design details on the site retaining walls. Structural design and the preparation of design drawings for the retaining walls were developed and provided to the City of Austin. Walker Partners f:'FREE E 4/20/2021 engineers + surveyors Insert Task 5.17 as follows: 5.17 Enhanced Freeze Protection. Provide additional design modifications to enhance protection again freeze damage. 5.17.1 Provide electric radiant heaters at the RWPS pump level room.These will radiate heat at the pipes and the slab. 5.17.2 Provide electric radiant heaters at the pump room mezzanine level for the surge tank and the water quality analyzer panel small piping components. 5.17.3 Provide insulation and heat tracing for cooling water pipes and accessories. 5.17.4 Provide unit heaters for electrical rooms for better heat during prolonged, cold conditions. 5.17.5 Provide an auxiliary heat coil at the SCADA room air handling unit for better heat during prolonged, cold conditions. 5.17.6 Provide electrical power to new heater equipment and heat tracing. 5.17.7 Provide additional switchgear sections for future generator connections. 5.17.8 Provide duct banks, raceway, and manhole design for future generator connections. 5.17.9 Update protective relay system and relay network for additional generator breakers. 5.17.10 Preparation of TM 5-16, Power Availability During the Texas Freeze. @A2 WAer Partners r'FREESE 4/20/2021 engineers * surveyors iNI�NOLS ADDENDUM TO EXHIBIT C WORK SCHEDULE The submittal date for Final Bid Documents will be adjusted from June 11, 2021 to July 30, 2021. 4/20/2021 QWalkers * surveyors Partners r:'FREESEIOLS ADDENDUM TO EXHIBIT D FEE SCHEDULE Total compensation for services under Supplemental Amendment No. 7 is estimated to be $137,201 as shown in Attachment 1 to Exhibit D. Total compensation for Task 5.0 — Special Services shall be increased by an amount of $137,201 to $3,645,119. Total compensation for Lump Sum tasks shall be adjusted from $13,009,994 to$13,147,195. Total compensation for the Project shall be adjusted from $13,856,991 to$13,994,192. 4/20/20214�gr) ersPartne#s rm NICHOOL @,Fen S M......M M N M N N................ N C] � nFJ9'R Sgg. <gr RSLR • �g s u'i 3 u r, As a .A •x der A i �e tirsr$ a;eab F v tmu t tm a ORIGINAL EXECUTED DOCUMENT TO FOLLOW... w,NBRUSHYCREEK REGIONAL UTILITY AUTHORITY A P.rcna r.h Ip der P.-Y. L...4­ .n'J katnd kap. SUPPLEMENTAL CONTRACT NO. 7 TO CONTRACT FOR ENGINEERING SERVICES FIRM:WALKER PARTNERS/FREESE AND NICHOL_S JOINT VENTURE ("Engineer") ADDRESS: 804 Las_Cimas Parkway, Suite 150, Austin,TX 78746 _ PROJECT: BCRUA Phase 2 Raw Water Delivery System This Supplemental Contract No. 7 to Contract for Engineering Services is made by and between the BRUSHY CREEK REGIONAL UTILITY AUTHORITY, INC., hereinafter called "BCRUA" and Walker Partners//Freese and Nichols Joint Venture, hereinafter called the "Engineer". WHEREAS, BCRUA and Engineer executed a Contract for Engineering Services, hereinafter called the "Contract", on the 28th day of November, 2018 for the BCRUA Phase 2 Raw Water Delivery System Project in the lump sum amount of $12,518,037.00 for Engineering Services excluding Task 5.3.1 Geotechnical Investigation; and WHEREAS, BCRUA and Engineer executed Supplemental Contract No. 1 on April 24, 2019 to amend the scope of services, specifically, Task 6.0, and to increase the compensation by $75,496.00 to a total lump sum amount of $12,593,533.00 for a total project amount of $13,697,291.00; and WHEREAS, BCRUA and Engineer executed Supplemental Contract No. 2 on August 7, 2019 to amend the scope of services, specifically, Task 5.0 Special Services, and to increase the compensation by $42,348.00 to a total lump sum amount of $12,635,881.00 for a total project amount of$13,739,639.00; and WHEREAS, BCRUA and Engineer executed Supplemental Contract No. 3 on March 5, 2020 to amend the scope of services, specifically, Task 6.0— Agency and Stakeholder Coordination, and to increase the compensation by $47,000.00 to a total lump sum amount of$12,682,881.00 for a total project amount of$13,786,639.00; and WHEREAS, BCRUA and Engineer executed Supplemental Contract No. 4 on March 20, 2020 to amend the scope of services, specifically, Task 6.0 - Agency and Stakeholder Coordination, and to increase the compensation by $18,155.00 to a total lump sum amount of$12,701,036.00 for a total project amount of$13,804,794.00; and Supplemental Contract Rev.03.'2011 0140.4634-47; 00469998 215829 WHEREAS, BCRUA and Engineer executed Supplemental Contract No. 5 on May 28, 2020 to amend the scope of services, specifically, Task 5.3.1 Geotechnical Investigation, by reducing the compensation by $256,761.00 and adjusting the total Time and Materials amount to $846,997.00; and to reallocate $256,761.00 to Task 5.0 Special Services and Task 6.0 - Agency and Stakeholder Coordination, and to modify the provisions for the scope of services for Task 5.0 by increasing the compensation by $24,212.00 to a total lump sum amount of $12,982,009.00 for a total project amount of$13,829,006.00; and WHEREAS, BCRUA and Engineer executed Supplemental Contract No. 6 on October 22, 2020 to amend the scope of services, specifically, Task 5.0 - Special Services, and to increase the compensation by $27,985.00 to a total lump sum amount of $13,009,994.00 for a total project amount of$13,856,991.00; and WHEREAS, it has become necessary to amend the Contract to modify the provisions for the scope of services, specifically, Task 5.0 Special Services, and to increase the compensation by $137,20 1.00 to a total lump sum of$13,147,195.00 for a total project amount of$13,994,192.00; NOW THEREFORE, premises considered, BCRUA and the Engineer agree that said Contract is amended as follows: I. Article 2, Engineering Services and Exhibit B, Engineering Services shall be amended as set forth in the attached Addendum To Exhibit B. Exhibit C, Work Schedule shall be amended as set forth in the attached Addendum To Exhibit C. I1. Article 4, Compensation (1) Lump Sum and Exhibit D, Fee Schedule shall be amended by increasing by $137,201.00 the lump sum amount payable under the Contract for Engineering Services, specifically, Task 5.0-- Special Services to a total lump sum amount of$13,147,195.00 for a total Project amount of$13,994,192.00, as shown by the attached Addendum to Exhibit D. IN WITNESS WHEREOF, BCRUA and the Engineer have executed this Supplemental Contract in duplicate. Cvignature pages follovi-] 2 WALKER P RTNERS/FREESE AND NICHOLS JOINT VENTURE Geo[ e L Walker, Jr., President _ Drew Hardin, Vice President April 21,2021 April 22, 2021 Date Date x BRUSHY CREEK REGIONAL UTILITY AUTHORITY, INC. Ren t Flores, President �,2ff-211 Date APPROVE AS TO FORM• Stephan L Sheets, BCRUA Attorney 4 ADDENDUM TO EXHIBIT B ENGINEERING SERVICES BASIC SCOPE OF SERVICES Task 5.0-Special Services Insert Task 5.14 as follows: 5.14 Re-Design of Jackson Street Extension and other Associated Improvements. Through negotiations with the Village of Volente (Village), as part of the Interlocal Agreement, the current design of the Jackson Street Extension will be re-designed to incorporate specific decisions and guidance from the Village. The Village prefers the Jackson Street Extension not be fully connected to Bernard Street and Terrell Street, but instead be a stub-out from the Bernard Street cul-de-sac. This decision will provide for Bernard Street to be the primary approach route for the proposed Maintenance Building, opposed to the currently designed connecting Jackson Street. Other design accommodations, such as improvements to widening corners at intersections along Bernard Street/Sherman Street and Sherman Street/Lime Creek Road, will be required to allow longer trucks to maneuver and approach along Bernard/Sherman Streets. 5.14.1 Conceptual Project Coordination 5.14.1.1 Attend a Project (re)Kick-Off Meeting to develop and provide an updated typical section and project overview exhibit to be approved by the Village. Village has requested a typical section and plan view layout that does not adhere strictly to City of Austin or Texas Department of Transportation (TxDOT) standards. 5.14.1.2 Development of TM 5-15,Jackson Street Extension Re-Design Variances. 5.14.1.3 Development of conceptual exhibits of typical section, plan view, and Autoturn exhibits for Village coordination and approval. 5.14.1.4 Participation in weekly internal coordination meetings for coordination and progress review to obtain Owner and VOV approval of revised plan and typical section. 5.14.2 Project Coordination and Management. Provide project oversight and the daily management of the project. Frequent and appropriate communications will be maintained between the Engineer and Owner to expedite completion. 5.14.3 Project Design. The Project design criteria will be as follows: 5.14.3.1 The design standards to be used will include but not be limited to the City of Austin Transportation Design Criteria Manual, TxDOT Roadway Design Manual,TxDOT Bridge Design Manual— LRFD,TxDOT Hydraulic Design Manual, Highway Capacity Manual, the American Association of State Highway and Transportation Officials (AASHTO) A Policy on Geometric Design of Highways and Streets (Green Book), AASHTO LRFD Bridge Design Specifications,Texas Manual on Uniform Traffic Control @Palker Partnersr'NICHO�S 4/20/2021 ,:)-neers * sur, ors Devices, ADA Accessibility Guidelines,Texas Pollutant Discharge Elimination System (TPDES) Guidelines, and applicable Travis County Design Guidelines; and 5.14.3.2 Project specification and Standard Details will be developed using the latest Texas Department of Transportation Standard Specifications for Construction and Maintenance of Highways, Streets, and Bridge, the City of Austin Transportation Design Criteria Manual, and the City of Austin Drainage Criteria Manual. 5.14.3.3 Traffic Control Plan Services. Prepare a Traffic Control Plan (TCP) including Advanced Warning Signs, a Detour Plan if required and a Sequence of Work Narrative.The Traffic Control Plan will be developed in accordance with the most recent version of the Texas Manual of Uniform Traffic Control devices (TMUTCD). 5.14.3.4 Roadway Design Services. 5.14.3.4.1 Design with the approved roadway typical section and plan view utilizing the vertical profile from the previous submission, 5.14.3.4.2 Use the pavement section as specified in the Village Code of Ordinances. 5.14.3.4.3 Prepare Project Layout Sheets that clearly indicate the limits of the entire project and include the horizontal alignment data. 5.14.3.4.4 Revise the Proposed Typical Section Sheets. The proposed typical sections will include all pertinent information for the proposed roadway construction. 5.14.3.4.5 Revise the Roadway Plan and Profile Sheets with the revised horizontal geometry and typical section. 5.14.3.4.6 Develop Intersection Layout Sheets with spot elevations and proposed grading for the intersections of Jackson Street and Bernard Street of Lime Creek Road at Sherman Street. 5.14.3.4.7 Prepare cross-sections at 25-intervals to be included in the plan set. 5.14.3.5 Dry Stack Rock Wall Design Services. 5.14.3.5.1 Prepare dry stack rock wall Plan and Profile sheets as specified by the City of Austin including the following information: 5.14.3.5.1.1 Beginning and ending wall points by station, offset, and roadway alignment. 5.14.3.5.1.2 Additional points as necessary to describe relationship of wall alignment to roadway alignment(s). 5.14.3.5.1.3 Typical Wall section depicting wall control points. 5.14.3.5.1.4 Beginning and ending of top/bottom wall points by station and elevation. (9Walker Partners r10,21FREESE 4/20/2021 nn..-, neers t surveyors RNICHOLS 5.14.3.5.1.5 Existing ground line along wall alignment. 5.14.3.5.1.6 Finished grade line at face of wall. 5.14.3.5.1.7 Top of retaining wall grade line. 5.14.3.5.1.8 Prepare dry stack rock wall miscellaneous details as necessary. 5.14.3.6 Drainage Design Services. 5.14.3.6.1 Prepare drainage ditch plan and profile sheets. 5.14.3.6.2 Perform drainage calculations for the drainage infrastructure included in the design according to the City of Austin Drainage Criteria Manual. 5.14.3.7 Signing and Pavement Markings Services. Prepare proposed signing layouts, and proposed pavement marking and delineation layouts for the Jackson Street Extension. The layouts will identify the various types of proposed signing, striping, and delineation. Signing and striping will be in accordance with the latest version of the TMUTCD or applicable TxDOT standards. 5.14.3.8 Environmental and Storm Water Management Plan Services. Prepare SW3P Layouts to include the necessary controls to minimize the runoff of sediment during construction. The layouts will include information presented in the WPAP and include permanent storm water features as appropriate. The SW3P control measures will be prepared and designed in accordance with the proposed phasing of construction. 5.14.4 Submittal Requirements. 5.14.4.1 Submit a 90% quality control plan set and address comments. 5.14.4.2 Provide 100% plans including the standard specifications from COA or TXDOT as applicable. 5.14.4.3 Submittal and Review Meetings: Attend an internal 90 percent submittal review meeting. Comments and revisions will be incorporated into the deliverables for the next submittal. 5.14.4.4 90 Percent Submittal: 5.14.4.4.1 Provide digital copies of plan sheets and cross-sections.The plan sheets and cross sections must be prepared and submitted in 11"x17" tabloid paper format. 5.14.4.4.2 The submittal must include the following: 5.14.4.4.2.1 Project Layout and Horizontal Alignment Data Sheet. 5.14.4.4.2.2 Revised Proposed Typical Sections. 5.14.4.4.2.3 Revised Sequence of Work and Traffic Control Plan Sheets. 5.14.4.4.2.4 Traffic Control Standards. 5.14.4.4.2.5 Revised Roadway Plan & Profile Sheet. @T�ker Partnersr'F[ENOLS 412012021 neers + surveyors �N� 5.14.4.4.2.6 Revised Intersection Layouts (Two Sheets). 5.14.4.4.2.7 Revised Driveway Details. 5.14.4.4.2.8 Revised Miscellaneous Roadway Details. 5.14.4.4.2.9 Revised Roadway Standards. 5.14.4.4.2.10 Revised Retaining Wall Plan and Profile. 5.14.4.4.2.11 Revised Retaining Wall Miscellaneous Details. 5.14.4.4.2.12 Revised Retaining Wall Standards. 5.14.4.4.2.13 Revised Drainage Ditch Layouts. 5.14.4.4.2.14 Revised Storm Sewer Layout Sheet. 5.14.4.4.2.15 Revised Storm Sewer Detail Sheet. 5.14.4.4.2.16 Revised Miscellaneous Drainage Details. 5.14.4.4.2.17 Revised Drainage Standards, 5.14.4.4.2.18 Revised Estimated Quantities. 5.14.4.4.2.19 Revised Signing & Pavement Marking Layouts. 5.14.4.4.2.20 Revised Signing & Pavement Marking Standards, 5.14.4.4.2.21 Revised Summary of Small Signs. 5.14.4.4.2.22 Revised Small Sign Details. 5.14.4.4.2.23 Revised SW313 Layout. 5.14.4.4.2.24 Revised Environmental Standards. 5.14.4.4.2.25 Revised Roadway Cross-Sections. 5.14.4.5 100 Percent Submittal:The submittal must include the following: PDF of signed (electronic signatures allowed) and sealed 22"x34" tabloid paper sets of the Final Construction Drawings. Insert Task 5.15 as follows: 5.15 TM 5-13 RWPS Back-up Power Capacity. Prepare a technical memorandum identifying the availability, capacity, timing, and source of back-up power for the RWPS at initial and ultimate build-out. Submit Draft TM, respond to BCRUA comments, and prepare a final, sealed TM. Insert Task 5.16 as follows: 5.16 Design of New Water Quality Related Structures and Retaining Walls per City of Austin. Provided structural design and the preparation of contract drawings for the implementation of two new water quality related structures at the RWPS property, as required by the City of Austin. Structures are inclusive of the Water Quality Basin and Detention Basin. These new structures were designed as cast-in-place concrete structures. Additionally, the City of Austin required design details on the site retaining walls. Structural design and the preparation of design drawings for the retaining walls were developed and provided to the City of Austin. (A)Walker Partners ■ Ni EESE 4/20/2021 engineers * surveyors � CHOLS Insert Task 5.17 as follows: 5.17 Enhanced Freeze Protection. Provide additional design modifications to enhance protection again freeze damage. 5.17.1 Provide electric radiant heaters at the RWPS pump level room. These will radiate heat at the pipes and the slab. 5.17.2 Provide electric radiant heaters at the pump room mezzanine level for the surge tank and the water quality analyzer panel small piping components. 5.17.3 Provide insulation and heat tracing for cooling water pipes and accessories. 5.17.4 Provide unit heaters for electrical rooms for better heat during prolonged, cold conditions. 5.17.5 Provide an auxiliary heat coil at the SCADA room air handling unit for better heat during prolonged, cold conditions. 5.17.6 Provide electrical power to new heater equipment and heat tracing. 5.17.7 Provide additional switchgear sections for future generator connections. 5.17.8 Provide duct banks, raceway, and manhole design for future generator connections. 5.17.9 Update protective relay system and relay network for additional generator breakers. 5.17.10 Preparation of TM 5-16, Power Availability During the Texas Freeze. (( Walker Partners r'FREESE 4/20/2021 engineers + surveyors N�CH�LS ADDENDUM TO EXHIBIT C WORK SCHEDULE The submittal date for Final Bid Documents will be adjusted from June 11, 2021 to July 30, 2021. Walker Partners rsmUFREESE 4/20/2021 engineers t sur,reyors t ADDENDUM TO EXHIBIT D FEE SCHEDULE Total compensation for services under Supplemental Amendment No. 7 is estimated to be $137,201 as shown in Attachment 1 to Exhibit D. Total compensation for Task 5.0 — Special Services shall be increased by an amount of $137,201 to $3,645,119. Total compensation for Lump Sum tasks shall be adjusted from $13,009,994 to $13,147,195. Total compensation for the Project shall be adjusted from $13,856,991 to $13,994,192. @)WAer Partners ■ Ni EESE 4/20/2021 engineers * surveyors �t CH�LS � || |�|■# $i#■ �K§■. �§■ ■ |§ � f ! ...�..�..\.................\... ° � .R,-� ■e�� !, ��� � @, � . � - - ) ® \ � �� | | a | . � � �� � ( � ` �� ■ ,■ I |! - ,■ | -§ ` f `� . ! | ,! | |! � �\` | | -- �` � ! �° { . ! � �§ . � � � � � . � `` � � -■ i ! � !; ! |- � ` $ `■ | � �� ` � � � �� � � ` | | � `�_ � | ! ■■ � � ! ! !� ` - � $ � �` [� ( � � �� � . � . � -■ ` | �! , . .� " i ,§# | �§ . . ,� | | � � | � .. �� - � | |! ��.� �� .. �| ■... � | ! .� � | |§ . � - |�` � a! \ � �. |i$ � - .� . , [ ,� . �� ! � ! !| �- if # | | � . | 7 � | � � | 2| f I ! § | §f | _ ��! • .|! - |�! � ! �� ■ ' | 2 |� | || �iK ��§ i . | �� |$ � \��{ i _�i � � � ; � � .. � . �.& � � �. � | - � � . � � � DATE: April 23, 2021 SUBJECT: BCRUA Board Meeting—April 28, 2021 ITEM: 6B. Consider a resolution authorizing the President to execute Supplemental Contract No. 7 with Walker Partners/Freese & Nichols Inc. Joint Venture for BCRUA Phase 2 Raw Water Delivery System. PRESENTER: Karen Bondy,General Manager BACKGROUND: The initial contract for the design of the Phase 2 Raw Water Delivery System Project, in the amount of $12,518,037, was awarded to Walker Partners/Freese and Nichols Joint Venture on November 28, 2018. Since that time six supplemental agreements have been awarded that increased the compensation to $13,856,991. Supplemental Agreement No. 7 includes engineering services for design modifications to enhance protection again freeze damage, modifications to address permitting requirements, and analysis of backup power. An access road was redesigned due to a Village of Volente request to change the primary approach road for the proposed Maintenance Building.The City of Austin required two new water quality related structures for the pump station site. A technical memorandum was developed identifying the availability, capacity, timing, and source of back-up power for the pump station at initial and ultimate build-out. Finally,additional design modifications were made to enhance protection again freeze damage. FUNDING: The total compensation for Supplemental Amendment No. 7 will not exceed $137,201 and will increase the total compensation for Lump Sum tasks to $13,994,192. Funding for this Supplemental Agreement for the City of Round Rock's portion will use Phase 1A project savings.The City of Leander's and the City of Cedar Park's portions will use BCRUA's 2018 SWIFT Loan bond funds. Staff and the Operations Committee (OC) have reviewed the attached amendment and exhibits and recommend approval. Staff and representatives of Walker Partners/Freese& Nichols Joint Venture will be present at the Board meeting and will be available to respond to any questions.