Loading...
R-2024-127 - 5/23/2024 RESOLUTION NO. R-2024-127 WHEREAS, Section 395.058 of the Texas Local Government Code ("the Act") requires the Capital Improvement Advisory Committee ("CIAC") to report to the City Council the progress of the capital improvements plan and any perceived inequities in implementing the plan or imposing the impact fee; and WHEREAS, the CIRC is also required to advise the Council of the need to update the land use assumptions,capital improvements plan and impact fees; and WHEREAS, the CIRC has submitted Capital Improvements Plan Progress Semi-Annual Report regarding Water and Wastewater Impact Fee Update; and WHEREAS, the City Council has reviewed the attached Capital Improvements Plan Progress Semi-Annual Report and has determined same to be in compliance with the Act, Now Therefore BE IT RESOLVED BY THE COUNCIL OF THE CITY OF ROUND ROCK, TEXAS, That the Capital Improvements Plan Progress Semi-Annual Report, attached hereto as Exhibit "A" and incorporated herein, are hereby approved. The City Council hereby finds and declares that written notice of the date, hour, place and subject of the meeting at which this Resolution was adopted was posted and that such meeting was open to the public as required by law at all times during which this Resolution and the subject matter hereof were discussed, considered and formally acted upon, all as required by the Open Meetings Act, Chapter 551, Texas Government Code, as amended. RESOLVED this 23rd day of May, 2024. z9Z CRAIGORPck, , Mayor City oftound Texas ATTEST: A4Z AVA.A MEAGAN S KS, ity Clerk 0112.20242;4890-6532-3197 EXHIBIT "All F1 Mayor Councilmembers City Manager Craig Morgan Michelle Ly Laurie Hadley Rene Flores Frank Ortega ROUND ROCK TEXAS Mayor Pro-Tem Kristin Stevens City Attorney PLANNING AND DEVELOPMENT SERVICES Matthew Baker Hilda Montgomery Stephanie Sandre May 1, 2024 Mayor Morgan Mayor Pro-Tem Baker Councilmember Ly Councilmember Flores Councilmember Ortega Councilmember Stevens Councilmember Montgomery RE: Capital Improvements Advisory Committee—Semi-Annual Meeting Dear Mayor Morgan and Council Members: The Capital Improvements Advisory Committee met on May 1, 2024, to consider and approve the semi-annual report to the City Council with respect to the progress of the Capital Improvements Plan and identification of any perceived inequities in the Impact Fees. The findings are addressed in Chapter 395.058(c) of the Texas Local Government Code. After discussion, the Committee found no perceived inequities in implementing the plan or imposing the Impact Fee. Therefore, a motion was made to approve and forward the report from the Utilities and Environmental Services Department to the City Council, with updated city comparison data. Sincerely, K( � J&A Rob Wendt, Chairman Capital Improvements Advisory Committee CITY OF ROUND ROCK PLANNING AND DEVELOPMENT SERVICES-301 W Bagdad, Round Rock,Texas 78664 Planning 512 218.5428-Code Enforcement 512 218 3329-Community Development 512 341.3148-roundrocktexas.gov 5/17/2024 ROUND ROCK TEXAS Capital Improvements Plan Semi -Annual Report Utilities & Environmental Services May 1, 2024 i Water Treatment Plant 3,000 39 38 2,500 - e } 37 9 O c 2,000 �.. 36 F 0 C I ° O 35 c 1,500 N � 34 U Z m 1.000 — - - --T 33 w O t 32 Q 500 - - 31 0 3rd QtrFY'22 4th Qtr FY'22 1 et Qtr FY'23 2nd Qtr FY'23 3rd Qtr FY'23 4th Qtr FY'23 1 st Qtr FY'24 2nd Qtr FY'24 30 'Active SsMtxe 36,670 38,888 36,771 38,8U 37,437 37,558 37,844 37,879 =,ndweter 178,345,000 268, 1 643,000 118,340,000 10fi,131,000 182,809,000 290,551,000 125,692,000 57,041,000 rteceWeter 2,198,673,000 2,531,822,000 1,788,654,000 1,S1S,99B4O00 ,865,962,000 2,691,567,000 1,655,524,000 1,392,921,000 2 1 5/17/2024 40 Average Potable Daily 35 30 Demand Each Month 25 20 0 15 10 5 0 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec N 2020 2021 2022 ■2023 2024 3 Potable vs. Reuse Water Average Daily Demand Each Month I 40 35 I 30 25 c ° 20 l7 ° 15 f 10 5 0 Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sept j E FY-20 •FY-21 ■FY-22 ■FY-23 CIFY-24 N Reuse 4 2 5/17/2024 Annual Single-Family Building Permits Issued Residential & MUDs 1400 ___- -- 1200 12- 1043 1057 1000 600 600 [1533 461 400 200 0 FY-2020 - FY-2021 FY-2022 FY-2023 FY-2024 (Oct-Mar) ■Round Rock ■Paloma#1 Paloma#2 ■Teravista#11 ■Siena#1 ■Siena#2 5 In-City Retail Fiscal Year Multi-Family Units FY 2020 430 Multi-Family Units FY 2021 584 Permitted Annually FY 2022 1626 FY 2023 359 FY 2024 (Oct-Mar) 0 Out-of-City Wholesale Fiscal Year Multi-Family Units FY 2022 720 6 3 5/17/2024 Commercial Fiscal Year Building Permits FY 2020 44 Commercial Building FY 2021 39 Permits Issued Annually FY 2022 39 FY 2023 32 FY 2024 (Oct-Mar) 15 7 - Impact Fees Collected FY 2020 - 2024 (Oct - Mar) FY-20 FY-21 FY-22 FY-23 FY-24l In-City Residential Water $2,008,822 $2,649,580 $2,043,907 $2,938,553 $1,417,464 Wastewater $ 930,467 $1,296,554 $1,695,908 $1,522,930 $ 883,387 In-City Commercial Water $1,752,110 $2,934,225 $4,085,751 $1,338,332 $ 222,134 Wastewate, $ 461,347 $1,457,580 $ 1,900,865 $1,153,932 $ 114,474 Out-of-City Wholesale Water $ 406,253 $ 114,713 $ 52,534 0 0 Wastewater $ 895,448 $ 20,711 $ 870,291 $ 671,680 0 Total Collected $6,454,447 $8,473,363 $10,649,255 $7,625,426 $2,637,458 8 4 5/17/2024 Impact Fees Collected FY 2020 - FY 2024 (Oct - Mar) $12 $10,649,255 $10 $8,473.362 $8 $7,625,426 $6,454,447 o $6 $4 $2,637,458 $2 ■$0 FY-20 FY-21 FY-22 FY-23 FY-24 (Oct-Mar) ■Residential Water ■Commercial Water ■Wholesale Water ■Residential Wastewater ■Commercial Wastewater ■Wholesale Wastewater 9 Population Projections Inside City Citys ETJ Projections Growth Rate Projections Growth Rate Year 2020(Census) 119,468 - 178,704 - 2021 122,455(122,827) 2.5%(2.8%) 182,336 2.0% 2022 125,516(124,614) 2.5%(1.5%) 184,993 1.5% 2023 128,292(131,235) 2.2%(5.3%) 189,286 2.3% 2024 134,540(132,927) 4.9%(1.3%) 196,035 3.6% 2025 139,834 3.9% 202,208 3.1% 2026 145,208 3.8% 208,843 3.3% 2027 149,621 3.0% 214,486 2.7% 2028 153,530 2.6% 219,624 2.4% 2029 157,298 2.5% 224,320 2.1% 2030 161,136 2.4% 228,933 2.1% Notes:2020 is the base year for these projections O Annual Estimates by Planning&Development Services Department 10 5 5/17/2024 I q� OF ROUND ROCK IER DIS TRIBUTtON SYSTEM - `/-• JULY M21 11 Water System Capital Improvement Projects COMPLETED Impact Fee Report Completion_ Estimated Cost Actual Cost South 81 Elevated Storage Tank Pump Station 2019 $157,000 $1,070,900 Arterial H Phase II 2020 $1,470,500 $1,375,045 BCRUA Phase 1C-WTP Expansion t0 32MGD 2020 $4,465,000 $3,635,540 Water Dist.Master Plan&Impact Fee 2020 $66,000 $220,570 University Blvd extension from end of 36-Inch main to CR-110 2022 $1,150,000 $775,481 E Liberty Avenue,N Shephard St&Fannin Ave 2022 $500,000 $938,983 Kenny Fort Blvd from Old Settlers to Chandler Creek(24"WL) 2024 $4,212,134 $4,212,134 $12,020,634! $12,228,653 12 6 5/17/2024 Water System Capital Improvement Projects IN PROGRESS Estimated Impact Fee Report Completion Estimated Cost Actual Cost Kenny Fort Blvd from Forest Creek Blvd to SH45(12'WL) 2024 $1,787,073' $1,787,073 Oki Settlers from Red Bud to CR-110(16'WL) 2025 ;1,500,000 ;1,500,000 Sam Bass Rd from FM-1431 to Wyoming Springs Or(42"WL) 2025 $10,770,000 $10,770,000 Redbud Lane from south of Palm Valley Blvd to Gattis School Rd(24' 2026 $4,560,000 $4,560,000 BCRUA Phase 1D-WTP Expansion to 42MGD 2025 $4,934,911 $4,934,911 BCRUA Phase 2-Deep Water Intake 2027 $77,437,930 $77,437,930 BCRUA Phase 2A-WTP Expansion to 64MGD* 2028 $35,000,000 $35,000,000 $135,989,914 $135,989,914 *Current estimates based on updated industry rales for projects in the design phase. 13 Water System Capital Improvement Projects UPCOMING Estimated Impact Fee Report Completion Estimated Cost Groundwater GST and Pump Station Land Purchase 2024 $784,000 GR-07:Hesters Crossing and CR-172 from west 971 zone to 5-81 EST 2025 $2,500,000 Kenny Fort Blvd 5 8 6(24"WL) 2026 $1,800,000 Eagle's Nest In Connection w/Road Extension 2027 $2,300,000 BCRUA 6MG Clearwell 2027 $4,760,000 Red Bud&Gattis School to High County EST(24"WL) 2030 $1,500,000 East Groundwater Supply(Joint Project w/Georgetown) 2030 $35,000,000 $48,644,000 14 7 5/17/2024 A At _ } LD ClrYOFROlID 1l00JI ' MMSTFlGITFR COI I FCipM SYSiFY ^•" �. narnm 15 Wastewater System Capital Improvement Projects Impact Fee Report i COMPLETED Completion Estimated Cost Actual Cost Brushy Creek 2 2019 ;685,000 $349,000 Brushy Creek 4 2019 ;173,000 $173,000 MC-1:New 6,760LF of 18-in 2022 ;1,973,000 $0 $2,831,000 $522,000 IN-PROGRESS Completion Estimated Cost Actual Cost Lake Creek 1 2024 ;3,786,150 ;3,786,150 Kenny Fort Blvd(2/3)from Forest Creek to 2024 ;844,872 ;844,872 Gattis School 18'WW Cottonwood Creek interceptor* 2025 ;4,363,000 ;4,363,000 WWTP Expansion to 40MGD• 2027 ;99,000,000 ;109,000,000 $107,994,022 ;117,994,022 "Current estimates based on updated industry rates for projects in the design phase. 16 8 5/17/2024 Wastewater System Capital Improvement Projects UPCOMING Estimated Impact Fee Report Completion Estimated Cost CC-2-West of AW Grimes(12"WW) 2025 ;516,000 CC-1-Sunrise Rd South of University(15'WW) 2026 ;2,560,000 CC-4-Near Old Settlers Park(18"WW) 2026 ;2,092,000 MC-2-West side of SH 130(15'WW) 2026 ;3,961,000 BC-1-Downtown Round Rock(12"-18"WW) 2027 ;2,294,000 MC-3-North of Paloma Lake(24"WW) 2028 ;4,978,000 LC-3-Near Round Rock West(15"WW) 2028 ;2,748,000 MCi-South of University between AW Grimes and CR110 2029 ;7,433,000 10'-15'WW LC-4-South of McNeil Rd along 135(24'WW) 2030 ;3,694,000 $30,276,000 17 �t Cd%V r t.ur Reuse Water T.-Ag ��C.". �+ 1w.m x�u System c , ,`� T n.r Di,mwM F-PSR.� z c- -~..__.� i 1 co..i o.r Go.cm { 18 9 5/17/2024 Reuse Water System Capital Improvement Projects IN-PROGRESS Estimated Impact Fee Report Completion Estimated Cost Actual Cost Kenny Fort Blvd 16-Inch Reuse Une 2024 $1,705,468] $1,705,468 Reuse High Service Pump Addition* 20— 25 $750,000 $750,000 Kenny Fort Blvd 24-Inch Reuse Line* 2025 $6,000,000 $6,000,000 Reuse 2MG Ground Storage Tank* 2025 $4,000,000 $4,000,000 $12,455,468 $12,455,468 *Current estimates based on updated industry rates/or projects in the design phase. Estimated Impact Fee Report Estimated Cost UPCOMING Completion Reuse Line to Dell Way 2027 $4,995,000 $4,995,000 19 Single-Family Residential Water and Wastewater Rates Monthly Comparison *assumes 10,000 gallons water and 8,000 gallons wastewater used $220 $207.30 $200 $180 $170.47 $161.01 $159.83 $160 $142.27 $140 $120.15 $115.60 E120 - $113.62 $110.21 $105.22 $102.60$100 - — - $88.22 898.80 $96.80—$91.38—$88.86-- -— _ 860.11 $80 $60 - - $40 $20 $0 Pfluge-lie San Austin Hutto Manville Leander Paloma Walsh Ceder Cedar Georgetown %Asia Teravista 11 Brushy Teravists 10 Fern Round Marcos 182 Ranch Park Park Oaks Creek Bluff Rock Stege 3 (Annual Avg) ■Water ■Wastewater 20 10 5/17/2024 Area Impact Fee Comparison City/Utility Last Water Wastewater Total Updated Brushy Creek MUD 2012 $2,095 $1,804 $3,899 Cedar Park 2020 $3,160 $3,170 $6,330 San Marcos 2018 $3,801 $2,684 $6,485 Austin 2023 $4,800 $2,900 $7,700 Round Rock 2023 $4,912 $2,921 $7,833 Leander 2023 $8,762 $2,301 $11,063 Hutto 2021 $8,832 $2,788 $11,620 Pflugerville 1 2023 $14,713 $1,316* $16,029 Georgetown 2023 $11,000 $6,129* $17,129 *Indicates the City has two different Wastewater Impact Fees,based on service area.The amount shown reflects the lowest fee charged by that City. 21 Conclusion and Recommendations Due to the volatility in growth rates and infrastructure requirements, the City recommends a review of the Impact Fees approximately every three years. The latest Impact Fee update report was completed in September 2023, adopted by the City Council in November 2023, and went into effect on January 1, 2024. Over the past few years, the population growth in Round Rock has proceeded as projected in the Impact Fee Analysis. Therefore, the number of connections to the water and wastewater systems has increased as anticipated, and in some areas, more than was expected. Due to the number of connections to the water and wastewater systems and the anticipated infrastructure projects needed to serve these new connections, the City updates its Water and Wastewater Master Plans and Impact Fee Report approximately every three years.This ensures that the City is collecting the necessary fees so that new growth is paying its fair share for the cost of constructing the required water and wastewater infrastructure. The next Capital Improvements Plan Progress Report will be presented to the CIAC and the City Council in approximately six months. 22 11