R-2024-139 - 6/13/2024 RESOLUTION NO. R-2024-139
WHEREAS, the City of Round Rock has previously entered into a contract ("Contract") with
Jordan Foster Construction, LLC for the Kenney Fort Boulevard- Segment 4C Project, and
WHEREAS, the Council has determined that it is necessary to make adjustments/changes to
the quantity of work to be performed or materials, equipment, or supplies to be provided, and
WHEREAS, it has been determined that it is necessary to adjust/change the quantities in said
Contract in accordance with the attached Quantity Adjustment/Change Order No. 2, Now Therefore
BE IT RESOLVED BY THE COUNCIL OF THE CITY OF ROUND ROCK,TEXAS,
That the Mayor is hereby authorized and directed to execute on behalf of the City, Quantity
Adjustment/Change Order No. 2 to the Contract with Jordan Foster Construction, LLC for the Kenney
Fort Boulevard - Segment 4C Project, a copy of said quantity adjustment/change order being attached
hereto as Exhibit"A" and incorporated herein for all purposes.
The City Council hereby finds and declares that written notice of the date, hour, place and
subject of the meeting at which this Resolution was adopted was posted and that such meeting was
open to the public as required by law at all times during which this Resolution and the subject matter
hereof were discussed, considered and formally acted upon, all as required by the Open Meetings Act,
Chapter 551, Texas Government Code, as amended.
RESOLVED this 13th day of June, 2024.
CRAIG O G , Mayor
City of Round 7
k, Texas
ATTEST:
JAA ', I%-
AGAN S KS, Jity Clerk
L
0112.20242;4868-6408-8513
Page 1 of 3
Contract Quantity Adjustment/Change Order EXHIBIT
/�„
rev.05/23 "All
Department: Transportation
Project Name: Kenney Fort Boulevard-Segment 4C Date: 4/11/2024
City Project
ID Number: Quantity Adjustment/Change Order No. 2
Vendor: Jordan Foster Construction 15603 IH 35,Pflugerville,TX 78660 (512)990-8313
Company Name Address Phone No.
Justification
The existing reclaimed water line from STA 7+00 to STA 17+00 and along Chandler Creek Blvd.was reclocated to outside the proposed roadway and sleeved at
the crossing. The additional inlets were added to improve the storm water draingage near the residential area. The proposed 4-inch conduit was bored under
the existing driveways at the Round Rock Multi-Purpose Complex near Old Settlers Blvd. To mitigate issues with the Phase 3 Traffic Control Plan,the
construction of the intersection of Chandler Creek Blvd.was fast-tracked by replacing the the proposed flexible base with HMAC Ty B. The intersection of Joe
DiMaggio Blvd.needed temporary traffic signals to maintain traffic control during construction. The proposed 4-inch conduit was bored under the Joe DiMaggio
Blvd.near the fire station. The existing asphalt pavement within the project is to be milled 2 inches.
SUMMARY Amount %Change
Original Contract Price: $18,577,470.14
Previous Quantity Adjustment(s): $14,872.20 0.1%
This Quantity Adjustment: -$5,636.00 0.0%
Total Quantity Adjustment(s)To Date: $9,236.20 0.0%
Total Contract Price with Quantity Adjustment(s): $18,586,706.34
Previous Change Order(s): $56,156.25 0.3%
This Change Order: $160,469.05 0.9%
Total Change Order(s)To Date: $216,625.30 1.2%
Adjusted Contract Price: $18,803,331.64
[Original Contract Price Plus Quantity Adjustment(s)Plus Change Order(s))
Difference between Original and Adjusted Contract Prices: $225,861.50
Original Contract Time: 372
Time Adjustment by previous Quan.Adj./Change Order: 0
Time Adjustment by this Quan.Adj./Change Order: 0
New Contract Time: 372
Submftted for Approval
Prepared By:
Signature Printed Name,Title,Company Date
(lJApprovals
Contra or. j "— ----- John Goodrich,PE,Executive Vice President 4-11-2024
Signature Printed Name,Title,Company Date
City Project ' t ,t
_Manager: �`��� S `C 1�.� P/h -4 -—901 -29
Signature Printed Name,Title Date
Mayor/City
Manager:
Signature Printed Name,Title Date
Page 2 of 3
opocM"%^' Contract Quantity Adjustment/Change Order
ev.05/23
Project Name: Kenney Fort Boulevard-Segment 4C
Quantity Adj./Change Order No.: 2
Change Order Data
Contract Time
Adjustment
Item# Item Description Unit Quantity Unit Price Amount (Days)
Coll-01 CORR 510 Relocate Existing Reclaimed Water Line LF 1,200.00 $25.49 $30,588.00 0
C012-01 104-0000 REMOVING CONC LS 1.00 $4,004.45 $4,004.45 0
C012-02 400-6006 CUT&RESTORING PAV SY 25.00 $335.72 $8,393.00 0
C012-03 3665-6 26 INLET(COMPL)(PSL)(FG)(3F1X3FT- EA 2.00 $11,301.54 $22,603.08 0
CO 12-04 CONC(CURB&GUTTER/SIDEWALK) LS 1.00 $9,867.43 $9,867.43 0
C013-01 6 �a59 CONDT(PVC)(SCH 80)(4")(BORE)(Under LF 100.00 $103.93 $10,393.00 0
DrivC014-01 340-6011 Install HMAC Ty B(9 IN)(Fast-Track) SY 442.00 $115.32 $50,971.44 0
C016-01 681-6001 TEMP TRAF SIGNALS EA 1.00 $4,029.90 $4,029.90 0
CO 16-02 690-6051 REMOVE SIGNAL POLE ASSEMBLY EA 1.00 $1,590.75 $1,590.75 0
CO21-01 618-6059 CONDT(PVC)(SCH 80)(4")(BORE)(Near LF 200.00 $90.14 $18,028.00 0
Joe Dimaggio Blvd.
$0.00 0
$0.00 0
$0.00 0
$0.00 0
$0.00 0
$0.00 0
$0.00 0
$0.00 0
$0.00 0
$0.00 0
$0.00 0
$0.00 0
$0.00 0
$0.00 0
$0.00 0
$0.00 0
TOTALS: $160,469.05 0
Page 3 of 3
No�cN"F^ Contract Quantity Adjustment/Change Order
rev 05/23
Project Name: Kenney Fort Boulevard-Segment 4C
Quantity Adj./Change Order No.: 2
Quantity Adjustment Data
ontract Time
Adjustment
Bid Item# Item Description Unit Quantity Unit Price Amount (Days)
42 464-6003 RC PIPE(CL III)(18 IN) LF 40.00 $87.00 $3,480.00 0
14 247-6366 FL BS(CMP IN PCL)(TY A GR 5)(FNAL CY
POS (172.00) ;53.00 (;9,116.00) 0
$0.00 0
$0.00 0
$0.00 0
$0.00 0
$0.00 0
$0.00 0
$0.00 0
$0.00 0
$0.00 0
$0.00 0
$0.00 0
$0.00 0
$0.00 0
$0.00 0
$0.00 0
$0.00 0
$0.00 0
$0.00 0
$0.00 0
$0.00 0
$0.00 0
$0.00 0
$0.00 0
$0.00 0
TOTALS: -$5,636.00 0
`0 4--J
CD
w
y
to 6
tit
cy
Ak
� . O
I
l f
Kti
'i a /�e/1JlagfaN9a ass 0 a�;p. _� b L
oG
• eFld�,�''' �,eJ �6p�b`a�, ,
'ry�d �` %7J m p'�•wes1e�.
l +of Wd
r � `� t - tb • �de�eA'�r ��,�
es •�