Contract - Patin Construction - 9/12/2024 Page I of 3 Contract Quantity Adjustment/Change Order W,Olh$ Department: PARD Project Name: Heritage Trail West Date: 8/1/24 City Project Change Order/Quantlty ID Number Adjustment No. 5 Vendor Patin Construction 3800 W. Second St.,Taylor,Texas 76574 __ 512 269 1071 Company Name Address Phone No. )ustitication See attached justification form. SUMMARY Amount %Chan e Original ContraCt Price: $19 500 000.00 Previous Quantity Adjustrnent(s), $0.00 This Quantity Adjustment: $0.00 Total Quantity Adjustment(s): $0,00 Total Contract Price with QuanUty Adjustment(s): $19,500,000. Previous Change Order(s): 8% $1,61 S,700.00 This Change Order: $208,395.57 10rb Total Change Order(s)To Date. $1,824,095.57 9% Adjusted Contract Price (Original Contract Price Plus Quantity Adjustment(s)Plus Change Order(s)j: $21,324,095.57 Difference between Original and Adjusted Contract Prices: ;1,824,095.51 Original Contract Time. 480 days Y Time Adjustment by previous Quan.Ad)./Change Order: 130 Time Adjustment by this Quan.Adj./Change Order: 21 New Contract Time: 631 days Prepared By: gem y- '6� PPAK 1-/ Sr turer Printed Name,Title,Company Date Contractor: Slgre Printed Name,Titte,Co rly Date City Project !A' Manager: ig ure Printed Name,Title Date Mayor/City Manager Ar :'Ol, do Sig lure Printed a e, Tit e Date -2oz44 -237 Nngc 2 of 3 Contract Quantity Adjustment/Change Order IIOUH60D[M Gar1 icy,01116 Project Name: Heritage Trail West Quan,Adj,/Change Order No.: 5 Change Order Data Contract Time Adjustment Item# Item Descrition Unit Aty- Unit Price Amount p Embed Plate revision •due to engineer 1 res se from shop drawing LS 1 $36,050.00 $36,050.00 2 Deduct for slgnage removed from scope EA -1 $5,500.00 •$5,500.00 3 Engrave"Memorial Park"on planter wall LS 1 $3,110.00 $3,110.00 Remove and replace concrete approach 4 at Lee Street low water crossing SF 525 $22.00 $11,550.00 5 Restroom wood panel with vinyl wrap LS 1 $4,821.00 $4,821.00 6 Modifications of metal panels at restroom LS 1 $21,728.00 $21,728.00 Deduct or collector ox,scupper, rain 7 chain at pavilion LS -1 $6,963.43 46,963.43 8 Piers for scu Lure EA 12 $8S0.00 $10,200.00 9 Concrete pad for sculpture SF 50 $65.00 $3,250.00 Electrical and recepta or camera at 10 Round Rock LS i $13,900,00 $13,900.00 11 Paintinq structural steel at ram L 1 $73,500.00 $73,500.00 12 Stone Cladding for spiral ramp abutment SF 1450 $27.00 $39,150,00 21 Install rock maintenance drive a 13 Chisholm Trail Road LS 1 $3,600.00 $3,600.00 $0.00 $0.00 0.00 0.00 $0.00 _ $0.00 $0.00 $0,00 0.00 $0.00 0. 0.00 I'agc 3 of 1 Contract Quantity Adjustment/Change Order RilIPO RO(M 1t^t !p/,01116 Project Name, Herl"Trail West Quan Adj./Change Order No.: 5 antilty Adjustment Data WHOM Contract Time Bid Item# Item Description Unit Unit Price Amount Adjustment .00 $0.00 0.00 - 0.00 S .00 ;0.00 ---16-00 X0.00 x.00 $0.00 $0.00 $0.00 0,00 .00 $0,00 ;0.00 ;0. .00 0.00 $0.00 TOTAL5:[ $0,001 0