BCRUA-2024-007 - 6/26/2024Change Order No. 001 Date of Issuance. June 26, 2024 Effective Date: June 26, 2024 Proj«e BCRUA Phase I WTP Expansion owner BCRUA ow ees Conga« No: NA contract. Date of Contract: May 10, 2023 Contractor. Excel Construction Services, L.L.0 Engineer s Project No.: 3-00809 The Contract Documents are modified as follows upon execution of this Change Order. Description: This Change Order includes approved Change Proposals 001, 002, 003, and 004 as identified below. CP-001: Additional excavation and subgrade preparation resulting from an unknown, buried trash/burn bit discovered beneath the proposed Sedimentation Basin. Price, Time: $14,283.00, 0 days. CP-002: Repair of a wall leak in an existing expansion joint at the intersection of the existing Phase 1 A and Phase 1 C settled water channels. Price, Time: $10,583.00, 0 days. CP-003: Modifications to Culvert #7 due to the elevations of two existing duct banks being shallower than indicated on record drawings. Price, Time: $32,256.00, 0 days. CP-004: Upgrades to eight existing Filter Remote Input/Output panels to replace control modules that are being phased out of production by the manufacturer. Price, Time: $133,841.00, 0 days. Attachments: (list documents supporting change): CP-001, 002, 003, and 004 CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES: Original Contract Price: Original Contract Tunes: ❑ Working days . J. © Calendar days ` Substantial completion (day, or date): 11 /20/2024 $16,836,100.00 Ready for final paymcnt (days or date): 01119/2025 [Increase] [Decrease] from previously approved Change Orders [Increase] [Decreasel from previously approved Change Orders No. to No. No. to No. Substantial completion (days): NA $ Ready for final payment (days): NA Contract Price prior to this Change Order. Contract Times prior to this Change Order Substantial completion {days or date): 11 /20/2024 516,836,100.00 Ready for final payment (da)s or date): 01 /19/2025 Increase of this Change Order. [Increase[ [Decrease[ of this Change Order. 0O days Substantial completion (days or date): 11 /20/2024 5190 963.00 Ready for final payment (days or date): 01 / 19/2025 Contract Price incorporating this Change Order Contract Times with all approved Change Orders: Substantial completion (days or date): 11 $i T027,063.00 Ready for final payment ,days or date): 1 2 RECOMMENDED: Ln(,rincer (Authorised Signature) Date: 61 14aA_ , ACCE 'D: By: v` Ownerr (Authorized Signature) " Date: 6 u'Z+ ACCEPTED: By: Contractor (Authorized Signature, Dare: 6/14/24 Approved by Funding Agenq (if applicable): DO&