Contract - C.C. Carlton Industries, LTD - 2/13/2025 Page I of 4 �-- Contract Quantity Adjustment/Change Order ev,01/16 Department: Public Works Project Name: Chandler Road 36-Inch Water Transmission MAIN Date: 1/15/25 City Project Change Order/Quantity ID Number CRDWL Adjustment No. CO 1 Vendor C.0 Carlton Industries,LTD 3102 Bee Caves Rd.Ste.200 Austin Texas,78746 512-4764282 Company Name Address Phone No. Justification Removal of last bore at FM 1660 to avoid conflicts with a planned future intersection improvement.Addition of flowable fill along portions of the project that are in conflict with future Chandler Road expansion,adding a bore location at CR 130 and omitting installation of 1-36-Inch Gate Valve. SUMMARY Amount %Change Original Contract Price: $11,161,145.40 Previous Quantity Adjustment(s): $0.00 This Quantity Adjustment: -$156,556.00 Total Quantity Adjustment(s): -$156,556.00 Total Contract Price with Quantity Adjustment(s): $11,004,589.40 Previous Change Order(s): $0.00 0% This Change Order: $163,103.13 1% Total Change Order(s)To Date: $163,103.13 1% Adjusted Contract Price [Original Contract Price Plus Quantity Adjustment(s)Plus Change Order(s)]: $11,167,692.53 Difference between Original and Adjusted Contract Prices: $6,547.13 Original Contract Time: 300 days Time Adjustment by previous Quan.Adj./Change Order: 0 Time Adjustment by this Quan.Adj./Change Order: 35 New Contract Time: 335 days Prepared By: �ZLC'el !Z4"L" Mark Hurd, Project Manager,City of Round Rock 1/15/25 S' nabure Printed Name,Title,Company Date Contractor: Garrett Gunter, Project Manager, CCCarlton 1/15/2025 Signature Printed Name,Title,Company Date City Project /11 Manager: Mark Hurd 1/15/25 SignAlbure Printed Name,Title Date Mayor/City �r � O Manager Sign*ure Printed NaMe,Tid Date Page 2 of Contract Quantity Adjustment/Change Order ioo[rixn', ev,01/16 Project Name: Chandler Road 36-Inch Water Transmission MAIN Quan.Adj./Change Order No.: CO 1 Change Order Data Contract Time Item# Item Description Unit Qty. Unit Price Adjustment evise backtill of pipe per Detall 1:3 on sheet CZ-2 as indicated on Revised 1.1 Sheets C-11,C-12,C-13 and C-21 LF 822 $127.09 $104,467.98 5 Per revised Sheet C-19, provide and field route 1-Inch Sch 80 PVC conduit from rectifier(STA 87-60)to a power source provided by the City of Round Rock. 1.4 Estimated length is 2,300 LF. LS 1 $3,350.00 $3,350.00 5 Per revisea Sneets an , revise installed depth of 36-inch CL 250 Ductile IronPipe to depths from STA 102+00 to 1.5 STA109+00 LF 700 $74.23 $51,961.00 5 1.11 Restocking fee 10%for Steel Casing LF 159 $35.85 $5,700.15 0 1.12 Deduct for installation of Gate Valve EA 1 -$5,876.00 -$5,876.00 0 1.13 Enlarge thrust block EA 1 3,500.00 $3,500.00 0 $0.00 0 0.00 0 $0.00 0 $0.00 0 $0.00 0 $0.00 0 0.00 0 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 $0.00 $0.00 0.00 0.00 0.00 Page 3 of 4 Contract Quantity Adjustment/Change Order rev,01/16 Project Name: Chandler Road 36-Inch Water Transmission MAIN Quan.Adj./Change Order No.: CO 1 Quantity Adjustment Data Contract Time ;;Per Item Description Unit Qty. Unit Price Amount Adjustment revised sheet C-12 and C-13,provide 36-inch CL 250 Ductile Iron Pipe in steel casing by trenchless method,Including excavation,joint restraints,steel casing, boring pits,dewatering,polyethylene wrap,bedding,backfill and trench surface restoration,complete in place as detailed 1.2 and specified. LF 215 $1,940.00 $417,100.00 20 Per revised sheet C-12 and C-13, provide 36-inch CL 250 Ductile Iron Pipe in steel casing, (open cut),Including excavation, joint restraints, steel casing, boring pits, dewatering,polyethylene wrap, bedding, backfill and trench surface restoration, complete in place as detailed and 1.3 specified. LF -215 $940.00 -$202,100.00 0 Per revised Sheet C-25,provide 36-Inch CL 250 Ductile Iron Pipe in Steel Casing by Trenchless Method,including excavation,joint restraints,steel casing, boring pits,dewatering,polyethylene wrap,bedding, backfill,and trench surface restoration,complete in place as 1.6 detailed and specified. LF 110 $1,940.00 $213,400.00 0 Per revised Sheet C-25,remove 36-Inch CL250 Ductile Iron Pipe in steel casing, (open cut), including excavation,joint restraints,steel casing,dewatering, polyethylene wrap, bedding,backfill,and trench surface restoration,complete in 1.7 place as detailed and specified. LF -110 $940.00 -$103,400.00 0 remove 36-Inch CL250 Ductile Iron Pipe in steel casing,(open cut),joint restraints(as required),fittings, excavation,dewatering, polyethylene wrap,bedding, backfill,and trench surface restoration,complete in place as 1.8 detailed and specified. LF -187 $448.00 -$83,776.00 0 Page 4 of 4 Contract Quantity Adjustment/Change Order ev,01/16 Per revised Sheets C-36, remove 36-Inch CL250 Ductile Iron Pipe in steel casing, (open cut), including excavation,joint restraints,steel casing,dewatering, polyethylene wrap, bedding, backfill,and trench surface restoration,complete in 1.9 place as detailed and specified. LF -159 $940.00 -$149,460.00 0 Per revised Sheets C-36, remove 36-Inch CL250 Ductile Iron Pipe in steel casing by trenchless method, including excavation, joint restraints, steel casing, boring pits, dewatering, polyethylene wrap, bedding, backfill, and trench surface restoration, complete in place as detailed and 1.10 specified. LF -128 $1,940.00 -$248,320.00 0 $0.00 0 $0.00 0 0.00 0 00 0.00 $0.00 $0.00 $0.00 $0.00 0.00 0.00 0.00 $0.00 0.00 $0.00 0.00 0.00 0.00 -$15 556.00 20