Contract - SpawGlass Contractors, Inc. - 2/13/2025
Document A133v - 2019 Exhibit A Guaranteed Maximum Price Amendment This Amendment dated the Twentieth day of January in the year Two Thousand Twenty-Five,is incorporated into the accompanying AIA Document A133TM-2019, Standard Forth of Agreement Between Owner and Construction Manager as Constructor where the basis of payment is the Cost of the Work Plus a Fee with a ADDITIONS AND DELETIONS: Guaranteed Maximum Price dated the day of in the year(the"Agreement") The author of this document may (In words, indicate day, month,and year.) have revised the text of the original AIA standard form An Additions for the following PROJECT: and Deletions Report that notes (Name and address or location) revisions to the standard form text Old Settlers Park Buildout—Package 3C—Rec Center- Earthwork- is available from the author and Old Settlers Park should be reviewed.A vertical line 3300 E.Palm Valley Blvd in the left margin of this document Round Rock,TX 78665 indicates where the author has added to or deleted from the THE OWNER: original AIA text. (Name, legal status, and address) This document has important legal consequences. Consultation with City of Round Rock an attorney is encouraged with 221 East Main Street,Round Rock,TX 78644 respect to its completion or modification. THE CONSTRUCTION MANAGER: AIA Document A201 TI-2017, (Name, legal status, and address) General Conditions of the Contract SpawGlass Contractors,Inc. for Construction. is adopted in this 1111 Smith Road,Austin TX 78721 document by reference. Do not use with other general conditions TABLE OF ARTICLES unless this document is modified. A.1 GUARANTEED MAXIMUM PRICE A.2 DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION A.3 INFORMATION UPON WHICH AMENDMENT IS BASED AA CONSTRUCTION MANAGER'S CONSULTANTS,CONTRACTORS, DESIGN PROFESSIONALS,AND SUPPLIERS ARTICLE A.1 GUARANTEED MAXIMUM PRICE §A.1.1 Guaranteed Maximum Price Pursuant to Section 3.2.6 of the Agreement,the Owner and Construction Manager hereby amend the Agreement to establish a Guaranteed Maximum Price.As agreed by the Owner and Construction Manager,the Guaranteed Maximum Price is an amount that the Contract Sum shall not exceed.The Contract Sum consists of the Construction Manager's Fee plus the Cost of the Work,as that term is defined in Article 6 of the Agreement. §A.1.1.1 The Contract Sum is guaranteed by the Construction Manager not to exceed Five Million Two Hundred and Eighty-Seven Thousand One Hundred Twenty-One Dollars and Zero Cents($5,287,121.00),subject to additions and deductions by Change Order as provided in the Contract Documents. §A.1.1.2 Itemized Statement of the Guaranteed Maximum Price. Provided below is an AIA Document A133—2019 Exhibit A.Copyright @ 1991,2003,2009,and 2019.All rights reserved."The American Institute of Architects,""American Institute of Architects,""AIA,"the AIA Logo,and"AIA Contract Documents"are trademarks of The American Institute of Architects.This document was produced at 15:29:16 CST on 01/20/2025 under Subscription No.20240040942 which expires on 07/05/2025,is not for resale,is licensed for one-time use only,and may only be used in accordance with the AIA Contract Documents®Terms of Service.To report copyright violations,e-mail docinfo@aiacontracts.com. t(� User Notes: (673cb30257573cc341eac230 itemized statement of the Guaranteed Maximum Price organized by trade categories,including allowances;the Construction Manager's contingency;alternates;the Construction Manager's Fee;and other items that comprise the Guaranteed Maximum Price as defined in Section 3.2.1 of the Agreement. (Provide itemized statement below or reference an attachment.) «Reference attached GMP package-TAB 06 §A.1.1.3 The Construction Manager's Fee is set forth in Section 6.1.2 of the Agreement. §A.1.1.4 The method of adjustment of the Construction Manager's Fee for changes in the Work is set forth in Section 6.1.3 of the Agreement. §A.1.1.5 Alternates §A.1.1.5.1 Altcrnates,if any,included in the Guaranteed Maximum Price: Item Price §A.1.1.5.2 Subject to the conditions noted below,the following alternates may be accepted by the Owner following execution of this Exhibit A.Upon acceptance,the Owner shall issue a Modification to the Agreement. (Insert below each alternate and the conditions that must be met for the Owner to accept the alternate) Item Price Conditions for Acceptance §A.1.1.6 Unit prices,if any: (Identify the item and state the unit price and quantity limitations, if any, to which the unit price will be applicable) Item Units and Limitations Price per Unit($0.00) ARTICLE A.2 DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION §A.2.1 The date of commencement of the Work shall be: (Check one of the following boxes) [ ] The date of execution of this Amendment. [X] Established as follows: (Insert a date or a means to determine the date of commencement of the Work.) April 16th,2025 If a date of commencement of the Work is not selected,then the date of commencement shall be the date of execution of this Amendment. §A.2.2 Unless otherwise provided,the Contract Time is the period of time,including authorized adjustments,allotted in the Contract Documents for Substantial Completion of the Work.The Contract Time shall be measured from the date of commencement of the Work. §A.2.3 Substantial Completion §A.2.3.1 Subject to adjustments of the Contract Time as provided in the Contract Documents,the Construction Manager shall achieve Substantial Completion of the entire Work: (Check one of the following boxes and complete the necessary information) [ ] Not later than()calendar days from the date of commencement of the Work. [X] By the following date:November 02,2026 AIA Document A133—2019 Exhibit A.Copyright©1991,2003,2009,and 2019.All rights reserved."The American Institute of Architects,""American Institute of Architects,""AIA,"the AIA Logo,and"AIA Contract Documents"are trademarks of The American Institute of Architects.This document was produced at 15:29:16 2 CST on 01/20/2025 under Subscription No.20240040942 which expires on 07/05/2025,is not for resale,is licensed for one-time use only,and may only be used in accordance with the AIA Contract Documents®Terms of Service.To report copyright violations,e-mail docinfo@aiacontracts.com. User Notes: (673cb30257573cc341 eac23f) §A.2.3.2 Subject to adjustments of the Contract Time as provided in the Contract Documents,if portions of the Work are to be completed prior to Substantial Completion of the entire Work,the Construction Manager shall achieve Substantial Completion of such portions by the following dates: Portion of Work Substantial Completion Date §A.2.3.3 If the Construction Manager fails to achieve Substantial Completion as provided in this Section A.2.3,liquidated damages,if any,shall be assessed as set forth in Section 6.1.6 of the Agreement. ARTICLE A.3 INFORMATION UPON WHICH AMENDMENT IS BASED §A.3.1 The Guaranteed Maximum Price and Contract Time set forth in this Amendment are based on the Contract Documents and the following: §A.3.1.1 The following Supplementary and other Conditions of the Contract: Document Title Date Pages §A.3.1.2 The following Specifications: (Either list the Specifications here, or refer to an exhibit attached to this Amendment.) Old Settler 's Park Buildout-Rec Center Complex 100%Construction Documents Technical Specifications issued August 2024 Proposed Old Settlers Park Improvements Rec Center Complex -Soccer and Practice Fields as issued by UE S on November 20, 2024 Proposed Old Settlers Park Improvements Rec Center Complex as issued by UES on November 4, 2024 Section Title Date Pages §A.3.1.3 The following Drawings: (Either list the Drawings here, or refer to an exhibit attached to this Amendment.) Old Settlers Park Improvements-Rock N River Expansion 90%Construction Documents as issued by Kimley-Horn in September 2024 Number Title Date §A.3.1.4 The Sustainability Plan,if any: (If the Owner identified a Sustainable Objective in the Owner's Criteria, identify the document or documents that comprise the Sustainability Plan by title, date and number of pages, and include other identifying information. The Sustainability Plan identifies and describes the Sustainable Objective;the targeted Sustainable Measures; implementation strategies selected to achieve the Sustainable Measures;the Owner's and Construction Manager's roles and responsibilities associated with achieving the Sustainable Measures; the specific details about design reviews, testing or metrics to verify achievement of each Sustainable Measure;and the Sustainability Documentation required for the Project, as those terms are defined in Exhibit C to the Agreement.) Title Date Pages Other identifying information: AIA Document A133-2019 Exhibit A.Copyright©1991,2003,2009,and 2019.All rights reserved."The American Institute of Architects,""American Institute of Architects,""AIA,"the AIA Logo,and"AIA Contract Documents"are trademarks of The American Institute of Architects.This document was produced at 15:29:16 3 CST on 01/20/2025 under Subscription No.20240040942 which expires on 07/05/2025,is not for resale,is licensed for one-time use only,and may only be used in accordance with the AIA Contract Documents®Terms of Service.To report copyright violations,e-mail docinfo@aiacontracts.com. User Notes: (673cb30257573cc341 eac23f) §A.3.1.5 Allowances,if any,included in the Guaranteed Maximum Price: (Identify each allowance.) Storm Drain Piping for Roof and Landscape $225,000.00 Reclaimed Water Extension to Irrigation Meeter$24,000.00 Drinking Fountains and Hose Bibbs $55,000.00 §A.3.1.6 Assumptions and clarifications,if any,upon which the Guaranteed Maximum Price is based: (Identify each assumption and clarification) Reference attached GMP Package—TAB 05 §A.3.1.7 The Guaranteed Maximum Price is based upon the following other documents and information: (List any other documents or information here, or refer to an exhibit attached to this Amendment.) ARTICLE A.4 CONSTRUCTION MANAGER'S CONSULTANTS, CONTRACTORS, DESIGN PROFESSIONALS, AND SUPPLIERS §A.4.1 The Construction Manager shall retain the consultants,contractors,design professionals,and suppliers,identified below: (List name, discipline, address, and other information.) This Amendment to the Agreement entered into as of the day and year first written above. 11/19/2024 OWNER i at re) CO UC ION AGER(Signature) BY:Craig Morga Mayor : D d Paden,Austin Division President (Printed name and title) Minted name and title) AIA Document A133—2019 Exhibit A,Copyright©1991,2003,2009,and 2019.All rights reserved."The American Institute of Architects,""American Institute of Architects,""AIA,"the AIA Logo,and"AIA Contract Documents"are trademarks of The American Institute of Architects.This document was produced at 15:29:16 4 CST on 01/20/2025 under Subscription No.20240040942 which expires on 07/05/2025,is not for resale,is licensed for one-time use only,and may only be used in accordance with the AIA Contract Documents®Terms of Service.To report copyright violations,e-mail docinfo@aiacontracts.com. User Notes: (673cb30257573cc341 eac23f) SpawGIass Providing the Absolute Best Construction Experience 1 TABLE OF CONTENTS TAB 1 TAB 6 BUDGET ESTIMATE OVERVIEW BUDGET PROPOSAL COST BREAKDOWN TAB 2 TAB 1 EXECUTIVE PROJECT SUMMARY MASTER PROJECT SCHEDULE TAB 3 TAB 8 PROJECT TEAM BID/PROPOSAL PACKAGE STRATEGY TAB 4 TAB 9 LIST OF DOCUMENTS TAB 5 ASSUMPTIONS & CLARIFICATIONS TAB1 BUDGET ESTIMATE OVERVIEW Tow, W' , I ow 1 . Providing the Absolute Best Construction Experience I, Project Cost Summary FLI 60% DD GMP OVERVIEW SpawGlass Contractors, Inc. hereby submits to the City of Round Rock for the use and benefit of the new Old Settler's Park Buildout - Package 3C Rec Center - EARTHWORK, based on the 60% DD Drawings, as follows: 1. The proposed amount for the Direct Cost of the Work: $ 4,464,511 2. General Conditions (see ARCH budget): $ 0 3. Builder's Risk Insurance: $ 6,873 4. General Liability Insurance: $ 39,865 5. Payment & Performance Bonds: $ 52,215 6. Subcontractor Default Insurance (1.25%): $ 55,806 7. Warranty: $ 13,218 8. Construction Manager's Contingency (3.00/o): $ 158,614 9. Design Progression Contingency (60/6): $ 317,227 10. Construction Phase Fee (3.500/o): $ 178,792 11. Price Forecasting: $ 0 12.TOTAL: LINE ITEMS 1 THROUGH 11: $ 5,287,121 Lem- W e*%,zel. Tyler Wenzel, Project Executive AB 2 EXECUTIVE PROJECT SUMMARY F r r SpawGlass Executive Summary City of Round Rock - Old Settler's Park Build Out Package 3C -Rec Center - EARTHWORK 60% DD Drawings 3300 E Palm Valley Blvd Round Rock, TX 75665 Scope of Work Package 3C - Rec Center - EARTHWORK includes the earthwork and site wet utilities construction of the Rec Center and Admin site. This includes mass grading of the site, clear and grubbing, demo, asphalt paving, all weather access road for AHJ, SWPPP, building pads, site wet utilities, and allowances for: 1. Connections to Drinking Fountains 2. Reclaimed Water Connections 3. Storm Drain Piping to Building Roof Drains Overview The new Rec Center and Admin building is now being tracked in 3 GMP packages. This is: 1. Rec Center - EARTHWORK 2. Rec Center - SITE IMPROVEMENTS 3. Rec Center - BUILDINGS The Rec Center - EARTHWORK package was broken out separately for shared efficiencies in performing the earthwork for Rock 'N River at the same time as the Rec Center. Depending on the timing of the rest of the Rec Center drawings, it may be an option to now combine the Rec Center BUILDING with the Rec Center SITE IMPROVEMENTS, and make this one GMP. AB 3 PROJECT TEAM ••Ry1!l TA II low j — - �PP, /AI ► � r i '� �•.► '��- pS awGlass '®►, ORGANIZATION CHART1 LEGEND Management Support Team Lead/Single Point-of-Contact On-site Team Safety CITY OF ROUND ROCK Preconstruction/Estimating Support '~ DAVID PADEN TOM MCCLANAHAN DIVISION PRESIDENT SENIOR ESTIMATOR JOEY GEORGE ADAM WARDEN OPERATIONS MANAGER ESTIMATOR JUAN MARQUEZ BRIAN CLAXTON SAFETY COORDINATOR BIMNDC COORDINATOR TYLER WENZEL PROJECT EXECUTIVE/ PRECONSTRUCTION SERVICES MANAGER PARKER BLASCHKE HARRISON HOLLEY SENIOR PROJECT MANAGER SENIOR SUPERINTENDENT f CHRIS SOTO © ASSISTANT SUPERINTENDENTS ASSISTANT PROJECT MANAGER FASSISTANT PROJECT MANAGER DAYLON DYESS QUALITY CONTROL COORDINATOR TAB LIST OF DOCUMENTS gamin 1s V d Providing the Absolute Best Construction Experience List of Documents City of Round Rock-Old Settler's Park Build Out Package 3C-Rec Center-EARTHWORK-60%Drawings 3300 E Palm Valley Blvd Round Rock,TX 78665 PAGE# SHEET DESCRIPTION REVISION DATE Page 1 L-0.0 COVER SHEET AUGUST 2024 Page 2 L-0.1 KEY SHEET AUGUST 2024 Page 3 L-1.0 GENERAL NOTES AUGUST 2024 Page 4 L-2.0 EXISTING CONDITIONS AUGUST 2024 Page 5 L-3.0 DEMOLITION PLAN AUGUST 2024 Page 6 L-3.1 DEMOLITION PLAN AUGUST 2024 Page 7 L-3.2 DEMOLITION PLAN AUGUST 2024 Page 8 L-3.3 DEMOLITION PLAN AUGUST 2024 Page 9 L-3.4 DEMOLITION PLAN AUGUST 2024 Page 10 L-4.0 SITE PLAN AUGUST 2024 Page 11 L-5.0 JOINTING PLAN&DETAIL KEY AUGUST 2024 Page 12 L-6.0 SITE DETAILS AUGUST 2024 Page 13 L-7.0 LANDSCAPE PLAN AUGUST 2024 Page 14 L-7.1 LANDSCAPE PLAN AUGUST 2024 Page 15 L-7.2 LANDSCAPE PLAN AUGUST 2024 Page 16 L-7.3 LANDSCAPE PLAN AUGUST 2024 Page 17 L-7.4 LANDSCAPE PLAN AUGUST 2024 Page 18 L-7.5 LANDSCAPE PLAN AUGUST 2024 Page 19 L-7.6 PLANT SCHEDULE AUGUST 2024 Page 20 L-8.0 LANDSCAPE DETAILS AUGUST 2024 Page 21 L-9.0 IRRIGATION PLAN AUGUST 2024 Page 22 L-9.1 IRRIGATION PLAN AUGUST 2024 Page 23 L-9.2 IRRIGATION PLAN AUGUST 2024 Page 24 L-9.3 IRRIGATION PLAN AUGUST 2024 Page 25 L-9.4 IRRIGATION PLAN AUGUST 2024 Page 26 L-9.5 IRRIGATION PLAN AUGUST 2024 Page 27 L-10.0 IRRIGATION DETAILS AUGUST 2024 Page 28 L-10.1 IRRIGATION SPECIFICATIONS AUGUST 2024 Page 29 PF-1.0 PLAYING FIELD AUGUST 2024 Page 30 PF-1.1 PLAYING FIELD AUGUST 2024 Page 31 PF-1.2 PLAYING FIELD AUGUST 2024 Page 32 PF-1.3 PLAYING FIELD AUGUST 2024 Page 33 PF-2.0 PLAYING FIELD DETAILS AUGUST 2024 Page 34 PF-2.1 PLAYING FIELD DETAILS AUGUST 2024 Page 35 PF-2.2 PLAYING FIELD DETAILS AUGUST 2024 Page 36 PF-2.3 PLAYING FIELD DETAILS AUGUST 2024 Page 37 PF-2.4 PLAYING FIELD DETAILS AUGUST 2024 Page 38 PF-2.5 PLAYING FIELD DETAILS AUGUST 2024 Page 39 PF-2.6 PLAYING FIELD DETAILS AUGUST 2024 Page 40 PF-2.7 PLAYING FIELD DETAILS AUGUST 2024 Page 41 PF-2.8 PLAYING FIELD DETAILS AUGUST 2024 Page 42 PF-2.9 PLAYING FIELD DETAILS AUGUST 2024 Page 43 PF-2.10 PLAYING FIELD DETAILS AUGUST 2024 Page 44 PF-2.11 PLAYING FIELD DETAILS AUGUST 2024 Page 45 PF-3.0 PLAYING FIELD GRADING AUGUST 2024 Page 46 PF-3.1 PLAYING FIELD GRADING AUGUST 2024 Page 47 PF-3.2 PLAYING FIELD GRADING AUGUST 2024 Page 48 PF-3.3 PLAYING FIELD GRADING AUGUST 2024 Page 49 PF-4.0 PLAYING FIELD SUB-DRAINAGE AUGUST 2024 Page 50 PF-4.1 PLAYING FIELD SUB-DRAINAGE AUGUST 2024 Page 51 PF-4.2 PLAYING FIELD SUB-DRAINAGE AUGUST2024 Page 52 PF-4.3 PLAYING FIELD SUB-DRAINAGE AUGUST 2024 Page 53 PF-5.0 PLAYING FIELD SUB-DRAINAGE DETAILS AUGUST 2024 Page 54 PF-5.1 PLAYING FIELD SUB-DRAINAGE DETAILS AUGUST 2024 Page 55 C-1.0 EROSION CONTROL PLAN AUGUST 2024 Page 56 C-1.1 EROSION CONTROL PLAN AUGUST 2024 Page 57 C-1.2 EROSION CONTROL PLAN AUGUST 2024 Page 58 C-1.3 EROSION CONTROL PLAN AUGUST 2024 Page 59 C-2.0 GRADING PLAN AUGUST 2024 Page 60 C-2.1 GRADING PLAN AUGUST 2024 Page 61 C-3.0 PAVING PLAN AUGUST 2024 Page 62 C-3.1 PAVING PLAN AUGUST 2024 Page 63 C-4.0 STORM PLAN AUGUST 2024 Page 64 C-4.1 STORM PLAN AUGUST 2024 Page 65 C-5.0 UTILITY PLAN AUGUST 2024 Page 66 C-5.1 UTILITY PLAN AUGUST 2024 Page 67 C-6.0 CONSTRUCTION DETAILS AUGUST 2024 Page 68 C-6.1 CONSTRUCTION DETAILS AUGUST 2024 Page 69 A.101-RECREATION CENTER COMPLEX RESTROOM FLOOR PLAN AUGUST 2024 Page 70 A.102-RECREATION CENTER COMPLEX RESTROOM REFLECTED PLAN AUGUST 2024 Page 71 A.103-RECREATION CENTER COMPLEX RESTROOM ROOF PLAN AUGUST 2024 Page 72 A.201-RECREATION CENTER COMPLEX RESTROOM EXTERIOR ELEVATIONS AUGUST 2024 Page 73 A.301-RECREATION CENTER COMPLEX RESTROOM BUILDING CROSS SECTIONS AUGUST 2024 Page 74 A.401-RECREATION CENTER COMPLEX RESTROOM INTERIOR ELEVATIONS AUGUST 2024 Page 75 5A.501-RECREATION CENTER COMPLEX RESTROOM WALL SECTIONS AUGUST 2024 Page 76 A.502-ROCKIN'RIVER PUMP FILTRATION/RESTROOM BUILDING DOOR DETAILS AUGUST 2024 Page 77 A.601-ROCKIN'RIVER PUMP FILTRATION/RESTROOM BUILDING SCHEDULES AUGUST 2024 Page 78 5A.701-ROCKIN'RIVER PUMP FILTRATION/RESTROOM BUILDING SCHEDULES AUGUST 2024 Page 79 AS-1 -RECREATION CENTER COMPLEX RESTROOM GENERAL NOTES AUGUST 2024 Page 80 AS-2 -RECREATION CENTER COMPLEX RESTROOM FOUNDATION PLAN AUGUST 2024 Page 81 AS-3 -RECREATION CENTER COMPLEX RESTROOM ROOF FRAMING PLAN AUGUST 2024 Page 82 AS-4 -RECREATION CENTER COMPLEX RESTROOM FOUNDATION DETAILS AUGUST 2024 Page 83 AS-5 -RECREATION CENTER COMPLEX RESTROOM ROOF FRAMING DETAILS AUGUST 2024 Page 84 M-1-RECREATION CENTER COMPLEX RESTROOM-HVAC AUGUST 2024 Page 85 M-2-DETAILS-HVAC AUGUST 2024 Page 86 P-1-FILTRATION& RESTROOM BUILDING-PLUMBING AUGUST 2024 Page 87 P-2-NOTES&DETAILS- PLUMBING AUGUST 2024 Page 88 E-0-ELECTRICAL SYMBOL LEGEND AUGUST 2024 Page 89 E-1-OVERALL SITE PLAN-ELECTRICAL AUGUST 2024 Page 90 E-2-TRACK&FIELD COMPLEX PLAN-ELECTRICAL AUGUST 2024 Page 91 E-3-NORTH SOCCER FIELDS PLAN-ELECTRICAL AUGUST 2024 Page 92 E-4-PARKING LOT PLAN-ELECTRICAL AUGUST 2024 Page 93 E-5-RESTROOM BUILDING PLANS-ELECTRICAL AUGUST 2024 Page 94 E-6-ELECTRICAL RISER DIAGRAM AUGUST 2024 Page 95 E-7-ELECTRICAL DETAILS AUGUST 2024 TAB ASSUMPTIONS CLARIFICATIONS w 1 V`� 5 i1 * Y �•� rte.. /'• �'�. �� Providing the Absolute Best Construction Experience Assumptions and Clarifications City of Round Rock - Old Settler's Park Build Out Package 3C - Rec Center EARTHWORK 60% DD Drawings 3300 E Palm Valley Blvd Round Rock, TX 78665 GENERAL QUALIFICATIONS 1. Kimley Horn and Associates, Inc. is the civil engineer/prime consultant of record. 2. Based on an anticipated NTP of February 2025. 3. No specifications provided. Structural and MEP narratives provided. 4. The baseline schedule is based on a 5-day work week. 5. Normal working hours have been included from 7:00 AM to 5:30 PM unless otherwise noted, with exception to early concrete operations as deemed necessary. It is also assumed that work can occur on a 7 day a week schedule if required. 6. In order to subcontract scopes of work in a timely manner to meet the construction schedule it is assumed that buyout packages will be reviewed within 5 business days of their submission. 7. LEED Certifications or Green Building Programs are not incorporated into the project. 8. Builders Risk Insurance is provided by SpawGlass. Builder's Risk deductible to be paid from construction contingency. 9. Performance & Payment Bonds are provided by SpawGlass. 10. General Liability is provided by SpawGlass. 11. Proposal assumes that the specified material and equipment are available as required to meet the schedule. If they are not available as required, we assume the Owner/Architect will authorize alternate material or equipment selections. 12. Owner must accept GMP within 30 calendar days, at which time pricing may expire. 13. General conditions were included in Rec Center - SITE IMPROVEMENTS package. Any general conditions savings or losses from that package are to be rolled into the other GMP packages. SPECIFIC QUALIFICATIONS Division 01 - General Requirements and General Conditions 1. SpawGlass general requirements assume a 16 month project construction schedule. 2. Construction photos will be taken on a regular basis by SpawGlass. Digital files will be turned in monthly. 3. As-Built drawings, record drawings and record submittals will be kept in electronic format. These files will be accessible to all on the jobsite. 4. Reasonable repairs or damage caused by contractor(s) will be funded from the CM Contingency if funds remain and approved by CoRR. 5. Dimensional Control for the Project is included. 6. Individual non-photographic hard hat stickers for workers will be utilized. 1 . Assumptions and Clarifications 7. Temporary barriers and enclosures are included to delineate construction zone from the public. 8. No sound/vibration monitoring included. 9. Balance of General Requirements to be included in Rec Center - SITE IMPROVEMENTS package. Division 02 - Existing Conditions 1. Site demolition and clearing is included. Division 03 - Concrete 1. NA Division 04 - Masonry 1. NA Division 05 - Metals 1. NA Division 06 - Wood, Plastics, and Composites 1. NA Division 07 - Thermal and Moisture Protection 1. NA Division 08 - Openings 1. NA Division 09 - Finishes 1. NA Division 10 - Specialties 1. NA Division 11 - Equipment 1. NA Division 12 - Furnishings 1. NA Division 13 - Special Construction 1. NA Division 14 - Conveying Equipment Assumptions and Clarifications 1. NA Division 21 - Fire Suppression 1. NA Division 22 - Plumbing 1. NA Division 23 - HVAC and Controls 1. NA Division 26 - Electrical 1. NA Division 27 - Communications 1. NA Division 28 - Electronic Safety &Security 1. NA Division 31 - Earthwork 1. Includes all clear and grub and earthwork. 2. SWPPP setup included. 3. SpawGlass assumes that all water can be taken from existing City of Round Rock water utilities on-site, and no water will need to be trucked in from other cities due to water restrictions. 4. Includes 1.5" - 2" PVR at playing fields, as outlined in draft Playing Fields Geotech Report. 5. Includes removal of fat clays and minimum 12"of select fill at building pads for 3/a" PVR. 6. Includes a 3/4" PVR at track. Includes leaving subgrade at middle of track down 2'for infill by others in future GMP. 7. Includes stockpiling of existing onsite material for respread later at planters. 8. Includes asphalt paving. 9. Includes temp road for AH]. 10. Potential $263,000 credit can be provided to CoRR if onsite material can be mined at Rock'N River detention pond and used at Rec Center. Division 32 - Exterior Improvements 1. NA Division 33 - Utilities Assumptions and Clarifications 1. Site utilities are included. 2. $225,000 allowance for storm drain piping for roof drains and landscape drains. 3. $24,000 allowance for reclaimed water extension to irrigation meter. 4. $55,000 allowance for drinking fountains and hose bibs throughout site. EXCLUSIONS 1. All building work. This estimate only includes site work. 2. Permits, by Owner. 3. LEED documentation and Submittals. 4. We have not included the following items as we assume, they will be provided in a timely manner by the Owner at no cost to SpawGlass: a. Materials Testing Services b. Excludes all local electrical utility fees for permanent power 5. Preconstruction costs for the Project are not included in this budget. 6. Contaminated soils - hauling or disposal �,�� BUDGET PROPOSAL COST '�� BREAKDOWN � f ■ 00or SpawGlass Construction Experience Il;l® Summary Report Recreation Center Earthwork and Site Wet Utilities 60% Earthwork and Site Utilities GMP Rev 01 Estimate Date: 01/15/2025 Documents Date: 08/23/2024 Project Size (SF): 1,621,737 Project #: 3023121.03C Project Location: Round Rock Lead Estimator: Tom McClanahan ITEM COST COST I SF % OF TOTAL General Requirements (1,621,737 SF) 59,043 0.04 1.12 Site - Earthwork, Utilities, Parking, and Site 2,974,194 1.83 56.25 Building Pads - Administration, Recreation, and 855,700 9.51 16.18 % Track and Field (239,842 SF) 155,575 1 0.65 2.94 % Practice Field (204,105 SF) 85,800 1 0.42 1.62 % Four Pack - Soccer Artificial Turf Fields (656,094 315,000 0.48 5.96 % Restroom Building (1,680 SF) 19,200 11.43 0.36 Indirect Costs 822,610 ! 0.51 15.56 % Total Cost $ 5,287,121 $ 3.26 100.00 % Recreation Center Earthwork and Site Wet Utilities 60% Estimate Date: 01/15/2025 Earthwork and Site Utilities GMP Rev 01 Page 1 of 1 Documents Date: 08/23/2024 Recap Report Recreation Center Earthwork and Site Wet Utilities 60% Earthwork and Site Utilities GMP Rev 01 Estimate Date: 01/15/2025 Documents Date: 08/23/2024 Project Size (SF): 1,621,737 Project #: 3023121.03C Project Location: Round Rock Lead Estimator: Tom McClanahan ITEM COST COST I SF % OF TOTAL General Requirements (1,621,737 SF) 59,043 0.04 1.12 % Div. 01 - General Requirements 59,043 0.04 100.00 % Site - Earthwork, Utilities, Parking, and Site 2,974,194 1.83 56.25 % Improvements (1,621,737 SF) Div. 02 - Existing Conditions 81,306 0.05 2.73 % Div. 31 - Earthwork 1,510,808 0.93 50.80 % Div. 33 - Utilities 1,382,080 0.85 46.47 % Building Pads -Administration, Recreation, 855,700 9.51 16.18 % and Airnasium (90,000 SF) Div. 31 - Earthwork 855,700 9.51 100.00 % Track and Field (239,842 SF) 155,575 0.65 2.94 % Div. 31 - Earthwork 132,500 0.55 85.17 % Div. 33 - Utilities 23,075 0.10 14.83 % Practice Field (204,105 SF) 85,800 0.42 1.6201b Div. 31 - Earthwork 85,800 0.42 100.00 % Four Pack - Soccer Artificial Turf Fields 315,000 0.48 5.96 (656,094 SF) Div. 31 - Earthwork 315,000 0.48 100.00 Restroom Building (1,680 SF) 19,200 11.43 0.36 % Div. 31 - Earthwork 19,200 11.43 100.00 Recreation Center Earthwork and Site Wet Utilities 60% Estimate Date: 0111512025 Earthwork and Site Utilities GMP Rev 01 Page 1 of 2 Documents Date:0812312024 ITEC-. COST COST I SF % OF TOTAL Indirect • 822,610 I Builder's Risk Insurance 6,873 0.00 0.13 % General Liability Insurance 39,865 0.02 0.75 % Payment and Performance Bonds 52,215 I 0.03 0.99 % Subcontractor Default Insurance (SDI): 55,806 0.03 j 1.06 y Warranty 13,218 0.01 i 0.25 % Contractor's Contingency 158,614 0.10 1 3.00 % Owner's Design Progression Contingency 317,227 0.20 6.00 % Overhead and Profit 178,792 0.11 3.38 Total Cost $ 5,287,121 $ 3.26 100.000/0 Recreation Center Earthwork and Site Wet Utilities 60% Estimate Date: 01/15/2025 Earthwork and Site Utilities GMP Rev 01 Page 2 of 2 Documents Date: 0812312024 Detail Report (Direct Costs Only) Recreation Center Earthwork and Site Wet Utilities 60% Earthwork and Site Utilities GMP Rev 01 Estimate Date: 01/15/2025 Documents Date: 08/23/2024 Project Size (SF): 1,621,737 Project #: 3023121.03C Project Location: Round Rock Lead Estimator: Tom McClanahan ITEM QUANTITY I UM UNIT COST TOTAL COST General Requirements 59,043 Div. -- General Requirements 59,043 Temp. Fencing - Rental (6' h Chain Link Fence w/ 5,218.2 LF 10.16 53,043 Driven Posts) Licensed Professional Certified Survey (Intial 1.0 LS 3,000.00 3,000 Control Points) T Licensed Professional Certified Survey (Final) 1.0 Each 3,000.00 3,000 Site - Earthwork, Utilities, Parking, and Site Improvements 2,974,194 iConditions0. Demolition 81,306 Remove Rock Road 362,090.0 SF 0.05 18,104 Remove T-Post and Rope Fencing 35,922.0 LF 0.50 17,961 to Signs Remove 64.0 Each 10.00 g — � 640 Trees to Remove 446.0 Each 100.00 44,600 Div. 0 :0: Earthwork 1,486,948 Clear and Grub Site, Grading, Subgrade 1.0 LS 1,248,000.00 1,248,000 Preparation, and Asphalt Paving —_i Finish Grading / Spreading Stock Piled Top Soil - General Site Area - Buildings, Airnasium, Parking, 1.0 LS 13,500.00 13,500 and Plaza Areas Grading For Site Improvements Between the —t — Building Foundations 1.0 LS 31,000.00 31,000 Temporary All Weather Road For Fire and EMS Around the Buildings 52,036.3 SF 3.55 184,729 Clay Cap Around Perimeter of Buildings Without 694.3 CY 14.00 9,720 Abutting Paved Surface Erosion Control 23,860 SWPPP Narrative 1.0 Each 1,300.00 1,300 Recreation Center Earthwork and Site Wet Utilities 60% Estimate Date:01115/2025 Earthwork and Site Utilities GMP Rev 01 Page 1 of 3 Documents Date:08123/2024 ITEM QUANTITY I UM UNIT COST TOTAL COST SWPPP Inspections 18.0 Mos i 425.00 7,650 ---------------- - SWPPP Signage 1.0 Each 175.00 175 Stabilized Construction Entrance 1.0 Each 3,000.00 3,000 Silt Fencing 2,033.1 LF 3.85 7,827 OSHA Safety Caps on T Posts - Silt Fencing 339.0 Each 2.60 881 Mulch Sock 274.9 LF 3.85 1,058 Tree Protection - Allowance 268.5 LF 5.00 1,343 Inlet Protection 5.0 Each 125.00 625 Div. 33 - Utilities • : • Site Utilities 1,382,080 Sanitary Sewer Scope of Work- Per Drawings 1.0 LS 219,570.00 219,570 Storm Sewer Scope of Work - Per Drawings 1.0 LS 444,410.00 444,410 Water Service Scope of Work - Per Drawings 1.0 Each 389,500.00 389,500 Fire Risers 5' Out to 12" AFF Flange 3.0 Each 6,500.00 19,500 Connect Sanitary Sewer and Water Service Lines 6.0 Each 850.00 5,100 to Buildings Drinking Fountains and Hose Connections - Piping, 1.0 Allow. 55,000.00 55,000 Fountains, and Dry Wells Reclaimed Water Service Line - Extension, 1.0 Allow. 24,000.00 24,000 Connections, BFP, & Metering Storm Drain System For Landscaping and Buildings - Piping, Inlets, and Roof Drain & Downspout 1.0 Allow. 225,000.00 225,000 Connections Building Pads - Administration, Recreation, and Airnasium 855,700 DEarthwork - I • Earthwork 855,700 Admin - Building Pad - Excavate, Subgrade Prep, 1.0 LS 215,300.00 215,300 Select Fill and Haul Off Expansive Clay Airnasium -Building Pad - Excavate, Subgrade 1.0 LS 337,400.00 337,400 Prep, Select Fill and Haul Off Expansive Clay Recreation Center-Building Pad - Excavate, Subgrade Prep, Select Fill and Haul Off Expansive 1.0 LS 303,000.00 303,000 Clay Track and Field 155,575 Div. 31 - Earthwork 132,500 Earthwork 132,500 Grade and Backfill With Low PI On-Site Material for 1 1/2" to Z" PVR 1.0 LS 122,000.00 122,000 Finish Grading / Respreading Stock Piled Top Soil - 1.0 LS 10,500.00 10,500 Track and Seating Area Recreation Center Earthwork and Site Wet Utilities 60% Estimate Date: 0111512025 Earthwork and Site Utilities GMP Rev 01 Page 2 of 3 Documents Date: 0812312024 ITEM QUANTITY I UM UNIT COST TOTAL COST Div. 23,075 Site Utilities 23,075 18" HDPE Storm Drain Piping From Track & Field to 192.3 LF 120.00 23,075 Storm System Practice Field 85,800 r Earthwork 85,800 Excavate Fat Clay Soils, Backfill With Low PI Soils 1.0 LS 76,000.00 76,000 For 1 1/2" to 2 RVR Finish Grading / Respreading Stock Piled Top Soil - 1.0 LS 9,800.00 9,800 Practice Field Area Four Pack-Soccer Artificial Turf Fields 315,000 Div. iii Earthwork 315,000 Excavate Fat Clay Soils and Grade to Subgrade With On-Site Select Fill - 4 Pack Soccer Fields - 1.0 LS 303,000.00 303,000 PVR 1 1/2" to 2" Finish Grading/ Respreading Stock Piled Top Soil - 1.0 LS 12,000.00 12,000 4 Pack Soccer Fields Restroom Building 19,200 Div. 0i Earthwork 19,200 Restroom - Building Pad - Excavate, Subgrade 1.0 LS 19,200.00 19,200 Prep, Site Select Fill and Haul Off Expansive Clay Total - Direct Costs $ 4,464,511 Recreation Center Earthwork and Site Wet Utilities 60010 Estimate Date: 0111512025 Earthwork and Site Utilities GMP Rev 01 Page 3 of 3 Documents Date: 0812312024 �'} MASTER PROJECT SCHEDULE _t iF ►jam SpawGlass Construction Activity ID Activity Name Ong Rem Stan Finish Late Finish Total Float e CoRR• r c Milestones 800 590 23fab-24A- 2SAW-27 29-Apr-27 3 MSTONE-10 -NTP for Proconstruction Activities 0 0 23-Feb-24 A ;4;,"NTP 1W Pjeogns(rucjio Acjviljas MSTONE-10 GMP Approval_2-Lakeview 0 0 08-Aug-24A 01-Nov-24 GMP A pprbveil_12-�alpvi¢w MSTONE-10 GMP Approval_3A.1-Harrell Pkwy,Lakeview Panting 8 Apex Fields Relocation 0 0 09-Aug-24A 05-Nov-24 A 0M PAppilovil_3A11-HaheltPklv,yLeWsvlswpalldn$SAp9x Fieks Reldcelort; MSTONE-10 Construction Start 2-Lakeview 0 0 14-Oct-24 ..:..:..:..:..:..:......�..;._.__:__:_.. ---------------;._:._ _ _ __ ___ ____ __ __ __ _ ;♦Cohstfucdon,Stert ,2 a Lalcedewf ; ; MSTONE-10 Construction Start 3A.1-Harrell Pkwy,Lakeview Parking 8 Apex Fields Relomtion 0 0 21,0d-24A CpnsjruQiorj Start�3A1;-hlarr011 P,kw7,LpkeveW Piddng�.Apel FitIIdK R9bc�tlgt MSTONE-10 GMP Approval_3B-Tennis/Pictdeball 0 0 24-Oct-24A 11 Deo24 QAP:Approyal 3�-�errjrN P'ryddgbe� MSTONE-10 GMP Approval_3A.2-Harrel Pkwy 0 0 30-Deo24 04-Feb-25 25 ; ♦GMP AdprdveG_3A2-Haril l Pkwy MSTONE-11 GMPApproval_3C-RockNRNer 0 0 14-Jan-25 17-Jan-25 3 :♦;GNPAppha813C-RodfN Rhbr: r-r--. MSTONE-10 Construction Start_38-Tennis I Pidcleball 0 0 16-Jan-25 1 ;♦;CansWation;StM i 3 - ngis PiQc a MSTONE-11 Construction Start_3A2-Harrel Pkwy 0 0 05-Feb-25 25 00sb c*$til_;3A;2-}lajrel Pbpy, MSTONE-11 Construction Start_3C-RocKN River 0 0 19-Feb-25 3 :4j C}nehudlori Sort:3C-%2ooe4 Rhee MSTONE-11 GMP Approval_3A.3-Harrel Pkwy(Bridge) 0 0 25-Feb-25 19-Sep-25 145 ; r�ylRApprdvel; 3YL3-Herr61 P7av(Blid�e); MSTONE-10 GMP Approval_3B-MaintenanceArea 0 0 27-Feb-25 16-May-25 56 OMP.AppNval;_38-Meirtenartoe Arm : ; ; ; ; : : ; ♦�voratrUctton 3terj_8B'Meinlrinapce yup MSTONE-10 Construction Start_3&MaintenanceArea 0 0 014-Apr-25 56 a MSTONE-11 GMP Approval_3C-Roc Center Complex 0 0 18-Ap,25 21-Ap,25 1 j♦:GRIP l4pprotlal!30-Req Center Comple* MSTONE-11 Construction Start-3C-Rec Center Complex 0 0 27-May-25 76 f Conrltiuoiojl Start:_�C:Roc Cen>jer Cyortipltxx MSTONE-11 GMPApproval_3D-Multi-Purpose Center Expansion 0 0 07-Jul-25 05-Dec,25 106 It GM p Apprbvdl_3D:Mu6,Pulpo"Cerger Exflardtl MSTONE-11 Construction Start_3A.3-Harrel Pkwy(Bridge) 0 0 22-Sep-25 25 M COnsiruall Sill 3'4.3;-Harr•I Pkwy(Budge) MSTONE-12 Substantial Completion 2-Lakeview 0 .............................T-_;..;_.,_.,___ }. io-.;2 tLal._;..,._;........:.....:..:..: p _ 0 26Sep-25• 29-Sep-25 1 ; ♦Syb>ftar. . In t. 2 i L�tebeW MSTONE-12 Substantial Completion_3B-Tennis/Rcideball 0 0 17-Nov-25 22-Apr-26 107 j«Sybstpntjel torpplgtbp_QB�TRrnjs/�1tlAebplj MSTONE-12 Substantial Completion_3B-Maintenance Area 0 0 06-Jan-26 25-Mar-26 56 r>putietgntyl Cgmpbtton 78-Mai(rtejlance" MSTONE-11 Substantial Completion_3A.1-Harrell Pkwy Lakeview Parking 8 Apex Fields Rebc 0 0 09-Jan-26• 14-Jan-26 3 1�Su•suinbilt Corrfplationl 3A1-Ijlanell Pkwy,4all MSTONE-11 Construction Start_3D-MuttFPurpose Center Expansion 0 0 12-Jan-26 3n Sf9R 313 tldW ter F1e ; p -AP 1 ; ; I ; 1 ; ; : : : ; ; %-j -- - SYb%arRiampbtg nN;RNar��34t-1 odc' MSTONE-12 Substantial Completion_3C-RocKN River 0 0 27l.4ar-26• 01 r-26 1po 3 % MSTONE-12 Substantial Completion_3A.2-Hartel Pkwy 0 0 29Jun-26' 24Aug-26 40 Subrjlegtlal:Ccjnpjti 13,.2%Hj MSTONE-12 Substantial Completion 3A.3-Hanel Pkwy(Bridge) 0 0 27-Jul-26' 31 Aug-26 25 1 Subgtenbal:Coinplstibn:3A,3. MSTONE-12 Substantial Completion_3C-Rec Center Complex 0 0 30-Oct-26' 02-Nov-26 1 It,5ubltaritiaj Com MSTONE-12 Substantial Completion_3D-MulbPurpose Center Expansion 0 0 26-Ap,27 29-Apr-27 3 • ------------------------- Early Procurement 290 35 23-Feb-24A 20-Deo-24 29,4pr-27 598 1111111:Eft YrttLrbnNrtt: Adam tiui A5200 SG compile and tum in early package for long lead tiems 15 0 23-Feb-24A 28Jun•24A 12-Mar-27 8G corrq)k and tum In etarty package for bn�legd Canis A5210 CoRR review package and release SG to proceed with long lead dams 15 0 28-Jun-24 A 12Jul-24A 12-Mar-27 1e >,oRR; ,page a rind me ase 3G io piuo d WItl 16ng jeap iemi ------------------ ;A5250 0 3A1 Harrell Pkwy Contech Pedestrian Underpass Submittal 40 0 W-Jun-24A 31Jul-24A 12-MW-27 � 3KI- arrp1Qk,yCpntpdPgde�tridnQndprppss,-u m ital0 3A1-Harrell Pkwy Pedestrian Bridge Detailing and SubmittalApproval 40 0 03,1un-24 A 17JuF24A 12-Mar-27 br j 3/x.1=H hell Pkwy?eilesbiah Badge de*lin;acid SubinRLalAppiovil 0 3A1-Harrell Pkwy Con[ech Pedestrian Underpass Prowrement 160 35 17Ju1-24A 20-0eo-24 29-Apr-27 598 3A1:HOrrall Pkw)1 CdntdchPede"A UAdeYpe§a ProlurrmMt 3A1-Merrell Pkwy Pedestrian Bridge Procurement 1B0 35 31 Ju1-20 A ZO-0eo-24 29-Apr-27 598 :3,111.1 F H•rrell Pkwyl PAdsprirti"0""t• • •.•..._ 2 Lakeview 498 230 26JilA 26-Sep-25 29-Sep-25 1 L•Iceeiel• .'---r- .- r d LKVW-100 SG Receipt of Lakeview 80%Drawigs 1 0 26Jan-24A 26Jan-24A 01-Nov-24 j SG Recelptot�alpNOw BO Dlawjngtj Start Date: 15-Jan-24 — Actual Work ♦ ♦Milestone r_ Actual Level of Effort CoRR OSP-Preconstruction Schedule Finish Date: 26-Apr-27 — Remaining Work �Summary Data Date: 31-Oct-24 w Critical Remaining Work Level of Effort .WBS Layout H1o 15Activities r Run Date: 31-Oct-24 ---,I D Act"i Name Ong Rem Start Fk4ah Lds Fvfmh Total Ploat Q Q a Q Q a Q Q Q a a Q Q Q Our Our . N 0 J F M A M J J A S 0 N JIUMM^ M J J A S 0 N . LKVW-104 Development of Lakeview 90%Drawings 60 0 08-Feb-24A O6Jun-24A 01-Nov-24 mof Lakpvisw DmwTgs LKVW-109 SG Receiptof Lakevierw90%Drawings(Target Date 05.24.24) 1 0 06Jun-24A 06Jun-24A 01-Nov-24 ;n $G{iepeigt oL.r;)aeajiewj 91 Qralerips Oarpet pa(e 0.*.*); LKVW-111 Development of Lakeview 100%Drawings 30 0 07Jun-24A 10-Sep-24A 01-Nov-24 :0is Peloprrien1 of Lalievfew MOQ%QraMng: LKVW-116 "SG receipt of Lakeview 100%Drawings(Target Dale xx.xx.xx) 1 O 1t^^0Sep-2��4A 10-Sep-24A 01-Nov-24 :r r8cept Of L.ko'vie' 1DO%D}axingp(14rgbt Day nLaSoc); BWgii ing 60%Lakeview Drawings 31 0 29Jan-24A 11-Apr-24A 01-Nov-24 LalkaN"06m ingS' ----------- -- -- -- - - - LKVW-101 SG provide ounstrudability review comments on 60%Lakeview drugs 5 0 29Jan-24A 02-Feb-24A 01-Nov-24 LKVW-102 Conduct page flip meeting reviewing 60%Lakeview dnwgs 5 0 05-Feb-24 A 05-Feb-24 A 01 Nov-24 i �orici pp90 flip maetOn vipwljrg 6Ot Lekey' diwgy LKVW-103 SG solicit Lakeview 60%drawings for budgeting 15 0 07Feb-24A 23-Feb-24A 01-Nov-24 :r•;So splO1-4keriew 61%trapings fpr budgebpg, LKVW-105 SG compile pricing for Lakeview 60%drawings 4 0 23Feb24A 04-Mar-24A 01-Nov-24 • SG iompiii long for L*keyiew60%drapings LKVW-106 SG submit budgetary pricing for Lakeview 60%drawings 1 0 05-Mar-24 A 05-Mar-24A 01-Nov-24 + 4G¢utimit:buogefar*prion;for LAkeiriew 60%bm** LKVW-107 Owner provide comments on 60%Lakeview drwg budgetary numbers 5 0 06-Mar-24A 03-Apr-24 A 01 Nov-24 60%:LaOeview)drvlg tilt tary 91urobers LKVW-108 SG revise Lakeview pricing according to owner comments 5 0 04Apr-24A 11-Apr-24A 01Nov-24 !• SGjreVae;Lateviaw g;actor4,ing top4erjo6mOntO VENE"GMP LKVW-110 SG provide construdability review comments on 90%Lakeview drugs 5 0 07Jun-24A 13Jun-24A 01-Nov-24 :e : S( prgvide cPns�n,pabilily.49%w coin6anp op 9p%ueljewpw dn�s: LKVW-113 SG solicit Lakeview 90%drawings for GMP 15 0 12Jun-24A 09Jul-24A 01-Nov-24 .i IGIsoNdt akiaY QO%drpwijrgefoi GfjlP: '-'--'-----1----,�SG corn GMBfok LAkeA"PA froln 90%drAwtl 9: -- -- -- -- LKVW-114 SG compile GMP for Lakeview Package from 90%drawings 4 0 09Ju1-24A 12Ju1-24A 01-Nov-24 d*el g LKVW-115 SG submit GMP for Lakeview Package 1 0 12Juk24A 12-Jul-24A 01-Nov-24 Ir SGsubm'G)!PYorLateviawPadk"e: LKVW-117 Owner/Design Team reviewGMPfor Lakeview Package and provide comments 3 0 12Jul-24A 17Jul-24A 01 Nov-24 Iel04ner/I esbnYeamjevipwGMPf6,Lpksvi Ppcl�agearid provjdeicorjlmpnto LKVW-122 CoRR City Council approval process for Lakeview GMP(07.22-EF 08.08)[LF 08.05a 9 0 24-Jul-24A 08-Aug-24A 01 Nov-24 sl Ooh R itj Cpurjdl gppfovpl pjocaaw:forUa evipw6MP(67.04F 06.66)LF 06.".$2): 1-KVW-124 CoRR provide approval for recommended subcontractors 5 0 02-Sep-24 A 05-Sep-24A 01-Nov-24 LOF R proyido a0.proval:f0riecpmjneirded ejrboontjacjore Bury-Out and ContractAdmn'stration 42 0 29,1ul-24A 11-Od-24A 01-Nov-24 Eluy-(U aha CohirAd AdrAm•ba6orti I LKVW-121 SG conduct buyout meetings for priority scopes of work for Lakeview Package 20 0 29-Jul-24A 23-Aug-24A 01 Nov-24r:SG cbndud:buyout Meetings far pllorily sboesa bf ibrK M6 LalreJew!Palrldpe; LKVW-125 SG administer contracts to subcontractors for Lakeview Package 10 0 10Sep-24 A 24-Sep-24 A 01-Nov-24 W SG administer Contracts to sobdtntfacC.D s'for:LalteviawPatikage LKVW-126 Subcontractors review SG subcontract for Lakeview Package 5 0 24Sep-24 A 01.Oct-24 A 01 Nov-24 i 9ub6oiractori rage SG suboontiaci foc Lakeww.Pati LKVW-127 SG finalize and execute subcontracts for Lakeview Package 5 0 01-0d-24A 08-Od-24A 01-Nov-24 LKVW-128 Mobilization of preliminary suWnntredors for Lakeview Package 5 0 08dcl-24A 11-0ct-24 A 01-Nov-24 Mobigatidn Af pieliriiin}ry suacorjtreEtors for L}keyiew P}kitbge r ,. r r •. I : : ConOtruGioh LKVW-129 Construction(See Lakeview Construction Schedule) 250 230 14-W-24A 26-Sap-25 29-Sep-25 1 Conatnrttioh(See:Lekevbw'Cohstriictlon'SdhedLle) 3A.1-Hanel Pkwy,Lakeview Parking&Apex Fields RebMtlDn 496 300 15-Jan-24A O%Jan-26 14Jan-26 3 9A9-7ielrelrPkWy,Lakeview Pa ldnq a?1p4t I'Idds -•--•--•--•--•--•--•---•--•-- -- --- ------------------ - Issues&Constraints Design �n 3A.1-100 "SG receipt of Package 3A.1 30%Drawings 5 0 15-Jan-24 A 15-Jan-24 A 05-Nov-24 ;--SG radipt pf Rackaga 314.1 30%Dra*ng3 3A.1-104 Development of Package 3A.1 60%Drawings 60 0 15Feb-24A /2-Apr-24A 05-Nov-24 ;mss* pejelppnjent of�p_,.Laje$A166%brawirps; 3AA-109 SG Receipt of Package 3A.1 60%Drawings(Target Date 04.09.24) 1 0 12Apn-24 A 12Apr-24 A 05-Nov-24 :r GRgoeipt k$Ppi:*0 Al 00%Djawjngj(YPrg01 bat 0t0j2� 3A.1-111 City review of Package 3A.160%Drawings 10 0 12Apf-24A 01-May-24A 05-Nov-24 Cltyieviewbf Pa**3ikl;6D'%C)mwinbs 3A.1-114 Development of Package 3A.1 100%Drawings 23 0 15Apr-24 A 28-May-24 A 05Nov-24 :ski Development¢f Pad mgA*1.100%DrdninOs 3A.1-118 SG receipt of Package 3A 1 100%Drawings(Target Date 05.28 24) 1 0 29-May-24 A 29-May-24 A 05-Nov-24 r; SG receipt bf drag0 300:100%Drawings Qa".D•te 05.26.24)t 30.1-120 City review of Package 3A.1100%Drawings 10 0 29-May-24A 14-Jun-24A 05-Nov-24 *;Cityrgviejvo Pnkkage:3Aj1100 �ratjiLps 30.1-123 Fnal plan revisions for Package 3A.1 10 0 17-Jun-24 A 31 JuF24A D5-Nov-24 r_ Fined p n r9v4lonF fqr Ppd♦pq 31,1 Package3A.130%Drawings 85 0 15-Jae-24A 22-Mar-2aA 05-Nov-24 PAckage3A130%1Drawinga 3AA-101 SG previde constructabilhy reviewcomments on 30%Package 3A.1 dnwgs 5 0 15-Jan-24A 17Jan-24A 05-Nov-24 r;SCT pry'viae oon}tru#a¢iIq o6rnrrienls qn 31,0%;P*kiiipe 30.;1 d}Ngs Start Date: 15-Jan-24 » Actual Work ♦ ♦Milestone Actual Level of Effort CoRR OSP-Preconstruction Schedule Finish Date: 26-Apr-27 Remenng Work V..—V Summary .WBS Layout-HH of All Activities Data Date: 31-Oct-24 » Critical Remaining Work ® Level of Effort Pape 2 Of 15 Run Date: 31-Oct-24 Ac&*10 Actk*Nam Ong Rem Start Firdliff Late Finish Total Fkfj�:0 Q Q Q 0 a a a Q a Q 0 mm Our Dur 3A.1-102 Conduit page flip meeting reviewing 30%Package 3A.1 drugs 5 0 17-Jan-24A 17-Jan-24 A 05Nov-24 .COMpd page fl'p meeting mOeving 30%package 3A.1 dryqiK 3A.1-103 SG solicit 30%Package 3A.1 drawings for budgeting 15 0 22Jen24A 19-Feb-24 A 05Nov-24 SG eplirii 30,%Package 3J l::dr4:-dgs Jor budge6nQ ........__y_ _.............._.__._.._.__ . .__.__. 3A.1-105 SG compile pricing for 30%Package 3A.1 drawings 4 0 19-Feb-24A 27-Feb-24 A 05-Nov-24 rr SG compile pddn2 for 3q°6,Package*,l;di*%*N gs; 3A.1-106 SG submit budgetary prying for 30%Package 3A.1 drawings 1 0 28-Feb-24A 28-Feb-24 A 05-Nov-24 L SG 9ubfeit budgefary.p4ng foe 30%package 3A 1:driWrlga 3AA-107 Owner provide comments on 30%Package 3A.1 drwg budgetary numbers 5 0 29-Feb-24A 15-Mar-24 A 05-Nov-24 i- ;OWneL provide comfne�rts On 90%Padtlge 3A.1 tlrwp bodgetely hurAleb 3A.1-108 SG revise Package 3A.1 pricing according to owner comments 5 0 15-Mar-24 A22-Mar-24 A 06-Nov-24 -:S rr Package 1 pridpg acobrdng io gmvr oommaintsl Package 3A1 60%Drawngs48 0 18 Apr-24A 21-May-24A 05-Nov-24 �►P e 1 D 4dk49 ;3A ql rFwkr9q 3A.1-113 "SG solicit 60%Packs Package drawn sfor budgeting 18 r-24A 10- 24A 05-Nov-24 k' ----� �-:--------�--.._1._t..f__�--�--�•� �--1_.f--�- 9 9 9 9 15 0 -AP 0-May-24 So splicjt 60%Dailkajo$A.1 drpwiftjfor,bu0ggtln8 3AA-115 SGcompile pricing for60%Package 3A.1 drawings 4 0 13-May-24A 20-May-24A 05Nov-24 la Sfp como.ile Oric ng YorPO%"9+3A.1 Ara"q 3A.1-116 SG submit budgetary prong for 60%Package 3A.1 drawings 1 0 21-May-24A 21-May-24A 05-Nov-24 l r SIG sJbMil bkjdl story Pricing railti+a 1 3A.1-119 SG Drovitle consbuctabilily review comments on 100%Package 3A.1 tlrvgs 5 0 29av1ay-24A 07-Jun-24 A 05Nov-24 ee `-- --OD%Pddo :, : : . gepAil 15 0 10un-24A 08-Jul-24 05-Nov-24 , . . . ±3A.1-124 SGsolcit 100%package3A.l forGMP -4-4-4-4-4 . . i--'"-;-"'-- '. "" - --i••{-.�..; 3A.1-125 SG compile GMP for Package 3A.1 from 100%drawings 4 0 09Ju1-24A 09-Jul-24A 05-Nov-24 :r OG, 4MPfoi Padk40,3,411jon110014 d*virjga: 3A.1-126 SG submit GMP for Package 3A 1 1 0 104ul-24A 10Jul-24A 05-Nov-24 r IS3(3:,suoml GMP for Pa{kaje�A.1 3A.1-127 Owner)Design Team review G MP for Package 3A.1 and provide comments 5 0 11 Jul-24A 17-Jul-24A 06Now24 • 016neF/ "n Team bview GMPfor fascliag0*.I"provide dorrOrlehts: 3A.1-132 CoRR City Council approval process for Package 3A.1 GMP(07.22-08.08 EF)(LFOE 9 0 24-Jul-24A OB-Aug-24A 05Nov-24 t 1 1 I * CoRR i j CourOdl spptoval proclow:forPeCkaQe 9A7 GMP.(07.22-08.08 E� .0 22 3A.1-134 CoRR provide approval for recommended subcontractors 5 0 03Sep-24 A 111-Sep-24A 05-Nov-24 to �Co R;prgvidB aDPrOval dot raConlmelrldgd raubDontraL9oR Buy-Out and ContractAdministralion 47 0 02Sap•24A 114)c426A 05Nov,24 Buj-CydandCo6trgctAdrrjlnigbakon: 3A.1-131 SG conduct buyout meetings for preliminary scopes of wok for Package 3A.1 20 0 02-Sep-24 A 01 Sep-24A 05-Nov-24 �G rjdup bNyput jnesbnjgafor prekmljkary'arjopgs of wpk or pagrape�A.� 3A.1-135 SG administer contracts to subcontractors for Package 3A.1 10 0 09-Sep-24 A 24Sep,24A D5-Nov-24 No:S m atlminisler Onoa*to 4bdp l**rsYor:Parrlk*PAI --- --•--------•--------- ................ - - -- -- :. :..:_ 3A1-136 Subcontractors review SG subcontract for Package 3A 1 5 0 24-Sep-24A 01 Oct-24A D5-Nov-24 P $Ublo"gork rahedkSGsbbd,ont ddfor Pdddge3k1 : : : : ' ' ' 3A 1-137 SG finalize and execute subcontracts for Package 3A.1 5 0 01-Oct-24A 084)ct-24A 05Nov-24 a $G finaliz9 and dkecutel subc('tracts:for.Psldkege 9A.1 3A1-138 Mobilization of preliminary subcontractors for Package 3A.1 5 0 08Od-24 A 11430-24A 05-Nov-24 a b ifiabpn of pieliminary a 1bicti tractor?for Package 3A.1 .opataidbn 3A.1-140 Construction(See Harrell Parkway Construction Schedule) 310 300 21430-24 A 09,1an-28 14-Jan-26 3 Oopsyldlon ISge Harr011 Par*iej Cpnslrujho l Somi 3A2-Harrel Pkwy 808 420 15,lan-24 A 29,k#Q5 29-Apr-27 213 3p2:-Han*j Flkvrjr Issues&Constraints Design ��� r•.:., ip Al 700 "SG receipt of Package 3A.2 30%Drawings 5 0 15-Jan-24 A 15-Jan-24 A 09-Dec-24 "5G receipt of Package 3'1.2 3046 Drauiirt2a A1710 Devebpment of Package 3A.2 60%Drawings 48 0 15-Apr-24A 18-Jun-24 A 09-Dec-24 �r;DOvebprhe t of Prtdkdga,3K20 0%'Droviiih At 720 SG Receipt of Package 3A.2 60%Drawings(Target Date 06 18,24) 1 0 18-Jun-24 A 18-Jun-24 A 09-Dec-24 r So Racelpt ef Racitaga 3A2160%DraWnge(rargel Datb 06.18.24) Al 750 City review of Package 3A.260%Drawngs 10 0 18Jun-24A 25Jun-24A 09-Dec-24 ajCkyrjivlawfP,a ga3,A28076graviings A1730 Development of Package 3A.2 100%Drawings 22 0 19-Jun-24 A 16Sep-24A 09-0eo-24 : Gionoo-ii- Dc veIgprj ertlt o}Pgdk�ge;3A:2 100}'e grevjkr& Al 740 SG receipt of Package 3A.2 100%Drawings(Target Date 08.06.24) 1 0 16-Sep-24 A 16-Sep-24 A 09-0e-24 So r*01 of P4d*le;.*2 100%Qratl*(Target Qatp 0¢.0.24,)1 ®��� r•... Bddgeting Package 3A230%Drawings 90 0 15J -24A an22-Mar-24A 05-Nov-24 :Pkk* '3A:230%D*%ingd : : '-- A1800 SG provide constructability review comments on 30%Package 3A2 drugs 5 0 15-Jan-24 A 17Jan-24 A 05Nov-24 SG provide don9lrutta4ility rai odnrdents on 30%Pd.*aos 3AB d vo A1810 Conduct page flip meeting mviewing 30%Package 3A.2 drwgs 5 0 17-Jan-24 A 17-Jan-24 A 05-Nov-24 -0Conduct page flip meutin�re ng 3g%111. .e 3. .dMge A1820 "SG solicit 30%Package 3A.2 drawings for budgeting 15 0 22Jan-24 A 19-Feb-24 A 05Nov-24 I :"$G Wick 30%Package 3At2 oravlinga for bGdgatipg A1830 SG compile prong for 30%Package 3A.2 drawings 4 0 19-Feb-24 A 27-Feb-24 A 05-1 a, So gompile pnpng foj 30i'h Packaga 3t4.$drawrlgs: 9 9 � g rip ` Q.......-•--;-ge `--. . - -- A1840 SG submit budgetary prong for 30%Package 3A.2 drawings 1 0 28-Feb-24A 28-Feb-24 A 05-Nov-24 : f gG omit bud e(a pnain'for 30%Package 3I .dr�W:93: : : : j At 850 Omer provide comments on 30%Package 3A.2 drug budgetary numbers 5 0 29-F b-24A 15-Mar-24 A 05-Nov-24 r :Owned provide cbmmeii is on 30%Padk3gd 3X2 tlnvg birdgetaly dumberB Start Date: 15-Jan-24 Actual Work ♦ ♦Milestone Actual Level of Effort CoRR OSP-Preconstruction Schedule Finish Date:26-Apr-27 Remaining Work V00000rroW Summary .WBS Layout-HH All Activities Data Date: 31-Oct-24 r �� Cnlical Remaining Work Leval of Effort Page 3 of 15 Run Date: 31-Oct-24 Activity I D Act"Nam Ong Rem __-Start Finish :`-M*ft Finish Total Float Q a a a Q 0 a a Dur Dur . N D J F M A M J J A S . A1860 SG revise Package 3A2 pnong according to owner comments 5 0 15-Mar--24A 22Mar-24 A 05-Nov-24 a;SO ravise Package 2 ping according to 0wair cort meats: Package 3A260%Drawings 42 0 28Jun-24A 19-Aug-24A 09-0ec-24 P4dcige3Ai200%Drpwiirpq Al 960 —SG solid 60%Package 3A.2 drawings for budge" 15 0 28-Jun-24 A 16-Aug-24 A 09-0eo-24 �;'•$G>joligd fi0%Pgtlkajge 3A.2�ngp fq brjdgp8rtp A1970 SG compile priding for 60%Package 3A.2 drawings 2 0 12,011 A 16-Aug-24A 09-0eo•24 : j 1 a ISC}a mpile priding for 6%Package 3A.2 Arajvin+s A1980 SG submit budgetary pricing for 60%Package 3A.2 drawings 1 0 19,4ug-24 A 19-1wg-24 A 08-0eo-24 ; .;S6 s4 brdit bLdget9ry pricing for 6076 Pill If 3A.2 draJen�a �• ��� r a Timm-*MV(3Mp A2030 SG solicit 100%Package 3A.2 for GMP 15 0 19Sep-24A 10-0ct-24A 09-0eo-24 a* SG;sollci1100%Paa 3A2 foe OMP; A2040 SG compiler GMP for Package 3A.2 from 100%drawings 4 0 10Oct-24A 15-0d-24A 09-0eo-24 :6 Sd ocinpile tMP fpr P"ge A2 bora 1(1071 dr6vAnglt A2050 SG submit GMP for Package 3A.2 1 0 16-Oct-24A IS-W-24 A 09-0eo-24 ; r Stj submit Ob1P!fob P*kpge(,1A;2 , A2070 SG review comments for Package 3A.2 GMP and revise accordingly 4 4 31-W-24 05-Nov-24 12-0eo-24 25 ;G review:cornmenti for P}ckWa 31.2 ISP and isAts}ccprdigy A2080 SG resubmit Package 3A.2 GMP 1 1 06-Nov-24 ffi-N v-24 13-0eo-24 25 r SG}asLbrfid Package 3A.2"P: A2090 Owner forward Package 3A.2 GMP to Cl City Council 5 5 07-Nov-24 13-Nov-24 20-D o-24 25 0 ;p.pke�e foMeal P.adtage 3A210NP Ib CoRR Clly CounCl , A5310 Cl City Count approval process for Package 3A.2 30 30 14-Nov-24 30-0eo-24 04-Feb-25 25 dokR tity.Col n'abprpvalprpoeps for pacfwge 3A.2 .................... _ _ _ A5350 SG provide Cl list of recommended priority subcontractors for approval 1 1 16-0eo-24 16-0eo-24 28-Jan-25 29 ;.;SQ Winikie Oil Ist of rpcainnjendsd:pr"&#)*trpdpr s(or;p*vnl A5370 CoRR provide approval for recommended subcontractors 5 5 17-Deo-24 23-0eo-24 04-Feb-25 29 e.4RR piovfda 00rovp1 fpr nicomnienfled:sultadntrllil Pb-Con.ru:btioh Buy-0Utand CAntradAdrrlinistration 55 55 14-Nov-24 04-Feb-25 11atar25 25 TIlPul a4dCorlbalAdmhistratWn A2100 SG conduct buyout meetings for preliminary scopes of work for Package 3A.2 20 20 14-Nov-24 13-Dec-24 27-Jan-25 29 a=?3 ;SO eohddct buyAut mireting4 foe.prdlimnadlr sbopes bf vibdl folPabkape aAa ; A2110 SG administer contrails to subcontractors for Package 3A.2 10 10 31-Dec-24 14-Jan-25 18-Feb-25 25 93 ;SO adtnklistilr oontradt6 td submntractass fbr package 314.2: ; - - A2120 Subcontractors review SG subcontract for Package 3A.2 5 5 15-Jan-25 21 Jan-25 25-Feb-25 25 ;a;Subcontisctbrs:rsvlewS(3 subopntrjct for Package jA.� A2130 SG finalize and execute subcontracts for Package 3A.2 5 5 22-Jan-25 2BJan-25 04-Mar-25 25 o $G final=e enrjtria a pugcoritrej;ts for Package 3A.2 A2140 Mobilization of preliminary subcontractors for Package 3A.2 5 5 29-Jan-25 04-Feb-25 11 order-25 25 k Mogilizption of pr¢NrrlYiery**nfradorq foi Pild uige;3Aj2 Submittals 40 40 05feb 25 01-Apr-25 08-0eo-26 428 IFEF"Subtit"ls: A2150 "Submittals-Long lead materials for Package 3A2(Eac,etc) 40 40 05-Feb-25 01-Apr-25 08-0ec-26 428 '.'SkrlprNttals-Lorlp Wad m"Is For Aadkao Lk;(RIaej sl!) Procurament 100 100 02Apr-25 21-Aug-25 29-Apr-27 428 Wig;Ploalrertlent A2160 —Procurement-Long lead materials for Package 3A2(Eder,etc) 100 100 02- pr-25 21-Aug-25 29-Apr-27 428 ;^ProCurMMnt:Ld g"nlatAdall fW Pill""3k2 PW-I ®®®®® Qonatruution Northam Section 150 150 05-Feb-25 05Sep-25 10-Aug-26 235 *No them 9ectjon! . , , A5290 Demolition of existing site elements 20 20 05-Feb-25 04-Mar-25 08-Apr-25 25 ;4 enaYtlor.of axislinp ai0e etemerr06 ; A5300 Underground utilities 40 40 05-Feb-25 01-Apr-25 06-May-25 25 :o llndpgibund pliliyes: A5320 Construct roadway and sidewalks 70 70 12-Mar-25 18-Jun-25 22-May-26 235 r� Cgnslrud m¢dvpl tiilehallk} A5390 Install light poles 10 10 05Jun-25 18-Jun-25 10-Aug-26 290 ;o;In/tal:lgat pbIl A5340 ligation 30 30 19Jun-25 31 Jul-25 06-Jul-26 235 c;==l IOig" A5360 Landscaping 20 20 01-Aug25 28,4ug-25 03-Aug-26 235 P Landecepirp ; A5380 Install site furnishings I site signage 15 15 15-Aug-25 05-Sep-25 10-Aug-26 235 :cr (install Bite furti'shjga/yte agnagis Southern Section 190 190 02-Apr-25 02Jan26 29-Apr-27 338 $oulh*$fin; A6840 Demolition of existing site elements 20 20 02-Apr-25 29-Apr-25 04-Jun-25 25 t=i DerrloM(on bf existing sill."rits A6850 Underground utilities 40 40 02-Apr-25 28-May-25 02-Jul-25 25 UndOgrbudd dtilWas; .. .. .. .. ......�._�.Y__ _ .............. A6860 Constroil roadway and sidewalks 110 110 21 stay-25 24-W-25 02-0eo-25 25 Cbnetruct rdedaB%said sldelkaNb ; A6880 Irrigation 30 30 13-0ct-25 21-Nov-25 11-Mar-27 328 j Qj Irtipa(fon; A6870 Install light poles 10 10 10Jdov-25 21-Nov-25 29-Apr-27 363 01 Inoal talc pslps A6890 Landscaping 20 20 24-Nov-25 23-0ec-25 0&Apr-27 328 bI LpndpCepYk� A6900 Install site furnishings/site signage 15 15 10-0eo-25 02Jan-26 15,4pr-27 328 ;d IMAGI aloe Nedshhgd/alta Mgdage t�S�on 120 120 12-Jan-26 29-Jun-215 29-Apr-27 213 Y_ ___------------------------------ Nidi iilio Start Date: 15-Jan-24 Actual Work ♦ ♦Milestone Actual Level of Effort CoRR OSP-Preconstruction Schedule Finish Date:26-Apr-27 Remaining Work V..el Summary WBS Layout-HH All Activities Data Date: 31-Oct-24 Critical Remaining Work Level of Effort Page 4 of 15 1 , Run Date: 31-Oct-24 rN Actiliftyll) ActivitirNarria, -Cg Re" Still Finish Late Finish Total Float Q a a Q a Q a Q Q a Q Q a Q Dur J F M A M J J A S 0 IN D J F M A M J J A S 0 IN 0 J F M A M J J A S 0 IN D J F M A M A6910 Demolition of existing site elements zu zu 12-Jan-26 06-Feb-26 03,Vr-26 40 4r3siFollon of:e)*ing site ebrMMa A6920 underground utilities 40 40 12-Jan-26 06-Mar-26 014May-26 40 A6930 Construct roadway and sidewalks 70 70 16-Feb-26 22-May-26 20-Ju1-26 40 �:Conl ritial,rill s4krAm* A6950 Irrigation 30 30 20-Apr-26 01-Jun-26 27-jul-26 40 th"klit, .......---------------T-T-' .............r-7............................7--."- ---------------- A6940 Install light poles 10 10 11-May-26 22-May-26 29-Apr-27 238 . . . . . . . . . 0:Intstall light porlea A6960 Landscaping 20 20 02-Jun-26 29,1un-26 24-Aug-26 40 :F=�, .: Landscaping 10 10 16-Jun 26 29-Jun-26 24-Aug-26 40 16SWI 00 fyrnoil Oe slignog A6970 Install site furnishings i site signage Punchist/CiDseout 10 10 16-Jun-26 29-1ur-26 24-AW-26 40 :W Fliunoli4t/�IooscIjt A5400 Punchlist and Closeout 10 10 16-Jun-26 29,)un-26 24-Aug-26 40 sit PIunl aihcl CloOscrV:t - - ---- ------------------------------..................-------------------------------------- 3k3-Flarrel Pkwy(Bridge) 626 440 15-Jan-24A 27-jui-26 29,Apr-27 193 t!a"N (13.ridQe): Issues&Constraints Design A2180 -SG racept of Package 3A.3 30%Drawings 5 0 15-Jan-24 A 15-Jan-24A 29-May-25 r'i-so i6ow 6f liaciliegis 314 30%Drawings A2190 Development of Package 3A.3 60%Drawings 61 0 03-Jun-24 A 19-Aug-24A 29-May-25 issississ; r Davelo rie t oP&j : A6% ge33 Nei9 wln . .pfd r? . . . . . .0 . . .91 1-6f-il ---I- - -------- :6-�-6- eibai�-W+'i#j :": A2200 SG Receipt of Package 3A 3 60%Drawings(Target Date 09 17 24) 1 0 19-Aug-24 A 19-Aug-24 A 29-May-25 ,ii�. 6 ngs el poeopt is 3AY (Ye� A2220 Development of Package 3A,3 100%Drawings 24 8 14-W-24 A 11-Nov-24 09-Jun-25 145 OeNeklprjerrj of:Papkabe M.$100%D*+gj A2230 SG receipt of Package 3A.3 100%Drawings(Target Date 11,05.24) 1 1 12-Nov-24 12-Nov-24 10-Jun-25 145 $Sq r*ip.k of.Pa6. 'e 3A.0 100'.Mav#ngo(Illi Qat}11.0.24) A2240 City review of Package 3A.3 100%Drawings 10 10 13-Nov-24 26-Nov-24 1 O-Oct-25 221 Ckyview bfRactag�3A3:109%1)riWrI 5: A2250 Final plan revisions for Package 3A,3 10 10 27-Nov-24 12-De 24 24-W-25 221 43 Fill plan;rarimiclins for P cka e 3A.3 --------------- ....ii;d....... ................ cIp ng: Package 3A3 30%Drawings 90 0 15-Ari-24 A 22-Mer-24A 05-Nov-24 :Pjdajg�3A:3jO-ADr3wir'q%' . . . . . . . . . . . . . . . A1870 SIG provide construclability review comments on 30%Package 3A3 cirwgs 5 0 15-Jan-24A 17-Jan-24 A 05-Nov-24 .,li P'" . Tn!&UF"ility oc!nnijenis cin t Pe6aBs hill,B dj4 . . . . . . . 17- 24A 17-Jan 5 0 -24 A 05-Nov-24 j.Oind ns�lev'ind "g:e 3jk-j d4gP A1880 Conduct page flip meeting reviewing 30%Package 3A 3 drugs i Page aas:-4G sI.I I I . A1890 "SG solicit 30%Package 3A.3 drawings for budgeting 15 0 22-Jan-24A 19-Feb-24 A 05-Nov-24 0 10%Paickilige'3Aj3 dravit gs for lbj dgatrri g A1900 SG compile pricing for 30%Package 3A.3 drawings 4 0 19-Feb-24A 27-Feb-24 A 05-Nov-24 S--!3--C:l miii�- i- -C-C�ao-i�. -idr-d-Ywri----------------------------- -------- ........................... gs: A1910 SG submit budgetary pricing for 30%Package 3A 3 drawings 1 0 28-Feb-24A 28-Feb-24A 05-Nov-24 i SG!bulk for'.30%Package 3X3 draWr!gs: A1920 Owner provide comments on 30%Package 3A.3 ding budgetary numbers 5 0 29-Feb-24A 15-Mar-24 A 05-Nov-24 in OOW PprpviclIe opinine,its�n 1pjckjg�3A�3 lbOdg�tsiry dumb" . . . . . . . . . . . . . . A1930 SG revise Package 3A.3 pricing according to owner comments 5 0 15-Mar-24 A 22-Mar-24 A 05-Nov-24 Sill relvaiiii OcI 3A.3 inalng ls:;cpnclrg to cpArri Coir*nantil: Package 3A3 60%Drawings 38 0 26-Aug-24 A 04-Od-24A 11-Ju1,25 TIT aotago 3A. BON Prairinjs A2260 SG provide constructability review comments on 60%Package 3A.3 drwgs 6 0 26-Aug-24 A 05-Sep-24 A 11-Jul-25 ili PG .*4 cqnst1ru bility isviaw 1*Ito m#nt4or60I%Pa*q'e*.3 ; * d ® A2280 -SG spli&60%Package 3A.3 drawings for budgeting 15 0 12-Sep-24A 30-Sep-24A 11-Jul-25 ad SG sollicil Pac"*34rawinos for budgeting; A2290 SG compile pricing for 60%Package 3A.3 drawings 4 0 30-Sep-24A 030ct-24 A 11-Ju425 P IG wropila pdcinp or aw a swn . I I I . f60%:Pd3A3 diia . . . 0 . .. . g. . . . . . . . A2300 SIG submit budgetary pricing for 60%Package 3A.3 drawings 1 0 04-Oct-24 A 04-Od-24A 11-Jull ':i i a julornft:buoqeiaj pricil for 60%P86raje*4 dr6v*gj . . . . . . . . . . . A2330 SIG provide oonstructability review comments on 100%Package 3A3 dugs 5 5 13-Nov-24 19-Nov-24 17-Jun-25 145 So pjpvipe ponorucltabikty,re'yarry o$m6sr4 in X0096 Pa*git*3,:dMs A2340 Conduct page flip meeting reviewing 100%Package 3A.3 cinrigs 1 1 20-!Nov-24 20-Nov24 18-Jun-25 145 r:C+ndPct:pajsjipre* in tinOnOv"nj1qO94P4ck#O,&�3ljrv4s A2350 SG solicit 100%Package 3A.3 for GMP 15 15 21-No,24 13-De0-24 1 OJul-25 145 c6 is6sto'cit:100%Pad * . .GMP; . . . . . . . . "ejA.3for A2360 SG compile GMP for Package 3A.3 from 1DO%drawings 4 4 16-Dec,24 19-080-24 16-Jul-25 145 :@:S6compile GMP fbrR'adtag63K3*oMlDO%dN" 1 1 20-Dec,24 20-Deo-24 17-Jul-25 145 :2:Sd;s�brrlftdMOfCjPjdcjga3Aj3: A2370 SG submit GMP for Package 3A,3 ... . . . . . . . ...... ...................- ...... A2380 Owner/Design Team reviewGMP for Package 3A.3 and provide comments 5 5 23-Dec-24 30-Deo-24 24,)ul-25 145 . . . . . . 0-jed.Dgsi T4njrejs%lIiG4F1.for)Paaial and pa**,corisin" A2390 SG review comments for Package 3A.3 GMP and revise accordingly 4 4 31-D.,24 06-Jan-25 30,)ul-25 145 b $G i9vbw:corllml fq Pil*3(pMp Od t-*liatolittl A2400 SG mwbmft Package 3A.3 GMP 1 1 07,J.n-25 07-Jan,25 31-Jul-25 145 ki:r9silubrinit Pa "Oe3AjGl1?P: A2410 Owner forward Package 3A.3 GMP to CoRR City Council 5 5 08-Jan-25 14-Jan-25 07-Aug-25 145 i0vineri.foi"Pladiagiit 3A.3 GUIP th CbRR City Cound A5430 CoRR City Council approval process for Package 3A.3 GMP 30 30 15-Jan-25 25-Feb-25 19-Sep-25 145 j Qj QoRR q"orill alpprovsl process for P,aclsagj*3.:GkiP Start Date: 15-Jan-24 - Actual Wori( Milestone Actual Level of Effort CoRR OSP-Preconstructlon Schedule Finish Date: 26-Apr-27 - Remainng Work VassassaW Summary WBS Layout-HH All Activities Data Date: 31-Oct-24 - Critical Remaining Work - Level of Effort Page 5 of 15 Run Date: 31-Oct-24 Activity ID Act"i Name Ong . . . Q . . a . . Q . Q . A5420 SG provide CoRR list of recommended priority subcontractors for approval 1 1 12-Feb-25 12-Feb-25 125ep-25 149 r ;SQ provide lint of mmmmenctlad priority,submntradors approval A5410 CoRR provide approval for recommended subcontractors 5 5 13-Feb-25 19-Feb-25 19-Sep-25 149 . CpRIk plpv a pp0ovpl fir rgminrr"ed:subwbtnic:t e Buy-Out and Contract Administration 55 55 15,1en-25 01-Apr-25 24-0d-25 145 Wliii- 79uy0u4 add l;ontrad Arministiatan A2420 SG conduct buyout meetings for preliminary scopes of work for Package 3A.3 20 20 15Jan-25 11-Feb-25 11-Sep-25 149 :b:SG eohdtictiiuy;ou)m}eting6 forpreliminary scopes pf vjork;foi;Pab"e j.ko ____________________:__ _ __ __ A2430 SG administer contracts to subcontractors for Package 3A.3 10 10 26-Feb-25 11-Mar-25 030d-25 145to;wdo"Mradols f6r PacNag#*3: A2440 Subcontractors review SG subcontract for Package 3A.3 5 5 12-Mar-25 18-Mar-25 10-0ct-25 145 :a;SUAcOnb. . Iavl. SG;submhirad for Wedkage 3143; A2450 SG finalize and execute subcontracts for Package 3A.3 5 5 19-Mer-25 25-Mar--25 17-W-25 145 0:SG fipallie ind:ex"iubGanjrsQs(pr Oad{agp*3; A2460 Mobilization of preliminary subcontractors for Package 3A.3 5 5 26-Mar-25 01-Apr-25 24-W-25 145 d 41ol lizitioq o�,prilimjnary spbcpntjac(ors,for:Pald®be BA o j Submdta s 40 40 02-Apr-25 28-May-25 08-0eo26 386 �7 Subm tt}Is A2470 —Submittals-Long lead materials for Package 3A.3(Flet,Bridge Elements) 40 40 02-Apr-25 28-May-25 08-0ec-26 388 4onb IBed Inelerlilib for Padrade 3j43(E K:B600.EI}m}ntil) Procurement 100 100 29-May-25 17-Oct-25 29-Apr-27 388 !7:Prbar}erdent A2480 "Procurement-Long lead materials for Package 3A.3(Elec,Bridge Elements) 100 100 29-May-25 17-W-25 29-Apr-27 388 l"WmCureirndlt:Laing bed m4telieNl tot PAdrAge 3A3 ®�_ �� fbntWdbh , A5480 Demolition of existing site elements 20 20 22Sep-25 17-0d-25 21 TJov-25 25 ; Cr DamdiODr d elbti..g NlelebineMe; A5490 Underground utilities 40 40 22—Sep-25 14-Nov-25 01-May-26 115 ; ; ; ; ; ; ; ; ; ; ; ; IUrldergmpn0 utlNieIs j A5560 Drill piers and construct footings for bridge structure 60 60 20-0d-25 16-Jan-26 20-Fab-26 25 0 D4I piers:ani cinsjrucl fopflnbs for¢ridge(rul;tuje A5570 Construct abutments columns and bents 50 50 17-0eo-25 27-Feb-26 03-Apr-26 25 Gonotrto dbufrneltts:coljrmos rind:be(tt: A5580 Erect precast girder beams and place bridge concrete 40 40 02-Mer-26 24-Apr-26 01-Jun-26 25 t==; Ned print glider boan)s and:plabe brill , A5500 Construct roadway and sidewalks 40 40 30-Mer-26 22-May-26 29-Jun-26 25 Cbnsdud rdad4ey entl sitleaelgl , A5510 Irrigation 20 20 26-May-26 22,1un-26 27Jul-26 25 ; - -- -- ---- - --- -- •Irr}patbn; Q; A5530 Install light poles 10 10 26-May-26 08-Jun-26 10-Aug-26 45 b Insall Ijghf po)ee; A5520 Landscaping 20 20 09-Jun-26 06Jul-26 10-Aug-26 25 4anps pijrg A5540 Install site fumishings/site signage 20 20 23-Jun-26 20-Jul-26 24-Aug-26 25e:Inttall sNo fkpnidhings 1 sito sign , , I A5550 Punchlist and Closeout 15 15 07-Jul-26 27-Jul-26 31-Aug-26 25 ;rq FLnChIiSt sari CkrSeoht 3B-Tennis/PUdeball9 Ap 452 266 31Jar,24A 17-Nov625 2 r27 367 ;31j- rn14,PgclebdC 'Delig A2500 "SG raceiptofPackage313-Tennis/Rcleball30%Drawings 5 0 31 Jan-24A 31 Jan-24A 01-Nov-24 j '&SQrsCaiofPgckige:3B-Tinn6 Plddegall00y6Diavlingo A4240 City review of Package 3B-Te ins/Pidd eball 309%Drawing s 10 0 01-Feb-24A 16-Feb-24A 01-Nov-24 !in;Clbrrivfe OPic4g03 -Tennis/:P*911gall:3016 grav�rgs --'--'__•__•__1__1._1__-`—`— . .............'-'-""--'—._....._..--'--- -- -- -- ----' ----' A2510 Development of Package 38-Tennis/Piddeba1160%Drawing s 34 0 16-Feb-24A 26Apr-24A 01-1Jov-24 Devebp*h.tofP ckOgd 38-Tennis f Pdlteball:60fo Drawings A2520 SG Receipt of Package 3B-Tennis/Picldebal 60%Drawings(Target Date 04 0424 1 0 01-May-24A 01-May-24A 01-Nov-24 : I SG Redsipt of Pa ge 3B:Tehnt/Pkitebbl 60%DreWN4(T2rge1 Dhte:04*424f 1 A2530 City review of Package 3B-Tens I Picideball 60%Drawings 10 0 01-May-24A 10-May-24A 01-Nov-24 % City review of Pa ckage 3B.Ternri9/"eba1160%Dra"s A2540 Development of Package 3B-Tennis/Picideball W1.Drawigs 34 0 12Jun-24A 25-Jul-24A 01-Nov-24 ;T; D9v8bp eptgf P9djg936-Tennis/,PiptebaII:90'bgraitrga; A2570 Development of Package 3B-Tennis/Pidteball 100%Dravhgs 23 0 25-Jul-24A 12-Aug-24A 17-Jan-25 ;Oeye prrjen(of ajinabe g8 f Te�rrig/f?id+ebpll f�>/s grrghps L Budgeting $ujlgeting Package 3B-Tens/Piddeba130%Drawings 100 0 31-Jan-24A 12n1 --24A - 01-Nov-24 r'„'W?Paomoe 3B-Tehnd/piddeb gill 30%Drawings A2610 SG provide constiuctability review comments on 30%Package 3B-Tennis I Pick late 5 0 31-Jan-24A 12-Feb-24 A 01-Nov-24 r:SG provide cbrisitruritatilitj review commenis 0 30%Paidkage 28 Unlg I Pkk1.9 ell dregs A2620 Conduct page flip meeting rsviewing 30%Package 3B-Tennis/Pckleball drwys 1 0 12-Feb-24A 12-Feb-24A 01-Nov-24 :r:Cohdild gaga flo Meeln ns"vW ng,30%Radkagb 3B-Terinis:/PEId6ball dring! A2630 "SG solicit 30%Package 3B-Tennis/Picideball drawingsfor budgeting 15 0 13-Feb24A 08-Mar-24A 01-Nov-24 ;arF "SG sblk330%Pe 3B.:Teri Fidlylb9N dtawingtbrbUdg6ting A2640 SG compile prieng for30%Package 313-Tennis/Rdkleba ltd®wogs 4 0 11-Mar-24A 15-Mer-24A 01-Nov-24 ;s ; mmple pricing for 0° Pedcega 38-19'l nie/;Flddebell;dmwiry8 A2650 SG submit budgetary pricing for 30%Package 3B-Tennis/Piciebal drawings 1 0 18-Mar-24A 18-Mar-24A 01-Nov-24 js/:Piclde4al Erajirgs: A2660 Owner provide comments on 30%Package 3B-Tends/Pidteball drwg budgetary r 5 0 18-Mar-24A 05Apr-24A 01-Nov-24i Qwnerprojridstom enlsdo3p*/;Pa.bkage3BLTsnri6/Pidiebelldrwybgd geta,ynumberjl A2670 SG revise 30%Package 3B-Tennis/Rcleball pricing according to ownercomment 5 0 08-Apr-24A 12-Apr-24A 01-Nov-24 :. SG.%iise;30YR g038-Tenhisl Pladdbal'primo afcotdng tdovnef mYnrtlents Start Date: 15-Jan-24 Actual Work ♦ ♦Milestone Actual Level of Effort CoRR OSP-Preconstruction Schedule Finish Date: 26-Apr-27 — Remaining Work V=�Summary .WBS Layout-HH All Activities Data Date: 31-Oct-24 w Critical Remaining Work — Level of Effort Page 6 of 15 Run Date: 31-Oct-24 start Finish Late Finish Total Float Q Q a Q a Q a 0 a a Q Q Q Q N Package 3B-Tennis/Pickleba160%Drawings 48 0 06-May-24A 11-Jen-24A 01-n/ov-24 Pilots e3J�go is/Piddebe1190%Dta.wng8 A2680 SG provide construdability,review comments on 60%Package 3B-Tennis/Pidclebe 5 0 08-May-24 A 15-May-24 A 01-Nov-24 . ;So ptovi mhilky,tavieW corments on 6Q9L;PaOnge iB}lib.; /L'id Ifl drvga; A2700 "SG solicit 60%Package 3B-Tennis/PirA eball drawings b r budgeting 15 0 13-May-24A 04-Jun-24A 01-Nov-24 � �� �•S�800clm&3)3-7e6rislodd"ldiav4ngifotbgdggbnb A2690 Conduit page flip meeting reviewing 60%Package 3B-Tennis/Pckleball drwgs 1 0 15-May-24 A 15-May-24 A 01-Nov-24 :n 1Cpndud 0agaeting re�iieWn4 60?A Paclot 6313-Tis nnis/Pel4ba)l diwgl A2710 SG compile pricing for 60%Package 3B-Ten ns/Rckleballclowngs 4 0 05-Jun-24A 11-Jun-24A 01-Nov-24 7s 5C'coMpiiie fbr 60%Pgckage13B:-Tin nis/Scideball del nosl A2720 SG submit budgetarypnong for 60%Package 3B-Tennis/Piddebal drawings 1 0 11-Jun-24A 11-Jul A 01-Nov-24 ;r SG submit ary ph rig for 60 h Package 38 r Tennis/Pidlebal drat<ings --- - -.,•- �-- � ; ; I GMP'--? I ?-> -: ;- -; �--� }-; }--% + -;--1,--i-'v- A2750 SG provide construdability review comments on 90%Padmge 3B-T9nns/Piduebe �5 �022J® 31 Jul-24 A 01-Nov-24 I iii 4G p s:cotnstrlkdpbil(ly n9vinlw ponjmeprts;on:gOt4 Pectase 3b- nlnis jn Pticlepal drp j A2760 Conduct page flip meeting reviewing 90%Package 3B-Tennis I Pckleball drags 1 0 31-Jul-24A 31Jul-24 A 01-Nov-24 ! 4orl pbgejflip:mgeting ievipwing$094 Pgdkr ge:3B:-Tgmps l�bldetjell dnl®s j A2770 SG solidi 90%Package 3B-Tennis/Pckleball for GMP 15 0 12-Aug-24 A 11Sep-24 A 01-Nov-24 OWN 5G soFdt 00%Pedage 3B-Tennis i,Pgkleball fon GMP I A2780 SG compile GMP for Package 3B-Tennis/Picideball from 90%drawings 4 0 11 Sep-24 A 12-Sep-24A 01-Nov-24 ;r I:SG col GMP for Pttdd3gd 38--4ndis I;Piddetlall frofil W dri irlgs A2790 SG submit GMP for Package 3B-Tennis/Piddeball 1 0 13Sep-24 A 13Sep-24A 01-Nov-24 ; ; ; ; :r sub GMRfbKPadmps 3B}Tehni!I FP bal ; A2800 Owner/Design Team mvimGMP for Package 3B-Tennis I Piddeball and provide c 5 0 16-Sap-24A 20-Sep-24A 01-Nov-24sj elr/be9gn'Teem fev{ew�MPIOr Padlag93b-teniae/P"bak aid pMo de'minrrl A2810 SG review comments for Package 3B-Tennis/Picdebal GMP and revise accordingl 4 0 23-Sep-24 A 27-Sep-24A 01-Nov-24 s ipvigw gonjmej ts:for•Paj;kege$B L Tgnrib/Qic4sl l 011AQ al ievge>lllaprdingly A2820 SG resubmit Package 3B-Tennis/Pkkleball GMP 1 0 27 Sep-24 A 30Sep-24A 01-Nov"24 it dG resubmit Waciog}3$-tenhis)PiQkleball GkdP 1 A2830 Owner forward Package 3B-Tenns/Pckleball GMP to CoRR City Council 5 0 30-Sep-24A 074)ct-24A 01-Nov-24 Merfonlsrd PA"ge3B-lbnds6PiiklebalCGMPtb CORR CilyCohncll __:__;__;__;__;__-__ A5330 CoRR City Council approval process for Package 3B-Tem s/Picke07-Oct-24d all 30 0 07-Oct-24 A 24-Oct-24A 11-Deo-24 :ss CORR CS y Cound aldprdvallpAOcess for Pad'taga 3111-Text is/PiddefoelI A2910 CoRR City Cound approval Process for Tennis/Pilball 13 0 07-Oct-24A 24-0d-24A 11-0eo-24 CpR� (fly Coindl approval:Prgoeis fOrl6nrjs/:Pkldeball: A5440 SG provide CoRR list of recommended priority subcontractors for approval 1 1 02-Deo-24 02-0eo-24 03-0eo-24 1 I $G ptoilds C4Rq list otitic hmine6d4d poo*yubbontri iJ for agptc I: A5450 CoRR provide approval for recommended subcontractors 5 5 03-0eo-24 09-0eo-24 10-0eo-24 1 Is CoRRlpr*Wo aop*-1 for!redorr(mend4d sub¢ontrador$ Buy-Out and ContradAdminstration • • . . . Bt/yCLI 51 51 31-0d-24 15 -25 16-Jon-25 1 Cnd;CdntridAdrhlnittrelbrl A2840 SG conduct buy-out meetings for preliminary scopes of work for Package 3B-Terme 20 20 31 Oct-24 27-Nov-24 02-Deo-24 1 SG dontlud bJyoltt A1eAtin$s fbr plreliMinhrysodpek oP.wolk tier C"Pa 3B-7snhis I Pkkl�el A2850 SG administer contracts to subcontractors for Package 3B-Tennis/Rddeball 10 10 1O-Deo-24 23-Deo-24 24-0eo-24 1 ;oj SG atlmtrtistsr toniracts t0 subconttadDrsYorPackage 3B:Teh nils/P.lddeb8111 A2860 Subcontractors review SG subcontract for Package 3B-Tennis/Piddeball 5 5 24-Deo-24 31-0eo-24 02-Jan-25 1 4 SubContraCtop myieW SG apbcLntiact for,Pt dkgge dB L Tinnls/I':ebpll A2870 SG finalize and execute subcontracts for Package 3B-Tennis/Piedebal 5 5 02-Jan-25 08Jarl 09Jan-25 1 e $G fniliz4 a6d rtxeiutg suit otnpct>for•P"ge,'38'-Tpnn ja/pboate l A2880 Mobhuition of preliminary subcontractors for Package 3B-Tennis/Pidilebal 5 5 09-Jan-25 15Jan-25 16-Jan-25 1 I I I I 7 I I I I I s IMdbili#atlon M prelihllrtPryleul)mhtradols fir pacl}ag}3Q-jen{ila I Plttlebel Submittals 40 40 16-Jan-25 12-Mar-25 08-0eo-26 442 M"ll"lg 5ubmittalt A2890 "Submittals-Long lead materials for Package 3B-Tenns/Pickleball(Bec,Canopi 40 40 16-Jan-25 12-Mar-25 08-0eo-26 442 :rte µSubrhittAls:Long 7eafl nlate4ie14fot P6dkigel36-Tlnris fPklksCellYBdc,CaAopbs,; Procurement 100 100 13-Mar-25 01,4ug-25 29-Apr-27 442 Orociurelnenl A2900 -Procurement-Long lead materials for Package 3B-Tennis/Pi klebal(Elec,Calc 100 100 13-Mar-25 01-Aug-25 29-Apr-27 442 38-TenlisV Pttilebal .. � ®®��� ' --�--•--•--•--•--+--�---r--r------ ---- ------ - -braes -- .........................- --..........iter A5590 Demolition of existing site elements 10 10 16Jer-25 29-Jan-25 30-Jan-25 1 ilill denjolglon pf etdeting site elements A5600 Earthwork/Pad Prep for Courts 45 45 30-Jan-25 02-Apr-25 03-Apr-25 1 02l. $artttw4rk�Pad Pnaq fot Cqurtti A5610 Underground Utilities/MEP Rough-In/Detention Pond 50 50 13-Mar-25 21-May-25 224)ct-25 107il UrhdejgrdunA Utilitles 6M$P Roygh;ln)l 04terjtbri P¢nd A5660 Stand Alone Parking Lot Construction 40 40 03-Apr-25 29aday-25' 30-May-25 1 k=-% Sterid Abn6 Pbddltg LoUCohatludbn: ----------- A5630 Court Construction 90 90 17,4pr-25 22-Aug-25 28-Jan-26 107 ; . . . . ;C. .Consbud'grt A5620 Adjacent Parking Lot Construction 50 50 06Jun-25 15-Aug-25 11-Feb-26 122 -' :Atfjeosnt Paidnp Lot donkruptoln A5640 Fencing Installation 40 40 28-Jul-25 22Sep-25 25-Feb-26 107 'L�I Fgncig)nslialletbn A5700 Installation of Misc.Metals and Site Furnishings 20 20 18-Aug-25 15Sep-25 08-Apr-26 142 b:Inetallo*of Misc.Vetale and She rur)tbf)Inlp A5670 Irrigation 20 20 18-Aug-25 15Sep-25 11-Mar-26 122 ;C+:lr i$albn . , , --•--•.....................,........... -- -- -- A5650 Light pole installation 40 40 25-Aug-25 20-0ct-25 25-Mar-26 107 : ; ; ; ; ; ; ; : : Li�ht polo h6alalgn r;� A6680 Landscaping 30 30 02-Sep-25 13-W-25 08-Apr-26 122 9=;2 ;Landscaping; A5690 Shade Structure Construction(By Others) 20 20 07-0d-25 03-Nov-25 OB-Apr-26 107 c=i yha{ie$tnjdy2 4�o4strWdign($y 0kjerat A5710 Punchlst and Closeout 10 10 04-Nov-25 17-Nov-25 22-Apr-26 107 ;w;Pyndilsttantl CGoepul Start Date: 15-Jan-24 Actual Work ♦ ♦Milestone sr_ Actual Level of Effort CORR OSP-Preconstruction Schedule Finish Date:26-Apr-27 Remaining Work �Summary .WBS Layout-HH of 15 Run Dale: 31-Oct-24 All Activities Data Data: 31-Oct-24 Critical Remaining Work Level of Effort Page 7 of g Actr4ity I D Activity Name Ong Rem Start Finish Late Finish Total Float Q Q a Q a a Q 0 Q a Q a 0 Q 3131-Maintenance Area 477 297 22,1an-24A 015-An-28 2g-Apr-27 336 &;Maintenaticalloe ; i Issues&Constraints Design A3030 Development of Package 3B-Maintenance Area 30%Drawings 25 0 22-Jan-24A 27-Feb-24 A 23-Jan-25 a^; Development of P6clteg4 36-MaiatenanCe Area 36%brawir@a A2920 SG receipt of Package 3B-MaintenanceArea 30%Drawings(Target Date 0226.24 1 0 27-Feb-24A 27-Feb-24 A 23-Jan-25 w Sb+cept cif padjagg 3 -Maihtepa6m�mp 3o%:DriWdgs(Taigei Date o2.g6.04); A4230 City mviewof Package 3B-Mahtenanci 30%Drawings 10 0 27-Feb-24A 11-Mar-24A 23-Jan-25 i Oily 4'"of Package B:Meinianince Aiea,a O4 Dravjngs A2930 Development of Package 3B-Maintenance Area 60%Drawings 35 0 28-Fab-24A 01-May-24A 23-Jan-25 66r D"IoOmAnt bf dtag9 3B•MaMrteharlce,Areb 80%;DrAwidgs: ' A2940 SG Receipt of Package 3B-MaintenanceArea 60%Drawings(Target Date 04.30 2r 1 0 01-May-24A 01-May-24A 23-Jan-25 j 9G Receipt of:Pa ge 3B:Maint6nanci"a 60%DYaWing6(INrg6t Date 04.30.24) A2950 City review of Package 3B-Mahtenance Area 60%Drawings 10 0 01-111 15-May-24A 23-Jan-25 r ICily remejv o{P drpge;3B Mainjengnda Ajeaj60+/o greWngs A2960 Development of Package 3B-Maintenance Area 90%Drawings 47 0 03-Jun-24 A 08-Aug-24A 23-Jan-25 pejel ontjof pagkage$B%Maintgnapcg lupe g0 Dgq A2970 Development of Package 3B-Maintenance Area 100%Drawings 20 10 21-Od-24 A 13-Nov-24 05-Feb-25 56 ID*Oprk ent of;Padkage 3B:Meinon¢nobAaea:10g%pre.W's't ----------------------- _ ------------- A2980 _____ _ A2980 SG Receipt of Package 38-MaintenanceArea 100%Drawings(Target Date 04.30.: 1 1 14-Nov24 14JJov24 06-Feb-25 56 ; ; t r:SG R6oet df Padtag0 3B-Maihleharice Are 100%Dlaw91g0(r6rgAt Datd OC.30:24) dgeLn Package 3B-Maintenance Area 30%Drawings 25 0 O6-Mar--24A 9,41*A A 10-1.I �"'�Pedre4e 3B;Man nehce Aria iO4i Dravkigi A3040 SG provide construdability review comments on 30%Package 3B-Maintenance An 5 0 08-Mar-24A 08-Mar-24 A 10-M-25 ;r SGproYida cdnstNcleb Ity levl"'T'manly ori 30%Package 3B MdntdnadcoArea drwgs A3060 SG solicit 30%Package 3B-Maintenance Area drawings for budgeting 15 0 08-Mar-24 A 29-Mar-24 A 10-Mar-25 Sr,dolkjt 3b%;Papm a$B}MeintBnance Area OratiAngs fpr budgeting A3050 Conduct page flip meeting reviewing 30%Package 3B-Maintenance Area drugs t 0 08-Mar-24A 08-Mar-24 A 10-Mar-254 Oorjduo page flip mpe ievim*g oO$Ppd(�gq 3$-Maiptepanps Ami dr vgp j A3070 SG compile pricing for 30%Package 3B-Maintenance Area drawings 4 0 09-Apr-24A 09-Apr-24A 10-Mar-25 :r SGicoirrpi{e*j gf rib%Pgc*epB:-Maintenencb Ajealdrpwingsi A3080 SG submit budgetary pricing for 30%Package 3B-Maintenance Area drawings 1 0 09-Apr-24A 09-Apr-24A 10-Mar-25 r BG;submd budgOar V pftrng for 30%;Pabkage 3B L Mbintenanch"a tlrahinDs f Package 3B-Maintenance Area 60%Drawings 48 0 08-May-24A 11-Jun-24A 10-Mar-25 i i r7Padkape3B Maintenance Area 60%DMv4nga A3110 SG provide construdability review comments on 60%Package 3B-Maintenance An 5 0 08-May-24 A 15-May-24A 10-Mar-25 :6 ;SG provide cont trudtatllidy reW"comments oh 60%;Pad98:Malnlenano6Aeia dn" .................................. A3130 SG solidi 60%Package 3B-Maintenance Area drawings for budgeting 15 0 13aday-24A 04-Jun-24 A 10-Mar-25 ;� G 8ollpt�0 Padrage;3B;•Iv�alryenen4e/yea;drBtMrlga lor�udgeGnS A3120 Conduct page flip meeting reviewing 60%Package 3B-Maintenance Area drwgs 5 0 15av1ay-24A 15-May-24A 10-Mar-25 %r 'Cojkdyd page fl 3 njeeting rayieujing 50k Pec(mg{3 30-rulajntgnarjrrej4iija dry P pricing 9 9 ...._._— 1 i SG'minpile @9 °A9 . . A3140 SG compile ndn for 60%Packs Package Area drawings 4 0 05-Jun-24 10-Jun-24A 10-Mar-25 for 60 Package 3B&-Manlenende Plea:drawirl A3150 SG submit budgetary pricing for 60%Package 3B-Maintenance Area drawings 1 0 11-Jun-24A 11-Jun-24A 10-Mar-25 ;1 SGsubmd b dg6tany pfldrig f6r Hl%Pdrkdpe 3B:M6intenancb Alea;draWnga Package 3B-Maintenance Area 90%Drawings 118 0 21,Au(}24A 11-Od-24A 23-Jan-25 iW �W a Woe7B:Mantbngnoili90%DaWngG _ -----------------___ A6240 Conduct age flipmeetingreviewing 90%Package 3B-Maintenance Area drugs 5 0 21-Aug-24A 21Ig-24A 234an-25 1::Cond ict Zia It meatinp rdvieMnp 90%Pelops 3B;MAintlnance Araa drwps A6220 SG provide construdabilily review comments on 90%Package 3B-Maintenance An 5 0 22,Aug-24A 23-Aug-24A 23Jan-25 r;sty p o4e Go4tnjdability rgvieM opmrjnents On 60-4 Package A-MairjterianCe lyes dMga A6230 SG solicit 90%Package 3B-Maintenance Area drawings for budgeting 15 0 23-Aug-24A 18Sep-24A 23-Jan-25 O;S sijlio 90k Package 30-Majn*apceArea k(rewingjr for bydgptirjg j A6250 SG compile pricing for 90%Package 3B-Maintenance Area drawings 4 0 09Sep-24A 18Sep-24A 23-Jen-25 ? ? 0 SG cdmpile pncing Tor 90%Piacliage 38-Maintenance Area dria hgs j j A6260 SG submit budgetary pricing for 90%Package 3B-MaintenanceArea drawings 1 0 18Sep-24A 18-Sep-24A 23-Jan-25 r;S sJbrrlil bOdgetdryPncing for 90%Pbdkbg9 38-MaidtedanCeArea drbwthgd - -- A6270 SG and CoRR to conduct Maintenance Area Budget Meeting to complete design 5 0 07-Od-24 A 11Od-24 A 23-Jan-25 ; ; :9 and doRRto conduct Malntetr ancegrda Budget Mebtidg to complete design GMP A3180 SG pmvkle constmctability raview comments on 100%Package 3B-Maintenance A 5 5 15-Nov-24 21-NOV-24 13-Feb-25 56 ■;Sb piovide Corp tnldarillty revise cdm{ne6te On 104%Pacllage 38-Majnte7kar ceAree drw A3190 Condud page flip meeting reviewing 100%Package 3B-Maintenance Area drwgs 1 1 22-Nov-24 22-Nov-24 14-Feb-25 56 r Conduct:papa pip jnepting rgviejainp 100%Ppckpgq 34.loakjte6anpe Areg driiii j j A3200 SG solicit 100%Package 38-Maintenance Area for GMP 15 15 25-Nov-24 17-Deo-24 07-Mar-25 56 b I Sq akilidt 100%Package j18:Meinfenanc}Ai6a'forGM? A3210 SG compile GMP fox Package 3B-Maintenance Area from 100%drawings 4 4 18-Dec-24 23-Dec-24 13-Mar-25 56 ; ; i i ; ;o:SG cbmpie;GMP for Pada4e 38-Maintehaace;Mda(cocci 100%;drdwirtgs; A3220 SG submit GMP for Package 3B-MaintenanceMea 1 1 24-Dec-24 24-De 24 14-Mar-25 56 r;sC slrbmit GMP idr PBkirgga 3B-MaiotenanCeArea A3230 Omer/Design Team review GMP for Package 3B-Maintenance Area and provide� 5 5 26-Dec-24 02-Jan-25 21-Mar-25 56 p 6vieri,Design TBarp review GMP,for,Papiege b8:Maintenance Ajea 8nd provide poajmejntaj A3240 SG review comments for Package 3B-Maintenance Area GMP and revise accordinc 4 4 03-Jan-25 08Jan-25 27-Mar-25 56 i $G;revj"coinrn9nto tdr Ppckogg 34-F�eirjterjano*rep G(AP j no rev*aj*Inply A3250 SG resubmit Package 38-Maintenance Area GMP 1 1 09Jan-25 09-Jan-25 28-Mar-25 56 :1 BGredubfnk Peom4e lB-Mdinl}naooe;"a GMP e;pk(net fohveld Radia 6 38-Mahtehadce Puab GMP to.CoRR.CKy Couadl; A3260 Owner forward Package 3B-MaintenanceMea GMP to CoRR City Council 5 5 10-Jan-25 16-Jan-25 04-Apr-25 56 g A5460 CoRR City Cound appmval process for Package 3B-Maintenance Area 30 30 17-Jan-25 27-Feb-25 16-May-25 56 CoRR Cily,CounkSl aQproval prOce6s Por Wadkaga 38-Mahtelarjcelire6 A5470 SG provide CoRR list of recommended priority subcontractors for approval 1 1 14-Feb-25 14-Feb-25 09-May-25 60 n;so prdvide bokR Ilst of remmmpnded;priprittt subckpitraddrs fpr approval Stan Date: 15-Jan-24 Actual Work ♦ ♦Milestone ««kokokokokr• Actual Level of Effort CoRR OSP-Preconstruction Schedule Finish Date: 26-Apr-27 Remaining Work Tommom®Summary Date Dote: 31-Ori-24 .WBS Layout- of 15 Run Data: 31-Oct-24 All Activities Remaining Work r_ Level of Effort Page 8 of g Activity I D Activity Name Ong Rem Start Finish Late Finish Total Float Q Q Q 0 0 a 0 a Q a Q Q Q A5720 CoRR provide approval for recommended subcontractors 5 5 17-Feb-25 21-Feb•25 16-May-25 60 ;.;Cop p(ovipe Appoov9l for remmmanded suboontr9ct4s; Pre-Construction . , , . . , , . , , Buy-Out and Contra tAdministration 55 55 17Jan-25 03-Apr-25 23-Jun-25 58 Vill$uyQ¢erW Gorjhagt Aj mi(ieltnr ipn A3270 SG conduct buyout meetings for preliminary scopes of Mork for Package 3B-Manti 20 20 17Jan-25 13-Feb-25 08-May-25 so b!Sid condyct yuy�out mjretingrj tor,prilinpnary sFopes pt vjorl(foi Paiclgge;313:Mainfer A3280 SG administer contracts to subcontractors for Package 3B-Maintenance Area 10 10 28-Feb-25 13-Mar-25 02-Jun-25 56 13 SG adlniHistlr cgntrect to:su0cohtral fpr package 3B-Maihteharice Area A3290 Subcontractors review SG subcontract for Package 3B-Maintenance Area 5 5 14-Mar-25 20-Mar-25 09-Jun-25 56 o:S"ntl IavlewSG suMphtriid for Package 3B-MaintAnahcsJuda A3300 SG finalize and execute subcontracts for Package 3B-Maintenance Area 5 5 21-Mar-25 27-Mar-25 16-Jun-25 56 i C SG flhale end a)"WbContrl for Wal' 36_MelntehaoeeAcea ; A3310 Mobilization of preliminary subcontractors for Package 3B-Maintenance Area 5 5 28-Mar-25 03-Apr-25 23-Jun-25 56 Mogilil-in 01!prolirrtnery epahlenence Area ; Submittals 40 40 04-Apr-25 30-May-25 08-0eo.26 386 �!��uDmhtpls; A3320 —Submittals-Long lead materials for Package 3B-Maintenance Area(Elec,Canop 40 40 04-Apr-25 30-May-25 08-Dec-26 386o NSubmkbalg-korlp k ad x*rlols for pagksge JB�Mgntpnahor;Arpa jDal Q Procurement 100 100 02-Jun-25 21-W-25 29-Apr-27 386 P#x jre*l A3330 "Procurement-Long lead materials for Package 3B-Maintenance Area(Elec,Can 100 100 02Jun-25 21-Oct-25 29-Ap,27 386 1:^Pmpnilmont-Long ieatl nfatedalo for P;Ii:114034-Kl[airiterl �. •r •r r . k: : ; ; ; I ; ; ;- - - --- -- --------------------------------- --- -- -- -- ----CodatrDctibn I I A6830 Earthwork/Building Pads 40 40 04-Apr-25 30-May-25 19-AW25 56 BartAvdrk GBulldldg Radio A5840 Underground Utilities/MEP Rough-In 80 80 02-May-25 25-Aug-25 12N0v-25 56 11nd9rgiburld Udlillea 9 MEP RougFl-In A5860 Concrete Foundations 40 40 16-May-25 14Jul-25 01-Oct-25 56 � ;Cojarete Fo ndptkhl A5870 Structural Steel 30 30 15,1ul-25 25-Aug-25 12-Nov-25 56 o Sf rugturpl Siell A5880 MEP Buildout 40 40 12-Aug-25 07-W-25 30-Deo-25 56 PEP guiklou4 A5920 Finishes 60 60 10Sep-25 04-Deo-25 25-Feb-26 56 ; Finilill A5900 litigation 20 20 08-Oct-25 04-Nov-25 28Jarl 56 hg lion A5930 Installatbn of Misc.Metals and Site Furnishings 20 20 05-Nov-25 04-0eo-25 25-Mar-26 76 IG Ipat011a1bR of Miel*el jinff S6 FYmi hill 04-Doo-25A5910 Landscaping 20 20 O5-Nov-2504-Doo-25 25-Feb-26 56 �+ I;anpec�pl�p A5940 Punchlist and Closeout 20 20 05-Deo25 06-Jan-26 25-Mar-26 56 j j ! . . . ; ; 1 :c=!' Puroo$nd Cloaeput 3C-Rock'N River 535 355 12-Feb-24A 27-Mar-26 29-Apr-27 278 3C-RobKN RiLaI Issues&Constraints : IlaulsBCdns6aldts A6070 Per CoRR-RocKN River needs to be complete by 04.01.2026 0 0 27avter-26• 01-Apr-26 3 Per CoRR:Rci t RiveF nled0 id bdcohtp A3350 Development of Package 3C-Rcl River 30%Dravings 25 0 12Fetr24 A 21-Mar-24A 05-Nov-24 :Davabpment of Pa C-ge;3Rodl'N Rivbr 30%Drawings A3360 SG receipt of Package 3C-Rodk'N River 30%Drawings(Target Date 03.15.24) 1 0 21-Ma,24 A 21-Mar-24A 05-Nov-24 r;S6 recalpt 4 Pill 30-doc:'N:River$091 Dravii(Target getq 03;15:24' A4220 City review of Package 3C-RockN River 30%Drawargs 10 0 21-Ma,24A 05,Apr-24A 05-Nov-24 % W.rayiev{of Pail a$C RgckN qk*3Q%pratwn' A3370 Development of Package 3C-RocKNRiver60%Dravnngs 27 0 08-Apr-24A 12-Jul-24A 05-Nov-24 : . . . eyelopirr am of Palla C:R}ckNRiver60%provinpe A3380 SG Receipt of Package 3C-Rock'N River 60%Drevnngs(Target Date 05 31,24) 1 0 12 Jul-24 A 12-Jul-24A 05Nov-24 SG Rlcei it of Pecll 3C-RockN;RNer 60%Dlaw{ng0(Tali l Dat!OS31:24) A3390 City reviewof Package 3C-RockN River60%Drawings 10 0 12-Jul-24A 17Jul-24A 05-Nov-24 le C r'6vls of Packaga3C-RocKN:Rhor60%Dorwelgs A3400 Development of Package 3C-Rocil River 90%Dmvdngs 35 0 01-Aug-24A 20-Sep-24 A 05-Nov-24 velopment of Package:30-RodrN Rlvar$099 Dr6w{ngs A3430 Development of Package 3C-Rock N River 100%Drawings 18 0 02Sep-24 A 01Od•24A 24-Feb-25 111114 ovgbpmgnl bf Nc(agg 3i�•}RooeN R(-e.100%Of4wi6gs: A3440 SG receipt of Package 3C-RocWN River 100%Drawings(Target Date 10.04.24) 1 0 01-Ocl 01Od-24A 24-Feb-25h G iec$Ipt of Package 3;C;R*WN"1gU%Dr}rM4ge;(ieryel Dpte;10.f14.124): VONO-000-04 Bud e4l; Package 3C-RoCKN River 30%Drawings 53 0 21-Mar-24A 03-May-24 A 05-Nov-24 A3470 SG provide constructability review comments on 30%Package 3C-Roclk'N River on 5 0 21-Mar-24 A 02-Ap,24 A 05-Nov-24 ; al SG""o mhstArct billy revi/w Orrlmintdon;30d.Recital 3C-Rol RM/dryl A3490 SG solicit 30%Package 3C-RodfN River drawings for budgeting 15 0 03-Apr-24 A 30-Apr-24 A 05-Nov-24 P" SSG solid{30%:Pe kal 3C:R"74 fRivlr citawin4 for bkOdgetn¢ A3480 Conduct page flip meeting reviewing 30%Package 3C-RocKN River drvgs 5 0 03-Apr-24 A 03-Apr-24 A 05-Nov-24 i 6orlduCt page flip mi etipg levi9wing J09A Ppcc8gel 3d-4ocKN:RNar 4nil A3500 SG compile pricing for 30%Package 3C-Roc k'N River drawings 4 0 30-Ap,24 A 03-May-24 A 05-Nov-24 } G ponipilq prjcn fdr3o%paykape$C,RpcieN piwq drpwingq A3510 SG submit budgetary pricing for 30%Package 3C-RodfN River drawings 1 0 03-May-24 A 03-May-24A 05Nov-24 % I 4 itubinl buQge ry;prigny foi 30%packs ge 3C jRddfN Five{drpwiiiga? Package 3C-RocWN River 60%Drawings 46 0 15-Jul-24A 30-Aug-24 A 05Nov-24 :VillliI R ge 3C-R."River"Oral Start Date: 15-Jan-24 fr• Actual Work ♦ ♦Milestone Actual Leel of effort CORR OSP-Preconstruction Schedule Finish Date: 26-Apr-27 Remaining Work Viiin6l""ill'Summary .WBS Layout-HH Al ActlNOes Data Date: 31-Oct-24 w Critical Remaining Work — Level of Effort Pee 9 of 15 Run Date: 31-Oct-24 9 Activity I D Activity Name Ong Rem Start Finish Late Finish Total Float Q Q a Q Q a a a Q Q a Q Q a Our Our J F M A M J J A S 0 IN 0 J F M A M J J A S 0 N D J F M A M J J A S 0 N D J F M A M A3040 SG provide oonstructability review comments on 60%Package 3C-RockIN River do 5 0 15-Jul-24A 22,Jul-24 A 05-Now24 —a is constructalbility review comments on 60 Pjl RocWN River clqs A3560 SG solicit 60%Package 3C-RockN River drawings for budgeting 15 0 23-Jul-24A 12-Aug-24A 054Jov-24 go flor pudj4g: a Sif,si brr�ft bud4etoryr pricing for Poill,"gd 3q-�o4*URI�er Onk*njs A3580 SG submit budgetary pricing for 60%Package 3C-RockN River drawngs 1 0 12-Aug-24A 19-Aug-24A 054Nov-24 ----------------------- ------ ......... g!or"Ps"g4 3C-R Riser�raM A3570 SG compile pricing for Package 3C-Rock'N Rivercrawings 4 0 13 24A A 19-Au 24A 05-Nov-24 SG a mp�e -- ------------------c*, 'r------no's: -RocWN River drvig budgetary numt 5 0 20AUg-24 A 23-Aug-24A 05-Nov-24 CWi r provide Comments on 61�%Pa"3C-:RoWN RIver.dnilg�Udl pullb" A3590 Owner provide comments on 60%Package 3C . . . . . . A3600 SG revise 60%Package 3C-RockN River pricing according to owner comments 5 0 23-Aug-24A 30-Aug-24A 05-Nov-24 ii siiallrvi, 00-Apacksige:3C:*-R,od5N'River pricing according to awl.pirnmisipta : . . . . . . . . . . . . . A3610 SIG provide constructaltillity,review comment wGiM Package 3C-RockN River do 4 0 23-Sep,24 A 27-Sep-24A 05-Nov-24 8; 81316ro%ide: AstrpObi*+vlaw4orrtrrtettts:onW%Pgi3 �-R*rARlyarorv,ps: -------- L.-L------------ce,__--- ...... A3620 Conduct page flip meeting reviewing 90%Package 3C-RockN River drAigs 1 0 01-W-24A 01-Oct-24A 05-Nov-24 : : 1 ; ; : : j 1 ondudtpogtiflip m#etihgievibvAAg"P#ck#ge:3q-qo *N?I*rorAos A3630 SiGsolicit 90%Package 3C-RockN RrverforGMP 15 0 10-Od-24A 31-W-24 A 05-Nov-24 m SG tolidit 90%Pal'a 3C:.Rbd?N River fdr OMR A3640 SO compile GMP for Package 3C-RockN River from 90%oral 4 4 31-Oct-24 05-Nov-24 08-Nov-24 3 1 jG k ompila GMP,for.Package 3C:-P;oc!�N kiviir h6mi 91�%drawn . . I . . I . I : . . . , . . A3650 SG submit GMP for Package 3C-Rock'N River 1 1 06-Nov-24 06-Nov-24 11-Nov-24 3 r �GSuomR GMP for Package 3r.%Rodt14 Rivet A3660 Omer/Design Team reviewGMP for Package 3C-RocWN River and provide comp 5 5 07-Nov-24 13-Nov-24 18-Nov-24 3 .0*et/OesbnYearn IevipdwoMpf4rP� � 30-�o*N:RF erpnop** m�� c� ts: A3670 SG review comments for Package 3C-RockN River GMP and revise accordingly 4 4 14-Nov-24 19-Nov-24 22-Nov-24 3 Sip*leiiv Ominerlts for Padralie SC-Rod "P Ono rs$ro acpDrl A3880 SO resubmit Package 3C-Ro&N River GMP 1 1 20-Nov-24 20-Nov-24 254Nov-24 3 I:SGivisuqmg.Pd,"ge:3C:-RDWNRiver GMR A3690 Owner forward Package 3C-RockN River GMP to CoRR City Council 5 5 21-Nov-24 27-Nov-24 04-Dec,24 3 r. Ownar fii"rd;Pa&w'pe�'C RD'&N' Firvar GMP.'to lC R'R;Ci�Cbujcl . . . : . . I . I . 0. A5730 CoRR City Council approval process for Package 3C-RocWN River 30 30 02-Dec-24 14-Jan-25 17-Jan-25 3 F? CcjRk City douncil 8pprmYal prl foj P"ge:3C:-koc�N kiver . . . . . . . . . . . . . . I . . A5740 SG provide CoRR list of recommended priority subcontractors for approval 1 1 31-Dec,24 31-Dec-24 10-Jan-25 7 : i JG jro*i0 C4Rq Il of jec�mjne6clad piio*ju*nfral fat apy,�I: -------- -------------- A5750 CoRR provide approval for recommended subcontractors 5 5 02-Jan-25 Ol 17-Jan-25 7 11 j f I -- poRRom�id+aoprovaFforroorrimeh* skjb0njrac*or4 cl T :ITITIT FirsjCostlIucton: Buy-Out and ContractAcInninistration 55 55 02-Dei>24 18-Feb-25 21 3 Tsormal BU.y-Out onq Cdntr9ct Adilifinistirstiorl A3700 SG conduct buy-out meetings for preliminary scopes of work for Package 3C-Rock 20 20 02-Deo-24 30-Deo24 09-Jan-25 7 SG itionduck led ,y-d.ut ineillitinos fbr Orellininory"pe6 crt w"fpr qac!agle 3C-ROWN Rived A3710 SG administer contracts to subcontractors for Package 3C-RockN River 10 10 15-Jan-25 28-Jan-25 31-Jan-25 3 q313do t6t ts o gubo co al e - River . . . . . . . . . . . n,ra,t 1 fat P, �. .:3C. . . .RocKN Ri.b . ...................... A3720 Subcontractors review SG subcontract for Package 3C-RocleN River 5 5 29-Jan-25 04-Feb-25 07-Fab-25 3 ntia(io;review ma r gw,id A3730 SG finalize and exectite,subcontracts for Package 3C-Roc*N River 5 5 05-Feb-25 11-Feb-25 14-Feb-25 3 :0:sofin�slzli a6d pxeputp%��ntffactq fo�PQ�ge:30-qoc*N��r : . . . . . . . . . . . . . . A3740 Mobivaton of preliminary subcontractors for Package 3C-Rock'N River 5 5 12-Feb-25 18-Feb-25 21-Fab-25 3 0 M+biloton of Orsloidar'su#c*trActoo fpr Qacilag§3P-RooeN River: Submittals 40 40 19-Feb-25 15-Apr-25 08-Deo-26 418 VPOW:Submttta . . . . . . . . A3750 Long lead materials for Package 3C-RocKN River(Elect,Canopies,e 40 40 19-Feb-25 15-Apr-25 08-Dec-26 418 :—SubtnkttlisLdng:leadnlatorisibldrPbdckgd -Rc,#N:RNer",,;an1,"s,l . .3G . ------------------------------ Procurement 100 100 16-Apr-25 05-Sep-25 29-Apr-27 418 . V pmW . . . . . . mlnt A3760 "Procurement-Long lead materials for Package 3C-RockN River(Elect,Canopies IDO 100 16-Apr-25 05,Sep-25 29-Apr-27 418 !-Procurement-Long Ill materials for 3C-:Rc�k`�Rivet . . . . . . . . . . VIsmIssiamanaossiossiss. . UorrslrUown A5950 Earthwork/Building Pads 120 120 19-Feb-25 07-Aug-25 12-Aug-25 3 �arhwprk j Buildiing Pads A5960 Underground Utilities/MEP Rough-In 120 120 14-May-25 314)ct-25 05-Nov-25 3 QndorgioupdOtiliierr,/4EFi.Rqugh4q A5970 Concrete Foundations 60 60 11,Jul-25 03-Oct-25 O8-0d-25 3 forjcrete Fouhdsfiods A5980 Structural Steel 80 80 08-Sep,25 02-Jar,26 07-Jan-26 3 itru6uial ilea A5990 Concrete Paving 80 80 06-W-25 30-jarl 04-Fel 3 Corbels Pp" A6000 Masonry/Stucco 90 90 03-Nov-25 13-Mar-26 13-May-26 43 A6010 MEP Buildout 80 BO 03-Nov-25 27-Feb-26 04-Mar-26 3 ME0.Bykll A6020 Finishes 60 60 17-Dec-25 134Mor-26 134May-26 43 :Rl . . . . . . . . . . A6030 Irrigation 20 20 17-Dec-25 16,)ar,26 21-Jan-26 3 ct-:Irr$al A6050 Landscaping 40 40 19-Jan-26 13-Mar-26 18-Mar-26 3 :1-andalng: A6040 Installation of Misc.Metals and Site Furnishings 40 40 02-Feb-26 27-Mar-26 01-Apr-26 3 Installation of Misr.Mpta� ll bite Fktmiilhinj A6060 Pundilist and Closeout/Commissioning 30 30 16-Feb-26 27-Mar-26 01-Apr-26 3 Nirl arld obill000/.tojnnpssiDni6g 3C-Rec Center Complex-Site 548 368 25-Jan-24A 15,Apr-26 29-Apr-27 265 . . . . . . . . . . . . . . . . . . . . . . ..:3C-ReCCehtei,C4m0Il Start Date: 15-Jan-24 Actual Work M,I.St.o. — Actual Level of Effort CoRR OSP-Preconstruction Schedule Finish Date 26-Apr-27 — Remaining Work �Summary WBS Layout-HH All Activities Data Date: 31-Oct-24 — Critical Remaining Work —i Level of Effort Page 10 of 15 Run Dale: 31-Oct-24 Activity I D Act"i Name Crig Rem start Finish Late Finish Total Post . . . . • • a a • • w o • w . N D J F M A M J J A S 0 N 11 A M J J &MM&DJFMAM r r Design 278 88 25,1..-24 A 1 21 Mer-25 27-May-25 46 f Design A3780 Development of Package 3C-Rec Center Complex-Site 30%Drawings 46 0 25-Jan-24 A 13-May-24A 01-Nov-24 bevebpnjeni of ap®ge$C}Rpc 0er'eer�_ojnplBx Sipe*)%Drewaiga; A3790 SG receipt of Package 3C-Rec Center Complex-Site 30%Drawings(Target Date 1 0 13-May-24 A 13-May-24A 01-Nov-24 SQ regeipj o(;Pa ge PC*'Rpc�erjter:Cojnplex,S$e l0*/q Drpwipgtj(Tifggt Dpte:D4:15.241 City 9 W 9 Y- 28-May-24A - - gla 3C Sled 30%Dra A4210 C review of Package 3C-Rec Center Complex-Sde 30%Drawings 10 0 13-May-24 A 014�1ov-24 '�, ��', City ievibw of ckage 3C-Ref Cbntgr Crorriplex-Ske 30%Dravings j A3800 Development of Package 3C-Rec Center Complex-Site 60%Drawings 47 0 15-Jul-24 A 18Sep-24 A 01-Nov-24 rrrl:D Ibprherlt of PeekAge:3C-Rec Collett Comdlexl-Site 60%DtavAng9 A3810 SG Receipt of Package 3C-Rec Center Complex-Site 60%Drawings(Target Date 1 0 18Sep.24A 18-Sep-24A 01-Nov-24 r:S Recall of Raetega 3C-Floc Cantor CorOplmc-Ska 60%Dravdnps 7argetaate 09.20.24)I A3830 Development of Package 3C-Rec Center Complex-Ste 90%Drawings 38 38 14-Nov�24 10-Jan-25 13-Jan-25 1 beyekipmenp of pedkage�C f ROe denier Gompl6x,'Sipe 9p%IDrawiggs: A3840 SG receipt of Package 3C-Rec Center Complex-Site 90%Drawings(target Date 1 1 13-Jan-25 13-Jan-25 14-Jan-25 1 r :sO mge6t ol.Package:3C:-Ftec oenter,Cgmplex:-Sjle$O%Dia*g4(Tbrg4t Doty OQ.2TQ4f A3850 City review of Package 3C-Rec Canter Complex-Site 90%Drawings 10 10 14-Jan-25 27-Jan-25 01-Apr-25 46 d Gity ievipw of padkagb 31C-i2ec Cbntgr Crornplex-Skq 90%Qrakings A3860 Development of Package 3C-Rec Center Complex-Sde 100%Drawings 18 18 28-Jan-25 20-Feb-25 25-Apr-25 46 ; �;Dovelopineli of Pit ge.'3C-Rao CehteF CbmdleX-She d00%DraWr A3870 SG receipt of Package 3C-Rec Center Complex-Site 100%Drawings(Target Dat< 1 1 21-Feb-25 21-Feb-25 28-Apr-25 46 r;SC rgkaipt Of Pgd�gA 3C-Red Contor Cbmplet-Ske:100%ar9wirlgs(Togas!Dote 70. A3880 City review of Package 3C-Rec Center Complex-Site 100%Drawings 10 10 24-Feb-25 07-Mar-25 12-May-25 46 4 tkyl reNeN of Qac m6e$C"ROe derperComplpx!Sipe lb0%D7a4ngg A3890 Final plan revisions for Package 3C-Rec Center Complex-Site 10 10 10-Mar-25 21-Mar-25 27-May-25 46 :o:FinI al pI laq ryispnsfor,'Paotpe 8c�Roc�erter•Cajnp(x L Siiee Butl atin PackageComplex j 3C-Rec Center Comp eX-Site 30%Drawings 25 0 13*1ay 24 A 18Jun 24 A 01 aJov 24 �►:Pgdr4ge3C-rZec Centel Complex:-Site PO4 Diewfng} A3900 SG provide construdabilify,review comments on 30%Package 3C-Rec Center Cor 5 0 13-May-24A 14-May-24A 01fJov-24 :r prPvide ab gWtiiltylraJiewioolnnjenla ol13QX:Pajirage pC:Rbc QerjterColnpiex Silo rinvga A3920 SG solicit 30%Package 3C-Rec Center Complex-Ste drawings for budgeting 15 0 14-May-24A 12-Jun-24 A 01-Nov-24 ;rl :SG sor' Pisoweg4'3C-Re0 CAnt4r Comptek-$ke:dr9wirigs for budgelFng: A3930 SG compile prong for 30%Package 3C-Rec Center Complex-Ste drawings 4 0 12-Jun-24 A 18-Jun-24 A 01-Nov-24 ;•;SO compile vil for 30%Pad�gA 3C-ReC CAntor Complex-Sdel drawn -�--+- -�--F--g-->--1 _+--� A3940 SG submit budgetary pricing for 30%Package 3C-Rec Center Complex-Ske draw 1 0 18-Jun-24 A 18-Jun-24 A 01-Nov-24 ;r;St}Wbrnk b d eWry pnang for.09.Pecks a 3C-F}e�Corker Com lex-8Re jdraWrrgs; Package 3C-Rec Center Complex-Site 60%Drawings 20 10 1 esep-24A 13-Nov-24 14-Nov-24 1 :PaFkage pC L Roc�erjter,Cojnplex;Sile 40%j Drowijfgij A3970 SG provide constructabilky review comments on 60%Package 3C-Rec Center Cor 5 0 18Sep-24 A 25Sep-24A 01-Nov-24 : S grovpe corjstr"biliiy rpviawc�minepta on SO%POdpagq 34F-tte4 Cant4r Cpmplei-$Ite;dM9ai A3980 Conduct page flip meeting reviewing 60%Package 3C-Rec Center Complex-Site 1 0 25Sep-24 A 25,Sep-24A 01-Nov-24 c�onducl page,pip ine'etirig rfviewirrb fib%Pac kgge BC:-fjec Center'ComplexL Sile s A3990 SG solicit 60%Package 3C-Rec Center Complex-Ste drawings for budgeting 15 0 26Sep-24A 24-0c-24A 01-Nov-24 ; 0'SG sblkit 60%Padka4e 3C:RdC Center Corhpl6x,Sitb dtaw8lg!fol brldg6tinp ______________________T_ A4000 SG compile prong for 60%Package 3C-Rec Center Complex-Site drawings 4 0 24-0c-24 A 30-01 A 01-Nov-24 I SG cordpils pricinp far 60%Padka�a 3C 41 Rbc Center Complex;Ska dtawl ilk I A4010 SG submit budgetary prong for 60%Package 3C-Rec Center Complex-Site draw 1 0 31.0ct-24A 31.W-24A 01-Nov-24 4G submit tludgelarK pr l fol 6Q%Package 3C+,Rac Clanger bornpbz-:SK4 diAwlpgs A4020 Owner provide comments on 60%Package 3C-Rec Center Complex-Ste drwg bit 5 5 31-W-24 06-Nov-24 07-Nov-24 1 Qwrier proyidq c4mrgerys 4n$0*4 P4ck4ge;3C:.Fbac];ente r,C4mp)ax L Soo ding bydgotary numbe• A4030 SG revise 60%Package 3C-Rec Center Complex-Site prong according to owner 5 5 07-Nov-24 13-Nov-24 14-Nov-24 1 0 :SG reivise 60%p,adkage 3C-72eb Cbntbr¢oniplex-Sil q prjano a4coidip t4 ohne{cojnniienfs GMP A4040 SG provide consbuctabilky review comments on 90%Package 3C-Rao Center Cor 3 3 14-Jan-25 16Jari-25 17-Jan-25 1 ;SG provide donStruttebilky re4iefi cdmr4ents do 90%Pa'dkdge 3C;-Roe Cedter:Complex:S A4050 Conduct page flip meeting reviewing 90%Package 3C-Rec Center Complex-Site 1 1 17-Jan-25 17Jarl 20-Jan-25 1 r:CdndUd baps flip me9tin$raYiel►in$90%Package 3C;Rdc Center Corhp",SAB dt.wo A4060 SG solicit 90%Package 3C-Rec Center Complex-Site for GMP 15 15 20-Jan-25 07-Feb-25 10-Feb-25 1 j 4SG;soW 90%Package 3C-Req Contej•CompleX-Ste yor WP j A4070 SG compile GMP or Package 3C-Rec Center Complex-Ske from 90%drawings 4 4 10-Fab-2513-Feb-25 14-Fab-25 1 :6;S(;'coinplle oMp for Podiig4 30-Rea C4ntar Comolei-$he:fmrii 9;o%dr4wi4gs A4080 SG submit GMP for Package 3C-Rec Center Complex-Site 1 1 14-Feb-25 14-Feb-25 17-Feb-25 1 :i:SG aubmo GMF,for Package pCI-Rbc Center Complex=Site A4090 Owner/Design Team review GMP for Package 3C-Rec Center Complex-Site and 5 5 17-Feb-25 21-Feb-25 24-Feb-25 1 :a;Oorrer/DeAigri Teom:raviewiGMP}br Racke�e 3C;ReC Cbntbr CorikplAx-Sit6 S A4100 SG review comments for Package 3C-Rec Center Complex-Site GMP and revise 4 4 24-Feb-25 27-Feb-25 28-Feb-25 1 ii siG ravlew Corrlrn"foCPahlrape 36 Roe Certter'•Cdnplax Site 13 P an Oay._ A4110 SG resubmit Package 3C-Rec Center Complex-Site GMP 1 1 28-Feb-25 28-Feb-25 03-Mar-25 1 S SG msWlrrdt Pskikage 3d-t2eG Cantor(ample;-$U:13�P A4120 Owner forward Package 3C-Rec Center Complex-Site GMP to CoRR City Counc 5 5 03-Mer-25 07-Mar--25 10-Mar-25 1 6 owner loryer4 P4ckpge;30-gec Cejitet Cpmple>-Sine oVe tp CpRfi cJ y oopnca A5760 CoRR City Council approval process for Package 3C-Rec Center Complex-Site 30 30 10-Mar-25 1B-Apr-25 21-Apr-25 1 b CORR City¢oundl;approvel pmfes¢for'P#dkfge 3G-ReclCentei CPmfle>i-Ske ..:....................1'' ---------------- A5770 __ -- -- A5770 SG provide CoRR list of recommended priority sutxnntracors for approval 1 1 07-Apr-25 07-Apr-25 14-Apr-25 5 - - -O�- ._ ._ _._dirl-.-.._ a l �fdr - ;r SG ra4itl0 CbRR lilt o1 retortlmendbd pdollry buHcodtraCWA far apprdval A5780 CoRR pmvide approval for rakxxnmended subcontractors 5 5 08-Apr-25 14-Apr-25 21-Apr-25 5 ;o:Cl provide approval for recor6mondad WticorttradoA PR-ConatruQorf Buy-Out and ContractAdminstration 55 55 10-Mar-25 23-May-25 27-May-25 1 Vmb-W. ,Brtl,40 Bind ContmdAdminlstrsfion A4130 SG conduct buyout meetings for preliminary scopes of work for Package 3C-Rec( 20 20 10-Mar-25 04-Apr-25 11-Apr-25 5 ;ej $G Wrp]uQ boy-jut meetings tDr prellmidapt scOpeliii of vi for PaUkag6 3C Rel Start Date: 15-Jan-24 Actual Work ♦ ♦Milestone Actual Level of Effort CORR OSP-Preconstructlon Schedule Finish Date. 26-Apr-27 roc Remaining Work �Summary .WBS Layout Data Date: 31-Oct-24 w Critical Remaining Work ® Level of Effort Page 11 oAll fr o Run Date: 31-Oct-24 g Actwityll) Activity Name 069 f%M shm Finish Late Finish Total Float Q Q a 0 a Q Q Q a Q Q Q Q . . N 0 J F M A M J J A S 0 N D J F M A M J J A S . A4140 SG administer contracts to subcontractors for Package 3C-Rec Center Complex 10 10 21-Apr-25 0244ay-25 05-May-25 1q G admingter000trslcta do 9ubcortradory for Peckege;3Q-Rec Ceptor Complex; A4150 Subcontractors review SG subcontract for Package 3C-Rec Center Complex-Site 5 05-May-25 09-May-25 12-May-25 1 e Ruycontrapojs rgviaw$G vubp�4t fc>f Pk4l;ej 3Q-gegCejntet Cpmplell-I A4160 SG finalize and execute subcontracts for Package 3C-Rec Center Complex-Site 5 5 12-May-25 16-May-25 19-May-25 1 ;.ISG finalize and'execute subcbntdacfa for Package 3C-Fk Call �Comolelj-5 A4170 Mobilization of praliminarysubcontractors for Package 3C-Rec Center Complex-S 5 5 19-May-25 23-May-25 27-May-25 1 ;e:Mbbikmtlon;of preAmirlay subodntridds for pacdkaoe 3C:Reb Center Corirple Submittals 75 75 27-May-25 10-Sep-25 25-Sep-26 265 ►SupmGtalf -- ^--�--�--�--�--�--T- -- A4180 "Submittals-Long lead materials for Package 3C-Rec Center Complex-Site(Ela 75 75 27-May-25 10-Sep-25 25-Sep-26 265 ; ; ; ; ; ; ; 1 ; ; ; Y MubrhRtals;Lttp bed rrtet"iI for Peelrega 3C-RecZehtat Cc Procurement 150 150 11-Sap-25 15-Apr-26 29-Apr-27 265 ? �;PrOculertjent A4190 "Procurement-Long lead materials for Package 3C-Rec Center Complex-Site(E 150 150 11-Sep-25 15-Apr-26 29-Apr-27 265 ;"dropseinept;Logo Ipat)ngtejlalq fot Pei . . Conalrjut. A6080 Earthwork/Building Pads 100 100 27blay-25 75-04-25 16-W-25 1 0 F�rlhaorl{I Qull�ling Pads: A6090 Underground Utilities/MEP Rough-In 100 100 23Ju1-25 12-Deo-25 02-Apr-26 76 ; ; . ; ; I LJr*eromjrnd UoNes I eIEP gouih-h1 3C-Rec Center Complex-Buildings 688 506 25Jan-24 A 30-Od-26 29-Apr-27 125 3C;Reb Center i li"a&Cbn9 A6830 REC Center to be turned over by 10.01.26 to allow for stocking for Opening 01.207 0 0 30-W-26' 02-Nov-26 1 4 REC Ginter td ....................................D ' A6390 Development of Package 3C-Rec Center Complex-Buildings 30%Drawings 46t 0 25,1an-24 A 13-May-24 A 21-Feb-25 �� DeVebpnlent of dope 3C:Rac CerfterColn ,BUiId tigs:30%Dra#A 9 ; A6310 SG receipt of Package 3C-Rec Center Complex 30%Drawings(Target Date 04.15 1 0 13-May-24 A 13-May-24 A 21-Feb-25 ;r W"Ipi of;Pa Juage j1C}Rpc terlter,Cgnpjex�0%Dravlingy( largpl Fete 04.10.24) A6670 City review of Package 3C-Rec Center Complex 30%Drawings 100 13-May-24A 28-May-24A 21-Feb-25 ally javipw pf adiagp 3C-#top Cgntgr(;orgpl�r 3b%jDrpwijgs j A6320 Development of Package 3C-Rec Center Complex 60%Drawings 47 0 15-Jul-24A 26.OclA 21-Feb-25 emir• 1306opmaht of Pac kpgo 3Cr-Roo Conten Compleic 6Q%prakil A6280 SG Receipt of Package 3C-Rec Center Complex 60%Drawings(Target Date 09.2 1 0 25-Oct-24 A 25-04-24 A 21-Feb-25 r SG ReofUpt o Pa. 0e 3C.Rdc Confer Corhpl0x 80%DlewingA(rArgdt OOate;09120;243 ; A6290 Development of Package 3C-Rec Center Complex 90%Drawings 38 3B 18-Deo-24 11-Fab-25 30-May-25 77 ; ; ; ; ; De"prn nt ofPatlkepe 3C:Rec CerllaYCdnpbx g0%DlaWng6 A6300 SG receipt of Package 3C-Rec Center Complex 90%Drawings(Target Date 08.27 1 1 12-Feb-25 12-Feb-25 02-Juni 77 ;r ;Sq reneipj of Pie OC:-Rec Gegter;Cgmplen�OiG greNinga(artpt I$at0 0$.2t.24) A6340 City review of Package 3C-Rec Center Complex 90%Drawings 10 10 13-Feb-25 26-Feb-25 21-Aug-25 124 of Cjly jevipwpi Papliagp 30-step Cpntpr Gorgplepk 90%;Drgwtggs; A6350 Development of Package 3C-Rec Center Complex 100%Drawings 18 18 27-Feb-25 24-Mar-25 17-Sep-25 124 d;Development of Pedkege 3G-HeoCenter Cemplemi 10;0%Drpwiigs? A6360 SG receipt of Package 3C-Rec Center Complex 100%Drawings(Target Date 10.2 1 1 25-Mer-25 25-Mar-25 18Sep-25 124 r:SG niol df Pia g4 3C-Red Carl Cbmplek 190%Dial d(TlIrgat Datil 10(22; _ A6370 City review of Package 3C-Rec Center Complex 100%Drawings 10 10 26-Mar-25 08+4pr--25 02-W-25 124 ; ; ; ; ; ; O City reVieW of patlkape 3C:Rec CarlterlCotnplex 7 OO,Yo Dravrinpe A6380 Final plan revisions for Package 3C-Rec Center Complex 10 10 09-Apr-25 22-Apr-25 16-04-25 124 Flpal plats"pn8 for,Package�C:-Filial;GeC ter.Camr ex: Package 3C-Rec Center Complex-Buildings 30%Drawings 25 0 13-May-24 A 18JurlA 21-Fel Pgtlkgge:3C-fjec Center;Cclmoll BNlklln94 30%prawIni A6400 SG provide consWctability review comments on 30%Package 3C-Rec Center Cor 5 0 13-May44A 14-May-24A 21-Feb-25 r ;So prig*cy truotaIjill rapevl cojnni oj13Q%:Papkage$C-Rp c CerjterCgnp(ex slaps A6410 SG solicit 30%Package 3C-Rec Center Complex drawings for budgeting 15 0 14-May-24A 12Jun-24 A 21-Feb-25 1 I 1 e>iISG soGcil30 Peddag4 3C-Reo Crintgr Comblek drewinge forbudgetin9 A6420 SG compile pricing for 30%Package 3C-Rec Center Complex drawings 4 0 12Jun-24A 18-Jun-24 A 21-Feb-25 .:SG odmdie ride9 for 30%P)tdiaga 3C-Red Canter Cionn is drawl A6430 SG submit budgetary pricing for 30%Package 3C-Rec Center Complex dmwings 1 0 18-Jun-24 A 18-Jun-24 A 21-Feb-25 r;S6 submit b idgetAry prong for 90%Package(3C-Rec:C enter Complex drawings: Package 3C-Rec Center Complex-Buildings 60%Drawings 32 32 25dd-24A 17-13 o 24 07-Apr-25 77 1 Package 3C:•Rec Center,,Cgmp$ax:-Buadyge 60%prayvinga A6440 SG provide construcability,review comments on 60%Package 3C-Rec Center Cor 5 1 25-Oc1-24 A 31-Oct-24 21-Feb-25 77 1 $G proxida const"biity r9viow nonimants on;e0kh Package 3G-Reo CBntpr aonjpleik dtwd A6480 Conduct page flip meeting reviewing 60%Package 3C-Rec Center Complex dwgs 1 1 01-Nov-24 01-Nov-24 24-Feb-25 77 �o ugt piii flq mpetipg levipwipg$0%Ppdkpgq 30-fkecjCej1*Cpmpll clijigal j A6450 SG solicit 60%Package 3C-Rec Center Complex drawings for budgeting 15 15 04-Nov-24 22-Nov-24 17-Mar-25 77 l SG solid(60%Packa4e 3C;Rec Center Corimplex drawing's for bud{fetirig A6460 SG compile prong for 60%Package 3C-Rac Center Complex drawings 4 4 25-Nov-24 02-Dec-24 21-Mar-25 77 a SG Gonlpild prking for 60%Patlaee 2C:RAc Center Corhplpcli x aranga 1 A6470 SG submit budgetary pricing for 60%Package 3C-Rec Center Complex drawings 1 1 03-Dec-24 03-Dec-24 24-Mar-25 771 3G 9utDntt;budgeiary pr►cng for 60%PakWaQe 3C:Rec Cenrer Corhplaz klraWn�s A6490 Owner provide comments on 60%Package 3C-Rec Center Complex drug budget 5 5 04-Deo-24 10-Dec-24 31-Mar-25 77 p OAMSr.prgwdp cpmrpeots on 00°A Package:3a-40C:Cejt tei Cpmplex drig budpetpry:nupl m A6500 SG revise 60%Package 3C-Rec Center Complex pricing according to owner comn 5 5 11-Dec-24 17-Dec-24 07-Apr-25 77 ;e So raylag 60%Pa de 3jC-Rqc aenfer Qorpplpx Ocil paprdipg jo ajwrpr apmjnetmts; Gli A6510 SG provide constructability,review comments on 90%Package 3C-Rec Center Cor 5 5 13-Feb-25 191 09-Juni 77 o:SQ pio a Ontnicability review comments On g0°Y,Pia ge�3C-qac Centel Cgmolex. A6550 Conduct page flip meeting reviewing 90%Package 3C-Rec Center Complex di 1 1 20-Fob-25 20-Feb-25 10Jun-25 77 r:Cdndud:page Aip pme0tin$rdvieikin$90%AaCkage 3C:Rdc Center Complex tlw.ijs Start Date: 15-Jan-24 w Actual Work ♦ ♦Milestone r_ Actual Level of Effort CORR OSP-Preconstruction Schedule Finish Date:26-Apr-27 Remaining Work Vi'll"limm►Summary .WBS Layout-HH All Activities t r Data Date: 31-Oct-24 er-r_ Critical Remaining Work et_ Level of Effort Page 12 of 15 Run Date: 31-Oct-24 Activity . . . . . . . . . . . . . . . A6520 SG still 90%Package 3C-Rec Center Complex for GMP 15 15 21-Feb-25 13-Mar-25 01-Jul-25 77 4 so sola 90%Patiiege 3 - eo Center Oompll for GMP; ; A6530 SG compile GMP for Package 3C-Rec Center Complex from 90%drawings 4 4 14-Mal 19-Mar-25 Ol1Jul-25 77 ;.:SG cgm4ile oMp fpr P�*gp 3C-}ley COntgr gonjplejc*m 00%dje+90 A6540 SG submit GMP for Package 3C-Rec Center Complex 1 1 20-Mar-25 20-Mar-25 09Jul-25 77 r:SCp subrtift GMP f4 PAck}g63G-gec:Cehtef Cr moksru A6560 Owner Design Team review GMP for Package 3C-Rec Center Complex and provi 5 5 21-Mar-25 27-Mar-25 16Jull 77 ; a;6... . ..Tdani reJieWGA. . Padraoe 3C.Rd. Center CorhplAx Andlprrivirf" A6570 SG review comments for Package 3C-Rec Center Complex Cdv1P and revise acoon 4 4 28-Mar-25 02-Apr-25 22Ju1-25 77 1 8G AsviBw Con7m6nt8 fol Package 9C;-Rec Cerltef Catrn{!ex'%aMP andlraViae;arxo� A6580 SG resubmit Package 3C-Rec Center Complex GMP 1 1 03-Apr-25 03-Apr-25 23-Jul-25 77 j $G kesobrn4 Package 3G-Reo Center Conkplep(�m1. A6590 Owner forward Package 3C-Rec Center Complex GMP to CoRR City Council 5 5 04-Apr-25 10-Apr-25 30-Jul-25 77 j j e O,lforyard Ppdkpgq 3Q-q*OCgn*Cpmplei GIAPto CoQR�*,,Cquno A6680 CoRR City Council approval process for Package 3C-Rec Center Complex 30 30 11-Apr-25 22-May-25 11Sep-25 77 1 b:CORR C'ty Councq eppri l Ofd.oaga for Pedkiiigo 3C}-Re0 Center Comprs* A6690 SG provide CoRR list of recommended prbdy subcontractors for approval 1 1 09-May-25 09-May-25 04-Sep-25 81 :i SG:prdrldb CbRR 141:of retonlmAndbd pdoMy 4u6codlraftofa fdr apprbvel A6700 CoRR provide approval for recommended subcontractors 5 5 12av1ay25 16-May-25 11-Sep-25 81 :.:CARR provide approval for rebortlmendBd 5conbaCorS ;Pre-CPn9auGioO 'mac 7, Buy-Out and ContradAdministrati0n - - 55 55 11-Apr-25- - 27Jun-25 16-Oct-25 77 -- Byy+�uCanp C;ntfactArbnioishetil , A6600 SG conduct buy-out meetings for preliminary scopes of work for Package 3C-Rec C 20 20 11-Apr-25 08-May-25 03-Sep-25 61 ;4 �G',mgdi buyout:mgetirjgs foryrelimiparq stiop9s of wprk for pedkape; A6610 SG administer contracts to subcontractors for Package 3C-Rec Center Complex 10 10 23-May-25 56Juo-25 25-Sep-2577 o $G�drjtinotet cootrictato(rut oo jtraooi�hjr Ppd(lagq 30-Req Cgntq A6620 Subcontractors review SG subcontract for Package 3C-Rec Center Complex 5 5 09-Jun-25 13-Jun-25 024)d-25 77 a Subcohtractors revgw$G 6u0corltra}t for Fla*g4 3Cy-Rso Cont}r Corr A6630 SG finalize and execute subcontracts for Package 3C-Rec Center Complex 5 5 16-Jun-25 20-Jun-25 09-Oct-25 771 ri S6 fi4alite And:exAwte subdon6ads fbr Rad+.eg0 3C-Red CAnlbr Corr" A6640 Motorization of praliminary subcontractors for Package 3C-Rec Center Complex 5 5 23-Jul 27-Jun-25 16-W-25 77 . ; ; ; : ; ; ,r Mobil�'kratbrt ofjlrelimiear#r skfbcOntrgctOrs for Padm$e 3C;RAc Center Com Submittals 75 75 30-Jun-25 14-Oct-25 25-Sep-26 241 ; ^;Suiimtttal$ , A6650 —Submittal-Long lead materials for Package 3C-Rec Center Complex(Elec.Be, 75 75 30Jun-25 14-W-25 25-Sep-26 241 :1 :'$ubmitlal f LOng:leap rrjatBdaltr fc►Pr}dk8gej 3d-f.e Ceche' Procurement 150 150 15.Od-25 19-May-26 29-Apr-27 241 A6660 —Procurement-Long lead materials for Package 3C-Rec Center Complex(Elec,E 150 150 15-Od-25 19-May-26 29-Apr-27 241 �'—�� ;—ProGursjmsjnt Lohg(eat)nptejielq fl, Cunotrui:tldn A6740 Concrete Foundations 100 100 16-0d-25 11-Mar-26 12-Mar-26 1 �ojra$te Pokjnd4tiojts A6730 Concrete Paving 80 80 15-Deo-25 08-Apr-26 24Jul-26 76 r Corlcri Paving: A6750 Structural Steel 80 80 O5-Feb-26 28-May-26 29-May-26 1 i SiruGurAl Steel A6760 Exterior Facade 80 80 02a1pr-26 23-Jul-26 24Jul-26 1 j Faterbr tac id9 IA6820 MEP Buildout 120 120 02-Apr-26 18-Sep-26 21 Sep-26 1 j j j o:Map 0uiboyt A6770 Finishes 100 100 14-May-26 024Dd-26 05-0d-26 1 : Piniahe$ A6790 Irrigation 40 40 14-May-26 09-Jul-26 07-Aug-26 21 : Imgl A6780 Installation of Misr.Metals and Site Furnishings 40 40 10-Jul-26 03-Sep-26 02-Nov-26 41 I C==:? lhstAllation;of Misic.Metals" A6800 Landscaping 40 40 1OJul-26 03Sep-26 05-Oct-26 21 �antlacapil A6810 Punchlist and Closeout 20 20 05-0ut-26 30-0ct-26 02-Nov-26 1 ;® punyhligt and b6eo 3D-MubPurpose Center Expansion 810 630 25-Jan-24A 2SAW--27 29-Apr-27 3 3 A6210 RFP Schedule showed completion by 04.2027 0 0 26-Apa27 29-Apr-27 3 A4250 Development of Package 3D-MuttFPurpose Center Expansion 30%Drawings 46 0 25-Jen-24 A 19Ju1-24A 03-Apr-25 Dr►valoaril 0f Pd,"ge,3Q-Mu polls,Cerfted n'eioh 39% 9: A4280 Development of Package 3D-MuttFPurpose Center Expansion 60%Drawings 43 20 1OSep-24A 27-Nov-24 3GApr-25 106 Minn=::: OevAbpmetrd bf Package 36-MuIiiPurp6e;Canto r Expansion 80%Dfawings A4290 SG Receipt of Package 3D-Mufti-Purpose Center Expansion 60%Drawings(fargel 1 1 02-Deo-24 02-Deo-24 01-May-25 106 I 8G�eceipi oh Pack a�D L Iw ROut ole Centerpxpansion 6d%braivinps ifariOboio d8.�4.' A4300 City review of Package 3D-Muri-Purpose Center Expansion 60%Drawings 10 10 03-0eo-24 16-0eo-24 23-Jun-25 132 p Cibr rgvb}v0 Pgdkpgo 30-I IuNf Pkjrygse Ceptet Erparjsion 60%brpwirjgs: A4310 Development of Package 3D-MultFPurpose Center Expansion 90%Drawings 43 43 24-Jan-25 25-r.Aar-25 22-Aug-25 106 Dpvelopineht oY Pod4ge 3D-ftlul yrryQae Cehtei Bioaillsildri 9b%Dr}wlhgs; ....................:--------------------------------------------- A4320 SG receipt of Package 3D-Mufti-Purpose,Center Expansion 90%Drawings(Target 1 1 26-Mar-25 26-Mar-25 25-Aug-25 106 k;SG rbcelpt Of Reckagb 3D-Muni-Purpbad CAntdr ElWahsiDn 90%DfawingS(fbrgAt Dli A4330 City review of Package 3D-Mufti-Purpose Center Expansion 90%Drawings 10 10 27-Mar-25 09-Apr-25 034Oct-25 124 P Cdy review of;Peltcage 3D F Mu1H?ufpose Cer4er£)pansion 90%Drawings A4340 Development of Package 3D-MuftWurpose Center Expansion 100%Drawings 47 47 10-Apr-25 16-Jun-25 11-0eo-25124 D9velopmerlt of Pacu®e 3D:-MuftWufpose Cenlerfxpan&ion 100%D A4350 SG receipt of Package 3D-Mul&Purpose Center Expansion 100%Drawings(targe 1 1 17Juo-25 17-Jun-25 12-0eo-25 124 j r:So receipt of PrierSge:31D,-Oult purpose Derjter,Exparjsiop 1 QO%Dtaw}ngp Start Date: 15-Jan-24 Actual Work ♦ ♦Milestone Actual Level of Effo= CORR OSP-Preconstruction Schedule Finish Date: 26-Apr-27 — Remaining Work V---/Summary .WBS Layout-HH All Activities Data Date: 31-Oct-24 Critical Remaining Work r_ Level of Effort Pae 13 of 15 Run Date: 31-Oct-24 g Activity 10 AcWrly Name Ong Rem Start Finish Late Finish Total Foat Q Q 0 Q Q 0 0 a Q Q Q Q a a . N D J F M A M J J A S 0 N . A4360 Coy review of Package 3D-Multi-Purpose Center Expansion 100%Drawings 10 10 18,1un-25 01-Jul-25 30-0e,25 124 ; ; ; ; ; : ; I q lty Ieviawuk' rpose Center Expansion 1 % rgwin A4370 Final pian my—ns for Package 3D-Multi-Purpose Center Expansion 10 10 02-Jul-25 16-Jul-25 14-Jan-26 124 j j j j j j j j ; ; in:Flrjal plea rejecrns for paekape$D Mpltii#uurposo Clenfler$xpjanijion: Package 3D-Mult Purpose Center Expansion 30%Drawings 37 0 os A g za A 10,%p-24A 03alpr z5 }e'!Iakage 30 Mj tti-0urpose Cen4ereneb96[)ri 30awinis A4400 SG solicit 30%Package 3D-Mufti-Purpose Center Expansion drawings for budgetin 15 0 05-Aug-24 A 30-Aug-24A 03-Apr-25 :l 5G lioliat 30%Pa0kage 3D L MuttiFufpo#e Cramer Egian0oA dr0v*gaforlbu#g*ing A4380 SG provide construcabilky review comments on 30%Package 3D-Mufti-Purpose C 5 0 02Sep-24 A D6-Sep-24 A 03-Apr-25 s SG m14d0 cdnsoudabiky levbw'torhmbnt#on 30%Padra$e 3D 4MdftFPur0ose Cbrltlsr SrgrOndon�drviga __;------------------------------------------- A4410 SG comets pricing for 30%Package 30-Mufti-Purpose Center Expansion drawings 4 0 03Sep-24 A 09-Sep-24 A 03-Apr-25 1• SG mr. . p. .g for 30%PedtBge 3D;-Muk6Pulpoie Center;Expeneion di9wingt A4420 SG submit budgetary pricing for 30%Package 3D-MuftFPurpose Center Expansion 1 0 03-Sep-24 A 10-Sep-24A 03-Apr-25 t SG submit b6cigptaiy pjittl fpr 3p%Padriige 9D;-1vfilittiOuipo6e terlter;Egjaniao6 drpwipga Package 3D-Witi-Purpose Center Expansion 60%Drawings 36 36 03-Dec-24 23Jal 23Jun-25 106 Ill PPc l 30-lllulPyrpgss Cehtej Eltiparnsign ill Drpwil A4450 SG provide construdabilily review comments on 60%Package 3D-Multl-Purpose C 5 5 03-Dec,24 09-Dec-24 08-May-25 106 6 f3G:pr,vAdq can0mciabilityievj w:oo n�ntg on 6Q%pagkape$D%Mpft-Purpos9 Cenf er�pn A4460 Conduct page flip meeting reviewing 60%Package 3D-Mufti-Puryose Center Expa 1 1 10-Deo-24 10-0eo-24 09-May-25 106 :1 ?Conduct ffag6 flib rr-iing;reviewjng;6046 gadfage 3D-M*b urpbso C$ntar Eoansi{Imps ...._________________:__�.__'.___ -------- __ __ ------ A4470 .- A4470 SG solidi 60%Package 3D-MuftkPurpose Center Expansion drawings for budgetin 15 15 11-Dec-24 02-Jan-25 02-Jun-25 106 : : : : : : : : :d SG 6olip160%Package 3D;-MuK4-1poll Cedter:Exiiarteiob dria ltgd fot butlgel in$ A4480 SG compile pricing for 60%Package 3D-Multi-Purpose Center Expansion drawings 4 4 03-Jan-25 08-Jan-25 06-Jun-25 106P SG:corhpi6 plidag fpr 60%PaYkege$D'-MukkPutpo6e Cerlterfxpenl:iop drHwipga A4490 SG submit budgetary pricing for 60%Package 3D-MuttFPurpose Center Expansion 1 1 09-Jan-25 09-Jan-25 09-Jun-25 106 :1 SGsubmi.b4dgjde. ppal for W%jPapksBe 3D MuftijPujpoee�eriter£ngjenbaa dr1 A4500 Owner provide comments on 60%Package 3D-Mufti-Purpose Center Expansion dr 5 5 10-Jan-25 16Jan-25 16-Jun-25 106 ;a jOhnej prpviae gommill ion 6096 P"ga 36-Multi-PUr se:Cantef E%pansgn Orwg budg A4510 SG mv®e 60%Package 3D-MuItFPurpose Center Expansion pricing according to 0 5 5 17-Jan-25 23Jan-25 23-Jun-25 106 ;S�rvib 6p%Paxpe D;Mtt�upo �erfrajij prpng axp9 tq currier cot A4520 SG provide construdability review comments on 90%Package 3D-Mufti-Puryose C 5 5 27-Mar-25 02-Apr-25 02-Sep-25 106 d $G}ro.}ide constMctabiPjty rlevow tlonf mentaonl padolg}3¢-MuC$ A4530 Conduct page flip meeting reviewing 90%Package 3D-Multi-Purpose Center Expa 1 1 03-Apr-25 03-Apr--25 03-Sep-25 106 t Conduit pbgd NO,m6eting levi6wl 90%Pit go 30-MuNI-Pdrpdse Cehtef E>1paq A4540 SG solid 90%Package 3D-Mufti-Purpose Center Expansion for GMP 15 15 04-Apr-25 24-Apr-25 24-Sep-25 106 P;SG solicit 90%Paczo'a 3D'Maki-Purpose Center Expaneton:for;GMP A4550 SG compile GMP for Package 3D-Multi-Purpose Center Expansion from 90%draw 4 4 25-Apr-25 30-Apr-25 30-Sep-25 106 t a SG Compile GYIP Yor?a"'a'a�'D.Mill,ur fwea Cenjer nikxVi lm 90%tire A4560 SG submit GMP for Package 3D-Multi-Purpose Center Expansion 1 1 01-May-25 01-May-25 014)d-25 106 -lUj . Pt9 Center Expansion; A4570 Owner/Design Team reviewGMPfor Package 3D-Multi-Purpose Center Expansion 5 5 02-May-25 08-May-25 08-W-25 106 6 04er%Design team rpvieyu(Ili.i of Padkage;3D;-4ukwPxgpope oerrter,Ekpa A4580 SG review comments for Package 3D-MuftFPurpose Center Expansion GMP and in 4 4 09-May-25 14-May-25 144W-25 106 a :SG reyiev{xximrrienl5 fpr Pladjag¢3Q-Multi-Purppse Centdr Eipaf*n WP alr A4590 SG resubmit Package 3D-Multi-Purpose Center Expansion GMP 1 1 15-May-25 154kAay-25 154Oct-25 106 :n :SG miubtnh Pebka$e 2D:MbftWurpoae Center Ex{fendion GMP: A4600 Owner forward Package 3D-Multi-purpose Center Expansion GMP to CORR City C 5 5 16-May-25 22-May-25 22-0c-25 106 ;6:Coiner fcowerd Pa. . 3D;Mdkl•PurposB Canter Expanabn XaMP to CoRR C A5790 CoRR City Council approval process for Package 3D-Mutti-Purpose Center Expan; 30 30 23-May-25 07-Jul-25 05-Doo-25 106 ; ; ; ; ; ; : ; : ; ; 7 I701,R ............... M/Cpundl appjovpl plooesalor�packso sD'MUMurpoas Benj A5800 SG provide CoRR list of recommended priority subcontractors for approval 1 1 23Jull 23Jun-25 26-Nov-25 110 r;SO provide t;okR list Of rpcgmnjxsr fed prlc*ikjbopnbr ctprs forj ppmyal A5810 CoRR provide approval for recommended subcontractors 5 5 24Juil 30-Jul 05-0eo-25 110 d GGORR O00%oe;apor l for"mrfneddeQ subcbntrlt4rs F1re•Codslructibn Buy-Out and Contract Administration 55 55 23-May-25 11-AM25 14-Jan-26 106 ;�►Bu"tandCobtrattAdrrlindral ______________—_1_._._..__ ---------------- A4610 SG conduct buyout meetings for preliminary scopes of work for Package 3D-Multi-I 20 20 23-May-25 20Jun-25 25TJov-25 110 : j j ; ; ; : ; j j : : : G:SG odndbct.ki It rr"e ngk fol prelirilindry dxApes,of pork foF Pedkhge 3D A4620 SG administer contracts to subcontractors for Package 3D-Multi-Purpose Center E) 10 10 08-Jul-25 21Ju145 19-0eo-25 106 :0:SG admlhlater conlial to aiibaii tr 'm for Pax9xa e' .Miltti-Purpo A4630 Subcontractors review SG subcontract for Package 3D-Multi-Purpose Center Expar 5 5 22Jul-25 28-Jul-25 30-0eo25 106 R Spbcontractora reV eN S(�aabcDntrac;for'P apkage 3'13'h Il W' x A4640 SG finalize and execute subcontracts for Package 3D-Multi-Purpose Center Explain 5 5 29Ju1-25 04,Aug-25 07-Jan-26 106 b $G finalize,an{i ejkecytgsut7coptract s;forPajd®pe$D L Myttl A4650 Mobilization of preliminary subcontractors for Package 3D-Multi-Purpose Center Ex 5 5 05-Aug-25 11-Aug-25 14-Jan-26 106 ? MobiIiaatpn df plat iron�ubcafha{.tor}for P#dx}ige 3D•IfAwn,-.T ------------------ ------------------------ -_____ __ .................................... Submittals 75 75 12-Aug-25 25-Nov-25 25-Sep-26 211 ; ;1�7 Slfbril A4660 "Submittals-Long lead materials for Package 3D-Multi-Purpose Center Expansion 75 75 12-Aug-25 25-Nov-25 25-Sep-26 211 'Submittalk-Lon$load Irnateri is for package 3D:MJIti4? Procurement 150 150 26-Nov-25 01-Jul-26 29-Apr-27 211 ProrLrahneht A4670 "Procurement-Long lead materials for Pexkege 3D-Multi-Puryose Center Fxpena 150 150 26-Nov-25 01Ju1-26 29-Apr-27 211 "Prdcubnbnt•Lbnlead mato' 3D.1-Far Eastern Folds F ; 110 t10 12-Jan-26 15-Jun-26 27-Aug-26 53 ����3Q.1+Far E8st9m Cuba 3A.1-162 Demolition of existing site elements 10 10 12-Jan-26 23-Jan-26 28-Jan-26 3 l Dpmplitipn of slid ng aka ale al 3AA-172 Underground utilities 20 20 12-Jan-26 06-Feb-26 11-Feb-26 3 o Onoergmynd,•utilltitl Start Date: 15-Jan-24 Actual Work ♦ ♦Milestone Actual Level of Effort CoRR OSP-Preconstruction Schedule Finish Date: 26-Apr-27 Remaining Work V-00111"Summary .WBS Layout-HH All Activities Data Date: 31-Oct-24 w Critical Remaining Work — Level of Effort Page 14 of 15 t r Run Date: 31-Oct-24 Admty I D Acteitity Name Ong Rem Start Finish Late Finish Total Float Q Q41 . . . . . . Dur Dur JFMAMJJ'ooMMMMMMMINJ - Al; ONqlloffidb.JJASONDJFMAM 3A.1-182 Construct fields 80 6o 09-Feb-26 01Jurr26 04-Jun-26 3 onetnp 3A.1-212 Field Irrigation 40 40 20Apr-26 15-Jun-26 27-Aug-26 53 �,��;Fled IHgjtb(r 3D.2-Middle Folds/Aux Building 230 230 09-Feb-26 04-Jan-27 21-Jan-27 13 j j : - - -- - -- -- -- - -- --JD;-Middle t 3A.1-222 Demolition of existing site elements 10 10 09-Feb-26 20-Fab-26 06-May-26 53 :e:D"'lititin 4f eidsting Me:aid manp� 3A.1-232 Underground utilities 20 20 09-Feb-26 06-Mar-26 20-May-26 53 :IIS Underg"d Utilities 3A.1-242 Construct fields 80 80 1B-May-26 OBSep-26 11 Sep-26 3 r Constarctikflds: 3A.1-262 Constmct Auxiliary Building 120 120 14-Jul-26 04-Jan-27 21-Jan-27 13 �orietrOct�u1Q _a...__.___.._.__.__ 3A.1-252 Field Irrigation 40 40 28-Jul-26 22Sep-26 23-0ct-26 23 ; ; : - -- �Figp 3rdgatgn 3D.3-Far Western Folds/Club House 260 260 07-Jan-26 13-Jan-27 01-Apr-27 56 :3U.3 Far W 3A1-272 Demolition of existing site elements 10 10 07-Jan-26 20Jan-26 08Apr-26 56 'o:D}m}Iki4n of eidstng gitrrelgrnanb 3A1-262 Underground utilities 40 40 07-Jan-26 03-Mar-26 20-May-26 56 Undergluuhd utili6esl 3/11322 Clubhouse Building Pad and Foundation 50 50 04-1 14Apr-26 02-Jul-26 56 : : : : :Clubhouse Buidng:Pad'and Founds6oh 3A.1-= Clubhouse Structure 50 50 15 r-26 24Jun-26 11 Se 26 56 r c c r AP P : : : : : : : : : : : : : : : : : : C�ubbouea iitructrDe'; 3k1362 Clubhouse MEPs 100 100 11 Jun-26 29-Oct-26 21 Jan-27 56 :o Qlubho4sejMO 3A.1342 Clubhouse Skin and Roof 80 80 25-Jun-26 15-Oct-26 21 Jan-27 66 : r 'Clybhouae$kinlenrl 3A1-292 Construct fields 80 80 28Jul-26 17-Nov-26 20-Nov-26 3 Cdnshuck fidlde: 3A.1372 Clubhouse Finishes 100 100 20-Aug-26 13Jan-27 01-Apr-27 56 � ;Clobhbuas A ............................... _ 3A.1352 Clubhouse Exterior Facade 80 80 03-Sep-26 29-Deo-26 01-Apr-27 66 � glupho�.se, 3A.1302 Field Irrigation and sod grass field 60 60 07-Oct-26 04-Jan-27 21-Jan-27 13 'o I:ielo lnr gaiionj Overall 3D 160 160 09-Seip26 26-Apr-27 29-Apr-27 3 A4690 Construct parking lots and sidewalks 100 100 09-Sep-26 01-Feb-27 04-Fab-27 3 ct A4940 Install light poles 40 40 05-Jan-27 01-Mar-27 18-Mar-27 13 Ir=� IhatAll l' A4950 Install overall landscaping and irrigation(not fields) 40 40 02-Feb-27 29-Mar-27 01-Apr-27 3 : : : : : In A4960 Install site furnishings/site signage 20 20 02-Mar-27 29-Mar-27 01-Apr-27 3 ji Install A4970 Punchlst and Closeout 20 20 30-Mar-27 26-Apr-27 29-Apr-27 3 0:Fj Start Date: 15-Jan-24 Actual Work ♦ ♦Milestone Actual Level of Effort CoRR OSP-Preconstruction Schedule Finish Date:26-Apr-27 Remaining Work T—mm/Summary WBS Layout-HH All Activities Data Date: 31-Oct-24 Critical Remaining Work r_ Level of Effort Page'5 of '5 Run Date: 31-Oct-24 TAB 8 BID/PROPOSAL . STRATEGY . .......... t, VW r i # -.. Providing the Absolute Best Construction Experience i r C� SpawGlass Contractors, Inc. 1111 Smith Road Austin, TX 78721 512-719-5251 SpawGlass.com ACORO® CERT ;ATE OF LIABILITY INSURE ;E 71/16/2025 (MM%DD'YYYV) THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE HOLDER. THIS CERTIFICATE DOES NOT AFFIRMATIVELY OR NEGATIVELY AMEND. EXTEND OR ALTER THE COVERAGE AFFORDED BY THE POLICIES BELOW. THIS CERTIFICATE OF INSURANCE DOES NOT CONSTITUTE A CONTRACT BETWEEN THE ISSUING INSURER(S). AUTHORIZED REPRESENTATIVE OR PRODUCER,AND THE CERTIFICATE HOLDER. IMPORTANT: If the certificate holder is an ADDITIONAL INSURED, the policy(ies) must have ADDITIONAL INSURED provisions or be endorsed. If SUBROGATION IS WAIVED, subject to the terms and conditions of the policy, certain policies may require an endorsement. A statement on this certificate does not confer rights to the certificate holder in lieu of such endorsement(s). PRODUCER CONTACT NAME: Mlrta TameZ Adams Risk Management Services, LLCPHONE _ FAX Adams Insurance Service, Inc. (A�c No Eril:(713)869-8346 (A C No):__713 869-9144 1 111 North Loop W, Suite 600 ADD IESS: mtamez@adamsins.com Houston TX 77008 INSURER(S)AFFORDING COVERAGE NAIL* INSURER A:American Contractors Insurance Co.RRG 12300 INSURED SGADMIN-01 INSURER e:ACIG Insurance Company 19984 SpawGlass Contractors, Inc. 1111 Smith Road INSURER C:Valley Forge Insurance Company 20508 Austin, TX 78721 INSURER D:The Continental Insurance Company 35289 INSURER E:Travelers Lloyds Insurance Company 41262 INSURER F:XL Insurance America,Inc. 24554 COVERAGES CERTIFICATE NUMBER:1257883251 REVISION NUMBER: THIS IS TO CERTIFY THAT THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD INDICATED. NOTWITHSTANDING ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS CERTIFICATE MAY BE ISSUED OR MAY PERTAIN, THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS, EXCLUSIONS AND CONDITIONS OF SUCH POLICIES LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS. INSR ADDLTYPE OF INSURANCE INSI SUER POLICY NUMBER MM/DDPOLICW POLICY EXP LTR YFY MM DO VYYV LIMITS A X COMMERCIAL GENERAL LIABILITY y Y GL24ABC00046 6/1/2024 6/1/2025 EACH OCCURRENCE $10,000,000 MA EO R Eli CLAIMS MADE X OCCUR PREMISES Ea occurrence $100,000 r _ MED EXP(Any one person) $5,000 PERSONAL 8 ADV INJURY $10,000,000 GEN'L AGGREGATE LIMIT APPLIES PER I GENERAL AGGREGATE $10,000,000 POLICY U JPEC LOG PRODUCTS-COMP/OP AGG $10,000,000 OTHER: $ C AUTOMOBILE LIABILITY y v BUA7033775896 6/1/2024 6/1/2025 EOMaB`INEED SINGLE LIMIT $5,000,000 X ANY AUTO BODILY INJURY(Per person) $ OWNED SCHEDULED AUTOS ONLY AUTOS BODILY INJURY(Per accident) $ X HIRED X NON-OWNED j PROPERTY DAMAGE $ , AUTOS ONLY AUTOS ONLY I Per accident S D UMBRELLA LIAB X_ OCCUR y y CUE7034067095 6/1/2024 6/1/2025 EACH OCCURRENCE $10,000,000 X EXCESS LIAB CLAIMS-MADE AGGREGATE $10,000,000 i _ DED RETENTION$ $ B WORKERS COMPENSATION Y WCA000008324 6/1/2024 6/1/2025 X AND EMPLOYERS'LIABILITY Y/N STATUTE ER 1 ANYPROPRIETOR/PARTNER/EXECUTIVE INN A E.L.EACH ACCIDENT $1,000,000 OFFICER/MEMBER EXCLUDED? ` (Mandatory In NH) E.L.DISEASE-EA EMPLOYEE $1,000,000 If as,descr be under DESCRIPTION OF OPERATIONS below E.L.DISEASE-POLICY LIMIT $1,000,000 E CONTRACTORS EQUIPMENT QT-630-7625B35-0-TLC-24 6/1/2024 6/1/2025 LEASED/RENTED SEE BELOW F BUILDERS RISK(BROAD FORM) US00116369CA24A 6/1/2024 6/1/2025 PROJECT AMOUNT <$10,000,000 SEE PAGE 2. DESCRIPTION OF OPERATIONS/LOCATIONS/VEHICLES (ACORD 101,Additional Remarks Schedule,may be attached it more space is required) Contractors Equipment Continued: Per Item:$1,500,000 Aggregate:$3,000,000 The Automobile policy includes the following endorsements: 1)CNA63359-Blanket Additional Insured as required by written contract executed prior to the bodily injury or property damage.2)CNA63359-Blanket Waiver of Subrogation as required by written contract executed prior to the bodily injury or property damage.3)CNA63359&CNA71527-Primary Non-Contributory basis only when required by a written contract prior to Accident or Loss.4)CNA68021 -Notice of Cancellation-30 days blanket as required by written contract. See Attached... CERTIFICATE HOLDER CANCELLATION SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE THE EXPIRATION DATE THEREOF, NOTICE WILL BE DELIVERED IN ACCORDANCE WITH THE POLICY PROVISIONS. City of Round Rock 221 East Main Street Round Rock TX 78644 AUTHORIZED REPRESENTATIVE ©1988-2015 ACORD CORPORATION. All rights reserved. ACORD 25(2016 03) The ACORD name and logo are registered marks of ACORD AGENCY CUSTOMER ID: SG< 1-01 LOC#: AC V ADDITIONAL REMARKS SCHEDULE Page 1 of 1 AGENCY NAMED INSURED Adams Risk Management Services, LLC SpawGlass Contractors, Inc. 1111 Smith Road POLICY NUMBER Austin,TX 78721 CARRIER NAIC CODE EFFECTIVE DATE: ADDITIONAL REMARKS THIS ADDITIONAL REMARKS FORM IS A SCHEDULE TO ACORD FORM, FORM NUMBER: 25 FORM TITLE: CERTIFICATE OF LIABILITY INSURANCE The General Liability policy includes the following endorsements: 1) 1170-Additional Insured-Automatic Status as required by Contract-Blanket-Who is an insured is amended to include as Additional Insured any person or organization when you have agreed in a written contract that such person or organization be added as an additional insured on your policy.The endorsement also provides for the coverage to apply on a primary and non-contributory basis for ongoing and completed operations when required by written contract.2)205-Blanket Waiver of Subrogation when required in a written contract or agreement.3)336- Notice of Cancellation,Nonrenewal or Material Change-30 days blanket as required by written contract.4)9-Aggregate Limits of insurance Per Project. The Workers'Compensation policy includes the following endorsements: 1)WC990304-Waiver of Subrogation-Blanket waiver for any person or organization for whom the named insured has agreed in a written contract to furnish the waiver.2)WC420601 -Notice of Cancellation-30 days blanket as required by written contract. The Umbrella/Excess Liability policy applies in excess and follows form of the underlying General Liability,Automobile Liability and Employers Liability policies above including the terms of any additional insured,waiver of subrogation and 30 day notice of cancellation endorsements.The policy follows the terms and conditions of such underlying policies unless they are inconsistent with the terms of the policy. The Equipment Floater policy includes a Blanket Automatic Loss Payee Endorsement CMU618 that provides Loss Payee status to the Certificate Holder only when there is a written contract between the Named Insured and the Certificate Holder that requires such status. Re.Project Old Settlers Park Buildout,Package 3C—Rec Center-EARTHWORK 60%DD Drawings,3300 E Palm Valley Blvd Round Rock,TX 78665.Project Amount$5,287,121 ACORD 101 (2008/01) ©2008 ACORD CORPORATION. All rights reserved. The ACORD name and logo are registered marks of ACORD ADDIT IAL INSURED - AUTOMATIC kTUS 170 AS F,._„1UIRED BY CONTRACT - BLk...ET This endorsement modifies insurance provided under the following: COMMERCIAL GENERAL LIABILITY COVERAGE PART SCHEDULE Any person or organization that you are required by written contract to include as an additional insured on this policy if the contract is executed prior to the loss. A. Section II,Who Is An Insured is amended to include as an additional insured any person or organization shown in the above SCHEDULE (called additional insured), but only with respect to liability for"bodily injury","property damage"or"personal and advertising injury"arising out of your premises or your operations for the additional insured, and only to the extent and for the minimum limits required in the written contract. B. The insurance provided to the additional insured is subject to the following limitations: 1. Unless a written contract specifically requires additional insured coverage for your completed operations,this insurance does not apply to"bodily injury"or"property damage"occurring after"your work"for the additional insured has been completed or after that portion of .your work"out of which the"bodily injury"or"property damage"arises has been put to its intended use by any person or organization, whichever occurs first. 2. Unless specifically required by written contract,this insurance provides additional insured coverage only for liability for"bodily injury", "property damage"or"personal and advertising injury"to the extent caused by the named insured's acts or omissions or the acts or omissions of those acting on the named insured's behalf. 3. This insurance does not apply to"bodily injury","property damage"or"personal and advertising injury"for which the additional insured is obligated to pay damages by reason of the assumption of liability in a contract or agreement except to the extent that the additional insured would have been obligated to pay such damages in the absence of the contract or agreement. 4. This insurance does not apply to"bodily injury", "property damage"or"personal and advertising injury"arising out of the rendering or failure to render any professional services by any insured or on any insured's behalf,including: a) The preparing, approving or failing to prepare or approve maps, shop drawings, opinions, reports, surveys, field orders,change orders,drawings or specifications;or b) Supervisory,inspection,architectural,or engineering services. This exclusion applies even if the claims against any insured allege negligence or other wrongdoing in the supervision, hiring,employment,training or monitoring of others by that insured,if the"occurrence"which caused the"bodily injury" or"property damage", or the offense which caused the"personal and advertising injury", involved the rendering of, or the failure to render,any professional architectural,engineering or surveying services. 5. This endorsement shall not apply to a person or organization if any other additional insured endorsement attached to this policy specifically applies to that person or organization. 6. The insurance afforded herein only applies to the extent permitted by applicable state law, including statutes governing additional insured coverage in the construction industry. 7. The insurance afforded to the additional insured shall not exceed the minimum limits required in the written contract. C. In no event shall the insurance provided to the additional insured exceed the minimum coverage required by the written contract, including but not limited to minimum limits,minimum scope of coverage,or minimum duration of coverage. If a written contract or agreement requires that additional insured status be provided by the use of specified edition dates of the ISO CG2010 and/or CG2037,then the terms of that endorsement are incorporated into this endorsement as respects such additional insured and shall supersede the coverage grant and limitations in Sections A. and B. of this endorsement. In the event that CG2010 and/or CG2037 are required but no edition dates are specified,the 04/13 editions shall apply. D. This insurance is excess to any other insurance, whether primary, excess, contingent or on any other basis, available to the additional insured unless a written contract requires that this insurance be primary or primary and non-contributing. However,this insurance is always excess to other insurance,whether primary, excess,contingent or on any other basis,when the additional insured has been added to the other insurance as an additional insured. Nothing herein contained shall be held to vary,alter,waive or extend any of the terms,conditions, provisions,agreements or limitations of the mentioned Policy,other than as above stated. This endorsement changes the policy to which it is attached and is effective on the date issued unless otherwise stated. (The information below is required only when this endorsement is issued subsequent to preparation of the policy.) Policy Effective: 6/1/2024 Policy No.: GL24ABC00046 Insured: SpawGlass Contractors, Inc., SpawGlass Construction Corp., SpawGlass Civil Construction, Inc., Westland Equipment and Supplies, LLC Insurance Company: American Contractors Insurance Company Risk Retention Group 205 WAIVER OF TRANSFER OF RIGHTS OF RECOVERY AGAINST OTHERS TO US This endorsement modifies insurance provided under the following: COMMERCIAL GENERAL LIABILITY COVERAGE PART SCHEDULE Name of Persons or Organization(s): Any person or organization for whom you have agreed by written contract to furnish this waiver. Section IV—Commercial General Liability Conditions, 14. Transfer of Rights of Recovery Against Others to Us Condition is amended by the addition of the following: We waive any right of recovery we may have against the person or organization shown in the Schedule above because of payments we make for injury or damage arising out of your ongoing operations or"your work" done under a contract with that person or organization and included in the "products-completed operations hazard". This waiver applies only to the person or organization shown in the Schedule above. Nothing herein contained shall be held to vary, alter, waive or extend any of the terms, conditions, provisions, agreements or limitations of the mentioned Policy, other than as above stated. This endorsement changes the policy to which it is attached and is effective on the date issued unless otherwise stated. (The information below is required only when this endorsement is issued subsequent to preparation of the policy.) Policy Effective: 6/1/2024 Policy No.: GL24ABC00046 Insured: SpawGlass Contractors, Inc., SpawGlass Construction Corp., SpawGlass Civil Construction, Inc.,Westland Equipment and Supplies, LLC Insurance Company: American Contractors Insurance Company Risk Retention Group 336 NOTICE OF CANCELLATION, NONRENEWAL OR MATERIAL CHANGE - CERTIFICATE HOLDERS This endorsement modifies insurance provided under the following: COMMERCIAL GENERAL LIABILITY COVERAGE PART The certificate of insurance holders shown in the schedule below have requested that they receive written notice of cancellation, nonrenewal or material change with respect to this policy. If we decide to cancel, nonrenew or make a material change to this policy, we agree to mail or deliver sixty(60) days advance written notice to the certificate of insurance holders shown in the schedule below. However, if we are cancelling or nonrenewing due to nonpayment of premium, we will only provide the certificate of insurance holders shown in the schedule below with ten (10) days advance written notice. The notice of cancellation, nonrenewal or material change will be mailed to the addresses provided to us by the certificate of insurance issuer. Proof of mailing will be considered sufficient proof of our good faith attempt to provide notice of cancellation, nonrenewal or material change to the certificate of insurance holders shown in the schedule below. SCHEDULE All certificate of insurance holders where written notice of cancellation, nonrenewal or material change to this policy is required by written contract, permit or agreement with the Named Insured. Nothing herein contained shall be held to vary, alter, waive or extend any of the terms, conditions, provisions, agreements or limitations of the mentioned Policy, other than as above stated. This endorsement changes the policy to which it is attached and is effective on the date issued unless otherwise stated. (The information below is required only when this endorsement is issued subsequent to preparation of the policy.) Policy Effective: 6/1/2024 Policy No.: GL24ABC00046 Insured: SpawGlass Contractors, Inc., SpawGlass Construction Corp., SpawGlass Civil Construction, Inc., Westland Equipment and Supplies, LLC Insurance Company: American Contractors Insurance Company Risk Retention Group 9 AGGREGATE LIMITS OF INSURANCE (PER PROJECT) This endorsement modifies insurance provided under the following: COMMERCIAL GENERAL LIABILITY COVERAGE PART It is hereby understood and agreed the General Aggregate Limit under Section III, Limits of Insurance of the Coverage Form applies separately to each of your projects away from premises owned by or rented to you. Nothing herein contained shall be held to vary, alter, waive or extend any of the terms, conditions, provisions, agreements or limitations of the mentioned Policy, other than as above stated. This endorsement changes the policy to which it is attached and is effective on the date issued unless otherwise stated. (The information below is required only when this endorsement is issued subsequent to preparation of the policy.) Policy Effective: 6/1/2024 Policy No.: GL24ABC00046 Insured: SpawGlass Contractors, Inc., SpawGlass Construction Corp., SpawGlass Civil Construction, Inc., Westland Equipment and Supplies, LLC Insurance Company: American Contractors Insurance Company Risk Retention Group CNASpawGIassBusiness Auto Policy Contractors,Inc.,SpawGlass Construction Corp., SpawGlass Civil Construction,Inc.,Westland Equipment and Supplies,LLC CONTRACTORS EXTENDED COVERAGE ENDORSEMENT • PLUS THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY. This endorsement modifies insurance provided under the following: BUSINESS AUTO COVERAGE FORM I. LIABILITY COVERAGE A. Who Is An Insured The following is added to Section 11, Paragraph A.1., Who Is An Insured: 1. a. Any incorporated entity of which the Named Insured owns a majority of the voting stock on the date of inception of this Coverage Form; provided that, b. The insurance afforded by this provision A.1. does not apply to any such entity that is an insured under any other liability "policy" providing auto coverage. 2. Any organization you newly acquire or form, other than a limited liability company, partnership or joint venture, and over which you maintain majority ownership interest. The insurance afforded by this provision A.2.: a. Is effective on the acquisition or formation date, and is afforded only until the end of the policy period of this Coverage Form, or the next anniversary of its inception date, whichever is earlier. b. Does not apply to: (1) Bodily injury or property damage caused by an accident that occurred before you acquired or formed the organization; or (2) Any such organization that is an insured under any other liability "policy" providing auto coverage. 3O. 4ny person or organization that you are required by a written contract to name as an additional Insured is an insured but only with respect to their legal liability for acts or omissions of a person, who qualifies as an insured under SECTION II — WHO IS AN INSURED and for whom Liability Coverage is afforded under this policy. If required by written contract, this insurance will be primary and non-contributory to insurance on which the additional insured is a Named Insured. 4. An employee of yours is an insured while operating an auto hired or rented under a contract or agreement in that employee's name, with your permission, while performing duties related to the conduct of your business. "Policy", as used in this provision A. Who Is An Insured, includes those policies that were in force on the inception date of this Coverage Form but: 1. Which are no longer in force; or 2. Whose limits have been exhausted. B. Bail Bonds and Loss of Earnings Section 11, Paragraphs A.2. (2) and A.2. (4) are revised as follows: 1. In a.(2), the limit for the cost of bail bonds is changed from $2,000 to $5,000; and 2. In a.(4), the limit for the loss of earnings is changed from $250 to $500 a day. Form No: CNA63359XX (04-2012) Policy No:BUA 7033775896 Underwriting Company: Valley Forge Insurance Company Policy Effective Date: 06/01/2024 m Copyright CNA All Rights Reserved. Includes copyrighted material of the C/VA Business Auto Policy Policy Endorsement C. Fellow Employee Section II, Paragraph B.5 does not apply. Such coverage as is afforded by this provision C. is excess over any other collectible insurance. II. PHYSICAL DAMAGE COVERAGE A. Glass Breakage - Hitting A Bird Or Animal - Falling Objects Or Missiles The following is added to Section III, Paragraph A.3.: With respect to any covered auto, any deductible shown in the Declarations will not apply to glass breakage if such glass is repaired, in a manner acceptable to us, rather than replaced. B. Transportation Expenses Section III, Paragraph A.4.a. is revised, with respect to transportation expense incurred by you, to provide: a. $60 per day, in lieu of $20; subject to b. $1,800 maximum, in lieu of $600. C. Loss of Use Expenses Section III, Paragraph A.4.b. is revised, with respect to loss of use expenses incurred by you, to provide: a. $1,000 maximum, in lieu of $600. D. Hired "Autos" The following is added to Section Ill. Paragraph A.: 5. Hired "Autos" If Physical Damage coverage is provided under this policy, and such coverage does not extend to Hired Autos, then Physical Damage coverage is extended to: a. Any covered auto you lease, hire, rent or borrow without a driver; and b. Any covered auto hired or rented by your employee without a driver, under a contract in that individual employee's name, with your permission, while performing duties related to the conduct of your business. c. The most we will pay for any one accident or loss is the actual cash value, cost of repair, cost of replacement or $75,000, whichever is less, minus a $500 deductible for each covered auto. No deductible applies to loss caused by fire or lightning. d. The physical damage coverage as is provided by this provision is equal to the physical damage coverage(s) provided on your owned autos. e. Such physical damage coverage for hired autos will: (1) Include loss of use, provided it is the consequence of an accident for which the Named Insured is legally liable, and as a result of which a monetary loss is sustained by the leasing or rental concern. (2) Such coverage as is provided by this provision will be subject to a limit of $750 per accident. E. Airbag Coverage The following is added to Section III, Paragraph B.3.: The accidental discharge of an airbag shall not be considered mechanical breakdown. Form No: CNA63359XX (04-2012) Policy No:BUA 7033775896 Underwriting Company: Valley Forge Insurance Company Policy Effective Date: 06/01/2024 Co PY 9 ri ht CNA All Rights Reserved. Includes copyrighted material of the -- —___— 9 CNA Business Auto Policy Policy Endorsement F. Electronic Equipment Section III, Paragraphs B.4.c and B.4.d. are deleted and replaced by the following: c. Physical Damage Coverage on a covered auto also applies to loss to any permanently installed electronic equipment including its antennas and other accessories d. A $100 per occurrence deductible applies to the coverage provided by this provision. G. Diminution In Value The following is added to Section III, Paragraph B.6.: Subject to the following, the diminution in value exclusion does not apply to: a. Any covered auto of the private passenger type you lease, hire, rent or borrow, without a driver for a period of 30 days or less, while performing duties related to the conduct of your business; and b. Any covered auto of the private passenger type hired or rented by your employee without a driver for a period of 30 days or less, under a contract in that individual employee's name, with your permission, while performing duties related to the conduct of your business. c. Such coverage as is provided by this provision is limited to a diminution in value loss arising directly out of accidental damage and not as a result of the failure to make repairs; faulty or incomplete maintenance or repairs; or the installation of substandard parts. d. The most we will pay for loss to a covered auto in any one accident is the lesser of: (1) $5,000; or (2) 20% of the auto's actual cash value (ACV). Ill. Drive Other Car Coverage — Executive Officers The following is added to Sections II and III: 1. Any auto you don't own, hire or borrow is a covered auto for Liability Coverage while being used by, and for Physical Damage Coverage while in the care, custody or control of, any of your "executive officers", except: a. An auto owned by that "executive officer" or a member of that person's household; or b. An auto used by that "executive officer" while working in a business of selling, servicing, repairing or parking autos. Such Liability and/or Physical Damage Coverage as is afforded by this provision. (1) Equal to the greatest of those coverages afforded any covered auto; and (2) Excess over any other collectible insurance. 2. For purposes of this provision, "executive officer" means a person holding any of the officer positions created by your charter, constitution, by-laws or any other similar governing document, and, while a resident of the same household, includes that person's spouse. Such "executive officers" are insureds while using a covered auto described in this provision. IV. BUSINESS AUTO CONDITIONS A. Duties In The Event Of Accident, Claim, Suit Or Loss The following is added to Section IV, Paragraph A.2.a.: Form No: CNA63359XX (04-2012) Policy No:BUA 7033775896 Underwriting Company: Valley Forge Insurance Company Policy Effective Date: 06/01/2024 m Copyright CNA All Rights Reserved. Includes copyrighted material of the CNA Business Auto Policy Policv Endorsement (4) Your employees may know of an accident or loss. This will not mean that you have such knowledge, unless such accident or loss is known to you or if you are not an individual, to any of your executive officers or partners or your insurance manager. The following is added to Section IV, Paragraph A.2.b.: (6) Your employees may know of documents received concerning a claim or suit. This will not mean that you have such knowledge, unless receipt of such documents is known to you or if you are cutive officers or partners or your insurance manager. B. Transfer Of Rights Of Recovery Against Others To Us e raph A.S. Transfer Of Rights Of Recovery Against Others To Us: We waive any right of recovery we may have, because of payments we make for injury or damage, against any person or organization for whom or which you are required by written contract or agreement to obtain this waiver from us. This injury or damage must arise out of your activities under a contract with that person or organization. You must agree to that requirement prior to an accident or loss. C. Concealment, Misrepresentation or Fraud The following is added to Section IV, Paragraph B.2.: Your failure to disclose all hazards existing on the date of inception of this Coverage Form shall not spect to the coverage afforded provided such failure or omission is not intentional. D. Other Insurance ed to to IV, Paragraph B.S.: Regardless of the provisions of Paragraphs 5.a. and 5.d. above, the coverage provided by this policy shall be on a primary non-contributory basis. This provision is applicable only when required by a written contract. That written contract must have been entered into prior to Accident or Loss. E. Policy Period, Coverage Territory Section IV, Paragraph B. 7.(5).(a). is revised to provide: a. 45 days of coverage in lieu of 30 days. V. DEFINITIONS Section V. paragraph C. is deleted and replaced by the following: Bodily injury means bodily injury, sickness or disease sustained by a person, including mental anguish, mental injury or death resulting from any of these. Form No: CNA63359XX (04-2012) Policy No:BUA 7033775896 Underwriting Company: Valley Forge Insurance Company Policy Effective Date: 06/01/2024 Copyright CNA All Rights Reserved. Includes copyrighted material of the SNA Business Auto Policy Policy Endorsement NOTICEOF • TO CERTIFICATEHOLDERS It is understood and agreed that: If you have agreed under written contract to provide notice of cancellation to a party to whom the Agent of Record has issued a Certificate of Insurance, and if we cancel a policy term described on that Certificate of Insurance for any reason other than nonpayment of premium, then notice of cancellation will be provided to such Certificateholders at least 30 days in advance of the date cancellation is effective. If notice is mailed, then proof of mailing to the last known mailing address of the Certificateholder on file with the Agent of Record will be sufficient to prove notice. Any failure by us to notify such persons or organizations will not extend or invalidate such cancellation, or impose any liability or obligation upon us or the Agent of Record. All other terms and conditions of the policy remain unchanged This endorsement, which forms a part of and is for attachment to the policy issued by the designated Insurers, takes effect on the Policy Effective date of said policy at the hour stated in said policy, unless another effective date (the Endorsement Effective Date) is shown below, and expires concurrently with said policy. SpawGlass Contractors,Inc.,SpawGlass Construction Corp., SpawGlass Civil Construction,Inc.,Westland Equipment and Supplies,LLC Form No: CNA68021 XX (02-2013) Policy No:BUA 7033775896 Underwriting Company: Valley Forge Insurance Company Policy Effective Date: 06/01/2024 m Copyright CNA All Rights Reserved. CNA Business Auto Policy Policy Endorsement ADDITIONAL INSURED - PRIMARY AND NON-CONTRIBUTORY It is understood and agreed that this endorsement amends the BUSINESS AUTO COVERAGE FORM as follows: SCHEDULE Name of Additional Insured Person Or Organization ANY PERSON OR ORGANIZATION THAT YOU ARE REQUIRED BY WRITTEN CONTRACT OR WRITTEN AGREEMENT TO NAME AS AN ADDITIONAL INSURED 1. In conformance with paragraph A.1.c. of Who Is An Insured of Section II - LIABILITY COVERAGE, the person or organization scheduled above is an insured under this policy. 2. The insurance afforded to the additional insured under this policy will apply on a primary and non-contributory basis if you have committed it to be so in a written contract or written agreement executed prior to the date of the "accident" for which the additional insured seeks coverage under this policy. All other terms and conditions of the policy remain unchanged This endorsement, which forms a part of and is for attachment to the policy issued by the designated Insurers, takes effect on the Policy Effective date of said policy at the hour stated in said policy, unless another effective date (the Endorsement Effective Date) is shown below, and expires concurrently with said policy. Form No: CNA71527XX (10-2012) Policy No:BUA 7033775896 Underwriting Company: Valley Forge Insurance Company Policy Effective Date: 06/01/2024 Insured:SpawGlass Contractors,Inc.,SpawGlass Construction Corp., SpawGlass Civil Construction,Inc.,Westland Equipment and Supplies,LLC ID Copyright CNA All Rights Reserved. TEXAS WORKERS COMPENSA _ 4 AND EMPLOYERS LIABILITY PO_._ r WC 99 03 04 (Ed. 04-07) WAIVER OF OUR RIGHT TO RECOVER FROM OTHERS ENDORSEMENT This endorsement applies only to the insurance provided by the policy because Texas is shown in Item 3.A. of the Information Page. We have the right to recover our payments from anyone liable for an injury covered by this policy. We will not enforce our right against the person or organization named in the Schedule, but this waiver applies only with respect to bodily injury arising out of the operations described in the Schedule where you are required by a written contract to obtain this waiver. This waiver does not extend to the statutory right of reimbursement from a claimant who recovers any amount under Section 417.002 of the Texas Labor Code. This endorsement shall not operate directly or indirectly to benefit anyone not named in the Schedule. The premium for this endorsement is shown in the Schedule. Schedule 1. ( ) Specific Waiver Name of person organization ( X ) Blanket Waiver Any person or organization for whom the Named Insured has agreed by written contract to furnish this waiver. This waiver does not extend to the statutory right of reimbursement under Section 417.002 of the Texas Labor Code. 2. Operations: CONSTRUCTION AND RELATED CONSTRUCTION RELATED WORK ALL TEXAS OPERATIONS 3. Premium: The premium charge of this endorsement shall be 2 percent of the premium developed on payroll in connection with work performed for the above person(s)or organization(s)arising out of the operations described. 4. Minimum Premium: $0 5. Advance Premium: $0 This endorsement changes the policy to which it is attached and is effective on the date issued unless otherwise stated. (The information below is required only when this endorsement is issued subsequent to preparation of the policy.) Endorsement Effective: Same as Policy Effective Date unless otherwise indicated above. Policy Effective Date: 6/1/2024 Policy No. WCA000008324 Insured SpawGlass Contractors, Inc., SpawGlass Construction Corp., SpawGlass Civil Construction, Inc., Westland Equipment and Supplies, LLC Carrier Name/Code: ACIG Insurance Company WC 99 03 04 (Ed. 04-07) WORKERS COMPENSATION AND EMPLOYERS LIABILITY INSURANCE POLICY WC 42 06 01 (Ed. 03-13) TEXAS NOTICE OF MATERIAL CHANGE ENDORSEMENT This endorsement applies only to the insurance provided by the policy because Texas is shown in Item 3.A. of the Information Page. In the event of cancelation or other material change of the policy, we will mail advance notice to the person or organization named in the Schedule. The number of days advance notice is shown in the Schedule. This endorsement shall not operate directly or indirectly to benefit anyone not named in the Schedule. Schedule 1 . Number of days advance notice: 60 days. However, in the case of cancellation or nonrenewal due to nonpayment of premium, only 10 days advance notice will be provided. 2. Notice will be mailed to: All certificate holders where written notice of cancellation, nonrenewal or material change to this policy is required by written contract, permit or agreement with the Named Insured. The notice will be mailed to the addresses provided to us by the certificate of insurance issuer. Proof of mailing will be considered sufficient proof of our good faith attempt to provide written notice. This endorsement changes the policy to which it is attached and is effective on the date issued unless otherwise stated. (The information below is required only when this endorsement is issued subsequent to preparation of the policy.) Endorsement Effective 06/01/2024 Policy No. WCA000008324 Insured SpawGlass Contractors,Inc. , SpawGlass Construction Corp. , Premium$ SpawGlass Civil Construction, Inc. , Westland Equipment and Supplies, LLC Insurance Company ACIG Insurance Company WC 42 06 01 Wolters Kluwer Financial Services I Uniform Forms Page 1 of 1 (Ed. 03-13) TM --)MMERCIAL INLAND MARINE THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY. BLANKET LOSS PAYEES This endorsement modifies insurance provided under the COMMERCIAL INLAND MARINE COVERAGE PART The following is added to Section E — ADDITIONAL b. Pay any claim for loss or damage jointly to you COVERAGE CONDITIONS: and the Loss Payee as your interests may Loss Payable Provision appear. In the event of a Covered Cause of Loss to Covered This endorsement applies to all Covered Property for Property in which both you and a Loss Payee share which a Loss Payee is on file with us or your an insurable interest, we will: insurance agent or insurance broker. a. Adjust the loss or damage with you; and SpawGlass Contractors, Inc., SpawGlass Construction Corp., SpawGlass Civil Construction, Inc., Westland Equipment and Supplies, LLC Travelers Property&Casualty Co. Policy No. QT-630-7625635-0-TLC-24 CM U6 18 05 21 ©2021 The Travelers Indemnity Company Page 1 of 1 Includes copyrighted material of Insurance Services Office, Inc.with its permission. C H U B B` Surety o + 908 903.3485 202B Halls Mill Road,PO Box 1650 F +908.903.3656 Whitehouse Station.N108889-1650 Federal Insurance Company Liberty Mutual Insurance Company AIA Document A312 Performance Bond K41875616(Federal) 58S218527(Liberty Mutual) Any singular reference to Contractor,Surety.Owner or other party shall be considered plural where applicable. CONTRACTOR(Name and Address): SURETY(Name and Principal Place of Business): SpawGlass Contractors, Inc. Federal Insurance Company(IN) 1 1 I 1 Smith Road Liberty Mutual Insurance Company(MA) Austin, Texas 78721 OWNER(Name and Address): City of Round Rock 221 East Main Street Round Rock, TX 78644 CONSTRUCTION CONTRACT Date: ZD day of 2025 Amount:$5,287,121.00 Five Million Two Hundred Eighty Seven Thousand One Hundred Twenty One& 00/100 Dollars Description (Name and Location): Old Settler's Park Build Out-60%GMP for Rec Center-EARTHWORK BOND Date(Not earlier than Construction Contract Date): 70 day of I'I k ,2024 AMOUNT: $5,287,121.00 Five Million Two Hundred Eighty Seven Thousand One Hundred Twenty One& 00/100 Dollars Modifications to this Bond: ® None ❑ See Page 3 CONTRACTORSAS SURETY PRINCIPAL Company: _ (Corporate Seal) SpawGlass Contractors,I % Company: (Corporate Seal) Federal Insurance C ny Liberty Mutual sur cc i Signature: Signature: Name and tie: vi n Name and Tit John .Prince Pr ' ent -Austin Division Attorney-in-Fact (Any additional signatures appear on page 3) (FOR INFORM=ITION ONLY—Name, Address and Telephone) AGENT or BROKER: Adams Instuance Service OWNER'S REPRESENTATIVE(Architect,Engineer or other parry): 427 W 201h.Suite 500 Houston,TX 77008 713-869-8346 Printed in cooperation with the American Institute of Architects(AIA)by Chubb. The language in this document conforms exactly to the language used in AIA Document A312 December 1984 edition. Third Printing.March 1987. Form 15-02-0279-FED(Rev 11/16) A312-1984 1 I The Contractor and the Surety,jointly and severally, performance and payment bonds executed by a bind themselves, their heirs, executors, administrators, qualified surety equivalent to the bonds issued on the successors and assigns to the Owner for the performance of Construction Contract,and pay to the Owner the amount the Construction Contract,which is incorporated herein by of damages as described in Paragraph 6 in excess of the reference. Balance of the Contract Price incurred by the Owner 2 If the Contractor performs the Construction Contract, resulting from the Contractor's default;or the Surety and the Contractor shall have no obligation under 4.4 Waive its right to perform and complete, arrange this Bond,except to participate in conferences as provided for completion, or obtain a new contractor and with in Sub-paragraph 3.1. reasonable promptness under the circumstances: 3 If there is no Owner Default, the Surety's obligation .1 After investigation,determine the amount for under this Bond shall arise after: which it may be liable to the Owner and,as soon 3.1 The Owner has notified the Contractor and the as practicable after the amount is determined, Surety at its address described in Paragraph 10 below tender payment therefor to the Owner;or that the Owner is considering declaring a Contractor .2 Deny liability in whole or in part and notify the Default and has requested and attempted to arrange a Owner citing reasons therefor. conference with the Contractor and the Surety to be held 5 If the Surety does not proceed as provided in Paragraph not later than fifteen days after receipt of such notice 4 with reasonable promptness,the Surety shall be deemed to discuss methods of performing the Construction to be in default on this Bond fifteen days after receipt of Contract. if the Owner,the Contractor and the Surety an additional written notice from the Owner to the Surety agree, the Contractor shall be allowed a reasonable demanding that the Surety perform its obligations under this time to perform the Construction Contract, but such Bond,and the Owner shall be entitled to enforce any remedy an agreement shall not waive the Owner's right,if any, available to the Owner.If the Surety proceeds as provided subsequently to declare a Contractor Default;and in Subparagraph 4.4, and the Owner refuses the payment 3.2 The Owner has declared a Contractor Default and tendered or the Surety has denied liability, in whole or in formally terminated the Contractor's right to complete part, without further notice the Owner shall be entitled to the contract. Such Contractor Default shall not be enforce any remedy available to the Owner. declared earlier than twenty days after the Contractor 6 After the Owner has terminated the Contractor's right and the Surety have received notice as provided in to complete the Construction Contract, and if the Surety Subparagraph 3.1;and elects to act under Subparagraph 4.1, 4.2, or 4.3 above, 3.3 The Owner has agreed to pay the Balance of the then the responsibilities of the Surety to the Owner shall Contract Price to the Surety in accordance with the terms not be greater than those of the Contractor under the of the Construction Contract or to a contractor selected Construction Contract,and the responsibilities of the Owner to perform the Construction Contract in accordance with to the Surety shall not be greater than those of the Owner the terms of the contract with the Owner. under the Construction Contract. To the limit of the amount of this Bond, but subject to commitment by the Owner 4 When the Owner has satisfied the conditions of of the Balance of the Contract Price to mitigation of costs Paragraph 3,the Surety shall promptly and at the Surety's and damages on the Construction Contract, the Surety is expense take one of the following actions: obligated without duplication for: 4.1 Arrange for the Contractor, with consent of the 6.1 The responsibilities of the Contractor for correction Owner, to perform and complete the Construction of defective work and completion of the Construction Contract;or Contract; 4.2 Undertake to perform and complete the 6.2 Additionallegal,design professional and delay costs Construction Contract itself, through its agents or resulting from the Contractor's Default, and resulting through independent contractors;or from the actions or failure to act of the Surety under 4.3 Obtain bids or negotiated proposals from qualified Paragraph 4;and contractors acceptable to the Owner for a contract 6.3 Liquidated damages,or if no liquidated damages are for performance and completion of the Construction specified Contract, arrange for a contract to be prepared for fied in the Construction Contract,actual damages execution by the Owner and the contractor selected caused by delayed performance or non-performance of with the Owner's concurrence,to be secured with the Contractor. Printed in cooperation with the American Institute of Architects(AIA)by Chubb.The language in this document conforms exactly to the language used in AIA Document A312 December 1984 edition,Third Printing,March 1987. Form 15-02-0279-FED(Rev.11/16) A312-19842 7 The Surety shall not be liable to the Owner or others be deemed deleted herefrom and provisions conforming to for obligations of the Contractor that are unrelated to the such statutory or other legal requirement shall be deemed Construction Contract, and the Balance of the Contract incorporated herein. The intent is that this Bond shall be Price shall not be reduced or set off on account of any such construed as a statutory bond and not as a common law bond. unrelated obligations. No right of action shall accrue on this 12 DEFINITIONS Bond to any person or entity other than the Owner or its heirs,executors,administrators or successors. 12.1 Balance of the Contract Price:The total amount payable by the Owner to the Contractor under the 8 The surety hereby waives notice of any change,including Construction Contract after all proper adjustments have changes of time,to the Construction Contract or to related been made, including allowance to the Contractor of subcontractors,purchase orders and other obligations. any amounts received or to be received by the owner in 9 Any proceeding,legal or equitable,under this Bond may settlement of insurance or other claims for damages to be instituted in any court of competent jurisdiction in the which the Contractor is entitled,reduced by all valid and location in which the work or part of the work is located and proper payments made to or on behalf of the Contractor shall be instituted within two years after Contractor Default under the Construction Contract. or within two years after the Contractor ceased working or 12.2 Construction Contract: The agreement between within two years after the Surety refuses or fails to perform the Owner and the Contractor identified on the signature its obligations under this Bond,whichever occurs first. If the page, including all Contract Documents and changes provisions of this Paragraph are void or prohibited by law, thereto. the minimum period of limitation available to sureties as 12.3 Contractor Default: Failure of the Contractor, a defense in the jurisdiction of the suit shall be applicable. which has neither been remedied nor waived, to 10 Notice to the Surety,the Owner or the Contractor shall perform or otherwise to comply with the terms of the be mailed or delivered to the address shown on the signature Construction Contract. page. 12.4 Owner Default: Failure of the Owner,which has 11 When this Bond has been furnished to comply with a neither been remedied nor waived,to pay the Contractor statutory or other legal requirement in the location where as required by the Construction Contract or to perform the construction was to be performed,any provision in this and complete or comply with the other terms thereof. Bond conflicting with said statutory or legal requirement shall MODIFICATIONS TO THIS BOND ARE AS FOLLOWS: (Space is provided below for additional signatures of added parties,other than those appearing on the cover page.) CONTRACTOR AS PRINCIPAL SURETY Company: (CorporateSeal) Company: (CorporateSeal) Federal Insurance Company Signature: Signature: Name and Title: Name and Title: Address: Address: Printed in cooperation with the American Institute of Architects(AIA)by Chubb.The language in this document conforms exactly to the language used in AIA Document A312 December 1984 edition,Third Printing,March 1987. Form 15-02-0279-FED(Rev.11/16) A312-19843 CHUBB Power of Attorney Federal Insurance Company I Vigilant Insurance Company I Pacific Indemnity Company Westchester Fire Insurance Company I ACE American Insurance Company Know All by These Presents, that FEDERAL INSURANCE COMPANY, an Indiana corporation, VIGILANT INSURANCE COMPANY, a New York corporation. PACIFIC INDEMNITY COMPANY, a Wisconsin corporation, WESTCHESTER FIRE INSURANCE COMPANY and ACE AMERICAN INSURANCE COMPANY corporations of the Commonwealth of Pennsylvania, do each hereby constitute and appoint Andrew A. Adams, Norman E. Adams, Michael Macomber, John A. Prince and LarryD.Snider of Houston,Texas--------------------------------------------------------------------------------------------------------------------------------------------------- each as their true and lawful Attomey-in-Fact to execute under such designation in their names and to affix their corporate seals to and deliver for and on their behalf as surety thereon or otherwise,bonds and undertakings and other writings obligatory in the nature thereof(other than bail bonds)given or executed in the course of business,and any instruments amending or altering the same,and consents to the modification or alteration of any instrument referred to in said bonds or obligations. In Witness Whereof,said FEDERAL INSURANCE COMPANY,VIGILANT INSURANCE COMPANY, PACIFIC INDEMNITY COMPANY.WESTCHESTER FIRE INSURANCE COMPANY and ACE AMERICAN INSURANCE COMPANY have each executed and attested these presents and affixed their corporate seals on this 11 day of June,2020. Riwn M Chh)cls.AscistanI Secretary Stephen M.Ilaney.Vice President 00 TO 0 STATE OF NEW JERSEY County of Hunterdon ss On this 1' day of June,2020 before me,a Notary Public of New Jersey,personally came Dawn M.Chloros and Stephen M.Haney,to me known to be Assistant Secretary and Vice President,respectively,of FEDERAL INSURANCE COMPANY,VIGILANT INSURANCE COMPANY,PACIFIC INDEMNITY COMPANY,WESTCHESTER FIRE INSURANCE COMPANY and ACE AMERICAN INSURANCE COMPANY,the companies which executed the foregoing Power of Attorney,and the said Dawn M.Chloros and Stephen M.Haney,being by me duly sworn,severally and each for herself and himself did depose and say that they are Assistant Secretary and Vice President,respectively,of FEDERAL INSURANCE COMPANY, VIGILANT INSURANCE COMPANY,PACIFIC INDEMNITY COMPANY,WESTCHESTER FIRE INSURANCE COMPANY and ACE AMERICAN INSURANCE COMPANY and know the corporate seals thereof,that the seals affixed to the foregoing Power of Attorney are such corporate seals and were thereto affixed by authority of said Companies:and that their signatures as such officers were duly affixed and subscribed by like authority. Notarial Seal aD KATHERINE J.ADELAAR NOTARY PUBLIC OF NEW JERSEYN0.23166Corrvn"ion ExOree8uy is,2024 iary Public CERTIFICATION Resolutions adopted by the Boards of Directors of FEDERAL INSURANCE COMPANY,VIGILANT INSURANCE COMPANY,and PACIFIC INDEMNITY COMPANY on August 30,2016; WESTCHESTER FIRE INSURANCE COMPANY on December ll,2006;and ACE AMERICAN INSURANCE COMPANY on March 20,2009: "RESOLVED,that the following authorizations relate to the execution,for and on behalf of the Company,of bonds,undertakings,recognizances,contracts and other written commitments of the Company entered Into in the ordinary course of business(each a"Written Commitment"): (1) Each of the Chairman,the President and the Vice Presidents of the Company is hereby authorized to execute any Written Commitment for and on behalf of the Company,under the seal of the Company or otherwise. (2) Each duty appointed attomey-in-fact of the Company is hereby authorized to execute any Written Commitment for and on behalf of the Company,under the seal of the Company or otherwise,to the extent that such action is authorized by the grant of powers provided for in such person's written appointment as such attomey-in-fact. (3) Each of the Chairman,the President and the Vice Presidents of the Company is hereby authorized,for and on behalf of the Company,to appoint in writing any person the attorney- in-fact of the Company with full power and authority to execute,for and on behalf of Company,under the seal of the Company or otherwise,such Written Commitments of the Company as may be specified in such written appointment,which specification may be by general type or class of Written Commitments or by specification of one or more particular Written Commitments. (4) Each of the Chairman,the President and the Vice Residents of the Company is hereby authorized,for and on behalf of the Company,to delegate in writing to any other officer of the Company the authority to execute,for and on behalf of the Company, under the Company's seal or otherwise,such Written Commitments of the Company as are specified In such written delegation,which specification may be by general type or class of Written Commitments or by specification of one or more particular Written Commitments. (5) The signature of any officer or other person executing any Written Commitment or appointment or delegation pursuant to this Resolution,and the seal of the Company,may be affixed by facsimile on such Written Commitment or written appointment or delegation. FURTHER RESOLVED, that the foregoing Resolution shall not be deemed to be an exclusive statement of the powers and authority of officers,employees and other persons to act for and on behalf of the Company,and such Resolution shall not limit or otherwise affect the exercise of any such power or authority otherwise validly granted or vested" 1, Dawn M. Chloros, Assistant Secretary of FEDERAL INSURANCE COMPANY, VIGILANT INSURANCE COMPANY, PACIFIC INDEMNITY COMPANY, WESTCHESTER FIRE. INSURANCE COMPANY and ACE AMERICAN INSURANCE COMPANY(the"Companies-)do hereby certify that (i) the foregoing Resolutions adopted by the Board of Directors of the Companies are true,correct and in full force and effect, (ii) the foregoing Power of Attorney is true,correct and in full force and effect. / Given under my hand and seals of said Companies at Whitehouse Station,NJ,this � day of ✓a r- , 20255 0Ila n\L Chk ros.A-caistani Secretary°1211 0 IN THE EVENT YOU WISH TO VERIFY THE AUTHENTICITY OF THIS BOND OR NOTIFY US OF ANY OTHER MATTER,PLEASE CONTACT US AT: Telephone(908)903-3493 Fax(908)903-3656 e-mail:surety@chubb.com Combined:FED-VIG-PI-WFIC-AAIC(rev.11-19) This Powe orney limits the acts of those named herein,and they have ority to bind the Company except in the manner and to the extent herein stated. Liberty Liberty Mutual Insurance Company Mutual. The Ohio Casualty Insurance Company Certificate No 8205857.974105 West American Insurance Company SURETY POWER OF ATTORNEY KNOWN ALL PERSONS BY THESE PRESENTS:That The Ohio Casualty Insurance Company is a corporation duly organized under the laws of the State of New Hampshire,that Liberty Mutual Insurance Company is a corporation duly organized under the laws of the State of Massachusetts,and West American Insurance Company is a corporation duly organized under the laws of the State of Indiana(herein collectively called the"Companies"),pursuant to and by authority herein set forth,does hereby name,constitute and appoint, Andrew A. Adams;John A.Prince;Larry D.Snider;Michael Macomber;Norman E.Adams all of the city of Houston state of TX each individually if there be more than one named,its true and lawful attorney-in-fact to make, execute,seal,acknowledge and deliver,for and on its behalf as surety and as its act and deed,any and all undertakings,bonds,recognizances and other surety obligations,in pursuance of these presents and shall be as binding upon the Companies as if they have been duly signed by the president and attested by the secretary of the Companies in their own proper persons. IN WITNESS WHEREOF,this Power of Attorney has been subscribed by an authorized officer or official of the Companies and the corporate seals of the Companies have been affixed thereto this 28th day of June 2021 Liberty Mutual Insurance Company P� 01 INS&%V su/ Pa 1NSURq The Ohio Casualty Insurance Company AJ �oa0 "4r `oavo zgr Pyy �V GoaP0 tiC West American Insurance Company J 3 Fo v 3 Fo m QrLU 3 Fo m 1912 0 0 1919 „ 1991 o N N _ '/e ///r/�/////.. d�''�s,c„us�,('aD3 yp1NnrAvsa�ya�J fs �Nou„P aa3 '�_ U c ej> * >� dy1 * *a ''M * tt� By: to David M.Carey,Assistant Secretary 3 ” m State of PENNSYLVANIA 0 a) 0 County of MONTGOMERY ss 0 E 0 0On this 28th day of June 2021 before me personally appeared David M.Carey,who acknowledged himself to be the Assistant Secretary of Liberty Mutual Insurance io Company,The Ohio Casualty Company, and West American Insurance Company,and that he,as such,being authorized so to do,execute the foregoing instrument for the purposes a)> therein contained by signing on behalf of the corporations by himself as a duly authorized officer. N co — IN WITNESS WHEREOF,I have hereunto subscribed my name and affixed my notarial seal at King of Prussia,Pennsylvania,on the day and year first above written. O PA C N a•t� p S 0 Q7(.�MO„K,F rF� Common,veafth of Pennsylvania-Notary Seal i A/I 1 o �s C Teresa Pastella,Notary Public G%� E E .0.� 0 u = Montgomery County O� OF My commission expires March 28,2025 B 0 0 C tt1 �v Commission number 1126044 y• eresa Pastella,Nota Public Q 0 LNp' �G Member,Pennsylvania Association of Notaries Notary 0)N qRy Pte” O CIJ This Power of Attorney is made and executed pursuant to and by authority of the following By-laws and Authorizations of The Ohio Casualty Insurance Company, Liberty Mutual 3 C? 0.9 Insurance Company,and West American Insurance Company which resolutions are now in full force and effect reading as follows 0M ARTICLE IV-OFFICERS:Section 12.Power of Attorney. 0 0 @ Any officer or other official of the Corporation authorized for that purpose in writing by the Chairman or the President, and subject to such limitation as the Chairman or the _0 >1 President may prescribe,shall appoint such attomeys-in-fact,as may be necessary to act in behalf of the Corporation to make,execute,seal,acknowledge and deliver as surety cm= U > N any and all undertakings,bonds,recognizances and other surety obligations.Such attomeys-in-fact,subject to the limitations set forth in their respective powers of attorney,shall 0 u o t have full power to bind the Corporation by their signature and execution of any such instruments and to attach thereto the seal of the Corporation. When so executed, such 0 a) Z L) instruments shall be as binding as if signed by the President and attested to by the Secretary.Any power or authority granted to any representative or attomey-in-fact under the_ U) provisions of this article may be revoked at any time by the Board,the Chairman,the President or by the officer or officers granting such power or authority. t0 a ARTICLE XIII-Execution of Contracts:Section 5.Surety Bonds and Undertakings. Any officer of the Company authorized for that purpose in writing by the chairman or the president,and subject to such limitations as the chairman or the president may prescribe, shall appoint such attorneys-in-fact,as may be necessary to act in behalf of the Company to make,execute,seal,acknowledge and deliver as surety any and all undertakings, bonds,recognizances and other surety obligations.Such attorneys-in-fact subject to the limitations set forth in their respective powers of attorney,shall have full power to bind the Company by their signature and execution of any such instruments and to attach thereto the seal of the Company.When so executed such instruments shall be as binding as if signed by the president and attested by the secretary. Certificate of Designation-The President of the Company,acting pursuant to the Bylaws of the Company,authorizes David M.Carey,Assistant Secretary to appoint such attorneys-in- fact as may be necessary to act on behalf of the Company to make,execute,seal,acknowledge and deliver as surety any and all undertakings,bonds,recognizances and other surety obligations. Authorization-By unanimous consent of the Company's Board of Directors,the Company consents that facsimile or mechanically reproduced signature of any assistant secretary of the Company,wherever appearing upon a certified copy of any power of attorney issued by the Company in connection with surety bonds,shall be valid and binding upon the Company with the same force and effect as though manually affixed. I, Renee C.Llewellyn,the undersigned,Assistant Secretary,The Ohio Casualty Insurance Company,Liberty Mutual Insurance Company,and West American Insurance Company do hereby certify that the original power of attorney of which the foregoing is a full,true and correct copy of the Power of Attorney executed by said Companies,is in full force and effect and has not been revoked IN TESTIMONY WHEREOF,I have hereunto set my hand and affixed the seals of said Companies this��day of rQ.gt/C/'j,�, 2025 1NSU4 110 INS&q a INSVy avorr�rgyc hr Oikrogyr`9y CGPooaPORar4'tCi J + Fo m Q 3 Fo n UJ Q- 3 `�o to Aclri_1912 0 0 1919 1991 0 Y 9f ('q 3' S =F P� 0 Q 3 By d� SSF da o -11 .15 da fs NDIAN� ya Renee C Llewellyn,Assistant Secretary LMS-12873 LMIC OCIC WAIC Multi Co 02121 Surety O + 908.903.3485 202B Halls Mill Road,PO Box 1650 F +908.903.3656 Whitehouse Station,NJ 08889-1650 Federal Insurance Company Liberty Mutual Insurance Company AIA Document A312 TM- 2010 Payment Bond K418756i6(Federal) 58S218527(Liberty Mutual) Any singular reference to Contractor,Surety,Owner or other party shall be considered plural where applicable. CONTRACTOR SURETY (Nance, legal status and address): (Name, legal status and principal place of business): SpawGlass Contractors,Inc. Federal Insurance Company(IN) 1111 Smith Road Austin,Texas 78721 Liberty Mutual Insurance Company(MA) OWNER (Name, legal status and address): City of Round Rock 221 East Main Street Round Rock,TX 7864 CONSTRUCTION CONTRACT Date: .20 day of a✓ ,2025 Amount: $5,287,121.00 Five Million Two Hundred Eighty Seven Thousand One Hundred Twenty One& 00/100 Dollars Description(Name and Location): Old Settler's Park Build Out-6o%GMP for Rec Center-EARTHWORK BOND Date(Not earlier than Construction Contract Date):.2D - day of JeLint4gril,2025 Amount: $5,287,121.00 Fivi Million Two Hundred Eighty Seven Thousand One Hundred Twenty One& 00/100 Dollars Modifications to this Bond: El None ❑ See Page 4 CONTRACTORS AS PRINCIPAL SURETY " Company: SpawGlasCn ors (C� porate Seal) Company: (Corporate Seal) Federal Insurance Co any ibe Mutual Insurance omp Signature: Name and Title: �ent'- Signature: tin Division Attorney-in-Fac ame: John A.Prince Signed and Sealed this gao— day of ,2025 (Any additional signatures appear on the last page of this Performance Bond.) (FOR INFORMATION OATL) ---Name,Address and Telephone) AGENT or BROKER: OWNER'S REPRESENTATIVE(Architect.Engineeror otherparty) Adams Insurance Service 427 W loth.Suite 500 Houston,TX 77oo8 713-869-8346 Printed in cooperation frith the American Institute of Architects(AIA)by Chubb. The language in this document conforms to the language used in AIA Document A312"'-2010. Form 15-02-0574-FED(Ra 11116) 1 L The Contractor and the Surety,jointly and severally,bind themselves,their heirs,executors,administrators, successors and assigns to the Owner to pay for labor, materials and equipment furnished for use in the performance of the Construction Contract,which is incorporated herein by reference,subject to the following terms. 2 If the Contractor promptly makes payment of all sums due to Claimants,and defends,indemnifies and holds harmless the Owner from claims,demands,liens or suits by any person or entity seeking payment for labor, materials or equipment furnished for use in the performance of the Construction Contract, then the Surety and the Contractor shall have no obligation under this Bond. 3. If there is no Owner Default under the Construction Contract,the Surety's obligation to the Owner under this Bond shall arise after the Owner has promptly notified the Contractor and the Surety(at the address described in Section 13)of claims,demands,liens or suits against the Owner or the Owner's property by any person or entity seeking payment for labor,materials or equipment furnished for use in the performance of the Construction Contract and tendered defense of such claims,demands,liens or suits to the Contractor and the Surety. 4 When the Owner has satisfied the conditions in Section 3,the Surety shall promptly and at the Surety's expense defend,indemnify and hold harmless the Owner against a duly tendered claim,demand, lien or suit. 5. The Surety's obligations to a Claimant under this Bond shall arise after the following: 5.1 Claimants,who do not have a direct contract with the Contractor, .1 have furnished a written notice of non-payment to the Contractor, stating with substantial accuracy the amount claimed and the name of the party to whom the materials were, or equipment was, furnished or supplied or for whom the labor was done or performed,within ninety(90)days after having last performed labor or last furnished materials or equipment included in the Claim;and .2 have sent a Claim to the Surety(at the address described in Section 13). 52 Claimants,who are employed by or have a direct contract with the Contractor,have sent a Claim to the Surety (at the address described in Section 13). 6. If a notice of non-payment required by Section 5.1.1 is given by the Owner to the Contractor,that is sufficient to satisfy a Claimant's obligation to furnish a written notice of non-payment under Section 5.1.1. 7. When a Claimant has satisfied the conditions of Sections 5.1 or 5.2,whichever is applicable, the Surety shall promptly and at the Surety's expense take the following actions: 71 Send an answer to the Claimant,with a copy to the Owner,within sixty(60)days after receipt of the Claim, stating the amounts that are undisputed and the basis for challenging any amounts that are disputed;and 72 Pay or arrange for payment of any undisputed amounts. 73 The Surety's failure to discharge its obligations under Section 7.1 or Section 7.2 shall not be deemed to constitute a waiver of defenses the Surety or Contractor may have or acquire as to a Claim, except as to undisputed amounts for which the Surety and Claimant have reached agreement.If,however,the Surety fails to discharge its obligations under Section 7.1 or Section 7.2, the Surety shall indemnify the Claimant for the reasonable attorney's fees the Claimant incurs thereafter to recover any sums found to be due and owing the Claimant. 8. The Surety's total obligation shall not exceed the amount of this Bond,plus the amount of reasonable attorney's fees provided under Section 7.3,and the amount of this Bond shall be credited for any payments made in good faith by the Surety. 9. Amounts owed by the Owner to the Contractor under the Construction Contract shall be used for the performance of the Construction Contract and to satisfy claims, if any,under any construction performance bond. By the Contractor furnishing and the Owner accepting this Bond, they agree that all funds earned by the Contractor in the performance of the Construction Contract are dedicated to satisfy obligations of the Contractor and the Surety under this Bond,subject to the Owner's priority to use the funds for the completion of the work. Printed in cooperation with the American Institute of Architects(AIA)by Chubb. The language in this document conforms to the language used in AIA Document A312 Tm-2010. Form 15-02-0574-FED(Rev.11/I6) 2 XX The Surety shall not be liable to the Owner, Claimants or others for obligations of the Contractor that are unrelated to the Construction Contract.The Owner shall not be liable for the payment of any costs or expenses of any Claimant under this Bond,and shall have under this Bond no obligations to make payments to,or give notice on behalf of, Claimants or otherwise have any obligations to Claimants under this Bond. 1L The Surety hereby waives notice of any change,including changes of time,to the Construction Contract or to related subcontracts,purchase orders and other obligations. 12 No suit or action shall be commenced by a Claimant under this Bond other than in a court of competent jurisdiction in the state in which the project that is subject of the Construction Contract is located or after the expiration of one year from the date (1) on which the Claimant sent a Claim to the Surety pursuant to Section 5.1.2 or 5.2,or(2)on which the last labor or service was performed by anyone or the last materials or equipment were furnished by anyone under the Construction Contract,whichever of(1)or(2)first occurs. If the provisions of this Paragraph are void or prohibited by law,the minimum period of limitation available to sureties as a defense in the jurisdiction of the suit shall be applicable. 13. Notice and Claims to the Surety,the Owner or the Contractor shall be mailed or delivered to the address shown on the page which their signature appears. Actual receipt of notice or Claims, however accomplished, shall be sufficient compliance as of the date received. 14 When this Bond has been furnished to comply with a statutory or other legal requirement in the location where the construction was to be performed, any provision in this Bond conflicting with said statutory or legal requirement shall be deemed deleted herefrom and provisions conforming to such statutory or other legal requirement shall be deemed incorporated herein.When so furnished,the intent is that this Bond shall be construed as a statutory bond and not as a common law bond. L5. Upon request by any person or entity appearing to be a potential beneficiary of this Bond,the Contractor and Owner shall promptly furnish a copy of this Bond or shall permit a copy to be made. 16. DEFINITIONS 161 Claim.A written statement by the Claimant including at a minimum: .1 the name of the Claimant; .2 the name of the person for whom the labor was done,or materials or equipment furnished; .3 a copy of the agreement or purchase order pursuant to which labor,materials or equipment was furnished for use in the performance of the Construction Contract; .4a brief description of the labor,materials or equipment furnished; .5 the date on which the Claimant last performed labor or last furnished materials or equipment for use in the performance of the Construction Contract; .tithe total amount earned by the Claimant for labor, materials or equipment furnished as of the date of the Claim; .7 the total amount of previous payments received by the Claimant;and, .8the total amount due and unpaid to the Claimant for labor,materials or equipment furnished as of the date of the Claim. 162 Claimant:An individual or entity having a direct contract with the Contractor or with a subcontractor of the Contractor to furnish labor,materials,or equipment for use in the performance of the Construction Contract. The term Claimant also includes any individual or entity that has rightfully asserted a claim under an applicable mechanic's lien or similar statute against the real property upon which the Project is located.The intent of this Bond shall be to include without limitation in the terms "labor, materials or equipment" that part of water, gas power, light, heat, oil gasoline, telephone service or rental equipment used in the Construction Contract, architectural and engineering services required for performance of the work of the Contractor Printed in cooperation with the American Institute of Architects(AIA)by Chubb. The language in this document conforms to the language used in AIA Document A312 rm-2010. Form 15-02-0574-FED(Rev.11/16) 3 and the Contractor's subcontractors,and all other items for which a mechanic's lien may be asserted in the jurisdiction where the labor,materials or equipment were furnished. 163 Construction Contract: The agreement between the Owner and the Contractor identified on the cover page,including all Contract Documents and all changes made to the agreement and the Contract Documents. 16.40wner Default:Failure of the Owner,which has neither been remedied nor waived,to pay the Contractor as required under the Construction Contract or to perform and complete or comply with the other material terms of the Construction Contract. 165 Contract Documents.All the documents that comprise the agreement between the Owner and Contractor. i7. If this Bond is issued for an agreement between a Contractor and subcontractor,the term Contractor in this Bond shall be deemed to be Subcontractor and the term Owner shall be deemed to be Contractor. I& MODIFICATIONS TO THIS BOND ARE AS FOLLOWS: 18.1 "Claim notices for FEDERAL INSURANCE COMPANY must be sent to the following address: Chubb,PO Box 2191, Chesapeake,Virginia 23327,Attention:Surety Support Team." (Space is provided below for additional signatures of added parties,other than those appearing on the cover page.) CONTRACTOR AS PRINCIPAL SURETY Company: (Corporate Seal) Company: (Corporate Seal) Federal Insurance Company Signature: Signature: Name and Title: Name and Title: Address: Address: Printed in cooperation with the American Institute of Architects(AIA)by Chubb. The language in this document conforms to the language used in AIA Document A312 TM-2010. Form 15-02-0574-FED(Rev.11/16) 4 C H U B B Power of Attorney Federal Insurance Company I Vigilant Insurance Company I Pacific Indemnity Company Westchester Fire Insurance Company I ACE American Insurance Company Know All by These Presents. that FEDERAL INSURANCE COMPANY, an Indiana corporation, VIGILANT INSURANCE COMPANY. a New York corporation, PACIFIC INDEMNITY COMPANY, a Wisconsin corporation, WESTCHESTER FIRE INSURANCE COMPANY and ACE AMERICAN INSURANCE COMPANY corporations of the Commonwealth of Pennsylvania, do each hereby constitute and appoint Andrew A. Adams, Norman E. Adams, Michael Macomber, John A. Prince and LarryD.Snider of Houston,Texas------------------------------------------------------------------------------------- -------------------------------------------------- each as their true and lawful Attorney-in-Fact to execute under such designation in their names and to affix their corporate seals to and deliver for and on their behalf as surety thereon or otherwise,bonds and undertakings and other writings obligatory in the nature thereof(other than bail bonds)given or executed in the course of business,and any instruments amending or altering the same,and consents to the modification or alteration of any instrument referred to in said bonds or obligations. in Witness Whereof, said FEDERAL INSURANCE COMPANY,VIGILANT INSURANCE COMPANY,PACIFIC INDEMNITY COMPANY,WESTCHESTER FIRE INSURANCE COMPANY and ACE AMERICAN INSURANCE COMPANY have each executed and attested these presents and affixed their corporate seals on this 11 day of June,2020. acss s'►�l`�. 5.\,� it-, 0_t_� Daum M.Chluros.Ac istant Secretary Stephen At.Raney.Vice President ��' ti� �`Y �1M�• •fir STATE OF NEW JERSEY County of Hunterdon SS On this 11 day of)une,2020 before me,a Notary Public of New Jersey,personally came Dawn M.Chloros and Stephen M.Haney,to me known to be Assistant Secretary and Vice President,respectively,of FEDERAL INSURANCE COMPANY,VIGILANT INSURANCE COMPANY,PACIFIC INDEMNITY COMPANY,WESTCHESTER FIRE INSURANCE COMPANY and ACE AMERICAN INSURANCE COMPANY,the companies which executed the foregoing Power of Attorney,and the said Dawn M.Chloros and Stephen M.Haney,being by me duly sworn,severally and each for herself and himself did depose and say that they are Assistant Secretary and Vice President,respectively,of FEDERAL INSURANCE COMPANY, VIGILANT INSURANCE COMPANY,PACIFIC INDEMNITY COMPANY,WESTCHESTER FIRE INSURANCE COMPANY and ACE AMERICAN INSURANCE COMPANY and know the corporate seals thereof,that the seals affixed to the foregoing Power of Attorney are such corporate seals and were thereto affixed by authority of said Companies;and that their signatures as such officers were duly affixed and subscribed by like authority. Notarial Seal rAq KATHERINE J.ADEI?.AR NOTARY PUBLIC OF NEW JERSEY �' a N0.2318885 L Commlsaion Expires JWy 18,2024 Weary PUNIC A, CERTIFICATION Resolutions adopted by the Boards of Directors of FEDERAL INSURANCE COMPANY,VIGILANT INSURANCE COMPANY,and PACIFIC INDEMNITY COMPANY on August 30,2016; WESTCHESTER FIRE INSURANCE COMPANY on December 11,2006;and ACE AMERICAN INSURANCE COMPANY on March 20,2009: "RESOLVED,that the following authorizations relate to the execution,for and on behalf of the Company,of bonds,undertakings,recognizances,contracts and other written commitments of the Company entered into in the ordinary course of business(each a"Written Commitment"): (1) Each of the Chairman,the President and the Vice Presidents of the Company is hereby authorized to execute any Written Commitment for and on behalf of the Company,under the seal of the Company or otherwise. (2) Each duly appointed attomey-in-fact of the Company is hereby authorized to execute any Written Commitment for and on behalf of the Company,under the seal of the Company or otherwise,to the extent that such action is authorized by the grant of powers provided for in such person's written appointment as such attorney-in-fact. (3) Each of the Chairman,the President and the Vice Presidents of the Company is hereby authorized,for and on behalf of the Company,to appoint in writing any person the attorney- in-fact of the Company with full power and authority to execute,for and on behalf of the Company,under the seal of the Company or otherwise,such Written Commitments of the Company as may be specified in such written appointment,which specification may be by general type or class of written Commitments or by specification of one or more particular Written Commitments. (4) Each of the Chairman,the President and the Vice Presidents of the Company is hereby authorized,for and on behalf of the Company,to delegate in writing to any other officer of the Company the authority to execute,for and on behalf of the Company.under the Company's seal or otherwise,such Written Commitments of the Company as are specified in such written delegation,which specification may be by general type or class of Written Commitments or by specification of one or more particular Written Commitments. (S) The signature of any officer or other person executing any Written Commitment or appointment or delegation pursuant to this Resolution,and the seal of the Company,may be affixed by facsimile on such Written Commitment or written appointment or delegation. FURTHER RESOLVED, that the foregoing Resolution shall not be deemed to be an exclusive statement of the powers and authority of officers,employees and other persons to act for and on behalf of the Company,and such Resolution shall not limit or otherwise affect the exercise of any such power or authority otherwise validly granted or vested" 1, Dawn M. Chloros, Assistant Secretary of FEDERAL INSURANCE COMPANY, VIGILANT INSURANCE COMPANY, PACIFIC INDEMNITY COMPANY, WESTCHESTER FIRE INSURANCE COMPANY and ACE AMERICAN INSURANCE COMPANY(the"Companies-)do hereby certify that (i) the foregoing Resolutions adopted by the Board of Directors of the Companies are true,correct and in full force and effect, (ii) the foregoing Power of Attorney is true,correct and in full force and effect. Given under my hand and seals of said Companies at Whitehouse Station,NJ,this -96 day of Q2025 Wwn M.Chlorris.,Vsz�istani secroarf' IN THE EVENT YOU WISH TO VERIFY THE AUTHENTICITY OF THIS BOND OR NOTIFY US OF ANY OTHER MATTER PLEASE CONTACT US AT: Telephone(908)903-3493 Fax(908)903-3656 email:surety@chubb.com Combined:FED-VIG-PI-WFIC-AAIC(rev.11-19) This Powe )rney limits the acts of those named herein,and they have i ority to bind the Company except in the manner and to the extent herein statea. Liberty Liberty Mutual Insurance Company Mutual. The Ohio Casualty Insurance Company Certificate No 8205857-974105 West American Insurance Company SURETY POWER OF ATTORNEY KNOWN ALL PERSONS BY THESE PRESENTS:That The Ohio Casualty Insurance Company is a corporation duly organized under the laws of the State of New Hampshire,that Liberty Mutual Insurance Company is a corporation duly organized under the laws of the State of Massachusetts,and West American Insurance Company is a corporation duly organized under the laws of the State of Indiana(herein collectively called the"Companies"),pursuant to and by authority herein set forth,does hereby name,constitute and appoint, Andrew A. Adams;John A.Prince;harry D.Snider;Michael Macomber;Norman E.Adams all of the city of Houston state of 7'X each individually if there be more than one named,its true and lawful attorney-in-fact to make, execute,seal,acknowledge and deliver,for and on its behalf as surety and as its act and deed,any and all undertakings,bonds,recognizances and other surety obligations,in pursuance of these presents and shall be as binding upon the Companies as if they have been duly signed by the president and attested by the secretary of the Companies in their own proper persons. IN WITNESS WHEREOF,this Power of Attorney has been subscribed by an authorized officer or official of the Companies and the corporate seals of the Companies have been affixed thereto this 28th day of June 2021 Liberty Mutual Insurance Company P�INSUgq P\SV ENSUo I 1NSUgq The Ohio Casualty Insurance Company°apOR" L J Dap°ea,w �r °a°°'t, F C� P West American Insurance Com an d o n y v y v r Y � 3 Fo rn e 3 Fo n � 3 Fo F U w 1912 0 1919 „ 1991 - O dj1 sSq CNUs�daHA MPs�,da; �s vNDIANP aa� T'�_! 1 N O(� By: =iu Co David M.Carey,Assistant Secretary t`tt State of PENNSYLVANIA — ::3 County of MONTGOMERY ss c E 0 c0 a� On this 28th da of June 2021 before me personally appeared David M.Care who acknowledged himself to be the Assistant Secreta of Liberty Mutual Insurance as � Y P Y PP Y� 9 Secretary rtY vCD � m Company,The Ohio Casualty Company,and West American Insurance Company,and that he,as such,being authorized so to do,execute the foregoing instrument for the purposes a)> therein contained by signing on behalf of the corporations by himself as a duly authorized officer. > — IN WITNESS WHEREOF,I have hereunto subscribed my name and affixed my notarial seal at King of Prussia.Pennsylvania,on the day and year first above written. O @ N PAS tlO O Q7(• ONWF r�C Commonwealth of Pennsylvania-Notary Seal O 9(a C Teresa Paste la Notary Public N'F0 te• Montgomery County rI///,,,,'',,,, •ll ( C O OF My commission eipires March 28,2025 By: /`"� �'�%� O C g �v Commission number 1126044 �, MvSy01P J Member,Pennsylvania Association of Notaries eresa Pastella,Notary Public Q O co qRv t v 0 This Power of Attorney is made and executed pursuant to and by authority of the following By-laws and Authorizations of The Ohio Casualty Insurance Company, Liberty Mutual 3 0? O Insurance Company,and West American Insurance Company which resolutions are now in full force and effect reading as follows: 0 CO ARTICLE IV-OFFICERS:Section 12.Power of Attorney. aI O O Any officer or other official of the Corporation authorized for that purpose in writing by the Chairman or the President, and subject to such limitation as the Chairman or the c �^ President may prescribe,shall appoint such attorneys-in-fact,as may be necessary to act in behalf of the Corporation to make,execute,seal,acknowledge and deliver as surety m— CO> N attorney,any ,and all undertakings,bonds,recognizances and other surety obligations.Such attomeys-in-fact,subject to the limitations set forth in their respective powers of attoey,shall c have full power to bind the Corporation by their signature and execution of any such instruments and to attach thereto the seal of the Corporation. When so executed, such o d Z instruments shall be as binding as if signed by the President and attested to by the Secretary.Any power or authority granted to any representative or attomey-in-fact under the ami provisions of this article may be revoked at any time by the Board,the Chairman,the President or by the officer or officers granting such power or authority. T ARTICLE XIII-Execution of Contracts:Section 5.Surety Bonds and Undertakings. Any officer of the Company authorized for that purpose in writing by the chairman or the president,and subject to such limitations as the chairman or the president may prescribe, shall appoint such attorneys-in-tact,as may be necessary to act in behalf of the Company to make,execute,seal,acknowledge and deliver as surety any and all undertakings, bonds,recognizances and other surety obligations.Such attorneys-in-fact subject to the limitations set forth in their respective powers of attorney,shall have full power to bind the Company by their signature and execution of any such instruments and to attach thereto the seal of the Company.When so executed such instruments shall be as binding as if signed by the president and attested by the secretary. Certificate of Designation-The President of the Company,acting pursuant to the Bylaws of the Company,authorizes David M Carey,Assistant Secretary to appoint such attomeys-in- fact as may be necessary to act on behalf of the Company to make,execute,seal,acknowledge and deliver as surety any and all undertakings,bonds,recognizances and other surety obligations Authorization-By unanimous consent of the Company's Board of Directors,the Company consents that facsimile or mechanically reproduced signature of any assistant secretaryof the Company,wherever appearing upon a certified copy of any power of attorney issued by the Company in connection with surety bonds,shall be valid and binding upon the Company with the same force and effect as though manually affixed. I,Renee C. Llewellyn,the undersigned,Assistant Secretary,The Ohio Casualty Insurance Company,Liberty Mutual Insurance Company,and West American Insurance Company do hereby certify that the original power of attorney of which the foregoing is a full,true and correct copy of the Power of Attorney executed by said Companies,is in full force and effect and has not been revoked IN TESTIMONY WHEREOF,I have hereunto set my hand and affixed the seals of said Companies this 2_day of 2025 1NSUR I,( INS& a 1NSU�q BJP`°µvoRq�gyn yJPo°avortyjRqVP`°avor�r4y� ? Fo m 0 u Q 3 o m F ; 1912 h o 0 = 1919� 0 1991 0 0 3 BY: d� di �Ngaai` s NDIA11 as yr 1.13 taps� YRenee C Llewellyn,Assistant Secretary 87) * *e� dpl * �N dM • lev LMS-12873 LMIC OCIC WAIC Multi Co 02/21 Have a complaint or need help? Tiene una queja o necesita ayuda? IMPORTANT NOTICE AWSO IMPORTANTE If you have a problem with a claim or your premiums, call Si tiene un problema con un reclamo o las primas,llame your insurance company first. If you can't work out the primero a la empresa de seguros.Si no puede resolver el issue, the Texas Department of Insurance may be able to problema,el Departamento de Seguros del estado de Tejas help. puede ayudar. Even if you file a complaint with the Texas Department of Si registra una queja con el Departamento de Seguros del Insurance, you should also file a complaint or appeal estado de tejas,tambien debe presentar una queja o through your insurance company. If you don't, you may apelacion a traves de su compania de seguros.Si no to hace lose your right to appeal. puede perder su derecho de apelar. To get information or file a complaint with CHUBB: Para obtener informacion o registro de una queja con CHUBB: Call Toll-free:1-Boo-36-CHUBB I1ame al:1-800-36-CHUBB Mail: Eastern Claim Service Center Correo: Eastern Claim Service Center 600 Independence Parkway 600 Independence Parkway Chesapeake,VA 23320 Chesapeake,VA 23320 Attn: Surety Support Attn: Surety Support Phone: 800-252-4670 Fax: 800-664-5358 Telefono: 800-252-4670 Fax: 800-664-5358 Email: ecsc.claims@chubb.com Correo electronico: ecsc.claims@chubb.com To get help with an insurance question or file a complaint Para ayuda con una pregunta de seguros o registrar una with the state: queja con el estado: The Texas Department of Insurance El Departamento de Seguros del Estado de Tejas Call with a question:1-800-252-3439 Preguntas: 1-800-252-3439 File a complaint: www.tdi.texas.gov Quejas: www.tdi.texas.gov E-mail: ConsumerProtection@tdi.texas.gov Correo electronico: ConsumerProtection@tdi.texas.gov Mail: MC-iii-1A,P.O.Box 149091 Correo: MC-iii-iA,P.O.Box 149091 Austin,TX 78714-9091 Austin,TX 78714-9091 Form 15-10-0347(Rev.2/23) Liberty Mutual. SURETY TEXAS TEXAS IMPORTANT NOTICE AVISO IMPORTANTE To obtain information or make a complaint: Para obtener informacion o para someter una queja: You may call toll-free for information or to Usted puede Ilamar al numero de telefono gratis make a complaint at para informacion o para someter una queja al 1-877-751-2640 1-877-751-2640 You may also write to: Usted tambien puede escribir a: 2200 Renaissance Blvd., Ste. 400 2200 Renaissance Blvd., Ste. 400 King of Prussia, PA 19406-2755 King of Prussia, PA 19406-2755 You may contact the Texas Department of Puede comunicarse con el Departamento de Insurance to obtain information on companies, Seguros de Texas para obtener informacion coverages, rights or complaints at acerca de companias, coberturas, derechos o 1-800-252-3439 quejas al 1-800-252-3439 You may write the Texas Department of Insurance Puede escribir al Departamento de Seguros Consumer Protection(I 11-I A) de Texas Consumer Protection(I 11-1 A) P. 0. Box 149091 P. 0. Box 149091 Austin,TX 78714-9091 Austin,TX 78714-9091 FAX: (512)490-1007 FAX#(512)490-1007 Web: http://www.tdi.texas.gov Web: hHp://www.tdi.texas.gov_ E-mail: ConsumerProtection&tdi.texas.gov E-mail: ConsumerProtection@tdi.texas.gov PREMIUM OR CLAIM DISPUTES: DISPUTAS SOBRE PRIMAS 0 RECLAMOS: Should you have a dispute concerning your Si tiena una disputa concemiente a su prima o a premium or about a claim you should first un reclamo, debe comunicarse con el agente o contact the agent or call 1-800-843-6446. primero. Si no se resuelve la disputa, puede If the dispute is not resolved, you may contact the entonces comunicarse con el departamento (TDI) Texas Department of Insurance. ATTACH THIS NOTICE TO YOUR UNA ESTE AVISO A SU POLIZA: POLICY: This notice is for information only and does not Este aviso es solo para proposito de informacion become a part or condition of the attached y no se convierte en parte o condicion del document. documento adjunto. NP 70 68 09 01 LMS-15292 10/15 CERTIFICATE OF INTERESTED PARTIES FORM 1295 1 of 1 Complete Nos.1-4 and 6 if there are interested parties. OFFICE USE ONLY Complete Nos.1,2,3,5,and 6 if there are no interested parties. CERTIFICATION OF FILING 1 Name of business entity filing form,and the city,state and country of the business entity's place Certificate Number: of business. 2025-1258146 SpawGlass Contractors, Inc. Austin,TX United States Date Filed: 2 Name of governmental entity or state agency that is a party to the contract for which the form is 01/16/2025 being filed. City of Round Rock Date Acknowledged: 3 Provide the identification number used by the governmental entity or state agency to track or identify the contract,and provide a description of the services,goods,or other property to be provided under the contract. 000000-Rec Center Earthwork Construction Management services for the Rec Center Earthwork Package on the Old Settler's Park Buildout 4 Nature of interest Name of Interested Party City,State,Country(place of business) (check applicable) Controlling I Intermediary SpawGlass Contractors, Inc. Austin,TX United States X 5 Check only if there is NO Interested Party. ❑ 6 UNSWORN DECLARATION My name is David Paden and my date of birth is doom My address is 1111 Smith Road Austin TX 78721 USA (street) (city) (state) (zip code) (country) I declare under penalty of perjury that the foregoing is true and correct. Executed in Travis County, State of Texas on the 16th day of January 20 25 . (month) (year) I ure authorized agent of contracting business entity (Declarant) Forms provided by Texas Ethics Commission www.ethlcs.state.tx.us Version V4.1.0.5dd2ace2