TB-2025-001 - 3/27/2025 RESOLUTION NO.TB-2025-001
WHEREAS, the Board of Directors of the Round Rock Transportation and Economic
Development Corporation ("TEDCO") has previously approved the Transportation Capital
Improvement Program ("TCIP") to provide funding for various Projects pursuant to Chapters 501 and
505 of the Texas Local Government Code (the "Code"); and
WHEREAS, among the Projects previously approved by TEDCO are the following:
(1) County Road 118 Widening (University Blvd to SH 130), (2) Gattis Schol Roads Segments 4 & 5
(Double Creek Dr to Meister Lane & Rusk Rd to Via Sonoma Trail), (3) Greenlawn Boulevard
Improvements, and (4) Sam Bass Road& Hairy Man Intersection Improvements; and
WHEREAS, the Board wishes to amend the TCIP to include increased funding for the above-
described Projects, Now Therefore
BE IT RESOLVED BY THE BOARD OF DIRECTORS OF THE ROUND ROCK
TRANSPORTATION AND ECONOMIC DEVELOPMENT CORPORATION,
That the TCIP is hereby amended to increase funding for the above-described Projects as set
forth in Exhibit"A," attached hereto and incorporated herein.
The Board of Directors hereby finds and declares that written notice of the date, hour, place and
subject of the meeting at which this Resolution was adopted was posted and that such meeting was
open to the public as required by law at all times during which this Resolution and the subject matter
hereof were discussed, considered and formally acted upon, all as required by the Open Meetings Act,
Chapter 551, Texas Government Code, as amended.
0112.20252:4908-3298-3080
RESOLVED this 27th day of March, 2025.
By_ Ao_
RE FLORES, Preside
Round Rock Transportation and Economic
Development Corporation
ATTEST:
RICK VILLARREAL, Secretary
2
EXHIBIT
"A"
TCIP Amendment#54
New Projects
Project Name Cost Transaction Description
Chisholm Trail Road at Brushy Creek Sidewalk Connection $ 1,500,000 Engineering Services
Northeast Downtown Improvements Phase 2 (Sheppard St) $ 2.500,000 Engineering Services
Total Budget for New Projects $ 4,000,000
Existing Projects Adjustments
Project Name Cost Transaction Description
County Road 118 Widening (University Blvd to SH 130) (A) $ 2,500,000 Budget Increase - Right-of-Way Acquisition
Gattis School Road Segments 4 & 5 (Double Creek Dr to Meister
$ 1,500,000 Budget Increase - Right-of-Way Acquisition
Lane & Rusk Rd to Via Sonoma Trail) (A)
Greenlawn Boulevard Improvements (B) $ 11,000,000 Budget Increase - Construction & Contingency
Sam Bass Road & Hairy Man Road Intersection Improvements (A) $ 1,000,000 Budget Increase - Right-of-Way Acquisition
Total Adjustments $ 16,000,000
Total Type B Impact $ 20,000,000
(A) Budget approved on prior TCIP amendment covered design. Additional budget required to start ROW acquisitions.
(B) Construction budget included in prior TCIP amendments during the design phase of the project. Additional budget required due to updated
engineer's estimate with 100% design plans.
Note: Additional budget needs are covered by the "Transportation Planned Projects" section of the 2025-2029 Funds Allocation Plan.